500kv Myanmar
500kv Myanmar
500kv Myanmar
Preparatory Survey
on
National Power Transmission Network
Development Project Phase III
Final Report
Pre-release Version
Separate‐Volume
(Preliminary Data Collection Survey on
Power Grid Expansion towards
Mawlamyaing)
January, 2021
Table of Contents
1. Data Collection on System Configuration ............................................................. 1-1
1.1. Outline of the survey ....................................................................................... 1-1
1.2. Current status and plans for system configuration ...................................... 1-1
Current Status of Grid Structure ............................................................ 1-1
Existing power supply .............................................................................. 1-3
1.3. Examining the adequacy of the power grid plan ........................................... 1-4
Power Demand Forecast .......................................................................... 1-4
New power plant construction plan ........................................................ 1-5
Approximate power flow forecast ............................................................ 1-6
Evaluation of power flow and power transmission capability ............ 1-10
Evaluation of the stability of the Kamarnat - Mawlamyaing - Myawaddy
transmission line section.......................................................................................... 1-11
Recommended system configuration ..................................................... 1-12
1.4. Single line diagrams of the existing power stations in Yangon .................. 1-13
Single line diagram of the Hlawga PS .................................................. 1-13
Single line diagram of the Thaketa PS ................................................. 1-14
Single line diagram of the Ahlone PS ................................................... 1-16
Single line diagram of the Iwama PS ................................................... 1-17
2. Data Collection for Construction and Expansion of Substations ........................ 2-1
2.1. 500 kV Pharyargyi Substation........................................................................ 2-1
Location ..................................................................................................... 2-1
Layout........................................................................................................ 2-1
Equipment Configuration ........................................................................ 2-2
Design Outline .......................................................................................... 2-3
2.2. 500 kV Mawlamyaing Substation .................................................................. 2-3
Location ..................................................................................................... 2-3
Layout........................................................................................................ 2-5
Equipment Configuration ........................................................................ 2-6
Design Outline .......................................................................................... 2-8
2.3. Cost Estimate for Substation ........................................................................ 2-15
3. Data Collection for Transmission Route................................................................ 3-1
3.1. Study for Transmission Route Selection ........................................................ 3-1
Methods for Transmission Route Selection ............................................ 3-1
Location of Substations ............................................................................ 3-1
Transmission Route .................................................................................. 3-3
3.2. Study on Soil Conditions of the Transmission Route .................................... 3-6
Geology of the Transmission Route ......................................................... 3-6
Soil Conditions of the Transmission Route............................................. 3-8
i
Transmission Project Preparatory Survey Phase III
Figure 1.2-1 System map from Pharyargyi to the southeast ............................................ 1-2
Figure 1.2-2 System configuration in eastern Yangon and southeast from Pharyargyi ... 1-3
Figure 1.3-1 System to be studied ................................................................................... 1-4
Figure 1.3-2 Power Demand Forecast in 2030 for the Target Area ................................. 1-5
Figure 1.3-3 Case 1. Peak power demand period. Maximum output of power generation
facilities.......................................................................................................... 1-8
Figure 1.3-4 Case 2. During off-peak power demand. Maximum output of generation
