PIpe Design
PIpe Design
HANDBOOK
FOR
SASKATCHEWAN
UNIT SIX ( VI ) -
TECHNICAL DESIGN
& OPERATIONAL GUIDE April 2009
UNIT VI – Technical Design & Operational Guide VI – 2
Assuming that the existing pipeline has enough flow to accommodate its needs and also
to supply the quantity of water needed for the new pipeline, pressure requirements still
have to be considered. In some situations a booster station may be required, or it may
be possible to twin sections along the existing pipeline to boost the flow and pressure to
meet the demands of the new line.
Supply line connection points that use below ground metering vaults or manholes are
not recommended because of the problems associated with below ground systems
such as potential flooding and cross contamination, confined space protocol, and
inability to add post chlorination equipment. A preferred method of connecting to a
supply line is to erect a building that will house the water meter, backflow protection
device, isolation valve and any other equipment that may be required. Accessibility is
an important issue and should be considered so that water quality and volumes can be
monitored and water samples can be easily extracted for analysis. Also, a pumphouse
UNIT VI – Technical Design & Operational Guide VI – 6
will allow the municipality a suitable site to check the current demand on the distribution
system versus the total future water demand including the new pipeline.
2.2 Wells
New and existing wells can also be used to provide a source of water for rural pipelines.
Unlike purchasing treated water from an existing supply line, the cost of the raw water is
minimal. The real cost however, will depend on what is required to find and develop the
water supply and the operational costs incurred to maintain acceptable quality
standards. If a well is chosen as the proposed water source, steps need to be taken to
determine if the well is of acceptable quality and capacity and whether it could be
developed as a source for the rural pipeline. Generally this would consist of extensive
water quality testing and also pump testing to determine the sustainable yield. As with
any water source, appropriate approvals and agreements need to be in place prior to
the development of the source. (See Unit V - Section 2.2).
River and lake intakes are only one of the hurdles that need to be overcome when using
surface water. Many challenges exist in the treatment of surface water as the quality of
the raw water is always changing. Each season presents new problems for the
operators.
UNIT VI – Technical Design & Operational Guide VI – 7
All PVC pipes that are used for rural water pipeline applications must be certified
suitable for potable water by the CSA testing Laboratory, and conform to the
requirements of CSA:B137.3-M1990.
Rigid PVC small diameter pipe of nominal diameter of 100 mm (4 in) or greater must be
manufactured in accordance with the latest edition of CSA B137.3 Rigid Polyvinyl
Chloride (PVC) Pipe for Pressure Applications, and also the latest standards issued by
the American Water and Wastewater Association (AWWA) and the Canadian General
Standards Board (CGSB).
The CSA B137.3 standard has a maximum allowable internal pressure in kPa (psi) to
which the pipe can be subjected (operating or working and surge pressure) which is
designed by the series number (Series 100, 125, 160, etc.) for IPS-Schedule, SDR, DR
sized PVC pipe. As a rule of thumb, the maximum allowable working pressure would be
approximately 62 per cent of the series rating. For example, the allowable working
pressure of Series 160 PVC would be 160 x 0.62 = 100 psi.
CI-DR and SDR PVC pipe sizes may be referred to by the class system where class
100 is equivalent to 690 kpa (100 psi) DR 25, Class 150 is equivalent to 1035 kpa (150
psi) DR 18 etc. The class number (100, 150, 200, etc.) corresponds to the maximum
allowable working pressure in psi (kpa) to which the pipe can be subjected. The class
ratings provide for a pressure rise above the maximum working pressure caused by a
surge that does not exceed that caused by an instantaneous velocity change of 0.6 m/s
(2ft/s).
If the pipe is to be used at a temperature above 23 C then the effective pressure rating
of the pipe must be lowered. For normal water pipeline installations, the expected
internal pressures will dictate the pipe strength requirements for the PVC pipe. For
UNIT VI – Technical Design & Operational Guide VI – 8
water pipelines, a minimum of Series rating 160 or Class 100 or equivalent should be
used.
All PE pipe used for water pipelines must be certified suitable for potable water by the
CSA testing Laboratory and conform to the requirements of the latest edition of B137.0-
1986 standards for polyethylene pipe, tubing and fittings for cold water pressure
services, and the latest standards issued by AWWA and CGSB. The CSA B137.1
standard covers pipe up to and including 150 mm (6 inch) nominal diameter.
With PE pipe, the Series number (100, 160, etc.) represents the maximum allowable
working pressure in psi (kPa) to which the pipe should be subjected at 23 C, with an
allowance for surge pressure of approximately three times the series number. Transient
or surge pressures normally experienced in pipes can be permitted to raise the total
internal pressure above the pipe series rating provided the normal working pressure is
below the series rating and the duration of the excessive pressure is short and followed
by a period of recovery. If required, contact the manufacturers for pressure-duration
specifics.
