Method Statement
Method Statement
Method Statement
20/11/2019
– Conveyor & Fence
dismantling on the
platform
– Cable tagging &
removing of
depalletizer
21/11/2019
– Overhead conveyor to
be dismantled inside
corridor (for
barrication curtains
will be provided by
AATCO JEDDAH )
– Cable tagging &
removing of
depalletizer
23/11/2019
– Dismantling the
be dismantled inside
corridor & production
area
– Cable tagging &
removing of
depalletizer
24/11/2019
– Dismantling the
start to install
overhead conveyor
inside production
area
– Cable removing from
depalletizer &
platform in new
location
25/11/2019
– installation of
overhead conveyor
inside production
area
– Electrical cable
installation of
overhead conveyor
– Installation or
plumbing of main
compressed air line
( if it is our scope to
provide the line till
machine on our own )
– Marking of the
depalletizer &
platform in new
location
– planning to lift the
structure and the
robotic beam
– Transporting all
materials to new
location
26/11/2019
– lifting of the structure
plumbing of main
compressed air line
( if it is our scope to
provide the line till
machine on our own )
27/11/2019
– Alignment &
Installation of the
depalletizer &
platform
– Installation of over
28/11/2019
– Installation of the
depalletizer &
platform
– Cabling for the
depalletizer
depalletizer &
platform
– Platform modification
if needed
– Cabling and sensor
installation
3/12/2019, 4/12/2019 ,
5/12/2019, 6/12/2019
– connection of cables
inside panel
– Testing &
Commissioning