Example-3.

1
[G.T.U., May/June 2012]
A small project consists of twelve activities. Interrelationship amongst
various activities are as follows
is starting activity and
Activity A precedes activities B,
Activity E depends on activities B and C.
C and D.

Activity F follows activities C and D.


Activities G and H can start as soon as activity D is completed.
Activity I succeeds activities G, E and F.
Activity J and K can start only when activities H and I are
completed.
Activity L is the last activity and it succeeds activities and K.
Prepare depending table and draw AOA diagram.
Solution: The dependency table can be prepared as below:
Activity Activities immediately
Preceding Succeeding
A B, C, D
B, C E
C, D F
D G, H
G, E, F I
H, I J, K

J, K L
3.14 Construction Management

The AOA diagram can be drawn as below (Fig. 3.15)

OA C O- A C E O
D

Fig. 3.15 (a) Fig. 3.15 (b)

OA C E
D

Fig. 3.15 (c)

OA C- E
D F G/

Fig. 3.15 (d)

OA E

G
H
Fig. 3.15 (e)
Network (Analysis) Techniques 3.15

The AOD diagran can be drawn as below:

A C E
D F L
G
H

Fig. 3.15 (f) Final network


Note: The students can be try to avoid more than one dummy activities.