Internal pressures will normally dictate PE pipe strength requirements for water
pipelines. Manufacturer’s design curves can provide sufficient information to allow a
designer to select the required pipe Series. Much of the pipe supplied for existing water
pipelines is coiled PE pipe. For water pipelines, a minimum of CSA Series 100 PE pipe
(DR17) may be used for main lines and laterals. Working pressures may be, for
example, 60 psi but the pipe could be subjected to 100 psi during flushing and cleaning.
Service lines should be a minimum of CSA Series 160 PE pipe.
Most pipelines are designed as low pressure distribution systems that include an in-
house storage reservoir. This type of distribution system adds reliability to the water
supply in the event of reduced water flow due to accidents or normal maintenance.
Properly designed storage facilities can also reduce the instant demand on the water
source thereby reducing the cost and size of pipes, pumps and related infrastructure.
For water pipelines with storage, each residential connection should have a storage
tank, preferably an in-house holding tank, which is sized for at least two days of future
average day demand. The typical size of water storage for in-house use with a family of
three persons is 1.4 m3 (300 imperial gallons). In addition to economic benefits to the
UNIT VI – Technical Design & Operational Guide VI – 9
pipeline because of reduced costs in pipes and equipment, in-house reservoirs provide
a means of safeguarding the distribution system from backflow contamination by
installing a proper overflow below the supply inlet on the holding tank to create and
maintain an air gap. Additional information on air gaps and backflow prevention can be
found in Unit IV - Section 2.3.4.
If the proposed water pipeline calls for no in-house storage, then water pipelines must
be sized to meet the future instant demand of the water pipeline which is considerably
greater than the future peak day demand of systems with storage. The design flow of
systems without storage may be more than 10 times greater than the design flow of a
system with storage. In a zero storage water pipeline, the mainline, lateral and service
connection pipes must be designed to have a higher flow rate than systems with
storage. As an example, if 15 subscribers simultaneously opened their kitchen tap, the
instant water demand may be 30 igpm (2.3L/s). A system with in-house storage in a
similar situation would have a peak demand of less then 5 igpm (0.4L/s). If a water
pipeline that is designed to supply water to zero-storage subscribers is not able to meet
the water demands, a negative pressure event may be experienced.
Pipeline water demands are to be based on evaluating the number of people living in
each household, number and types of livestock, extent of lawn and garden irrigation,
tank filling and other yard use. PFRA has collected data on several projects that they
have been involved with and this data can be viewed at: (Appendix VI - A). Design
flow for systems without storage is much higher than systems with in-house storage.
Future demand growth should also be considered in design flow calculations.
Most rural farm pipelines are designed to have a peak water demand of approximately
6.5 m3/day or 1.0 igpm if no other design information is available. However, some
operating water pipelines show peak water demands as low as 0.65m3/day or 0.1 igpm
for household purposes only. A chart showing typical water usage can be seen at
(Appendix VI - B).
Most rural pipelines are designed with flow velocities that are generally less than 1.0
m/s to minimize surge problems. Pressure losses in PVC and PE pipe should be
calculated using standard friction loss formulas, as recommended by the pipe
manufacturer. The modified ISO formula may be used to select the pipe pressure
ratings as per the manufacturer specifications. Other considerations are as follows:
The Series rating should not change in the middle of a section of pipeline,
unless elevation change is great (e.g. at coulees/river crossings)
Changes should be made
Where the potential for future expansion exists, the pipeline should be designed to
accommodate the anticipated expansion (e.g. an extra 5 igpm (0.38 L/s) for future
connections at a specific location along and/or at the end of a current pipeline).
The Organization should consider the possibility of reasonable future expansion from
two perspectives:
1) Over sizing pipe size and pressure rating and supply manifolds;
2) Designing higher capacity pump and pressure tank systems.
The Organization is encouraged to make every effort to provide for expansion of their
system to accommodate future users.
When determining the amount of additional flow to “build” into the pipeline, a number of
factors should be considered;
Potential for additional development within the pipeline area (e.g. Acreages,
subdivisions).
UNIT VI – Technical Design & Operational Guide VI – 11
It may be difficult to incorporate additional flow into the pipeline for potential large
volume users as the increase in cost vs. the possibility of a large subscriber may not be
justified.
Many of these issues are best answered by the local Pipeline Organization or Rural
Municipalities as they are often aware of development plans in the local area.
Some subscribers require more than basic 0.076 l/s flow (large livestock operations or
small communities). In these cases, the subscriber’s actual average daily flow
requirement is used. (Appendix VI - B)contains information on how to calculate the
amount of water that a subscriber may require.
In some situations a design flow of 0.038 l/s (0.5 igpm) has been used as the basis of
design. The designer should be aware of the potential future demand that may be
placed on the system and ensure that the system capacity can handle future demand.