facilities.......................................................................................................... 1-8
Figure 1.3-5 Case 3. Partial shutdown of power generation facilities during peak power
demand ........................................................................................................... 1-9
Figure 1.3-6 Case 4. During peak power demand, all power generation is shut down ... 1-9
Figure 1.3-7 Relationship between the transmission distance of an AC transmission line
and the power that can be transmitted stably ............................................... 1-11
Figure 1.3-8 Relationship between the power that can be transmitted stably and the heat
capacity of transmission lines ...................................................................... 1-12
Figure 1.3-9 Recommended system configuration ........................................................ 1-12
Figure 1.4-1 Single line diagram of the Hlawga PS (before rehabilitation) .................. 1-13
Figure 1.4-2 Single line diagram of Hlawga PS (after rehabilitation) ........................... 1-14
Figure 1.4-3 Single line diagram of the Thaketa PS (before rehabilitation) .................. 1-15
Figure 1.4-4 Single line diagram of the Thaketa PS (after rehabilitation) ..................... 1-15
Figure 1.4-5 Single line diagram of the Ahlone PS (before rehabilitation) ................... 1-16
Figure 1.4-6 Single line diagram of the Ahlone PS (after rehabilitation) ...................... 1-17
Figure 1.4-7 Single line diagram of the Iwama PS (before rehabilitation) .................... 1-18
Figure 1.4-8 Single line diagram of the Iwama PS (after rehabilitation)....................... 1-18
Figure 2.1-1 Location Map of Pharyargyi Substation ..................................................... 2-1
Figure 2.1-2 Layout of Pharyargyi Substation after Phase II Project .............................. 2-2
Figure 2.1-3 Single Line Diagram of Pharyargyi Substation after Phase II Project ........ 2-2
Figure 2.2-1 Location Map of Mawlamyaing 230 kV Substation ................................... 2-4
Figure 2.2-2 Area Map for Construction of New Malamyaing 500 kV Substation......... 2-5
ii
Transmission Project Preparatory Survey Phase III
iii
Transmission Project Preparatory Survey Phase III
iv
Transmission Project Preparatory Survey Phase III
Table 1.2-1 Overview of existing 230 kV transmission lines and substations from
Kamarnat to Mawlamyaing
230 kV Transmission Lines
No. Name of Transmission Line Conductor Size Distance (Miles) Number of Towers
1 230 kV Kamarnat - Sittaung 605 MCM 36.60 136
2 230 kV Sittaung - Thaton 605 MCM 60.25 266
3 230 kV Thaton - Mawlamyaing 605 MCM 49.77 233
230 kV Primary Substations
No. Substation Voltage ratio Capacity 230 kV Transmission Lines Location
(kV) (MVA)
1 Kamarnat 230/33/11 100 + 60 Tharyargone (1) Line Kamarnat village,
Tharyargone (2) Line Bago
Thanlyn Line
Sittaung Line
Myaungtagar Line
2 Sittaung 230/33/11 50 Kamarnat Line Kyeit-hto Township,
Thaton Line Tha-hton District
Theinzayat village
3 Mawlamyaing 230/66/11 50 Thaton Line Mawlamyaing
Myanmar Lighting (IPP) Line
Source: MOEE Website
The system map from Pharyargyi to the southeast, as obtained from DPTSC, is shown in Figure
1.2-1. 500 kV and 230 kV systems are planned from Pharyargyi to the southeast.
1-1
Transmission Project Preparatory Survey Phase III
Phase III is added to this plan because it was not included, and the 230 kV transmission line is also
added based on information from DPTSC that the construction of two 230 kV lines between Kamarnat
and Thaton has been decided. Also the plan of 500 kV lies from Thilawa to Sar Ta Lin is added to this
plan.
1-2
Transmission Project Preparatory Survey Phase III
2 x 265/35 sqmm
40.28 miles Thaephyu Lawpita
230 kV T/L (Existing)
230 kV T/L (Planned/U.C.)
Pyu
1 x 795 MCM 500 kV T/L (Planned/U.C.)
Taungoo 60.55 miles
Kun 230 kV Substation (Existing)
230 kV Substation (Planned/U.C.)
Shewtaung Tharyargone 500 kV Substation (Planned/U.C.)
Power Station
2 x 605 MCM 2 x 605 MCM
65.39 miles 58.8 miles (one side: 336.4 MCM)
Phryargyi
Minhla
2 x 605 MCM Kamarnat Sittaung
62.96 miles 230/33/11 kV 50 MVA
Source: Prepared by JICA Survey Team based on information obtained from DPTSC.
Figure 1.2-2 System configuration in eastern Yangon and southeast from
Pharyargyi
1-3
Transmission Project Preparatory Survey Phase III
Thailand
380 MW
Myawaddy
Pharyargyi
230 kV
80 miles
230 kV
Thaton Mawlamyaing
Kamarnat Sittaung
50 MW 230 MW
1-4
Transmission Project Preparatory Survey Phase III
Figure 1.3-2 Power Demand Forecast in 2030 for the Target Area
1-5
Transmission Project Preparatory Survey Phase III
DPTSC commented that the power supply envisioned for Kanbouk is uncertain and therefore does
not need to be considered in the study for this plan. Therefore, this power source will not be considered.
