Torben 1998
Torben 1998
Torben 1998
The introduction of Distribution Automation is studied by The primary incentive for utilities to invest in DA in cable
many utilities at the moment. In some countries or in networks is to reduce the impact of faults to their
some areas, utilities are quite mature with respect to customers. In areas with high population density or with
Distribution Automation (DA). Most utilities are however many industrial customers, such faults may have serious
in an introductory phase with pilot installations. The consequences. In large cities, traffic congestion can result
primary incentive for DA is to increase the quality of in long fault clearance time when manually operated
supply, but obviously increased quality must be justified switches are used. Thus, reduced outage time is important
by cosubenefit advantages. in cable networks even though the reliability in these
networks generally is good. Deregulation of the energy
The key components for DA in cable networks are the market will also result in pressure on the network
Ring Main Units (RMUs). Existing RMUs are companies to focus on the efficiency of operation and the
characterised by having been designed without DA in quality of supply. In some countries compensation will
mind. If necessary, DA functionality has been solved by have to be paid to customers for non-conformity of the
add-ons to these RMUs. quality of supply (e.g. compensation for not delivered
energy will be introduced in Norway from January 1999).
In this paper requirements and perceived obstacles for The basic functionality which must be implemented in
implementation of DA in cable networks are assessed. order to reduce fault clearance time is remote fault
Further, new technologies to overcome these obstacles are passage indication and remote control and position
considered. This results in the definition of a Distribution indication of load break switches along the ring.
Automation Ready RMU. Both the next generation of
RMU and the ultimate RMU as seen by the authors of this In addition to this basic functionality of a DA system for
article are discussed. cable networks, monitoring of the distribution network
and its components is of interest in order to increase the
efficiency of operation, maintenance and network
planning. Monitoring includes fault monitoring, load flow
monitoring, condition monitoring and power quality
monitoring. Documentation of fault impact is especially
important for compensation purposes (who are affected, at
what time, for how long). Monitoring of load flow and
voltage quality requires measurement of voltages and
currents. This functionality is often included in early
specifications for DA schemes from network companies
today but usually omitted or classified as possible future
extensions in the final specification. This is mainly due to
lack of sufficiently cost efficient solutions at present.
Trends in Distribution Switchgear, 10-12 November 1998, Conference Publication No. 459 0 IEE 1998
168
the benefits considerably. The benefit for network 0 Gas pressure indication available for RTUs
companies will also increase with the deregulation process 0 Current transformers that can be installed on cables or
(e.g. if compensation must be paid for not delivered on bushings
energy). As more complex Distribution Management 0 Voltage absent and present relays
Systems and Energy Management Systems are introduced
in the utilities, input from the distribution process will be In order to implement a DA scheme, a separate control
required in order to fully exploit these systems (e.g. for cabinet including a RTU, battery and battery charger,
documentation, statistics, planning, operation and communication units, overvoltage protection and if
maintenance) necessary a heating element must be installed and wired to
the RMU. This approach is characterised by a lot of
Communication. Lack of standardisation of engineering, wiring and testing during the design,
communication protocols and interoperability of different installation and commissioning of the DA system. It also
suppliers' products are also obstacles for utilities, which requires that there is space for the added control cabinet in
do not want to commit themselves to only one supplier. the secondary substation, space which are not always
Several standards for communication have been available. For new installations, the most compact
developed within the IEC TC57 the last years (e.g. IEC secondary substations might not be sufficient and bigger
870-5-101). However, certain degrees of liberty still exist and more expensive secondary substations must be
within some standards and interoperability between selected.
different suppliers is not automatically assured even if the
same standard is specified. The most widespread protocols If current and voltage measurements are included,
for the near future seem to be IEC 870-5-101, DNP 3.0 transducers are traditionally used in order to interface
and Modbus. standard analogue inputs of RTUs. Fault indicators and
relays for transformer protection (in case of CB
Most utilities already have an existing SCADA system transformer protection) are mostly separate units with
and to some extent a communication network. Thus, field corresponding sensors.
equipment must be able to interface the existing SCADA
systems and in some cases operate in an existing
communication infrastructure.
r
DispatchingCentre
Secondnr)' Substations
Jommunicntion Node
,, ,, ~ , . . ~...... ..............
LVDistribution- 4 b eE d Users
centre. An intelligent Node Controller in the secondary For the lowest level of functionality, simple fault
substation serving as gateway and concentrator is then passage indicators are provided as separate devices
needed. for each cable feeder
All secondary functions are wired to the secondary
NEXT GENERATION OF RMU technology compartment by pre-fabricated cables
with multi-connectors.
Drivers, obstacles and challenges for implementation of
DA in cable networks as well as limitations in available
technology and possibilities with new technology have
been outlined above. On this basis, what should
characterise the next generation of RMU?
SCADA
1 /'
Secondary
Subtation
p
...
/'
,/"
/
*CONDITION MONITaIRING
Close
.LOAD CONTROL
*PQ MONITORING
The next generation of RMU described above represents There is a clear need for DA in cable networks, especially
some important steps forward in order to reduce cost, in big cities and industrial areas. Reduced outage time and
improve reliability and solve practical problems related to increased voltage quality are becoming more and more
implementation of DA. However, this is not the end of the important in an IT- based society. Utilities are also under
road in order to obtain the ultimate RMU. pressure to increase their efficiency of operation of the
distribution network, especially in deregulated markets.
Sensors as Default Solution
Technical and economical obstacles to large-scale
When low cost sensors will be available, these can be implementation of DA can be significantly reduced by
offered as the default solution even if the RMU is not redesign of the traditional RMU. The main advantages for
intended for automation in the first place. This will an Automation Ready RMU are reduced costs for
facilitate retrofitting of secondary technology including implementation of DA, increased reliability and enhanced
analogue measurements later on. functionality. This is achieved through functional
integration and standardisation.
~ntell~gent
Sensors and Actuators
REFERENCES
A RMU has typically 18 DI and 6 DO that must be wired
to the RMU controller. Sensors for current and voltage 1. Volker Lohmann, Friedrich Frey, Gerhard Mauthe,
measurement also require to be connected to the same 1995 “Enhanced Customer Value Achieved by
unit. In order to reduce this internal wiring, position Integrated Protection, Monitoring and control” ,
indication sensors, current and voltage sensors, sensors for CIRED 95
condition monitoring and actuators should be connected to 2. S Torben, F Nilsen, T Gulbrandsen, S Johansen, S
an internal bus. Some basic pre-processing tasks can also Tryti, K Raami, M Heinonen “Distributed
be decentralised by this approach. Intelligence in Tomorrows Distribution System” ,
CIRED 97
Magnetic Actuators