Slides From Day 2
Slides From Day 2
Slides From Day 2
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Based on AXELOS PRINCE2® material. Material is reproduces under licence from AXELOS. All rights reserved.
Purpose and definition
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 2
The three project interests
.
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS. All rights reserved. (Figure 7.1 Managing Successful Projects with PRINCE2® version 1 p. 59)
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 3
The four management levels
Day-to-day management,
refers to Project board and
manages Team managers.
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS. All rights reserved. (Figure 7.2 Managing Successful Projects with PRINCE2® version 1 p. 60)
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 4
Project management team roles
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS. All rights reserved. (Figure 7.3 Managing Successful Projects with PRINCE2® version 1 p. 63)
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 5
The Project board
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 6
The Executive
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 7
The Senior user
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 8
The Senior supplier
• This role is responsible for the quality of the products supplied by the
supplier.
• This role often ensures subsequent operation and maintenance (unless
an external supplier supplies the product to a customer, who then will take care of
maintenance himself)
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 9
Project assurance
• The Project board is responsible, via its project assurance role, for
monitoring the project's performance and products. The role is called
Project assurance.
• Project assurance are responsible for aspects within the 3 respective
areas of concern – business, user and supplier
• If they have neither the time nor the right competence, they may
nominate others to carry out tasks. But Project board will always be
responsible.
• The Project assurance monitors the project independently of the
Project manager. However, the Project manager can get support,
advise and guidance from Project assurance
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 10
Change authority
• The Project board is responsible for approving any potential change before
it is implemented
• It may be appropriate for the Project board to delegate all or some og
these decisions to a Change authority.
• Before leaving the initiation stage, it must be decided who can take
decision regarding request for change
• Depending on their importance, requests for changes may be dealt with
by:
• Corporate, programme management or costumer
• Project board itself
• A Change authority
• The Project manager
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 11
The Project manager
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 12
The Team manager
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 13
Project support
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 14
More on the organization theme
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 15
Tailoring the organization theme
• Minimum requirements;
• Define structure and roles. All roles must be represented but can be
combined (supports “defined roles and responsibilities” principle)
• Ensure that the organizational structure is suitable for the size, scale
and complexity of the project.
• Managing Successful Programmes (MSP) describes the connection
between programme and project
• In a commercial environment, primary consideration should be given
to the choice of Project manager and Senior supplier.
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 16
Progress
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Based on AXELOS PRINCE2® material. Material is reproduces under licence from AXELOS. All rights reserved.
Purpose and definition
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
*Font denotes source Managing successful Projects with PRINCE2® 2017 edition.
Page 18
Tolerances
Tolerance Project Stage Work package Product
areas level level level level
Benefits
Defining target benefits Business Case
Time
+/- Time on target
completion dates
Project plan Stage plan Work package
Cost
+/- amounts of planned
budget
Project plan Stage plan Work package
Risk Risk
Limit on the aggregated
value of threats Management
approach
Scope
Permitted variation of
the scope of a project
solution Project plan Stage plan Work package
Quality Project
Defining quality targets Product
in terms of ranges product
descriptions
description .
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS. All rights reserved. (Table 12.1 Managing Successful Projects with PRINCE2® version 1 p. 149)
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 19
Exceptions
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 20
Management Levels and Progress
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS. All rights reserved. (Figure 12.1 Managing Successful Projects with PRINCE2® version 1 p. 150)
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 22
Baselines
• Project Plan
• Stage Plans
• Exception Plan
• Work Packages
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 23
Reviewing progress
• Daily log
• Issue register
• Product status account
• Quality register
• Risk register
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 24
Lessons and Progress reporting
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 25
Tailoring the progress theme
• Minimum requirements;
• Define approach to controlling progress in PID
• Manage by stage (supports principle)
• Set tolerances (supports “manage by exception” principle)
• Review business justification when exceptions are raised (supports
“continued business justification” principle)
PRINCE2® is a registered trade mark of AXELOS Limited. Used under permission of AXELOS Limited. All rights reserved.
Page 26