SPC - Guidelines & Circular
SPC - Guidelines & Circular
Sub: Guidelines for taking remedial measures to avoid non –operation of bus
bar protection at EHV sub-station.
1.0. The periodic hot line washing of insulators in the switchyard and on the lines
near the coastal /chemically prone area needs to be arranged on regular basis.
2.0. Multiple earthing in CT circuit if any should be checked up in all the bays and
should be removed immediately.
3.0. The spark gap arrestor provided in respect of 220kV CT secondary circuit of
busbar protection needs to be bypassed.
4.0. The auxiliary CTs used in the busbar protection scheme should be mounted in
the relay panel located in control room & rewired.
IPS tube connecting breaker of 400 kV Lonikand - II bay to 29B pantograph isolator base got
dislocated from isolator side. The IPS tube fell down from one side & touched the post
insulator metallic structure on breaker side. The busbar protection for 400kV Main Bus-I has
operated correctly for this fault. Due to continuous rains & storm, no manual yard inspection
could be carried till 40-50 minutes after the occurrence. After detailed study & analysis of the
occurrence, it was concluded that the occurrence took place due to dislocation of IPS
tube resulting into a bus fault and the dislocation of IPS tube can be attributed to
failure of bolts in shear. It was also pointed out that the last thermo vision scanning of
400kV switchyard was carried out in the month of August 2008 & no hot spot was observed
After detailed discussion, the committee has decided to check up & adopt the
1.0. The Nut-Bolts used for IPS tube clamp must be of good quality i.e. stainless
steel.
1.0. The span of IPS tube may reduced by providing additional BPI.
The above remedial measures should be implemented invariably for all 400kV sub-
station in MSETCL.
An occurrence took place at 400kV Padghe sub-station on 21.04.2010, wherein all the
220kV Lines, ICTs, Transformers connected to 220kV Main Bus-II along with B/C tripped due
to operation of 220kV Busbar protection. The Busbar protection of Main Bus-II operated
without any fault on primary side. Only ‘U’ flag indication appeared without any phase
indication (i.e., R, S, T flag) which confirms the mal-operation of Busbar protection. After
detailed investigations, during joint testing with M/s ABB representative, no abnormality
was noticed in the scheme & as such reasons for mal-operation, Busbar protection could not
be arrived at. However, in order to avoid such incidents of mal-operation of Busbar
protection scheme type RADSS, certain modifications in the RADSS scheme ( i. e. separation
of incoming positive & trip output terminals) were carried out as a part of corrective
measure.
Before Modification
In view of above after detailed discussion & deliberation, the committee suggested
that,
1.0. It is necessary that while availing outage on EHV lines & wherever bus-bar
protection is provided with CT switching relay & having line side CT, the
earthing needs to be provided after CT towards line.
2.0. The operating staff should invariably confirm that the CT switching relay in
Busbar protection having line side CT is in reset condition for the line /
transformer which is under outage.
OFFICE OF CHIEF ENGINEER (PAC) CO AIROLI 9
II) Single bus arrangement
1.0. It is necessary that while availing the outage on EHV lines & when ever bus bar
protection is not provided with CT switching relay & having line side CT, the
secured temporary earthing needs to be provided after CT toward line side.
2.0. However if bay maintenance is to be carried out & earthing is provided to both
side of CT, then bus – bar protection is to be taken out of service for that period.
3.0. The earthing on both side of CT to be avoided in any case to avoid the operation
of bus bar protection.
This is in connection with the above subject. The 220kV Parli-Harangul-I line trip on
distance protection due to opening of Wave trap jumper at 220kV Old GCR Parli s/s on
17.08.17 & subsequently recloses at both end. Simultaneously the 220kV bus-bar protection
ABB make type REB 670 operated during the auto reclosing of 220kV Parli-Harangul-I at
220kV Old GCR Parli s/s. Similarly on 15.10.2017 at 220kV Boisar sub-station, the 220kV
Boisar-PGCIL-I line tripped & subsequently CB charged on fault from Boisar end by shorting
closing wires at terminal block instead of through TNC control switch. Simultaneously the
ABB make REB670 bus-bar protection operated during charging of 220kV Boisar – PGCIL-I
line. As seen from DR of Bus Bar (ABB REB670) and Line DPR (Siemens 7SA522) while
charging 220kV PGCIL Line on persisted fault, it was observed that CB status to the BB and
Manual Closure command found missing which resulted into CT current forced to zero logic
operation. The BB relay didn’t measure 220 kV PGCIL Line -I fault current in calculation due
to which the other bays contributed current considered as differential current, and Busbar
initiated tripping to all bays of 220 kV B bus and Bus coupler.
In past also similar operation of ABB make REB670 bus bar protection was observed
at 400kV Kalwa sub-station on 30.12.2015. The single phase (R phase) fault was observed in
220 kV Borivali Line which was cleared by the line protection relay in Zone – 1. The Auto –
reclose (AR) in the protection was initiated and after a dead time of 1 second, AR close
command was issued. The fault was a persisting fault and the protection relay sensed the
fault zone – 1 and issued trip command. However, soon after the inception of fault in zone – 1
during reclaim time, bus bar protection operated and tripped all the feeders connected to
zone – A (Bus – 1). M/s ABB Engineer has visited to investigate the reason of operation of
bus-bar protection & after detailed investigation; a report was submitted.
1. The CB Open Status (NC contact) shall be connected in series such that only when all
the three phases of the circuit breaker open, does the current of any feeder is forced to
zero.
2. Connect the AR close command in parallel with the CB manual close command for all
line feeders.
3. The CB should be charged through TNC control switch when line tripped on fault. The
CB should not be charged through Local control switch or by passing TNC control
switch.
4. The End zone fault protection (ENFP) shall be kept OFF/disable.
5. The bay parameter setting shall be modified as under,
Setting Group 1
1 CT Connection Connected _
5 tTripPulse 0.200 _
7 tInvertCurrent 0.200 _
8 CT Connection Connected _
10 ZoneSwitching Conditionally _
13 tZeroCurrent 0.200 _
14 tInvertCurrent 0.200 _
16 ZoneSel CtrlIncludes _
17 ZoneSwitching Conditionally _
18 CheckZoneSel Connected _
20 tZeroCurrent 0.200 _
21 tInvertCurrent 0.200 _
6. The link between Block `ENFP’ & Block `Force to Zero’ in CB open status logic used in
relay configuration shall be disconnected/opened. The snapshot of CB open status
logic is attached as Annexure.
It is requested to verify the above recommended setting in existing bus-bar schemes &
rectify the same in order so as to avoid the mal operation of ABB make REB 670/500 bus bar
protection in future. Also due care in this respect shall be taken while commissioning/setting
configuration of future scheme. The compliance report shall be submitted to this office.
(Shashank S. Jewalikar)
Chief Engineer (PAC)
Copy s. w. rs. to:
1. The Chief Engineer, EHV PC (O&M) zone, MSETCL, Amravati/ Aurangabad / Karad
/ Nagpur/ Nasik / Pune / Vashi.
2. The Chief Engineer, (Tr. O&M) CO Mumbai.
Copy to:
Force out
Not Connected
Sub: Revised guidelines for Local Breaker Backup (LBB) Scheme EHV
(765/400/220/132 kV) Lines & ICTs/TFs in MSETCL system.
Ref: 1. Ramakrishna committee report
2. Maloperation of LBB protection during recent occurrences.
Trip Main
CB of dia. &
all CBs of
Tie CB LBB operation_ Half Trip Tie CB bus which
dia arrangement directly
connected to
tie bay.
