2020-Dec CE-306 74
2020-Dec CE-306 74
2020-Dec CE-306 74
1. A project consists of 10 jobs as detailed below. Write the steps and arrow diagram representation [5]
of the project.
Jobs Processor
A None
B None
C None
D A
E B
F B
G C, F
H D, G
I E, H
J C, F
2. The following information applies to a particular project. [10]
Jobs A and F can be started and completed independently.
Jobs B and C can start only after job A has been completed.
Jobs D, E and G can start only after jobs B, (C and D) and (E and F) are completed,
respectively.
Time estimates of all the jobs are given in the following table:
Job Time Estimates (Days)
Optimistic Pessimistic Most Likely
A 3 7 5
B 7 11 9
C 4 24 14
D 4 12 8
E 6 12 6
F 5 19 12
G 2 6 4
i. Draw the network and determine the critical path, and its expected duration (Te).
ii. What is the probability of completing the project in 30 days?
3. Compute the earliest and the latest event times as well as the following activity times for the [10]
network shown in the Fig. 1.
Fig. 1
i. Earliest start time
ii. Latest start time
iii. Earliest finish time
iv. Latest finish time
Also compute total float, free float, and independent float and determine the critical path.
5. Prepare manpower loading chats based on the late start times for the project network shown in [10]
Fig. 2. Compute the optimum crew size.
Fig. 2