1-6
Transmission Project Preparatory Survey Phase III
1-7
Transmission Project Preparatory Survey Phase III
Figure 1.3-3 Case 1. Peak power demand period. Maximum output of power
generation facilities
Figure 1.3-4 Case 2. During off-peak power demand. Maximum output of generation
facilities
1-8
Transmission Project Preparatory Survey Phase III
Figure 1.3-5 Case 3. Partial shutdown of power generation facilities during peak
power demand
Figure 1.3-6 Case 4. During peak power demand, all power generation is shut down
1-9
Transmission Project Preparatory Survey Phase III
1-10
Transmission Project Preparatory Survey Phase III
3.5
(P.U. of SIL)
3
2.5
1.5
0.5
(Miles)
0
0 50 100 150 200 250 300
Source: Analytical Development of Loadability Characteristics for EHV and UHV Transmission Lines," R.D. Dunlop, R. Gutman
and P.P. Marchenko, IEEE Transactions on Power Apparatus and Systems, Vol. PAS-98, No. 2, March/April 1979. Or
Power System Stability and Control, P228, 6.1.12 Loadability Characteristics, P. Kundur, 1993)
Figure 1.3-7 Relationship between the transmission distance of an AC transmission
line and the power that can be transmitted stably
The SIL value per line of the 230 kV transmission line in Myanmar is calculated to be about 177
MVA. The heat capacity per line of the standardly-used wire, ACSR 2 x 605 MCM, is 288 MVA,
which is about 1.6 times’ the SIL value.
From the graph, it can be seen that power flow of 1.6 times that of the SIL can be transmitted stably
up to about 150 miles (= 240 km), but beyond that distance, the power that can be transmitted stably
is smaller than 1.6 times that of the SIL and smaller than the thermal capacity. The above guideline is
applied to the rest of the circuits considering an accident at a single circuit in N-1.
1-11
Transmission Project Preparatory Survey Phase III
3.5
(P.U. of SIL)
3
2.5
2
Thermal capacity 576 MVA (2cct)
1.5
1
354 MVA (2cct)
0.5
0
0 50 100 150 200 250 300
Figure 1.3-8 Relationship between the power that can be transmitted stably and the
heat capacity of transmission lines
Pharyargyi Myawaddy
380 MW
Mawlamyaing
230 kV
80 miles
Thaton Mawlamyaing
Kamarnat Sittaung
.
50 MW 230 MW
1-12
Transmission Project Preparatory Survey Phase III
The SIL of a 500 kV transmission line is about 1,000 MVA, which is sufficient to ensure stable
transmission of power.
Note that due to the large charging capacity of the 500 kV transmission line, the voltage increases
at light loads, so a 500 kV shunt reactor is required for compensation. In addition, since the direction
of power flow is not constant, voltage regulation in combination with power capacitors will be required.
In the future, it will be necessary to examine the amount of power that can be transmitted in detail
through stability calculations based on the grid structure of the system in Thailand with the
interconnections.
1-13
Transmission Project Preparatory Survey Phase III
1-14
Transmission Project Preparatory Survey Phase III
1-15
Transmission Project Preparatory Survey Phase III
1-16
Transmission Project Preparatory Survey Phase III
1-17
Transmission Project Preparatory Survey Phase III
1-18
Transmission Project Preparatory Survey Phase III
Layout
As stated above, the Pharyargyi substation is under construction in the Phase II Project.
In this project, the 500 kV H-GIS, 500/230 kV transformers, 500 kV shunt reactors, 230 kV
switchgear (AIS) and control building are planned to be installed in an area of 516 m x 290m, as per
the following figure. In addition, since the 500 kV switchgear for the transmission line to
Mawlamyaing substation and associated equipment like the transmission line protection panel will
also be installed in the Phase II Project, expansion of Pharyargyi substation will not be required and
the scope of work in the new project will cover only the connection of the 500 kV transmission line.
2-1
Transmission Project Preparatory Survey Phase III
500kV Switchyard
230kV Switchyard
Equipment Configuration
The single line diagram for Pharyargyi substation after the Phase II Project is shown in the figure
below. As per another national power transmission network development project by JICA, H-GIS with
a one and a half circuit breaker system is adopted for 500 kV switchgear, and AIS with a double busbar
system is adopted for 230 kV switchgear.
North Side Mawlamyaing S/S Sar Ta Lin S/S
500kV Switchgear
For new 500 kV TL to
Mawlamyaing
230kV Switchgear
2-2
Transmission Project Preparatory Survey Phase III
Design Outline
It is not necessary to install new substation equipment in Pharyargyi substation for the transmission
line to Mawlamyaing 500 kV substation because all such equipment will be installed in the Phase I
Project.