3.7 Isolation link shall be invariably provided for LBB to BB trip Bus
command and for LBB initiation from Busbar protection to LBB relay
for ease of isolation during testing.
4. Initiation Philosophy
4.1 The LBB initiation contact shall be only of the trip relay utilized for CB
tripping and not from any other separate Contact multiplier relay.
LBB relays should be initiated on a single phase basis from the trip relays
as well as the AR LO relay. This is to achieve phase segregation of the
phases on single phase tripping.
4.3 LBB relay shall initiated by Bus bar protection trip relay(96 T), since failure
of CB to clear a bus fault would result in the loss of entire station if LBB
relay is not initiated. Whenever used in combination with bus bar protection
scheme, tripping logic of the same shall be used for LBB protection also.
4.4 The LBB protection shall not be initiated through non-fault /Alarm Internal
functions of the relay used for LBB protection as well viz LTS Alarm,
LTS Trip, Line overload Alarm, Line overload operated etc. Such Non
Fault/Alarm functions shall be implemented through a separate relay
preferably if the same cannot be achieved in the single relay
Distance Prot
√ √ √
(M1 & M2)
Overload
X X X
LTS/SPS/UVLS
Differential Protection X √ √
REF Protection X √ √
Overflux Protection X X X
ICT/TF LTS/SPS X X X
5.1. During the commissioning of the LBB protection relay the test for phase
segregation initiation & operation confirmation should be carried out to
avoid unwarranted trippings.
5.2. For the Inbuilt Local Breaker Backup protection the LBB initiation shall
be for internal/External protection operation and shall be checked for both
the conditions during commissioning/ Annual Protection testing cycle.
The above guidelines shall come into force with immediate effect &
should be followed scrupulously henceforth.
Also, immediate necessary action for adopting revised
guidelines/philosophy should be taken & compliance thereof be reported
to this office.
Copy to:
The issue was discussed in detail & it was pointed out that tripping of CB was
due to tripping extended through Lockout relay as per scheme. As such it was decided
to bypass the tripping of CB on Lockout condition.
Sub: Standardisation of Tripping & Closing coils for 220kV Circuit Breakers.
Presently, the 220KV Circuit Breakers are being provided / supplied with 110V DC
tripping and closing coils with resistance in series. As the station DC supply at majority of
220KV Sub-station is of 220V DC only, these closing and tripping coils should also be rated
for 220V DC thereby eliminating the need for series resistance. The replacement of faulty
resistors creates problem at later stage, due to non- availability of similar resistor readily at
site.
Members also shared their views in this regard and explained the problems
experiences at site due to utilization of 110V DC closing and tripping coils in 220 KV circuit
breakers.
After detailed discussions on the issue it has been decided that 220 KV class CBs
should be provided with closing and tripping coils rated for 220 V DC only (i. e without
any resistor etc.)
In some specific cases, where 220 KV sub-station are having 110 V DC control supply,
closing and tripping coils rated for 110 V DC would be required.
CE (Tr. PR) to take necessary action accordingly in this regard in future procurement
of 220 KV class CBs.
In line with the CBIP guidelines ( Section 2 of CBIP Publication 274 of Nov 1999),
the enquiry committee into the Grid Disturbance in Western Region of dates 25th & 28th
Feb. 2007 has recommended in its report under item 9-2 (V) that the Main - I and Main - II
protection should be of different make. Further the said issue was came up for discussions
during 98th WRPC PCM held at Raipur on 24-25th Oct. 2007 and the constitutes were
directed to take necessary measures in this regard. This issue was discussed in detail and it
was informed that MSETCL has decided to provide Main - I and Main - II protections
from the same manufacture but operating on different hardware and software
platforms on forthcoming 400KV lines. This has been implemented at 400KV Akola S/s.
Also, if the protection with different principle (i. e. other than Distance principle) is available
with proven performance, then the same can be considered for Main - II protection on future
400KV lines. However, nothing can be done for existing 400KV line protections as the
numerical relays have been installed recently and the same cannot be phased out at this
stage.
The issue of Utilization of auto-reclosing feature on EHV Lines was discussed during
SPC meeting dtd. 28.07.2010. It is informed that in Nagpur zone few 220kV & 132kV Lines,
auto-reclose scheme was taken into service due to which the transient trippings of Lines are
reduced considerably. Further it was observed that most of 400kV/220kV/132kV/100kV
lines tripped on transient fault. To avoid the delay in restoration & to understood the
healthiness of line and to maintain the availability of line, it is necessary to take A/R in
service.
The issue was discussed further and after detailed discussions & deliberations on
various issues, committee recommended that:
1.0. Single phase Auto-reclose scheme should be commissioned on all 220kV Lines
& 132kV/100kV Lines wherever feasible.
2.0. The settings should be adopted same as that of 400kV Lines.
i. e. Dead time= 1 Sec. and Reclaim time = 25 Sec.
3.0. In case of 132kV/100kV double circuit lines, three phase auto reclose scheme
should be commissioned as 132/100KV CB are gang operated.
4.0. In case of 132kV/100kV single redial line / feeders, the 3 phase A/R is to be
taken into service at source end only. At remote end, the under voltage relay is
to be provided to trip the LV side of transformer to avoid the sudden loading
after reclosing the lines at source end so that the transformer get charge after
reclosing at source end.
5.0. The A/R is not to be taken into service for cable feeders or mixed cable plus
overhead feeders / lines where fault are likely to be permanent.
6.0. The AR ON / OFF switch is to be provided.
All S. Es., TCC to take review in their respective jurisdiction and identify the
220kV & 132kV/100kV Lines on which Auto-reclose scheme can be commissioned
and take up commissioning activities immediately.
Sub: Provision of protection trip to Second trip coil of breaker with provision of trip
circuit supervision arrangement at EHV sub-station under MSETCL.
An occurrence took place at 220kV Uran sub-station on 26.03.2012, wherein all the
220kV Lines, ICTs, Transformers connected to 220kV Main Bus-II along with B/C tripped due
to operation of LBB protection. On detailed investigation, it was observed that Y & B pole of
220kV JNPT CB tripped instantly and the R pole did not trip through trip relay but tripped
through PDR subsequently. Further R Pole trip coil used for protection trip found weakened
drawing a heavy current resulting in burning of trip relay contacts, as such fault was cleared
delayed, resulted into operation of LBB protection at GTPS Uran. In this case protection trip
was extended only to trip coil-I.
After detailed discussion on the issue, the committee observed that in most of the
cases the protection trip is not given to both the trip coils available in the breaker. Therefore
in case of failure of this trip coil (due to any elect/mech. Problem) the LBB protection
operates resulting into tripping of complete bus. This happens, however in this case second
trip coil doesn’t get chance to pick up and trip the breaker to avoid LBB operation. The LBB
operation in the above case is unwarranted and can be avoided if the second trip coil is
healthy. As such committee has recommended `extending the protection trip to trip
coil-II (TC-II) also wherever possible with provision of trip circuit supervision
arrangement’.
Sub: Retrofitting of 220kV line back-up relays by state of the art Numerical relays.
The issue of retrofitting of 220kV Line Back-up relays by state of the art Numerical
Relays was discussed by S. E., TCC, Vashi. It was informed that, as per MSETCL connection
agreement and Gazette of India, it is mentioned that “Two main Numerical Distance
Protection shall be provided on transmission line of 220kV & above for all new substation.
For existing substation, it may be implemented in reasonable time frame”.
