Formulas
Formulas
Formulas
FORMUL
NAME TERMS SOLUTION EDGE SAMPLE QUESTION
A
AREA
beta is the
O is the most common
optimistic estimation
estimate formula, as it is
more exact.
M is the Additionally,
most this could also
likely be referred to
estimate as weighted
estimation.
P is the
pessimist
ic
estimate.
P is the
pessimist
ic
estimate.
Standard (P-O)/6 P is the This formula Time 4. If the task has an optimistic
Deviation pessimist helps you Manage estimate of 7 days and a
ic determine the ment pessimistic estimate of 15 days,
estimate possible range what is the standard deviation
an activity of the task?
O is the could take.
Once you
KNOWL
FORMUL
NAME TERMS SOLUTION EDGE SAMPLE QUESTION
A
AREA
d to a date.
certain
point in a If CV 0, the
project project is within
budget
AC is the
actual In the simplest
cost, or of terms, if CV
the 0, things are
actual good!
amount
spent to
a certain
point in a
project.
PV is
planned
KNOWL
FORMUL
NAME TERMS SOLUTION EDGE SAMPLE QUESTION
A
AREA
value, or
the
budgeted
value of
the work
at a
certain
point in a
project.
Estimate 1. AC + AC is the EAC, or Cost Let’s test if you can pick the
at Bottoms - actual estimate at Manage right formula with these two
Completio up ETC cost, or completion ment examples:
n (EAC) the helps you
actual determine from 9. In your current project the
(There are 2. amount this date planned value is 400, earned
four BAC/CPI spent to forward how value is 350, and actual cost is
variations a certain much you can 450. Based on the work effort
of this point in a expect the needed to date the team
formula 3. AC + project. project to cost determined the original $1000
based on (BAC - at completion. estimate is no longer valid. A
what the EV) EV is The word “at” reestimate of the remaining
question earned is very tasks is 750. What is the current
KNOWL
FORMUL
NAME TERMS SOLUTION EDGE SAMPLE QUESTION
A
AREA
to used if the
complete project is on
. target, tracking
to the budget
BAC is at completion
budget at and there are
completi no variations in
on, or rate of
what was spending
budgeted expected.
for the Formula 3 is
entire used when
project at there have
completi been atypical
on. differences in
the actual cost
CPI is of the project,
the cost but those
performa differences are
nce believed to be
index, or corrected and
the the remaining
evaluatio expenditures
n of work should be
KNOWL
FORMUL
NAME TERMS SOLUTION EDGE SAMPLE QUESTION
A
AREA
(BAC- AC is the TCPI, or to- Cost 11. The project was originally
To- EV)/(BAC actual complete Manage budgeted to spend $2,000. At
Complete -AC) cost, or performance ment this point your actual cost is
Performan the index helps 1,500 and 1,200 worth of work
ce Index actual you is complete. What is the TCPI
(TCPI) amount understand for the project?
spent to what pace the
a certain remaining
point in a tasks must be
project. completed to
keep the
EV is project within
earned budget.
value, or
the TCPI 1, the
actual project does
value of not need to
the work change speed
complete to complete
d to a within budget.
certain
point in a In the simplest
project. terms, TCPI 1
KNOWL
FORMUL
NAME TERMS SOLUTION EDGE SAMPLE QUESTION
A
AREA
Estimate EAC - AC EAC, or ETC, or Cost 12. Your project, with a budget
to estimate estimate to Manage at completion of $1,500,
Complete Reestimat at complete helps ment currently has a planned value of
(ETC) e completi you 400, earned value of 350, and
on helps understand the actual cost of 450. The current
There are you cost remaining work and all variances to date
two ways determin to complete the are expected to continue; based
to find e from project. on this, what is the estimate to
ETC this date complete the project?
forward
how
KNOWL
FORMUL
NAME TERMS SOLUTION EDGE SAMPLE QUESTION
A
AREA
much the
project is
expected
to cost at
completi
on.
AC is the
actual
cost, or
the
actual
amount
spent to
a certain
point in a
project.
Reestima
te,
means
just what
the name
implies,
KNOWL
FORMUL
NAME TERMS SOLUTION EDGE SAMPLE QUESTION
A
AREA
use the
same
strategie
s that
you used
during
project
planning
to
reestimat
e the
cost of
the work
remainin
g.
Variance BAC - BAC is VAC, variance Cost 13. Your project, with a budget
at EAC budget at at completion Managm at completion of $1,500,
Completio completi is the ent currently has a planned value of
n (VAC) on, or difference in 400, earned value of 350, and
what was what the actual cost of 450. The current
budgeted budgeted cost work and all variances to date
for the of the project are expected to continue; based
KNOWL
FORMUL
NAME TERMS SOLUTION EDGE SAMPLE QUESTION
A
AREA