Future demands may involve flows required by new subscribers and/or an increase in
the flows required by existing subscribers.
The actual flow at any given point and time along the pipeline will be different than the
design flow when the system is operational. The nature of the actual water use in the
system and the location of a specific user in the system will affect the flow that is
available for each user. However, when flows are considered over a 24 hour period,
they should be sufficient to meet the all of the subscriber’s daily water requirements.
Typical usage data for a member of a rural Pipeline Organization show the following
results: To date, the results indicate average usage rates of 800 to 1600 l/day (175 to
350 igpd). The average flow rates were 0.015 to 0.023 l/s/client (0.2 to 0.3 igpm) and
the peak flow rate was 0.053 to 0.121 l/s/subscriber (0.7 to 1.6 igpm).
The system is designed assuming that under the design flow condition (typically 0.076
l/s), the minimum water pressure at each curbstop is 98 kPa (10 m of head, 14 psi).
This minimum pressure should be checked to ensure that it is sufficient to compensate
for any head losses between the curbstop and the subscriber’s storage tank.
UNIT VI – Technical Design & Operational Guide VI – 12
The actual curbstop pressure may be significantly different than the pressure under the
design flow conditions. The pressure available at any specific point will depend on the
actual water use in the system and in most cases; the pressure will be higher than the
design flow pressure. During certain operating conditions, however, the pressure at
some curbstops may actually be below 98 kPa (10 m of head, 14 psi). This must be
carefully monitored with accurate data to ensure a negative head is not incurred on the
pipeline, which may result in damage to the pipeline.
Line sizing will be determined by the volume of water and the number of subscribers.
The distance of the following points should be considered when selecting line size and
series:
The diameter of all lines shall be such that the maximum water velocity is less
than 1.0 m/s.
In general, the minimum size of mainline serving three or more connections,
should not be less than 50 mm (2 in) nominal diameter.
In general, the minimum size of lateral line should not be less than 38 mm (1.5
in) nominal diameter.
The minimum size of pipe on the source side of the curbstop is 38 mm
diameter.
Typically 25 mm CTS PE Series 200 pipe is installed from the client side of the
curbstop to the client’s cistern.
On rural pipelines, flow velocities are generally designed to be less than 1 m/s to
minimize surge problems.
The pipeline should be designed to handle the operating pressure plus surge (if
applicable) as well as the pump shut off condition (if applicable). The designer should
be aware that negative pressures can occur and consider the conditions that may lead
to their occurrence.
Pressure losses in PVC and PE pipe shall be calculated using standard friction loss
formulas, as recommended by the pipe manufacturers. The modified ISO formula shall
be used to select the pipe pressure ratings as per the pipe manufacturer’s
specifications:
The Series rating should not change in the middle of a section of pipeline,
unless elevation change is great (e.g. at coulees/river crossing); changes
should be made at defined points such as valves, tees, pumphouses etc.
UNIT VI – Technical Design & Operational Guide VI – 13
4.1 Valves
4.1.1 Isolation Valves (Shut-Off Valves)
Where a mainline feeds several smaller lines, a valve should be placed at the beginning
of each of the smaller lines so they can be isolated from the larger mainline for repairs,
testing or flushing. Future connections can also be added without disrupting service on
the mainline.
Manual air release valves are not normally placed at high points along the pipeline. In
some cases, air release valves are installed after the pipeline is trenched in to assist
with filling, flushing and testing the new line. The number of manual air release valves
should be kept to a minimum. Location of the valves requires ease of access to the
land use and suitable drainage. House connections can also be used to purge air from
the pipeline for filling and for testing.
Automatic air release valves and combination air release/air vacuum valves are not
common and are only installed where a line break or other situations could create a
large negative pressure in the system. These valves are required to be placed inside a
manhole/pump house for frost protection.
Backflow prevention valve assemblies are required at the source connection and at all
subscriber connections.
Curb valves or “curbstops” are required to isolate each subscriber connection from the
main line. The location of the curbstop is determined by the Pipeline Organization in
consultation with the engineer, unless otherwise instructed by a regulatory agency such
as Ministry of Environment, Sask Health/Health Regions, Sask Water, or any other
water purveyor.
UNIT VI – Technical Design & Operational Guide VI – 15
Placing the valve close to the delivery point in the subscriber’s yard makes it quicker to
access when isolating the house from the system to repair or replace components.
Placing the curbstop too near the house, however, can result in flooded basements
should leaks occur at the curbstop.
Backflow prevention devices vary in size and shape but are generally designed for the
purpose of reducing the risk of contamination entering the distribution system.
Dual Check Valves are one of the simplest forms of backflow prevention devices and
are used in situations where there is a very low probability of it becoming a hazard.