2-3
Transmission Project Preparatory Survey Phase III
230kV Switchyard
TL Tower
66kV Switchyard
TL Tower
Under these circumstances, it is necessary to acquire land for construction of the new 500 kV
substation on the north side of the existing substation. DPTSC mentioned that the DPTSC side was in
the process of selecting a 500 kV substation site near the Kaw Bwee Township. It is recommended to
secure a minimum area of 400 m x 290 m for construction of the 500 kV substation, and Sar Ta Lin
Substation, because the system configuration of the new 500 kV substation in Mawlamyaing will be
similar to that of Sar Ta Lin Substation, which is to be constructed in the Phase III Project.
2-4
Transmission Project Preparatory Survey Phase III
Township Area
Layout
The layout plan for the new Malamyaing 500 kV substation is shown in the following figure.
Although it is so far unclear how much land can be secured for its construction, it is assumed that a
500 kV H-GIS with a one and a half circuit breaker system, as per other Phases by JICA, can be
installed on the land acquired.
Therefore, the layout is considered to be similar to that of Sar Ta Lin Substation, having the
dimensions of 400 m x 290 m, i.e. 30 Acres.
2-5
Transmission Project Preparatory Survey Phase III
To Phayagyi S/S To Kanbouk S/S Spare for future Spare for future
400 m
500 kV H-GIS
290 m
500/230 kV Transformers and Shunt Reators
230 kV AIS
To Mawlamyaing To Myawaddy
Spare for future
230kV S/S 230kV S/S
(Existing)
Equipment Configuration
The new Mawlamyaing 500 kV substation will apply H-GIS with a one and a half circuit breaker
system for 500 kV switchgear, and AIS with a double busbar system for 230 kV switchgear in
reference to similar projects, such as Phase I and Phase II of the JICA project, subject to securing
enough space for construction of H-GIS. Major equipment in the new Mawlamyaing 500 kV
substation is shown in the following table:
2-6
Transmission Project Preparatory Survey Phase III
The following figure shows the single line diagram plan for the new Mawlamyaing 500 kV
Substation. Since this substation will be part of the national power backbone network, it is
recommended to apply one and a half circuit breaker systems for 500 kV switchgear and a double
busbar system for 230 kV switchgear so as to secure reliability for the system, considering
coordination with other phases.
2-7
Transmission Project Preparatory Survey Phase III
500 kV Phayargyi (1) 500 kV Phayargyi (2) 500 kV Dawei (1) 500 kV Dawei (2) Spare for Future Spare for Future Spare for future Spare for future
LT LT LT LT LT LT LT LT
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
M
2,500-1,250/1A 5P20 M
2,500-1,250/1A 5P20 M
2,500-1,250/1A 5P20 M
2,500-1,250/1A 5P20 M
2,500-1,250/1A 5P20 M
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
M M
2,500-1,250/1A 0.2 2,500-1,250/1A 0.2 2,500-1,250/1A 0.2 2,500-1,250/1A 0.2 2,500-1,250/1A 0.2 2,500-1,250/1A 0.2 2,500-1,250/1A 0.2 2,500-1,250/1A 0.2
CVT 3P+0.5
P: 500kV/ 3
S: 110V/ 3 DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA
T: 110V/ 3 M M M M M M M M
DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA
M M M M M M M M
M M M M M M M M
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
M M M M M M M M
500kV System
DS+ES 2,500A, 50kA VT 3P+0.5 DS+ES 2,500A, 50kA VT 3P+0.5 DS+ES 2,500A, 50kA VT 3P+0.5 DS+ES 2,500A, 50kA VT 3P+0.5 DS+ES 2,500A, 50kA VT 3P+0.5 DS+ES 2,500A, 50kA VT 3P+0.5 DS+ES 2,500A, 50kA VT 3P+0.5 DS+ES 2,500A, 50kA VT 3P+0.5
M M M M M M
M P: 500kV/ 3 M P: 500kV/ 3 M P: 500kV/ 3 M P: 500kV/ 3 M P: 500kV/ 3 M P: 500kV/ 3 M M P: 500kV/ 3 M M P: 500kV/ 3
S: 110V/ 3 S: 110V/ 3 S: 110V/ 3 S: 110V/ 3 S: 110V/ 3 S: 110V/ 3 S: 110V/ 3 S: 110V/ 3
T: 110V/ 3 T: 110V/ 3 T: 110V/ 3 T: 110V/ 3 T: 110V/ 3 T: 110V/ 3 T: 110V/ 3 T: 110V/ 3
DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA
M M M M M M M M
M M M M M M M M
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
M 2,500-1,250/1A 5P20 M 2,500-1,250/1A 5P20 M 2,500-1,250/1A 5P20 M 2,500-1,250/1A 5P20 M 2,500-1,250/1A 5P20 M 2,500-1,250/1A 5P20 M M
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
VT 3P+0.5 VT 3P+0.5 VT 3P+0.5 VT 3P+0.5 VT 3P+0.5
P: 500kV/ 3 P: 500kV/ 3 P: 500kV/ 3 P: 500kV/ 3 P: 500kV/ 3
DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA S: 110V/ 3 DS+ES 2,500A, 50kA S: 110V/ 3 DS+ES 2,500A, 50kA S: 110V/ 3 DS+ES 2,500A, 50kA S: 110V/ 3 DS+ES 2,500A, 50kA S: 110V/ 3 DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA
M M T: 110V/ 3 M T: 110V/ 3 M T: 110V/ 3 M T: 110V/ 3 M T: 110V/ 3 M M
M M M M M M M M
DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA
M M M M M M M M
M M M M M M M M
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA GCB 2,500A 50kA
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20 2,500-1,250/1A 5P20
M 2,500-1,250/1A 5P20 M 2,500-1,250/1A 5P20 M 2,500-1,250/1A 5P20 M 2,500-1,250/1A 5P20 M 2,500-1,250/1A 5P20 M 2,500-1,250/1A 5P20 M 2,500-1,250/1A 5P20 M 2,500-1,250/1A 5P20
DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA DS+ES 2,500A, 50kA
M M M M M M M M
CVT 3P+0.5 M M M M M M M M
P: 500kV/ 3
S: 110V/ 3
T: 110V/ 3
500 kV Busbar-B, 6,000A, 50kA
1000/1A 5P20
1000/1A 5P20 200/1A 0.5 200/1A 0.5
CVT 3P+0.5 CVT 3P+0.5
1000/1A 0.5 1000/1A 0.5
P: 230kV/ 3 P: 230kV/ 3
M S: 110V/ 3
T: 110V/ 3
M S: 110V/ 3
T: 110V/ 3
If necessary M
CVT 3P+0.5
P: 230kV/ 3 M M M M M M
S: 110V/ 3 DS DS DS DS
T: 110V/ 3 2,000A 2,000A 2,000A 2,000A
40kA 40kA 40kA 40kA 230 kV Busbar-A, 4,000A, 40kA
230 kV Busbar-B, 4,000A, 40kA
CVT 3P+0.5 DS DS DS DS DS DS DS DS DS DS DS DS DS DS DS DS M M
P: 230kV/ 3 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A
+ESDS
40kA 40kA 40kA 40kA 40kA 40kA 40kA 40kA 40kA 40kA 40kA 40kA 40kA 40kA 40kA 40kA
230kV System
S: 110V/ 3 2,000A
M M M M M M M M M M M M M M M M
T: 110V/ 3 DS+ES 40kA
2,000A M M
40kA
GCB GCB GCB GCB GCB GCB GCB GCB
2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 2,000A 4,000/1A 5P20 4,000/1A 5P20
40kA 40kA 40kA 40kA 40kA 40kA 40kA 40kA 4,000/1A 5P20 4,000/1A 5P20
4,000-2,000/1A 5P20 4,000-2,000/1A 5P20 4,000-2,000/1A 5P20 4,000-2,000/1A 5P20 4,000-2,000/1A 5P20 4,000-2,000/1A 5P20 4,000-2,000/1A 5P20 4,000-2,000/1A 5P20 4000/1A 0.5 4000/1A 0.5
2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 GCB
2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 2,000-1,000/1A 5P20 4,000A
2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 40kA
2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 2,000-1,000/1A 0.2 2,000-1,000/1A 0.2
LT LT LT LT LT LT LT LT
CVT 0.5 CVT 0.5 CVT 0.5 CVT 0.5 CVT 0.5 CVT 0.5 CVT 0.5 CVT 0.5
P: 230kV/ 3 P: 230kV/ 3 P: 230kV/ 3 P: 230kV/ 3 P: 230kV/ 3 P: 230kV/ 3 P: 230kV/ 3 P: 230kV/ 3
4
S: 110V/ 3 S: 110V/ 3 S: 110V/ 3 S: 110V/ 3 S: 110V/ 3 S: 110V/ 3 S: 110V/ 3 S: 110V/ 3
SA10kA T: 110V/ 3 SA10kA T: 110V/ 3 SA10kA T: 110V/ 3 SA10kA T: 110V/ 3 SA10kA T: 110V/ 3 SA10kA T: 110V/ 3 SA10kA T: 110V/ 3 SA10kA T: 110V/ 3
230 kV Mawlamyaing (1) 230 kV Mawlamyaing (2) 230 kV Myawaddi (1) 230 kV Myawaddi (2) Spare for Furure Spare for Future Spare for Future Spare for Future
Design Outline
Applicable Standards
The design, materials, manufacture, testing, inspection and performance of all electrical and
electromechanical equipment shall comply with the latest revision of the International Electrotechnical
Commission Standards (IEC), as listed below:
Instrument transformers – Part 1: Current transformers
IEC 60044-1
Instrument transformers – Part 5: Capacitor voltage transformers
IEC 60044-1
IEC 60071
Insulation coordination
IEC 60076
Power transformers
Surge arresters – Part 4: Metal-oxide surge arresters without gaps for a.c.