The issue was discussed in detail. The members opined that, as only one DC source is
available at 220kV substations providing Numerical Distance relay instead of line back up
relay will not make duel redundant scheme. Further, panel replacement may also be required
hence will not be feasible at all the places. Moreover, the work of retrofit of old back-up
relays on EHV Lines by fully numerical back-up relays has been taken-up recently & as such
immediate retrofit may not be required & possible also. Further, this retrofit may not be
economical also.
After detailed discussion and deliberation on the issue committee recommended that:
1.0. In view of recommendations of CEA guidelines and MSETCL connection
agreement, retrofitting of 220kV Line Back-up relays by state of the art
Numerical Relays can be done in Mumbai region and ring main systems in
MSETCL, if required & feasible.
2.0. For new substations decision in this regard can be taken on case to case basis
by projects (Design) Dept.
3.0. For existing substations, all S. E., TCCs to take review in their respective
jurisdictions and if required submit the requirement of Numerical distance
relays for retrofitting of 220kV Line Back-up relays by state of the art
Numerical Relays considering various factors as mentioned above.
S. E. (LD) SLDC, Kalwa informed that the issue of implementation of Under Voltage
Load Shedding Scheme (UVLS) was discussed in the OCCM of WRPC & it was directed to
explore the possibility of implementation of the same in Western Region. This issue was also
discussed in WRPC Protection Committee meeting. It was informed that each SLDC should
identify the areas where UVLS can be envisaged. It was further informed that as per CEA
recommendation the under voltage setting should be 372kV. Further, the quantum of load
should be managed in such a way that, the voltage should boost upto 380kV.
S. E., SLDC, Kalwa informed that the UVLS scheme can be implemented at 400kV
Padghe, Lonikand, Parli, Babhaleshwar & Jejuri Substations. It was informed that the load
trimming schemes for 400/220kV ICTs are already implemented at above-mentioned 400kV
Substations & as such the UVLS can be implemented easily following the same logic by using
under-voltage relays.
After detailed discussion and deliberation on the issue committee recommended that,
the UVLS scheme can be implemented at above mentioned 400kV substations as follows:
1.0. Settings for stage - I UVLS scheme should be 370kV with 5 sec delay.
2.0. Settings for stage – II (if available) UVLS scheme should be 370kV with 10 sec
delay.
3.0. Separate discrete Under Voltage Relays should be provided for implementation
of this scheme.
4.0. Resetting feature should be used as per available setting of Under Voltage
Relay.
Sub: Guidelines for implementation of Load Trimming Scheme (LTS) for ICTs/PTRs in
MSETCL.
Ref: Meeting regarding Review of Load Trimming Schemes held at C.0. on 20.09.2016
1. The Load Trimming Schemes are implemented on various ICTs and Power
Transformers in MSETCL system to avoid the unwarranted tripping in the system
due to sustained/transient overloading of ICTs/Transformers. The data of existing
settings adopted for various ICTs and transformers is collected and studied at
corporate office and it is observed that there is no uniformity in the settings of LTS at
various substations in MSETCL system. For same capacity ICT/Transformers settings
of the LTS scheme implemented varies from substation to substation. Therefore, in
order to use the installed capacity of ICTs & PTRs optimally & to avoid load shedding,
it was decided to have uniformity in the settings of LTS being implemented in
MSETCL. Accordingly, a meeting was held at C.O. on 20.09.2016 for deciding the
policy to be adopted for implementation of LTS schemes in MSETCL. The
following guidelines are finalized for implementation and monitoring of load
trimmings schemes for ICTs/PTRs.
2 Applicability of LTS:-
Load trimming schemes shall be implemented for
1. All ICTs in MSETCL system
2. Power Transformers operating in parallel & carrying load more than 50% of its
rated capacity.
3. All independently run Power Transformer where season’s peak load last was
around 80% of full load capacity.
4. The scheme wiring & logic should be kept in ready condition in respect of all
ICTs & PTRs and scheme shall be taken in service after approval only.
1. Settings to be adopted:
A. Following settings are to be adopted for ICTs:
1. Alarm setting: At 100% loading of ICT's rated Capacity (i.e. Full load current)
with time delay of 1.0 sec,
When load on ICT increases to 100% of its rated capacity, after a time delay of
1 sec, an alarm should be generated.
3. General Preparedness:-
For optimum utilization of rated capacity of PTRs & ICTs, it is essential that 100%
cooling system is operational. The respective substation in charge should ensure this.
For all the locations where the load has reached 80% of full load in the last season,
review of complete availability of cooling system should be taken by concerned SE
EHV (O&M) well in advance.
The event of operation of load trimming scheme should be reported to the concerned Load
Dispatch Centre and the higher authorities at Circle, Zonal and Corporate level by the
concerned field officials.
The above guidelines shall come into force with immediate effect & settings of the existing
LTS may be revised accordingly at the earliest.
Sd/-
Director (Operations)
Copy s. w. rs. to:
The CMD, MSETCL, CO, Mumbai
Copy f. w. cs. to:
The Director (Projects), MSETCL, CO, Mumba
a) Incidents of forced load shedding due to transmission constraints have been observed.
Even load shedding of the order of 2-5 MW is being carried out for short durations
which is not desirable.
The force load shedding could be due to:
l) Transmission constraints such as overloading of Transmission tines & T/Fs/ ICTs.
2) Occurrence based
3) Low voltage
b) In order to avoid forced load shedding due to transmission constraints, following
measures can be taken and these can be classified /grouped as:
1) Immediate (l to 2 days)
2) Short term (6 months)
3) Long term (2 years)
Immediate Measures:
1. In case of load shedding due to overloading of transmission lines, explore the
possibility of loading lines upto its thermal limit with proper monitoring of critical sag
points and thermo-vision scanning of the bays at both ends and at cut points of
transmission lines.
2. Avoid self imposed limits on the line. Margin of safety if required, should be
reasonable and scientific and be annually validated by SE (TCC) & CE by February end.
The conductor can be loaded upto 110% of capacity as indicated in the attached
Annexure for a short duration (upto two hours).
3. In case of load shedding due to overloading of transformers, check the following:
l) Whether T/Fs are operating in parallel or independently and load can be managed
with parallel operation.
2) Explore possibility of loading Power T/Fs upto 105-110% for short duration (upto
2 hours) with proper arrangement of cooling system and monitoring OTI /WTI,
Thermo-scanning of CT, CB and Isolator jumpers of the concerned T/F bay.
3) Explore possibility of shifting of load on 33kV/ 22kV side to nearby/ adjacent EHV
substation in co-ordination with MSEDCL authorities.
4. In case of load shedding due to low voltage, check the following:
l) Whether capacitor banks are in service, if provided.
C. s. w. rs to:
The CMD, MSETCL, C.O, Mumbai
Copy f. w. cs to:
The Director (Projects), MSETCL, CO, Mumbai
Copy to:
1) The C.E. (LD), MSLDC, Kalwa
2) The C.E. (STU), MSETCL, C.O., Mumbai
3) The C.E. (Trans. O&M), MSETCL, C.O., Mumbai
4) The C.E., EHV CC O&M Zone, MSETCL, Amravati/ Aurangabad/ Karad/ Nagpur/
Nashik/ Pune/ Vashi
5) The S.E.(LD) Ambazari, Nagpur
6) The S.E.EHV (O&M) Circle, MSETCL, Amravati/ Aurangabad/ Parali/ Karad/
Kolhapur/ Nashik/ Bhusawal/ Nagpur/ Chandrapur/ HVDC Chandrapur/ Pune/
Solapur/ Kalwa/ Panvel/ HVDC Padhge
7) The S.E., T&C Circle, MSETCL Akola/ Aurangabad/ Karad/ Nagpur/ Nashik /
Pune/Vashi.
