Bulletin673 Cavity Battens
Bulletin673 Cavity Battens
Bulletin673 Cavity Battens
CAVITY BATTENS
Cavity battens are a key component This bulletin gives guidance about The bulletin includes updated
June 2022
of drained and vented wall cavities the selection and installation of content from Bulletin 582
and play a vital role in building cavity battens in external walls, Structurally fixed cavity battens and
weathertightness and durability. considering Acceptable Solution E2/ replaces that publication.
AS1 and Alternative Solutions.
1 INTRODUCTION
1.0.1 Drained and vented cavities are an important
element of weathertight construction, especially in
higher-risk buildings. Rather than wall claddings being
fixed directly to the wall framing, they are fixed to a
batten, providing an air cavity behind the cladding
(Figure 1). Cavities under Acceptable Solution E2/AS1
can be continuous up to 2 storeys.
1.0.2 Any water that does get through gaps around the
cladding can drain down the back of the cladding and
out of the bottom of the wall assembly. Air movement in
the cavity allows the wall assembly to dry out.
An excessive number of battens that will impact drainage and
1.0.3 Cavity cladding construction under E2/AS1 is drying in the wall cavity.
a back-up mechanism only. Buildings must still be
designed and constructed to keep water on the outside,
where it drains down the face of the building envelope. of moderating the air pressure around a building and in
the wall assembly.
1.0.4 While cavity construction has been around for
many years, building surveyors say they see many cases 2.0.2 What the 4Ds mean:
of poor installation of cavity battens (see photograph). ∫ Water is first deflected off the exterior surface of the
If battens are not installed properly, they can restrict building (Figure 1). The cladding itself and flashings
drainage and air circulation, trapping moisture behind deflect water away, especially from critical junctions.
the cladding. This can lead to corrosion, mould or even ∫ Wall assemblies in higher-risk situations must be
rot in the wall assembly. designed and built to incorporate drainage to allow
water that may have penetrated gaps in the exterior
1.0.5 Problems reported include: cladding to drain down the back of the wall cladding to
∫ far too many battens on a wall, both vertical and the outside.
horizontal ∫ Ventilation behind the wall cladding allows air
∫ multiple battens placed over studs at the sides of movement for drying out moisture absorbed by
exterior openings with no gap to allow them to dry out components of the exterior wall assembly. Removing
∫ two or three horizontal castellated battens installed at excess water vapour helps prevent corrosion, timber
floor joist lines or onto window lintels decay and mould growth in external walls.
∫ castellated battens placed together, obstructing or ∫ All components of a cladding and wall assembly must
blocking the castellations (notches) meet the durability requirements of the Building Code.
∫ short horizontal battens (cavity spacers) not fixed on
a slope and abutting vertical battens at the ends. 2.0.3 Vented cavities also help to moderate or equalise
air pressure differences. Wind impacting on a façade
1.0.6 Acceptable Solution E2/AS1 sets out one approach creates a pressure difference across the assembly. If
for constructing a drained and ventilated cavity and there are any gaps in the building envelope, air can be
demonstrating compliance with the Building Code. The drawn through, potentially carrying moisture with it.
use of E2/AS1 is not mandatory, however, and alternative The use of a vented cavity helps to minimise/moderate
methods (which become Alternative Solutions once the pressure difference across the cladding, with a
consented) can also be used. greater proportion of the pressure difference supported
across the underlay and internal lining. This results in
1.0.7 This bulletin explains the role of cavity battens the air pressure behind the cladding being as close as
as a component of drained and vented cavity wall possible to the air pressure on the exterior surface. The
construction and how they should be installed. It outcome of this moderation is that cavities help reduce
includes the updated content of bulletin 582 Structurally the potential for wind-driven water penetration through
fixed cavity battens and replaces that bulletin. It gaps in the wall claddings at joints and junctions.
does not cover the cavity behind masonry veneer wall
claddings. 2.0.4 A perforated cavity closer along the base of the
cavity, which may be uPVC, aluminium, stainless steel
1.0.8 The design and installation of wall claddings or a similar durable material, allows free drainage and
(including the construction of cavities with battens) in ventilation of cavities while keeping vermin out. The
residential low-rise buildings is restricted building work cavity must be designed and constructed so that, in
and must be carried out or supervised by a licensed buildings with suspended floors, subfloor air/moisture
building practitioner. cannot enter the cavity. Similarly, moist air from wall
cavities must not be able to enter the roof space.