IEC 60099-4
systems
IEC 60265-2 High-voltage switches – Part 2: High-voltage switches for rated voltage of
52 kV and above
IEC 60694 Common specifications for high-voltage switchgear and control gear
standards
IEC 61850 Communication network and systems in substations
IEC 62271-100 High-voltage switchgear and control gear – Part 100: High-voltage
alternative-current circuit breakers
IEC 62271-102 High-voltage switchgear and control gear – Part 102: Alternative-current
disconnectors and earthing switches
IEC 62271-203 High-voltage switchgear and control gear – Part 203: Gas-insulated metal
-enclosed switchgear for rated voltage above 52 kV
In cases where IEC standards are not applicable to the conditions, international standards such as
ANSI, ASTM, BS, JIS, JEC and JEM will be applied.
Insulation Coordination
Insulation co-ordination for the design of 500 kV, 230 kV and 33 kV equipment is as follows:
2-8
Transmission Project Preparatory Survey Phase III
2-9
Transmission Project Preparatory Survey Phase III
The associated steel support structures and foundations for the above equipment with all
necessary connecting materials shall be supplied and installed.
The connection work between the dead-end towers, associated gantry structures and the
above equipment shall be carried out and all necessary materials for the work, such as power
conductors, tension insulator sets, fittings, post insulators, connectors, accessories, power and
control cables, etc., shall be supplied and installed.
The above equipment shall be properly earthed with underground earthing mesh and all
necessary materials such as earthing conductors shall be supplied.
2) 230 kV Switchgear
i) 230 kV double busbar scheme switchgear
The 230 kV double busbar scheme includes eight (8) transmission line bays, two (2) transformer
bays and one (1) bus coupler bay.
- 230 kV GCB 11 sets
- 230 kV DS/ES 10 sets
- 230 kV DS 20 sets
- 230 kV CT 11 sets
- 230 kV CVT 12 sets
- 196 kV SA 10 sets
- Line trap 16 sets
- 230 kV busbar 1 lot (Double busbar scheme)
The associated gantry structures for the above system shall be supplied and installed.
The associated steel support structures and foundations for the above equipment with all
necessary connecting materials shall be supplied and installed.
The connection work between the dead-end towers, associated gantry structures and the
above equipment shall be carried out and all necessary materials for the work, such as power
conductors, tension insulator sets, fittings, post insulators, connectors, accessories, power and
control cables, etc., shall be supplied and installed.
The above equipment shall be properly earthed with underground earthing mesh and all
necessary materials such as earthing conductors shall be supplied.
2-10
Transmission Project Preparatory Survey Phase III
Control panels
- Main transformer primary side control panel 2 panels
- Main transformer OLTC panels 2 panels
- 500 kV shunt reactor control panel 2 panels
- 500 kV transmission line control and synchronizing panel 8 panels
- 230 kV transmission line control and synchronizing panel 8 panels
SCADA (SAS)
- Remote control and monitoring system 1 lot
The associated power and control cables with necessary accessories shall be supplied and
installed.
All necessary meters, including ammeters, voltmeters and watt-hour meters, etc., shall be
supplied and installed.