ACSR Code Nominal Aluminium Area Current carrying capacity in Amps
Dog 100 291
Wolf 150 405
Panther 200 487
Zebra 420 737
Deer 420 756
Moose 520 836
Morculla 560 862
1.0. Function:
To use the Numerical distance protection relay reverse zone feature as back
up to bus-bar protection in case of failure or non operation of bus bar protection
relay.
5.0. Precaution:
5.1. In case of both numerical distance protections on line/feeder (For
400kV sub-station) _
1. Both Main 1 & 2 relays shall be utilized for two stage reverse zone.
2. The reverse zone stage 1 and stage 2 tripping shall be obtained through
separate contacts from each of the Distance protection relay.
3. It is essential in this case that the reverse zone stage 1 trip should not
initiate the LBB protection for own line breaker.
4. The reverse zone stage-2 tripping shall be extended to LBB trip bus,
through proper isolation links so that faulty bus feeders & ICTs/TFs
isolated simultaneously.
5.2. In case of numerical distance protections & back up IDMT O/C &
E/F on line/feeder (For 220kV & below sub-station) _
1. The reverse zone stage 1 and stage 2 tripping shall be obtained through
separate contacts of Distance protection relay.
2. It is essential in this case that the reverse zone stage 1 trip should not
initiate the LBB protection for own line breaker.
3. The reverse zone stage-2 tripping shall be extended to LBB trip bus,
through proper isolation links so that faulty bus feeders & ICTs/TFs
isolated simultaneously.
The above guidelines shall come into force with immediate effect & should be
followed scrupulously henceforth till further instructions. Also, immediate necessary action
for adopting revised guidelines/philosophy should be taken & compliance thereof be
reported to this office.
Copy to:
Copy s. w. r. to:
Copy to:
The issue of analog triggering of Disturbance Recorders (DRs) as per the enquiry
committee into the Grid Disturbance in Western Region of dated 25th & 28th Feb. 2007 &
adoption of suitable settings thereof was taken up for discussions and obtaining guidelines in
this regard in the WRPC meeting by SE, TCCs. Accordingly the issue was discussed in the SPC
meeting dtd. 15.03.2008 & following decisions have been taken as per discussion in the
WRPC meeting which needs to be implemented.
1.0. It has been decided to provide a setting of 150% of rated voltage for analog
triggering of DRs on over voltage.
2.0. It has been decided to provide a setting of 70% of rated voltage for analog
triggering of DRs on under voltage without any intentional time delay.
3.0. A setting of 150% of rated secondary current is recommended for analog
triggering of DRs on over current feature.
The issue of adopting the overvoltage relay setting as per WRPC guidelines was
discussed in SPC dtd. 15.03.2008. As per WRPC guidelines, the overvoltage stage-II time
delay was set to instantaneous. However SPC members are of opinion that stage-II time delay
to be set to 100msec instead of instantaneous. Further this issue was discussed in WRPC
meeting & agreed to set time delay 100msec. in line with the CBIP guidelines (Section 2 of
CBIP Publication 274 of Nov 1999). Accordingly it was decided to adopt the over-voltage
stage-I time delay setting as per WRPC guidelines & stage –II time delay 100msec instead of
instantaneous.
Sub: Provision of Over-fluxing Relay for 400kV ICTs in MSETCL & adoption of setting
thereof.
The issue of providing the over-fluxing relays for all 400kV ICTs in MSETCL was
discussed in detailed in the SPC dtd. 24.06.2008. Director (Operations) pointed out that the
over fluxing relays are provided for ICTs in PGCIL sub-station & is of opinion that over fluxing
relay shall be provided in MSETCL. Further it was observed that these relays are not
provided for 400kV ICTs (barring few substations) in MSETCL. After detailed discussions on
the issue, it has been decided to provide over-fluxing relay on HV side of all 400kV ICTs
(existing as well as new) with two stage alarm mode in MSETCL system. The settings are to
be adopted as:
Sub: Guidelines for revision of relay setting & remedial measures to be taken to
minimize the incidents of power transformer trippings/failures due to fault on
DISCOM feeder.
The issue of tripping & failure of EHV transformers feeding the distribution network
was discussed during SPC dtd. 18.10.2008. It was pointed out that the incidents of
tripping/failure of power transformers feeding the distribution network are more in spite of
provision of high set relays for distribution feeders. Though the relays are operating
correctly, the CBs are not tripping thereby reflecting the fault on transformer. It was also
informed that this issue is taken-up regularly with DISCOM authorities but no action is taken
by them. It was pointed out that the CBs require more frequent maintenance/replacement as
their operations are unreliable. The issue was discussed at length & following actions
are proposed to minimize the incidents of power transformer trippings/failures due
to fault on DISCOM feeder.
Sub: Pole discrepancy relay (PDR) time setting for EHV feeders.
The 103rd PCM meeting of WRPC held on 12-13 Dec. 2008, has recommended that the
Pole Discrepancy Relay (PDR) timer in respect of CBs controlling EHV lines, Generator,
Transformer/ ICTs where auto reclosure is not provided, should be set to 100 msec. i.e.
less than LBB time setting.
The issue of adoption of this PDR setting in MSETCL was discussed in detail in SPC
meeting dtd. 29.06.2009. After detailed discussions on the issue, it was decided to adopt PDR
timer setting of 100 msec. for CBS controlling Generators, Transformers/ICTs & EHV lines
where A/R is not provided. Whereas the EHV lines with A/R in service, the PDR time
shall be set to 1.5sec.
However during SPC meeting dtd. 17.09.2009, it was informed that at many of the
places, the minimum timer setting available is 500ms & as such, either the timer is required
to be changed or to adopt available minimum setting. After detailed discussions &
deliberations on various issues, the committee recommended that, wherever provision of
100ms is not available, minimum timer setting should be adopted & 2nd trip coil
which is normally used for PDR, should be energized through master trip relay.
Accordingly Scheme to trip C.B. through second trip coil using PDR Aux. relay was
prepared for implementation as under:
1.0. In most of the cases the protection trip is not given to both the trip coils
available in the breaker. Therefore in case of failure of this trip coil (due to any
elect/mech. Problem) the LBB protection operates resulting into tripping of
complete bus. This happens, however in this case second trip coil doesn’t get
chance to pick up and trip the breaker to avoid LBB operation. The LBB
operation in the above case is unwarranted and can be avoided if the second
trip coil is healthy.
2.0. The arrangement of extending trip to second trip coil by using pole
discrepancy Aux. relay is shown in the schematic below. In this arrangement
one ‘NO’ contact is used in series to avoid continuous pick up of P.D aux relay.
3.0. As decided in SPC meeting to adopt PDR timing as 100 msec but this cannot be
achieved in the existing timers of some CB’s. So this scheme can be
implemented to achieve the objective of reducing time to 100 msec.
5.3. Where two trip coils are available to C.B. and one is used for PDR only.
After detailed discussions on the issue, it has been decided to immediately disable
the instantaneous high set E/F relays provided on ICTS at above mentioned substations.
However, the high set O/C protection/relays on HV/LV side should be kept in service
after deciding the proper setting on case to case basis.
The instantaneous high set E/F relays provided on ICTs shall be disabling
immediately.
1.0. The following settings are to be adopted for NDR with immediate effect:
Alarm setting: 12.5V, 1sec.