Double Check Valves are the minimum standard for backflow prevention in most
pipelines. They are usually part of the meter assembly and are located at the point of
water delivery to the in-house reservoir. Generally, a Dual Check Valve is considered to
be safe for any substance that has a low probability of becoming a nuisance or be
aesthetically objectionable if introduced to the domestic water supply.
UNIT VI – Technical Design & Operational Guide VI – 16
Testable Double Check Valves are a requirement of most source connections and are
designed to be tested in place by qualified technicians. The operation and maintenance
manual for your pipeline should include scheduling and procedures for regular testing of
testable devices.
Flush out assemblies generally should be placed at the end of all mainlines and at every
change in pipe diameter. Flush out assemblies can be used for purging air, flushing
water, or in some cases, swab retrieval during maintenance or start-up of a new line.
Flush out assemblies should be accessible, and must have the approval of the property
owner if located on private property. Additionally, the facilities should be marked and
protected from accidental damage caused by vehicles and/or equipment operating
within the vicinity. The flush out assembly should be locked or secured to prevent
unauthorized entry and to reduce the risk of contamination entering the distribution
system. Also, the site should be routinely monitored for suspicious activity and possible
tampering.
Most pipelines today are engineered with launch and retrieval stations for pigging or
swabbing. In contrast, many older existing pipelines were not designed with this in mind
and may need to be upgraded to accommodate this type of line cleaning. Although
pigging or swabbing stations were not normally installed along the pipeline route in the
past, pigging tees or wyes are sometimes installed in the pump stations or manholes to
assist with start-up of the pipeline.
Tees, caps or plugs can be used in locations of possible future expansion. A minimum
length of 2 metres of pipe should be installed at the tee to facilitate locating and
installing pipe in the future. It is also advisable to install tracer wire with the line to
assist with locating. If it is a HDPE pipeline, future expansion can continue by attaching
the new line and using heat fusion as a method of connecting the existing line.
Saddles come in various sizes and are made of different types of materials. Stainless
steel service saddles can be used for 75 mm or greater size pipe.
UNIT VI – Technical Design & Operational Guide VI – 18
Unit VII - Section 11.2 (Administration) describes in more detail the easement process.
If the pipeline route results in crop damage, the Organization, or in some cases the
contractor, is responsible for compensation of damages. (Responsibility should be
determined prior to tendering).
5.3 Crossings
Crossing permits may be required for some underground crossings (e.g. railway
companies). In some cases there may be a cost for the crossing permit (sometimes a
yearly renewal fee may be charged) to cover administration and inspection costs.
Before proceeding to final design, the consultant or engineer should meet with the
companies that are involved to determine these costs and obtain approvals.
Each agency will have its own set of standards and guidelines (regarding notice,
method of crossing, etc.) that must be followed. These standards must be known prior
to tendering so that the plans and specifications can be adjusted accordingly. It is
advisable to have all approvals in place prior to construction so that there are no
surprises once the installation begins. Unit IV (Approvals and Agreements), Sections
1.3 and 1.4 provides more details about crossings.
The preferred method of providing information on soil conditions is to dig test pits at any
number of locations during a pre-tender site meeting. Locations will need to be
identified prior to excavation and Utility Companies must be contacted so they can
locate and flag their existing utilities. This is especially important in the case of the
trenchless plough methods, where traditional geotechnical information does not provide
the contractors with the visual observation of the sub-surface conditions. The Pipeline
Organization may arrange to have a backhoe on hand to accommodate this test dig.
The second method of obtaining soil information is by using a drill rig. Usually test holes
are drilled every 800 to 3000 metres along the pipeline route. Where it is speculated
that soil conditions may significantly affect unit prices, areas close to augured crossings
such as highways, railways, and rivers may require additional test holes. This method
will have a significantly higher cost than digging test pits with a backhoe.
UNIT VI – Technical Design & Operational Guide VI – 20
Subscribers generally have an idea of where they would prefer the pipeline installed and
where existing buried underground utilities are located in their yard site. This will help to
determine the final pipeline routing.
It should also be clear who is responsible for clean-up and what the expectation is for
returning the site to as near to pre-construction conditions as reasonably possible.
Long term considerations may include who is responsible for maintaining the line and
what the provisions are for land transfer.
UNIT VI – Technical Design & Operational Guide VI – 21
should be installed to vent water from the vault should a leak occur. Frost protection of
the piping and mechanical assemblies within the manhole should also be considered.
Manhole or metering vaults are quite common and although they offer a relatively
inexpensive method of connecting to a water supply, the problems are they tend to fill
with water, access is restricted, and they present some safety concerns (e.g. build up of
gases, confined space entry). There are also some concerns about the ability to re-
chlorinate and operate chemical feed pumps in a normally damp environment.