2 THE ROLE OF CAVITY BATTENS
2.0.5 You can read more on cavities on the BRANZ
2.0.1 Ensuring that a wall cladding remains weathertight website www.weathertight.org.nz, especially the
requires an understanding of the 4Ds – deflection, page www.weathertight.org.nz/new-buildings/basic-
drainage, drying and durability – and also the importance weathertight-design-principles.
external drainage
path (primary) on
face of cladding
drainage path
(tertiary) face of
underlay
cavity closer
3 THE BUILDING CODE AND E2/AS1 3.0.5 Where a horizontal batten is needed to fix the top
or bottom edge of sheet cladding, a cavity spacer (a short
3.0.1 Two key Building Code clauses that relate to cavity length of batten) on a minimum 5° slope is installed. There
wall construction are B2 Durability and E2 External must be a minimum 50 mm gap between each end of
moisture. the spacer and the vertical battens to allow drainage and
ventilation (Figure 2).
3.0.2 Clause B2 sets out specific periods over which
different building elements must continue to satisfy 3.0.6 To maximise the drainage and drying capacity of
performance requirements with only normal maintenance. the cavity, install no more battens than are required to
Wall claddings and cavity battens must be durable for support the cladding. Too many battens will reduce the
a minimum of 15 years. Be aware, however, that clause effectiveness of the cavity. Where battens are required side
B2.3.2 requires that, in practical terms, anything that is by side, they should be separated with a gap between them.
concealed must have the same durability as the item that
is concealing it. If wall cladding is expected to last 50 years, 3.0.7 Where battens are not structurally fixed (see section
the battens behind it must also last 50 years. 6 below) they only need to be tacked in place – they will be
permanently fixed by the cladding fixings driven through
3.0.3 Clause E2 states that building exteriors must prevent them into the wall framing.
the penetration and accumulation of water. It recognises
that, in some situations, water may penetrate the building 3.0.8 BRANZ research shows that just having vents at the
exterior and requires that the building be designed to allow bottom of the cavity provides sufficient ventilation drying,
water to dissipate that could otherwise cause damage to and this is the solution shown in E2/AS1 as Figure 8A(b).
components or undue dampness. It shows a solid horizontal batten along the top of the wall
cavity, which restricts cavity air from reaching the roof
3.0.4 In Acceptable Solution E2/AS1, buildings in higher-risk space – an important consideration. It should be noted that
situations for weathertightness must incorporate a cavity E2/AS1 paragraph 9.1.8.1 states: “This Acceptable Solution
between the cladding and the wall underlay and timber is limited to systems where … c) The drained cavity behind
framing. (Table 3 in E2/AS1 sets out where claddings can be claddings, except in masonry veneer, is not vented at the
direct-fixed or must be over a cavity, depending on the risk top.”
score and the cladding type.) The construction of drained
cavities is set out in sections 9.1.8 to 9.1.9.4. Battens are 3.0.9 BRANZ research has also demonstrated that top
installed vertically over the studs, giving a nominal 20 mm ventilation can significantly increase drying potential
deep cavity behind the cladding (E2/AS1 states limits of and provide redundancy should the lower vents become
18 mm and 25 mm). Deeper cavity gaps, though generally restricted. If you opt to ventilate the top of the cavity to
beneficial, would be consented as an Alternative Solution. increase the amount of ventilation behind the cladding and
Vertical battens should extend the full height of the cavity – provide more drying capability and therefore do not install
it is acceptable if several pieces are joined. a horizontal batten along the top, it would be consented as
wall underlay 7.0.3 Wall claddings fixed to light steel framing must
have thermal breaks. The Acceptable Solution only
applies to construction where wall claddings are fixed
through the cavity battens and thermal break into the
wall framing.
20 mm
minimum 7.0.4 Like E2/AS1, the Acceptable Solution for light steel
weatherboard framing only covers vertically fixed cavity battens but
fixing
penetration bevel-back makes provision for cavity spacers for fixing between
weatherboards battens. The requirements are the same as those shown
in Figure 2 in this bulletin.
cavity batten
7.0.5 Cavity battens with light steel framing must be:
∫ a nominal 20 mm thick (between 18–25 mm)
∫ a minimum of 45 mm wide
∫ if timber, in compliance with B2/AS1 (LOSP-treated
timber battens must be separated from any
polystyrene thermal break with a wall underlay or DPC)
∫ if polystyrene, in compliance with either 9.9.3.1 (a) or
75 x 3.15 mm 9.9.3.1 (b) and be protected from any incompatible
jolthead hot-dip materials (such as LOSP-treated timber).
galvanised nail
7.0.6 There are also proprietary solutions such as plastic
timber frame fluted battens that can be used with steel framing.
BRANZ
Calls cost $1.99 per minute plus GST. Children please ask your parents first.
2537-7310 (Online)
Copyright © BRANZ 2022. No part of this publication may be photocopied or
otherwise reproduced without the prior permission in writing from BRANZ.