Trip setting: 30V, 4.5sec.
The above settings are to be adopted wherever possible. In case of static
(IDMT) relays, maximum possible voltage setting with TMS of 0.1 may be
adopted. Else, the above setting can be provided by providing external timer.
"In case of NDR alarm, the on duty In-charge / operator should immediately
carry out the yard inspection particularly that of tertiary delta arrangement of
ICTs & report abnormality Observed, if any, to the concerned authorities.
The Capacitance & Tan Delta measurement of Tertiary bushings to be
done invariably in the month of April every year & later before on-set of
monsoon every year.
*Note: Do not change the NDR setting & PTs at 400kV S/s where no
unwarranted operation of NDR has been reported last year & this year during
the pre monsoon rains.
2.0. Thorough cleaning of 33 KV or 20 kV bus support insulators, PTs, LAs &
Tertiary bushing of ICTs need to be ensured from time to time i.e. whenever an
outage is availed on the ICT, this activity should invariably be carried out. It is
to be ensured that the dust is not accumulated on equipments in delta system
at all, which otherwise may create the problem during subsequent rain.
Sd/-
Chief Engineer (Tr. O&M)
Copy s. w. r. to:
1. The Director (Operations/ Projects), MSETCL, C.O., Mumbai.
2. The Executive Director (Operations/Projects), MSETCL, C.O., Mumbai.
Copy w. cs. to:
1. The Chief Engineer, EHV CC O&M zone, MSETCL, Amravati /Aurangabad/ Karad/
Nagpur /Nasik/Pune/Vashi
2. The Chief Engineer (Tr. Project & Design), MSETCL, C. O., Mumbai
- The guidelines at Sr. No. 5.0 & 7.0 above needs to be considered for all future
project works.
Copy to:
4. The Superintending Engineer, T & C Circle, MSETCL, Akola/Aurangabad/Karad/
Nasik/ Nagpur/Pune/Vashi
5. The Superintending Engineer, Tr. (O&M) Circle, MSETCL, Amravati/Aurangabad/
Bhusawal/Chandrapur/HVDC Chandrapur/HVDC Padghe / Kalwa/ Karad/ Kolhapur
/Nagpur /Nasik/ Panvel/Parli/Pune/ Solapur.
1.0. Ramakrishna Committee had been constituted by CEA for analyzing the causes and
suggesting remedial measures in respect of Grid disturbance dtd. 30th and 31st July
2012 in WR. Ramakrishna committee has recommended for tripping of lines on
detection of power swing in Z – I instantaneously and block the tripping for Z –
II & Z – III permanently. Further, it is stated that, power swings entering Z – I are
generally non-recoverable and power swings entering Zone – II & III are generally
recoverable and hence allow tripping of line if power swing enters in zone-I.
2.0. WRPC has requested all utilities that the recommendations of Ramakrishna
Committee for revision in Power Swing blocking protection philosophy may be
implemented. The issue was discussed in detail in recent SPC meeting held at CO on
30.07.2015. After detailed discussion and deliberation on the issue, members opined
that, the recommendations of Ramakrishna Committee should be followed and
implemented in MSETCL.
The above guidelines shall come into force with immediate effect & should be
followed scrupulously henceforth till further instructions. Also immediate necessary action
for adopting revised philosophy should be taken & Compliance thereof be reported to this
office.
Sd/-
Chief Engineer (Tr. O&M)
Sub: Guidelines for taking remedial action/measures in case of CB `Trip circuit fault’.
1.0. The ‘Trip circuit Faulty’ indication should never be ignored and to be
considered very serious.
2.0. Faulty Annunciator to be replaced on top priority, at local level.
3.0. If `Trip circuit Faulty’ indication appears on any of the feeder then the use of
TBC should be made immediately to isolate the unhealthy breaker.
4.0. If TBC is not available, then use the emergency trip facilities of the Main
unhealthy breaker, provided the SF6/Air/N2 pressure of circuit breaker shall
be is order (as specified by manufacturer or in manual).
5.0. If `Trip circuit Faulty/Lockout’ is due to low SF6/Air/N2 pressure then the
CB should not be tripped through emergency trip facility. In that case the
faulty CB is to be opened /tripped in off peak hrs or night time after isolating
the same from all sources.
6.0. Specific instructions must be made available in all substations to handle the
“Trip circuit Faulty” situations.
Sd/-
Executive Director (Operations)
Copy to:
1. The CE EHV CC O & M Zone, MSETCL, Amravati / A'bad / Karad / Nasik / Nagpur /
Pune / Vashi.
2. The SE T & C Circle, MSETCL, A'bad / Nagpur / Nashik / Pune / Vashi. They are
directed to bring the details available in this regard for 400KV & 220KV class
transformers in their respective jurisdiction during SPC meeting to be held in May
2007.
3. The S.E. EHV (O&M) Circle, MSETCL/ Amravati/ A'bad/ Chandrapur/Karad / Khadka
(Bhusawal) / Kalwa / Nagpur / Nashik / Pune / Parli / Panvel.
4. The S.E. HVDC RS (O&M) Circle, MSETCL, Chandrapur / Padghe.
To,
The Chief Engineer,
EHV CC O&M Zone, MSETCL,
Amravati/Aurangabad/Karad/Nasik/Pune/Vashi
You may be aware that we have recently procured five nos. of state-of-the-art Leakage
Current Monitoring (LCM) test kits from M/s. DOBLE, USA. These kits are available with the
office of respective S.E. T&C Circle under your zone.
These LCM kits are very useful for monitoring and ensuring the healthiness of
Lightning Arrester (LAs.) installed in our EHV substations. This measurement does not
require outage on any feeder and can he performed in live conditions. The LAs are very
critical elements in the switchyard and their healthiness is very important as the
bursting/failure of LAs lead to damage to other adjacent important elements like
transformer bushing. etc. in the switchyard resulting in forced outage of the line or
transformer feeder and thereby reducing availability also.
As such, keeping in view the forthcoming monsoon, it is hereby directed that the
extensive use of LCM kit may be made to ensure the healthiness of LAs installed in various
EHV substations under the control of your Zone. Further, this work needs to be taken up
immediately and completed preferably before the onset of forthcoming monsoon. This will
certainly help us to reduce trippings / occurrences on account of failure of LAs. The work
may be taken up on priority basis at all 400KV S/S and 220/132KV S/S attached to power
stations and certain critical EHV S/S.
It may also be noted that very old LAs (of gap type) or LAs having doubt about the
healthiness should invariably be replaced. A weak, LA is like a live bomb in the switchyard.
Normally healthy (new) LAs have 10 to 150 micro amp leakage current (third harmonic
resistive current.) While of 10 years old LAs have leakage current of 500 micro amp. LAs of
10 years or having 500 micro amp leakages current shall be replaced.
Sd/-
Executive Director (Operations)
Copy s.w.rs.to:
1. The M.D., MSETCL, Mumbai.
2. The Director (Operations), MSETCL, Mumbai.
Copy to:
1. The S.E., T&C, Circle. MSETCL, A’bad/Nasik/Nagpur/ Pune/Vashi.
2. The S.E., EHV (O&M) Circle, MSETCL, Amravati/Aurangabad/ Bhusawal
(Khadka)/Chandrapur/Karad/Kalwa/Nasik/Nagpur/Parli / Pune/ Panvel.
The issue of submission of monthly status on healthiness of DRs and SERs to SLDC
Kalwa for onward submission to WRPC were discussed in detail during SPC dtd. 14.12.2007.