The Organization should be aware of all options with regard to choices of equipment,
telephone monitoring etc. so that they can make an informed choice. In general, the
Organization wants a simple fully functional pumphouse, requiring minimum
maintenance at a low cost with provisions for additional equipment, if required.
(Appendix VI – T) presents typical pumphouse plans which have been used very
successfully for the last number of years. The plans include typical mechanical
equipment used for a range of sizes and flows. (Appendix VI – T2).
Plough method - involves construction equipment with a plough shoe and pipe
placing sleeve. This method minimizes ground disturbance. Contractors have
successfully installed up to and including 150 mm diameter PE pipe.
Although line looping adds additional costs to the water pipeline, the benefits of line
looping outweigh the costs. One of the reasons for incorporating line looping into your
pipeline design would be to achieve a higher degree of safety in your distribution
system. The characteristics of chlorine disinfectant are such that branch lines which are
extremely long or have intermittent flow may experience dissipating disinfectant to a
point that the chlorine residuals could fall below the parameters for safe drinking water.
By incorporating line looping, water is refreshed quicker and is more likely to maintain
proper amounts of disinfectant.
Line looping also helps to relieve some of the pressure and/or flow demands in areas of
the pipeline that are experiencing marginal flow or pressure. Conditions may change as
the subscriber base grows and line looping may be necessary in order to maintain the
system’s design requirements. It is a good idea to develop a list of priority or preferred
segments of line that should be considered for line looping. Critical areas and places
where it is suspected that water demands may be reaching a point where it is no longer
possible to meet the flow demands should be monitored. It is important to document
any complaints of low volume or flow so that they can be reviewed and addressed in a
waterworks system assessment. The distribution system may be in danger of
depressurising if the situation is allowed to continue unchecked. Suspected lines
should be designated high priority and corrective action should be taken.
UNIT VI – Technical Design & Operational Guide VI – 24
6.4.2 Grids
Grids can be created as the pipeline expands and when lateral lines are added to the
infrastructure to accommodate new subscribers. Grids are quite favourable as it allows
alternative routing for water distribution, thereby reducing the chance of a disruption in
service.
Most of the pipelines today are designed with the ability to flush lines and clean them as
necessary. Pipelines that use HDPE pipe will remain relatively clean for several years
and have a much higher service life than pipelines that use ductile steel or some of the
other products.
It is essential to have accurate maps outlining the pipeline as it has been installed. The
maps should include all of the information about the pipeline such as where changes in
the pipe size occur, location and types of valves, location of pumphouses, manholes
and booster stations. As technology evolves, new tools are readily available to use for
identifying distribution lines and service connections. An example of this is the satellite
imagery that is available through Google™ Maps. Computer generated images of
terrain can easily be marked to show installed lines or GPS data can be overlayed into
the program to show as-built construction.
A shielded copper wire referred to as “tracer wire” is installed with the pipe to assist with
locating the line in the future. By attaching a cable or frequency locater to the end of the
tracer wire and sending a signal through the wire, it is possible to locate or “trace” the
signal at ground level and mark the water service line on the surface. Frequency
locaters are quite expensive, however, and utilities may choose to rent them when they
are required rather than buy their own. Care should be taken when installing tracer wire
to make sure the ends of the wire are accessible and easy to find. If the tracer wire has
been buried or cut off below the ground, it has no value and defeats the purpose of
installing it. Therefore it is a good idea to run the tracer wire up the curb valve or
isolation valve and attach the end of the wire to the top of the curb valve with tape so
that it is readily available for use. Likewise, the tracer wire should be attached to the
building at the point of entry or in a consistent manner that will be easily located by the
user.
UNIT VI – Technical Design & Operational Guide VI – 25
Line breaks are a reality with water distribution. Generally water line breaks are brought
to the attention of the Pipeline Organization by subscribers or concerned citizens that
have noticed water pooling in areas where it normally doesn’t pool or they may have
noticed a sudden cave-in. It is in the Organization’s best interest to investigate all
reported water line leaks and repair them as quickly as possible. Should the distribution
system develop a problem in which depressurization occurs, the potential for back
siphoning contaminated water is a real concern and can jeopardize the health and
safety of the subscribers.
Line break repair methods may vary according to each situation and the location of the
break, but Pipeline Groups should have an action plan ready with emergency repair
procedures. An action plan would include the contact numbers of available contractors
and personnel needed to repair the line. The plan will also include procedures for
locating other utility lines, steps required to alert downstream users of a possible water
outage, and the protocol for ensuring that the line is bacteriologicaly safe before it is put
back into service. All repairs must be completed in a safe, professional, and timely
manner. Consideration should be given to traffic flow and detours should be planned in
advance. If possible, repairs should be made when there is the least amount of traffic,
and therefore the minimum amount of disruption. Attention needs to be given to sign
placement as well as site and worker protection. Any excavation that has to be left
open for an extended period of time must be clearly marked, and preferably enclosed or
surrounded by suitable fencing. Care should be taken to keep pipes clean by covering
the ends so that dirt or debris will not enter the line, and lines should be plugged or
sealed when pipe laying is not in progress. Disinfection protocol must also be followed
according to the guidelines set out by Ministry of Environment.
