Method Statement

20/11/2019
– Conveyor & Fence

dismantling on the
platform
– Cable tagging &

removing of
depalletizer

21/11/2019
– Overhead conveyor to

be dismantled inside
corridor (for
barrication curtains
will be provided by
AATCO JEDDAH )
– Cable tagging &

removing of
depalletizer

23/11/2019
– Dismantling the

structures & suction


beam of depalletizer
– Overhead conveyor to

be dismantled inside
corridor & production
area
– Cable tagging &
removing of
depalletizer

24/11/2019
– Dismantling the

structures & robotic


beam of depalletizer
– Transporting of the

structures & suction


beam of palletizer
– Dismantling & also

start to install
overhead conveyor
inside production
area
– Cable removing from

the over head


conveyor
– Marking of the

depalletizer &
platform in new
location

25/11/2019
– installation of

overhead conveyor
inside production
area
– Electrical cable
installation of
overhead conveyor
– Installation or
plumbing of main
compressed air line
( if it is our scope to
provide the line till
machine on our own )
– Marking of the
depalletizer &
platform in new
location
– planning to lift the
structure and the
robotic beam
– Transporting all
materials to new
location

26/11/2019
– lifting of the structure

& robotic beam for


suction
– Installation of over

head conveyor &


cabling
– Installation or

plumbing of main
compressed air line
( if it is our scope to
provide the line till
machine on our own )

27/11/2019
– Alignment &

Installation of the
depalletizer &
platform
– Installation of over

head conveyor &


cabling

28/11/2019
– Installation of the

depalletizer &
platform
– Cabling for the

depalletizer

30/12/2019 , 1/12/2019 &


2/12/2019
– installation of the

depalletizer &
platform
– Platform modification

if needed
– Cabling and sensor
installation

3/12/2019, 4/12/2019 ,
5/12/2019, 6/12/2019
– connection of cables

inside panel
– Testing &

Commissioning

CIVIL SUPPORT NEEDED


1. Clear access for the
structure
transportation as
discussed, before
23/11/2019 end of the
day.
2. Access in new
location according to
the drawing before
24/11/2019 ( new
plan )
3. Opening in the
sandwich panel for
the conveyor and
platform once it is
marked by NAW team
( can be marked only
once the depalletizer
is placed )
List of equipments
needed
● Aluminum scaffolding
to be provided at site
ASAP
● 1 Pallet trolley needed
at site starting from
23/11/2019 till
2/12/2019 & one extra
when required
● 10 TON crane needed
at site on 24/11/2019
( contact & discuss
before ordering)
● 1 forklift with the
operator to be
provided at site
starting from
23/11/2019 till
30/11/2019 and one
extra when required
● 3 TON Trailer to be at
site the same day as
the crane arrival
( also confirm or
discuss before
booking )