The CE Tr. (O&M) vide letter no. MSETCL/CO/Tr (O&M)/ WRPC/11431 dt.5.11.2007 have
already issued clear cut guidelines in this regard which are to be scrupulously followed by
the concerned authorities. The information is to be submitted on monthly basis by
concerned as per format below:
1. Name of organisation/utility:
2. Name of 400kV sub-station/Generating station:
3. Name & designation of sub-station/generating station In-charge:
4. Address of sub-station:
5. Phone:
6. E-mail ID:
I certify that the above data /information are correct to the best of my knowledge & belief.
Executive Engineer
While taking the stock of substations on maintenance count, it is noticed that a very
Little attention is being paid by the substation staff, concerned EEs and SEs. Due to which key
equipments like Transformers CTs, PTs in substations are failing frequently, affecting the
supply in the regions being supplied by this substation at large. In fact the entire State
barring few places, is reeling under huge load shedding due to power shortage. Such
breakdowns in our system aggravate the situation further.
Failure of 600 MVA, BHEL make, ICT at Kalwa is the recent example of such
negligence. In fact the equipment manufacturers have recommended maintenance schedule
through manuals, but the concerned are not even bothering to go through this. In addition to
this, some latest technology tools in the market are also available which when adopted in the
maintenance practices, give some clues about predictive maintenance. e.g. analysis of results
of online DGA, C and Tan-delta measurement, thermo-vision camera, circuit breaker analyzer
etc.
It has been therefore felt essential once again to lay emphasis on the maintenance
practices which should be followed scrupulously.
The EE EHV (O&M) of each Division shall conduct immediate meeting of all Sub-
station In-charge and critically discuss the following issues in detail so that suggested
measures are taken on war footing basis, in order to ensure the reliable operation of our
system.
1 .Cooling system:-
You are quite aware that, this season huge Ag load is likely to come on our system
because of very good rainfall, thereby our power transformers will be running to its full
capacity giving rise to increased oil and winding temperatures. In order to control oil and
winding temperatures within safe Limits, entire cooling system must be in service
completely i.e. all cooling fans and oil pumps. If you neglect this important aspect then it will
pose danger to the life of power transformer in a way shortening the life. So the substation
In-charge, concerned EE and SE shall ensure the complete functioning of cooling system
during their visit personally.
This year Maharashtra has received adequate rainfall which has resulted in
withdrawing of load shedding in many parts of the state. In this context, it is observed that
many of our EHV transmission lines and transformers/ICTs are loaded substantially. The
tripping/breakdown of any single element is worsening the situation, thus jeopardizing the
system reliability, availability and stability also. The load shedding in some of the groups has
been withdrawn recently. Due to withdrawal of load shedding from some of the groups, the
EHV line/transformer loading will eventually increase considerably and EHV network will be
subjected to maximum loading. This substantial increased loading may result into hot spots
where joints are not intact and subsequently may result in tripping/breakdowns etc. due to
snapping/breakage of conductor, opening of jumper, damage / melting of clamp/connectors
etc.
To avoid such kind of incidents, following actions need to be taken immediately.
1) Identify and list out the overloaded elements i.e. lines, transformers/ICTs and
switchyard equipments in respective jurisdiction. Also, identify critical
lines/transformers. The details of overloaded elements should be sent to C.O.
2) Thermo vision scanning of the switchyard and important/critical and over loaded
lines should be done and appropriate action be taken immediately to attend
identified hot spots.
3) Ensure proper tightening and fitting of all joints/clamp-connectors etc.
4) Ensure healthiness of lines by making use of 'TAURUS" Line Fault Analyzer Kit
whenever opportunity becomes available.
5) Identify and correct sag problems.
6) Ensure complete maintenance of line such as thorough patrolling, monkey
patrolling, tree cutting, replacement of faulty disc insulators etc.
7) In the event of overloading of transformers / ICT's, EHV transmission lines,
possibility of shifting of such load to adjacent substations, EHV lines in order to
give relief to above said scenario may be explored in consultation with DISCOM
and MSLDC, Kalwa.
Sd/-
Director (Operations)
Copy s. w. rs. to:
The CMD, MSETCL, C.O.
Copy to:
1. The E.D. (Operations), MSETCL, C.O.
2. The C.E. EHV CC O&M Zone, MSETCL, Amravati / A'bad / Karad / Nashik / Nagpur /
Pune / Vashi.
A review of EHV equipment failures reveals that the incidents of LA failures are more
in numbers. Lightning Arresters are subject to rigorous duty during monsoon due to
recurring lightning discharges of atmospheric origin. The matter was discussed during O & M
Review Meeting held at C.O. on 31.01.2013 and following guidelines are issued to the field
staff to ensure secure performance of Lightning Arresters during monsoon:
1. Take the LCM of the LAs preferably before the onset of monsoon (i.e. in the m/o May-
June).
2. The defective LAs so detected should be replaced prior to the monsoon.
3. For identifying the LAs that have become weak due to severe lightning strokes during
monsoon, LCM of the LAs should be re-confirmed immediately after the monsoon (i.e.
in the m/o October-November).
4. The defective LAs so detected should be replaced immediately after monsoon.
5. The dates of LCM measurement, the atmospheric / system condition etc should be
incorporated in the failure report of LAs apart from other information such as make,
type, date of commissioning, service life etc. for proper analysis of the LA failure.
Above practice should be followed strictly by all field offices. Necessary instructions
should be issued to the field offices accordingly.
Sd/-
Director (Operations)
To,
1. The C.E., EHV CC (O&M) Zone, MSETCL, Amravati/ Aurangabad / Karad / Nagpur /
Nashik/ Pune/ Vashi.
2. The S.E., EHV (O&M) Circle, MSETCL, Amravati / Aurangabad / Parli/ Karad/
Kolhapur/ Nagpur / Chandrapur/ HVDC Chandrapur/Nashik/Bhusawal/ Pune /
Solapur / Kalwa/ Panvel /HVDC Padghe.
Sub: Guidelines for test frequency of various protection schemes & diagnostic testing
of EHV equipments.
MSETCL has adopted the concept of predictive & proactive maintenance practices
instead of earlier periodic maintenance practices, to maintain the transmission lines & sub-
station equipments in healthy condition. To achieve this, MSETCL has procured & provided
various types of modern & state of the art testing and measuring equipments to our
engineers, so that functionality & healthiness of various EHV equipments & transmission
lines can be monitored from time to time and suitable remedial action can be taken before
any major occurrence takes place.
The issue of formulation of test frequency of various diagnostic testing activities &
protection schemes in respect of EHV equipments was under consideration at CO. The issue
was discussed in detail in SPC meeting held on 05.03.2014 at CO & guidelines for the same
have been circulated along with MOM to field offices. However, during meeting held on
29.04.2014 at CO all SE TCCs requested to make some amendment in guidelines & presented
proper justification for the same. After detailed discussions & deliberation on the various
issues, necessary modifications have been made & test frequency for various diagnostic
testing activities & protection schemes in respect of EHV equipment, their limiting values &
action to be taken has been finalized. A copy of the same is enclosed herewith for reference,
record & further needful action. All Zonal CE, SE, TCCs & SE (O&M) are directed to take
necessary actions accordingly & ensure that these guidelines are followed scrupulously
henceforth from the date of issue of this circular. Sd/-
Director (Operations)
Encl.: As above
Copy to:
1. Executive Director (Operations/Projects) MSETCL, CO, Mumbai
2. The Chief Engineer Tr. (P&D) MSETCL CO, Mumbai
3. The Chief Engineer, EHV O&M Zone, MSETCL, Amravati/Aurangabad/Karad/Nagpur/
Nashik/Pune/Vashi
4. The Superintending Engineer, T & C Circle, MSETCL, Akola/Aurangabad/Karad/
Nasik/ Nagpur/Pune/Vashi
5. The Superintending Engineer, Tr. (O&M) Circle, MSETCL, Amravati/Aurangabad/
Bhusawal/Chandrapur/HVDC Chandrapur/HVDC Padghe/Kalwa/Karad/Kolhapur/
Nagpur/Nasik/Panvel/Parli/Pune/ Solapur.