UNIT VI – Technical Design & Operational Guide VI – 26
Commercial leak detection equipment is available to assist in locating line leaks. This
can include very expensive equipment such as ground penetrating radar, or relatively
inexpensive equipment like a stethoscope type of listening device which is used to hear
water venting from the damaged line.
Mathematical detection is done by recording the volume of water that is being used by
the subscribers and subtracting the volume from the supply line. If there is an
excessively high amount of unaccounted water, it is possible there is a line leak.
Pipelines that have an automated read system for data collection can use the system to
read segments or legs of the distribution system and compare the numbers to help
determine if a leak is present.
Valves that are not used for several years may become seized or stuck and are useless
in the event of an emergency shut off. Therefore, it is a good idea to develop a
schedule in which valves would be exercised to prevent them from seizing. A good
preventative maintenance plan would document when and what valves have been
exercised. This is particularly important for priority valves or isolation valves that may
need to be closed in a hurry.
It is not uncommon for leaks to develop at the location of a valve. This may be because
of the connections made to the pipeline or it may be a failure of the valve itself. In either
case the site will need to be excavated and the leak repaired. Usually the valve will be
replaced at the same time, regardless of the condition of the valve.
UNIT VI – Technical Design & Operational Guide VI – 28
8.1 Pumphouses
8.1.1 Site Selection
In general, an above ground building is ideal for a pumphouse, in an area that will
provide good drainage. It should be accessible year-round, visible from the road and
close to a suitable power source (3-phase power may be required). It is recommended
that it be inspected daily to monitor equipment and temperatures inside the building.
This may also be accomplished through remote monitoring. Appropriate signage should
be visible and include contact information with an emergency phone number.
Buildings should be designed so that they can accommodate the necessary equipment
that is to be housed inside. There also needs to be provisions for the supply and
discharge lines which should be sleeved at the point of entry into the building. A
structural plan for pumps, piping and
equipment can be seen at (Appendix
VI – T3). It is very important to
maintain the buildings in good repair
so that they will continue to provide
years of useful service. Consideration
should be given to future expansion as
well as adequate space for servicing
equipment and performing regular
maintenance. Buildings should have
adequate lighting and proper
ventilation. There should also be easy
access to safety equipment such as
eye wash stations. All guards, railings
or items pertinent to Occupational Health and Safety Regulations must be kept in place.
Blueprints of a typical building structure can be seen at (Appendix VI - T).
UNIT VI – Technical Design & Operational Guide VI – 29
Buildings should be monitored routinely to ensure that all systems are functioning
properly. Several companies offer monitoring services which can be programmed to
notify when there is a loss of heat or power, or when it senses smoke, fire or intrusion.
Equipment monitoring can also be used to protect equipment from adverse conditions
and warn of potential failure or shut downs. Usually a list of contacts is provided so that
the alarm company can go down the list and call out in the event of a problem.
Regular inspections of all buildings that are operated by your Organization are essential
for longevity of the buildings and to ensure that health and safety issues are being
addressed.
Care should be taken to keep the grounds accessible year round and reasonably
groomed. This shows credibility and promotes the Organization as being responsible.
It also makes routine visits easier and allows emergency repairs to be completed
quicker.
Ball valves should be used as an isolation valve inside the household, preferably at the
point of entry inside the house. They can be used to isolate the house downstream of
the curbstop when it is necessary to replace components of the meter assembly. In-
house valves offer a means of home owners to shut the water off in the event of an
emergency and allow responders and maintenance personnel more time to prepare for
the leak or repair.
A water meter with remote readout should be installed at every house/yard connection
to monitor water consumption for billing purposes and verify water consumption. Meters
must be installed according to manufacturer’s specifications and should be in a location
that is easily accessible. It is not recommended to install meters inside cisterns
because of contamination issues and also because of the normally damp environment.
Pressure reducing valves are generally installed as part of the meter assembly or
manifold in the house. Pressure reducing valves are normally equipped with a strainer
and a pressure gauge. Leakage from household mechanical systems could result if
pressure reducing valves are not installed and line pressure in the distribution system
exceeds the mechanical systems pressure rating.
It is advisable that flow restrictors are placed at each client’s location. This will ensure
that the pipeline system will operate as designed and provide each subscriber with the
flow, pressure and quantity of water that it was designed for. Flow restrictors should be
installed on the meter assembly or at a location that is easily accessible as they can
become plugged and require servicing.
