Sitxwhs006 - Appendix A
Sitxwhs006 - Appendix A
Sitxwhs006 - Appendix A
Date:
Assessment task:
Implementation
Activity/ Person
Hazards
Affected Potential risks
(describe the hazard and location) Risk Risk control measure
(work activity or job (describe consequences and
Score (based on Hierarchy of Controls) Action by Due Date
role associated with impacts of the risk)
hazard)
Implementation
Activity/ Person
Hazards
Affected Potential risks
(describe the hazard and location) Risk Risk control measure
(work activity or job (describe consequences and
Score (based on Hierarchy of Controls) Action by Due Date
role associated with impacts of the risk)
hazard)
Likelihood
Severity The numbers 1 to 6 in the chart indicate the level
Very likely Likely Unlikely Very unlikely of risk.
Fatal 1 1 2 3 1 to 2 = High (take action immediately)
3 to 4 = Medium (take action as soon as
Critical 1 1 2 3 possible)
5 to 6 = Low (may not need to take action)
Major 1 2 3 4
Minor 2 3 4 5
Negligible 3 4 5 6