6. The TA to CMD, MSETCL, CO, Mumbai.
To,
The Chief Engineer,
EHV CC O&M Zone, MSETCL,
Amravati/Aurangabad/Karad/Nagpur/Nasik/Pune/Vashi
Sub: Ensuring healthiness of spare Transformers & ICTs before putting it into
service.
Ref: L. No MSETCL/CO/CE/SE-I/EE-III/10708 Dated 03.09.2014 from C.E., TR. (O&M),
C.O. Mumbai.
In connection with above subject, vide letter cited under reference, it was directed to
ensure availability of two numbers of 25MVA. 132/11 kV OR 25MVA, 132/33 kV Power
Transformers in each zone to meet the emergency situation arising in the event of failure/
problem in the existing in-service Transformers. Moreover, filed offices are keeping Power
Transformers / ICTs as spare on need based basis to meet the emergency situation at any
time. Such Transformers are kept spare either after suitable conversions, repairs or major
overhauling in ready condition so that the same can be utilized as and when required. OFF
late, it is observed that such spare Transformers / ICTs are not getting utilized within
guarantee period & in many cases the guarantee after conversion/repair/overhauling works
gets expired.
As such, when such Transformers / ICTs are put into service after expiry of guarantee
period, the guarantee from repairers cannot be claimed also. Moreover as the Transformers
/ICTs remains unutilized for a prolonged period, its healthiness also becomes
doubtful/suspicious. Hence, whenever such Transformers / ICTs are to be used/put into
service after prolonged period, their healthiness need to be ensured/confirmed, If
required, filtration / testing may be required to be carried out & expenditure incurred
thereon shall be borne by MSETCL as R&M expenditure.
Further, it is directed to explore the possibility of utilization of spare
Transformers/ICTs within guarantee period wherever & whenever possible to avail the
benefit of guarantee period.
Sd/-
Director (Operations)
Copy to:
1. The Chief Engineer, EHV CC O&M Zone, MSETCL, Amravati / Aurangabad /
Karad / Nagpur / Nashik / Pune / Vashi.
2. The S.E. EHV O&M Circle, MSETCL, Amravati/Aurangabad /Parli-Vaijanath /
Karad / Kolhapur / Nagpur / HVDC Chandrapur/Chandrapur / Nashik /
Bhusawal / Pune / Solapur / HVDC Padghe / Kalwa / Panvel.
Sub.: Norms for procurement & availability of various Testing & Measuring
Equipments in MSETCL.
In context to the above subject, it is to mention that C.O. is procuring various Testing
& Measuring equipment required for diagnostic testing as well as periodical
checking/monitoring of healthiness of various sub-stations equipments. No policy/standard
norms were available for procurement & availability of various types of Testing & Measuring
equipment. The equipments are being procured based on requirement received from various
filed offices. Hon. CMD has directed to finalize these norms so as to have uniformity in
availability & placement of such kits in MSETCL. Accordingly, the issue of formation of norms
for procurement & availability of various Testing & Measuring equipments was discussed in
the Standing Protection Committee (SPC) meeting held on dtd. 15/01./201.6 at C.O. After
detailed discussions & deliberations, the norms for the same have been finalized in such
manner that adequate number of Testing & Measuring equipments will be available at
proper location for carrying out regular testing & diagnostic testing works in an efficient
manner. These norms have been approved by Hon" CMD & copy of approved norms is
enclosed herewith for ready reference & further needful action. It is directed to take a note
of this & henceforth ensure availability & placement of this equipment as per norms.
Sd/-
Director (Operations)
Encl: As above
Copy s. w. r. to:
The CMD, MSETCL, CO, Mumbai.
Copy to:
1. The Chief Engineer, EHV O&M Zone, MSETCL, Amravati/Aurangabad/Karad/Nagpur/
Nashik/Pune/Vashi
2. The Chief Engineer Tr. (P&D) MSETCL CO, Mumbai
3. The Chief Engineer, (procurement) Prakeshgad Bandra (E) Mumbai.
4. The Superintending Engineer, T & C Circle, MSETCL, Akola/Aurangabad/Karad/
Nasik/ Nagpur/Pune/Vashi
5. The TA to CMD, MSETCL, CO, Mumbai.
No Change i. e. -
One kit for each 400/220kV One kit for each 400kV S/s
S/s & One kit for each Testing +
9 DC Earth Fault Locator Dn. Further, One kit for One kit for each Testing Dn.
critical EHV S/s attached to +
power station One kit for critical EHV S/s attached to power
station
Tower footing Impedance Measurement One kit for each Transmission Line Maintenance
13 -
kit Sub-Division/Unit
Not Required.
PD Locator with Hot line probe may be beneficial.
18 Partial Discharge Surveyor -
However, demo of the same will be required
before finalization.
It is observed that at a time ICT’s are in Parallel but load sharing by ICT’s is Not
Proportional to their capacities. This is due to the Unequal Impedances of the different make
and Capacities of these ICT’s. This unequal sharing of the load results in underutilization
of ICT’s having more impedances and Overloading of other ICT’s. Sometimes this leads to
Marginal Load Sharing of the same amount which is available in the Underutilized
Transformer.
During s/s max load condition, it is noted that the ICT having low capacity
in comparison reaches full load condition & ICT having highest capacity is under loaded
which may trigger LTS or Overload protection operation although capacity margin is
available. This is not desirable as full load capacities of the highest MVA ICTs are not fully
utilized. To avert the above situation, it is suggested to adjust the OLTC of highest capacity
ICT such that its load sharing is increased thereby reducing the load on other ICT of low
capacity.
Such exercise is successfully carried out at 400 kV BBLR s/s. as detailed in
Annexure-A All SE TCC are directed to check / study in detail & implement the above load
sharing exercise at 400 kV s/s in coordination with O&M and SLDC so that the s/s full load
capacity is effectively utilized & avoid undesirable operation of Overload tripping / LTS
operation.
All field officers are hereby directed to scrupulously follow these guidelines
henceforth. Above circular is available on the employee portal namely ep.mahatransco.in
on company’s website. Sd/-
Director (Operations)
Copy s.w.rs.to:
The CMD, MSETCL, C.O. Mumbai.
Copy f. w. cs to:
The Director (Projects), MSETCL, CO, Mumbai.
Copy to:
1. The CE (PAC) MSETCL, Kalwa
2. The CE (STU) MSETCL, CO, Mumbai
3. The CE (LD) SLDC, Kalwa
4. The CE (Tr. O&M) CO, Mumbai
5. The Chief Engineer, EHV O&M Zone, MSETCL, Amravati/Aurangabad/Karad
/Nagpur/ Nashik/Pune/Vashi
6. The S.E. EHV O&M Circle, MSETCL, Amravati/Aurangabad /Parli-Vaijanath /
Karad / Kolhapur / Nagpur / HVDC Chandrapur/Chandrapur / Nashik /
Bhusawal / Pune / Solapur / HVDC Padghe / Kalwa / Panvel.