Although flow restrictors are not used on all rural pipelines, it is advisable to incorporate
them into the distribution system. Pipelines that do not have flow restrictors may find it
difficult to maintain the minimum pressure requirements set out in Ministry of
Environment guidelines. Elevation differences along the pipeline route can result in
highly variable flows at the points of delivery. This can affect the operation of the
system and further complicate the design of booster stations.
UNIT VI – Technical Design & Operational Guide VI – 32
Most water meters and pressure reducing valves have screens built into them which
prevent debris from within the pipeline to cause damage or malfunction. In-line
strainers or filters are not recommended because these devises could pose a health
concern by harbouring bacteria if not maintained properly.
9.1.8 Storage
Storage systems come in all sizes and shapes and are available to meet the needs of
the subscribers. A minimum 450 litre (100 gal) storage cistern is recommended for
every subscriber connection. Although it is not recommended, existing cisterns have
also been used for water storage in the past. Some examples of storage cisterns and
typical house connections can be seen at (Appendix VI - U).
Meter assemblies may require attention from time to time and could develop a leak due
to fatigue or corrosion. Each of the components is subject to failure such as the
pressure reducing valve which could lead to further problems. Generally, the subscriber
will notify the Organization of any leaking or abnormal noises that they have noticed. All
reported abnormal conditions should be investigated as soon as possible to prevent
further damages and possibly a major line leak or flood.
All maintenance and repair records should be well documented and kept for a minimum
of five years. Records should be stored in chronological order as per the regulations.
Original documents or record sheets should be filed for regulatory review and a hard
copy version should be created to extract data for completing charts and graphs that are
necessary for the organization to evaluate its position. Digital pictures can also be
included in the record files if possible. Also included are the records of all data relating
to water consumption, equipment run time, general conditions of pumphouses and
booster stations, repair and maintenance schedules. In addition, all records of
equipment failure and or replacements should be documented and filed.
UNIT VI – Technical Design & Operational Guide VI – 34
10.0 General
This section has been prepared to provide insight into the day to day operations of a
waterworks distribution system and to assist start up organizations in developing an
operational plan. Much of the information is based on situations encountered by
existing Pipeline Organizations and is intended to be used as a guide to identify areas
that might require further consideration and may be relevant to your Organization. As
owners of a rural water pipeline, some important decisions will have to be made in
regard to who will be in charge of the operations, how the pipeline will be staffed, and
how the workload will be accomplished.
10.1 Staffing
Each Pipeline Organization will have to determine how the work duties will be
accomplished and what will be the amount of compensation paid for the duties that are
performed. Some associations depend on volunteers to carry out specific duties.
Larger associations may have the resources to hire the necessary staff required to
maintain the pipeline. A combination of volunteer and paid positions may be an
alternative for Organizations that need to look at creative ways to be sustainable.
The operational plan and maintenance manual should include system operating and
maintenance instructions for all components. Daily, weekly and monthly testing
procedures should be outlined for each of the components and detailed records of all
equipment that is required to be tested or calibrated. A summary of household
mechanical systems should be included showing various assemblies that are used in
your distribution system. Also, pipeline and pumphouse design features that are
incorporated into your system like backflow prevention devices and pressure sustaining
valves should be included. A list of all pertinent information such as the manufacturer's
data and a suggested maintenance schedule should accompany the summary of
components used in your waterworks system. Other items of importance include
detailed maps of the entire system, schematic drawings of pump houses, pipelines and
individual subscriber’s yards.
UNIT VI – Technical Design & Operational Guide VI – 35
It is a good idea to document other important details in your plan such as policies that
your Organization has adopted on operational procedures and safety protocol. Plans
should be updated and reviewed regularly as new techniques or methods are
developed. The successors of the Organization will then have a better understanding of
what is required to keep the system operating smoothly and can easily modify the plan
to accommodate growth or structural changes.
Subscriber lists are an important aspect of record keeping for the Pipeline Organization
and should be accessible for quick reference so that all subscribers contact information
can easily be retrieved in the event of an emergency. Lists should be arranged in
chronological order and up-dated as new subscribers are added or whenever it is
necessary to do so. Electronic files can be created so that detailed information can be
easily accessed from a laptop in the field.
Each Organization will have to establish a method of reading the water meters so that
the billing process can be initiated. One method that is used to accomplish this is to
send a self read card out to subscribers so that the meter information can be collected.
The subscriber enters the meter information and returns the card to the billing clerk or
administrator so that that data can be calculated and the invoices prepared.
Alternatively the Organization may elect to have someone read the meters. Because
rural pipelines usually involve long distances between subscribers, meter reading can
be a costly and time consuming endeavor. Some larger pipelines have incorporated
automated meter reading technology into their distribution system. Some automated
meter read systems have the ability to collect the water meter information by sending a
signal to the water meter and triggering the meter to broadcast meter data over a radio
frequency so that it can be intercepted by a mobile unit. More sophisticated units can
also interface with billing software and import the data into the billing cycle.