SCADA system shall be designed with control, monitoring and measuring of 500 and 230 kV
switchyard, 500/230/33 kV main transformers, 500 kV shunt reactors and 33 kV switchgear
4) Installation of communication equipment
The following optical-fiber telecommunication equipment shall be supplied and installed.
- Optical distribution frame (ODF) for connection and 24 core optical fiber cable
- Patch cables connecting ODF with synchronous transport module -1 (STM-1) and
multiplexer
- Supply STM-1 and multiplexer with multi channels of not less than 2 Mbit/s interface.
- Optical fiber splicing boxes (i.e., for termination of OPGW on the steel gantry structure in
the substation)
5) Miscellaneous electrical equipment
- Indoor type 500 kVA auto start module type diesel generator set with associated
switchgear, power cables and fuel tank
- 400 V AC distribution switchboard equipped with double-throw breaker including
necessary cables and accessories
- 110 V DC system including two sets of 110 kV battery banks, two sets of chargers, and
one set of distribution boards
- 50 V DC system including two sets of 50 V batteries, two sets of chargers, and one set of
distribution board
- Earthing system covering the new substation area, including earthing rods, conductors, etc.
- Overhead substation shield wire system, including shield wires and supporting structures
for protection against lightning
- Outdoor substation lighting system
6) Civil and building work
The associated civil and building work for the above work shall be carried out as follows:
- Cleaning, cutting, filling, leveling and compacting of the new substation area
- Excavation and backfilling as required
2-11
Transmission Project Preparatory Survey Phase III
2-12
Transmission Project Preparatory Survey Phase III
v) Voltage transformer
Highest system voltage 525 kV
Rated frequency 50 Hz
500 𝑘𝑉 110 𝑉 110 𝑉
Voltage ratio : :
√3 √3 √3
Accuracy classes 3P+0.5
2-13
Transmission Project Preparatory Survey Phase III
2-14
Transmission Project Preparatory Survey Phase III
The 230 kV current transformers shall be single-phase, porcelain-insulated, oil-immersed and air-
tight sealed post insulator type, for outdoor use and shall be designed in accordance with IEC 60044-
1.
Highest system voltage 230 kV
Rated frequency 50 Hz
Rated insulation level
Rated short-duration power-frequency withstand voltage (r.m.s.
a) 750 kV
value)
b) Rated lightning impulse withstand voltage (peak value) 1,550 kV
4,000-2,000 A : 1 A(TL)
2,000-1,000 A : 1 A(TL)
Rated current ratio 4,000 A : 1 A (Busbar)
2,500-1,250 A : 1 A (SS)
1,000A : 1A (SS)
5P20 for protection, Class 0.2 for
Accuracy classes
metering
2-15
Transmission Project Preparatory Survey Phase III
Location of Substations
The target substations for this project are the 500 kV Pharyargyi substation, under construction in
the Phase II project, and the new 500 kV Mawlamyaing substation. The base 500 kV Pharyargyi
substation (Figure 3.1-1) is about 90 km north of Yangon city. The location of the new 500 kV
Mawlamyaing substation (Figure 3.1-2), determined after discussion with C/Ps, is about 170 km
southeast of the Pharyargyi substation in a straight line. There is a Kha-Ngu cultural heritage site near
the Mawlamyaing substation.
3-1
Transmission Project Preparatory Survey Phase III
Source: DPTSC
Figure 3.1-1 500 kV Pharyargyi Substation (Under construction)
3-2
Transmission Project Preparatory Survey Phase III
Transmission Route
Overview of Transmission Route
An overview of the 500 kV transmission route between the Pharyargyi substation and the
Mawlamyaing substation is shown in Figure 3.1-3. The transmission route is based on the following
points.
The shortest distance between substations
Easy to secure access road during construction (South route of the existing 230 kV
Kamarnut―Thaton― Mawlamyaing/North route of the future 230 kV Kamarnut― Mawlamyaing)
The existing transmission route of 230 kV Kamarnut-Thaton-Mawlamyaing is detoured to the north
side before Mawlamyaing in order to link with the Thaton substation, but the study team proposes the
shortest route to avoid the Kalamataung protection forest (Fig 3.1-4).