7. The SE (LD) ALDC, Ambazari, Nagpur.
At 400 KV Babhaleshwar S/s, there were 3 (Three) ICT’s of 2x315 MVA & 1x500 MVA. Before
commissioning of 4th ICT the Percentage Impedances of these ICT’s were mismatching
and that was resulting in Unequal Sharing of Load. Among the Three ICTs, ICT no. 1 was
reaching to its threshold (Full Load Capacity) early and the operation staff was resorting to
load shedding of 50 MW. However, 50 MW margin was available in the Third ICT of 500 MVA.
As the ICTs were in Parallel it was not possible to extract that 50 MW from Third
Underutilized ICT. With the help of Tap Changers this mismatching impedances of ICTs can
be corrected to certain extent and Load sharing can be adjusted to best Utilize the Optimum
Capacity of the ICT’s or T/f’s.
2. Case – 2: After Matching T/F Loading with Changing Tap of ICT-3 by 3 taps :
T1 = 421 A
T2 = 397 A Total = 1494 A
T3 = 676 A
Load balancing with OLTC Created Margin of 105 A
The same exercise can be done at 220 & 132 kV s/s where such mismatching in
Capacity & % Z of ICT/ Power transformers exists to avert undesirable tripping/load
shedding.
This is with reference to above subject. The CE (Tr. O&M), C.O., Mumbai vide above
informed that the disturbance are to be reported to SLDC / WRLDC in time. However
substantial time delay has been noticed while reporting of events, interruption or
disturbance to SLDC/WRLDC, which is not desirable. As such the mechanism for reporting
the disturbance events has been setup by CE (LD), so that each and every occurrence /
tripping can be reported to SLDC/WRLDC & CE PAC, as per sequence & schedule as
mentioned below:
As per the State Grid Code, Section 29.2.3, it is the responsibility of transmission
utility to provide the written report within two (2) weeks of the occurrence of the
event to SLDC / RLDC. The Superintending Engineer Testing & Communication Circle
has to submit the detailed report to SLDC / WRLDC / CE PAC (e-mail id:
cesldc@mahasldc.in / protectionwrldc@posoco.com / cepacmsetcl@gmail.com /
seprotectionmsetcl@gmail.com) within one week as per Standard major occurrence
analysis Report format.
You are therefore requested to submit the detailed tripping / event / occurrence
report invariably as per above to the SLDC / WRLDC & CE PAC on regular basis. The
Preliminary & Standard major occurrence analysis report format is enclosed herewith.
To,
1. The Superintending Engineer,
T&C, Circle, Akola/Aurangabad/Karad/Nagpur/Nashik/ Pune/ Vashi.
12. Load/Power loss due to operation of Load Trimming Scheme (LTS)/Special Protection
Scheme (SPS)/Under Voltage Load Trimming Scheme (UVLS).
a) Please specify whether existing Load trimming /SPS/ UVLS schemes if any, are serving
intended purpose.
b) Please specify whether load trimming scheme or special protection scheme operated as
desired or Nonoperation/maloperation, any modifications in LTS/SPS required.
c) Please specify Settings adopted for LTS/SPS/UVLS & revision required, if any.
16. System data including soft copies of DRs (in Comtrade format _ cfg & dat file, of both end in
case of line), Event Logger (EL) log and relevant data related to occurrence of SMS, SAS &
SCADA. :
19. Diagnostic test records of Equipments/lines including recent ones in soft. Past trends of
diagnostic testing results if results are alarming along with action taken or proposed.
22. Remedial Measures suggested & action taken in order to avoid recurrence.
Sub: Incidence of tripping of 400kV lines & ICTs/TFs on account of human error,
lapses, lack of adequate care while working in C&R panels etc.
It is noticed that the incidents of tripping of 400KV lines and ICTs / Transformer on
account of human error, lapses, lack of adequate care while working in C & R panels etc., have
increased considerably in recent time. During this month, following three such occurrences
took place, which could have been avoided, had proper precaution and care been taken while
working.
(i) Tripping of 400KV Aurangabad - Bhusawal Circuit while attending PLCC
Problems at Aurangabad end.
(ii) Tripping of 400KV Kalwa - Padghe Circuit while carrying out cable dressing
work in the RP at Kalwa end.
(iii) Tripping of 400KV Kolhapur-Karad Circuit - Il while assigning relay setting at
Kolhapur end.
Such incidents are highly undesirable as it leads to unnecessary interruptions which
could be dangerous sometimes as it hampers system stability, security and reliability.
Also, tripping of heavily loaded lines on account of such mistakes may invite a major
disturbance / occurrence. It is; therefore, felt that due care and proper precautions should be
taken particularly while working in C & R panels, PLCC panels etc. Such important and
sensitive works should always be carried out under strict supervision of expert testing /
telecom engineers.
It is, therefore, requested to instruct concerned Testing & Telecom Divisions,
Testing/Telecom/Sub-Divisions/Units under your jurisdiction to avoid casual approach
while working in live panels and take extreme care and precautions to avoid inadvertent
trippings of lines / ICTs, Transformers etc.
These instructions should be followed scrupulously with immediate effect.
Sd/-
Executive Director (Operations)
To:
The Chief Engineer, EHV CC (O&M) Zone, MSETCL, Amravati/Aurangabad / Karad /
Nashik / Nagpur/Pune /Vashi.
Copy s. w. rs. to:
The Director (Operations), MSETCL, C.O., Mumbai.
Copy to:
The S.E., T&C, Circle. MSETCL, Akola/Aurangabad/Karad/Nashik/Nagpur/
Pune/Vashi.
OFFICE OF CHIEF ENGINEER (PAC) CO AIROLI 99
SPC_09.02.2011
1.0. Proper Vermin proofing of all C & R panels should be ensured at all EHV S/S to
avoid such occurrences in future.
2.0. O&M staff should ensure that the doors/covers etc. of all C & R panels are
intact & properly closed.
3.0. Regular check should be done to ensure compliance of above
recommendations.
Sub: Non operation of 400kV bus-bar protection scheme at 400kV Jejuri s/s _
necessary precaution to be taken thereof.
Ref: T. O. L. No. MSETCL/CO/CE (PAC)/MO/510 dtd. 21.06.2017
This is with reference to above subject. On 01.06.2017, B-ph string insulator of 400kV
Main bus-I flashover at 400kV Jejuri sub-station, creating bus fault in the system. However
the 400kV bus-bar protection scheme RADSS, ABB make failed to operate resulted into
failure of total power supply. The one & half CB bus arrangement is provided at 400kV Jejuri
sub-station. After detailed checking & testing of non operation of bus bar, it was observed the
shorting of the CT terminals of the under construction bay at the terminal blocks with
disconnecting type of terminal through, resulted in the shorting of primary of the aux. CT of
all three phases with the ground which in turn provided an alternate low impedance path to
the fault current therefore resulting in non operation of the relay. In view of this non
operation of bus bar, it is imperative to take necessary precautions viz. shorting of CT
terminal blocks towards the yard side & dropping of disconnecting type link for the single
bus & one and half breaker arrangement with no CT switching arrangement for any
spare/under construction bay in bus bar panels to avoid the non operation of bus bar
protection schemes in future.
In view of the above, it is requested to pass on or circulate the necessary instruction to
field in order so as to avoid the non operation of bus bar protection in future.
To,
1. The Superintending Engineer,
T&C, Circle, Akola/Aurangabad/Karad/Nagpur/Nashik/ Pune/ Vashi.