UNIT VI – Technical Design & Operational Guide VI – 36
Many commercial types of marking paint are available for line locating. Applicators are
relatively inexpensive and make the task much easier. Consideration should be given
to the color of marking paint used so as not to duplicate the color that other utility
companies are using to identify their lines. Normally a blue paint is used to signify a
water line. In addition, various colors of flags are available and once again the
preferred choice is blue for identifying a water line. Customized pin-flags can be
purchased through various companies but not-for-profit agencies are also located in our
province.
Tools and equipment will vary according to size and finances for each Pipeline
Organization. A suggested list of inventory is shown below. The list may vary
depending on the Organizations needs. A completed list of all current inventories
should be kept on file for each service vehicle, piece of equipment or building and
updated as necessary. Some Organizations choose to equip an enclosed trailer with
items that they may need in an emergency. This provides a great place to keep your
tools and equipment secure and out of the weather and ready to go when you need it.
UNIT VI – Technical Design & Operational Guide VI – 37
Common items that could be carried in a service vehicle would include the following:
Fire Extinguisher
First Aid Kit
Warning Devices
Squeeze-off Tools
Flashlight
Maps
Reporting Forms
Manuals
Communication Equipment
Camera
Line Locater
Assorted Fittings
Hand Tools
Shovels
Head Protection
Hearing Protection
Eye and Face Protection
Foot Protection
Reflection Wear
UNIT VI – Technical Design & Operational Guide VI – 38
This section outlines regulatory issues that may affect your Organization and offers
some suggestions on how to accomplish these tasks. Other sections in this manual
may describe the topics in more detail and will be referred to as indicated.
Most pipelines are required to monitor chlorine residuals on a daily basis. Chlorine
monitoring can be achieved by collecting samples of water and adding a reagent to the
sample which reacts with the chlorine and turns the colour of the water sample to a
pinkish or purple colour. By observing the colour in the sample cell, the amount of
chlorine residual in the water can be determined. A colour wheel can used to compare
the colour chart to the sample cell, and thereby indicate the chlorine levels, but a
preferred method is to obtain a colorimeter for a more accurate measurement. More
UNIT VI – Technical Design & Operational Guide VI – 39
information on Chlorine sampling and protocol can be found in Unit IV Section 2.5.3
under Water Sample Testing.
The requirements for bacteriological sampling are defined in the “Permit to Operate”.
The number of samples required as well as the location and frequency of sampling will
be listed in the permit. Operators must record all information relevant to the sample
collection to verify compliance of sample submission and to track and record the sample
analysis. All entrees need to have the date and the initials of the person making the
entry assigned to them. Time of sample collection, location and sample identification
also need to be documented.
A follow up file should be established to record analysis reports and assist in preparing
lab reports that are to be presented to the council or board of directors. As a regulatory
requirement, reports must be presented to the permittee on a monthly basis for review
and to confirm that the Organization is operating within its parameters. An authorized
official should sign the report indicating that it has been reviewed. More information on
Bacteriological sampling and protocol can be found in the Unit IV Section 2.5.3 under
Water Sample Testing.
11.4 Rechlorination
According to Ministry of Environment regulations, pipelines are required to have the
ability to add chlorine to the water if chlorine tests reveal that the chlorine residuals do
not meet the parameters that are defined as safe for drinking water. Typically, this
would be done by injecting chlorine disinfectant into the distribution system usually at
the connection point to the supply line. This is a good argument for having an above
ground pump house at the connection point, as it may be too difficult to provide
additional chlorine if there is only a manhole at the tie-in point.
Rechlorination may vary from pipeline to pipeline and depends on the type of product
being used for disinfectant. Generally a chemical feed pump draws the product from
the supply and injects it into the distribution system. All records of chemical usage need
to be carefully monitored and recorded as well as equipment calibration and repair
records. As always the person recording the data needs to date and initial the entry.
UNIT VI – Technical Design & Operational Guide VI – 40
All data is presented for review and the signing authorities are asked to sign the data
sheet to ensure that operating parameters and water quality parameters of the
waterworks are being achieved.
http://www.saskh2o.ca/DWBinder.asp
Emergency Response Plans are also a regulatory requirement and are essential in the
event of an emergency. It is critical to have a plan in place so that important decisions
are not made in haste and emergency protocol can be followed. Templates are
available at:
UNIT VI – Technical Design & Operational Guide VI – 41
http://www.saskh20.ca/DWBinder/EPB241BWaterworksEmergencyResponsePla
nningTemplate.pdf
http://www.saskh2o.ca/DWBinder.asp
Scroll down to Point #7 and click on Annual Notification to Consumers Guidelines for
Compliance and Templates.
http://www.saskh2o.ca/PDF/Regional-ContractOperatorProgram.pdf