"Standard Bidding Documents and General Conditions of Contract" PPA
"Standard Bidding Documents and General Conditions of Contract" PPA
Training On
for
Unless otherwise specified in the SCC (from the Start Date until the Defects
Correction Certificate has been issued) the following are Employer’s risks:
• The risk of personal injury, death, or loss of or damage to
property, which are due to:
1. Use or occupation of the Site by the Works or for the
purpose of the Works, which is the unavoidable result of
the Works, or
2. Negligence, breach of statutory duty, or interference with
any legal right by the Employer or by any person
employed by or contracted to him except the Contractor.
However (from the Completion Date until the Defects Correction Certificate has been
issued) the risk of loss of or damage to the Works,
Cost + time
(eng. to determine by
how much to increase
the contract price and by Compensation event!!!
how much the intended
completion date has to
be extended)
1. Either party may refer the decision of the adjudicator to arbitrator within 28 days
2. otherwise adjudicator decision will be binding
3. Then arbitration should be conducted in accordance with any published arbitration
procedure
A new adjudicator to be
If no agreement is reached b/n
designated by the appointing
Them within 30 days
authority at the request of
either party within 14 days
NB: Cost of adjudicator will be shared equally by the employer and contractor.
The appointed adjudicator shall be known and agreed upon prior to signing of the
contract.
Cont. does not submit the updated The eng may withhold an amount sated in the
program within this period SCC from next payment, and continues to
withhold until it is submitted
NB:
• The engineers approval of the program does not alter the obligations of the contractor.
• Submission and approval of the program will assist the extension of intended completion
period.
NB: if contractor failed to give early warning of a delay or failed to cooperate in dealing with a
delay, the delay by this failure shall not be considered in assessing the new intended completion
date
1. The engineer shall check the contractor’s work and notify the contractor of any
defects that are found.
2. The engineer may instruct the contractor to search for a defect and to uncover
and test any work that the engineer considers may have a eefect.
If the contractor has not corrected 1. Engineer will assess the cost of having
Any defect within the time specified the defects corrected
By the engineer’s notice 1. The contractor will pay this amount
If the work in the variation corresponds to an item in the The rate in the BoQ shall be used
BoQ, and if the qty does not exceed the above limit to calculate the value of the
Or variation --- additional work
If the timing of its execution does not cause cost/unit qty
to change
1. If the unit qty changes The quotation of the contractor shall be in the
2. If the nature or timing of the works form of NEW RATES for the relevant items of
in the variation does not correspond work
with an item in the BoQ
Engineer may order the variation and make necessary changes to the contract price
BASED ON THE WNGINEERS OWN FORECAST OF THE EFFECTS OF THE VARIATION
ON THE CONTRACTORS COST,
for time – it is already a compensation event
If payment is delayed:
1. For less than 90 days, contractor shall be paid interest on late payments (at the prevailing
rate of interest for commercial borrowing)
2. For more than 90 days, contractor may terminate the contract at the default of the employer
(all losses and damages including profit loss will be compensated ?????)
9/7/2023 36
Ephrem Mesele (Cheif Enginner)
GCC – PPA 2006 D. Cost Control /clause 44 – Compensation events cont’d
If a compensation event:
1. Would cause additional cost Contract price shall be adjusted
2. Would prevent the work being AND/OR
completed before the intended Intended completion period shall be extended
completion date
Work completed
Eng to issue certificate of Takeover of the site
contract accomplished <7 days
completion by the employer
by both parries
Fundamental breach of contract Eng to issue a certificate for the value of work done,
by the employer OR materials ordered, and reasonable
Termination for convenience • Cost of removal of equipment
• Cost of return of persons
• Cost of protecting and securing the work
less advance payment