3-3
Transmission Project Preparatory Survey Phase III
3-4
Transmission Project Preparatory Survey Phase III
3-5
Transmission Project Preparatory Survey Phase III
3-6
Transmission Project Preparatory Survey Phase III
PM1 BH1
PM4
PM18
PM36
BH2
Legend
PM43
PM51
BH3
3-7
Transmission Project Preparatory Survey Phase III
Three boring logs for soft soil areas obtained in the soil literature survey for this project are shown
in Figure 3.2-3~Figure 3.2-5.
3-8
Transmission Project Preparatory Survey Phase III
3-9
Transmission Project Preparatory Survey Phase III
3-10
Transmission Project Preparatory Survey Phase III
Design Conditions
The design conditions are as mentioned below.
Temperature
Maximum air temperature 46 ºC
Minimum air temperature 10 ºC
Annual average temperature 27 ºC
Conductor Temperature
Maximum temperature 75 ºC
Minimum temperature 10 ºC
Wind Velocity
Maximum wind velocity 35 m/s
Wind Pressure
Tower 2,150 Pa
Conductor 900 Pa
Ground wire 970 Pa
Insulator assembly 900 Pa
Pollution Lebel
Medium (IEC standard); 34.7 mm/kV
3-11
Transmission Project Preparatory Survey Phase III
Insulation Design
Type and Size of Insulators
The insulator unit applied to the transmission line is a standard disc type porcelain insulator with
ball and socket, complying with IEC 60305. 210kN type insulators are applied for the suspension
towers and 300kN type insulators are applied for the tension towers. The technical characteristics
of the insulators are shown in the following table
Tower
Tower Type
(a) Type DA
Suspension type tower on a straight section of the line or on a section of the line with a
horizontal deviation angle up to 3 degrees with suspension insulator sets.
(b) Type DB
3-12
Transmission Project Preparatory Survey Phase III
Tension type tower on a section of the line with a horizontal deviation angle up to 20
degrees with tension insulator sets.
(c) Type DC
Tension type tower on a section of the line with a horizontal deviation angle from 20
degrees to 40 degrees with tension and jumper suspension insulator sets.
(d) Type DD
Tension type tower on a section of the line with a horizontal deviation angle from 40
degrees up to 60 degrees with tension and jumper suspension insulator sets.
(e) Type DE
Tension type tower used at the terminal of the line with tension insulator sets having
jumper insulator sets where required with a horizontal angle up to 40 degrees.
3-13
Transmission Project Preparatory Survey Phase III
3-14
Transmission Project Preparatory Survey Phase III
Foundations of Towers
The dimensions of the tower foundations are as per the concept in “National Power Transmission
Network Development Project Phase III” because this transmission line is assumed to be the same
specifications as the 500 kV Phayargyi-Sar Ta Lin transmission line.
The foundations of the towers in this project are shown in Figure 3.3-6 and Figure 3.3-7.
Tower Type DA DB DC DD DE
(a) m 0.60 0.75 0.75 0.75 0.75
Tower Type DA DB DC DD DE
(b) m 0.85 1.00 1.00 1.00 1.00
Chimney Geological Type II II II II II
(f') m 0.50 0.50 0.50 0.50 0.50
(a) m 0.60 0.80 0.80 0.80 0.80
(h1) m 1.50 1.50 1.50 1.50 1.50
(b) m 1.20 1.40 1.40 1.50 1.40
(B) m 3.20 3.20 3.70 4.80 3.50 Chimney
Pad (f') m 0.50 0.50 0.50 0.50 0.50
(t) m 1.00 1.00 1.00 1.00 1.00
Depth of Pad Bottom (H) m 2.00 2.00 2.00 2.00 2.00 (h1) m 3.50 3.60 3.90 4.00 3.80
Length (L) GL-m 34.00 34.00 34.00 34.00 34.00 (B) m 4.30 5.30 6.30 7.00 6.00
Pad
Pile Diameter (D) mm 800 800 800 800 800 (t) m 1.00 1.00 1.00 1.00 1.00
No. of Piles (n) - 4 4 4 4 4 Depth of Pad Bottom (H) m 4.00 4.10 4.40 4.50 4.30
3-15
Transmission Project Preparatory Survey Phase III
Subjects to be Solved
Examination of Pollution Level
Since around 33% of the length of the line passes within 30 km from the sea, examination of areas
where will be applied to IEC pollution level "Heavy" on the route is necessary after selectiing the final
route, and then the appropriate number of insulator will be determined.
3-16
Transmission Project Preparatory Survey Phase III
KBA (Key Biodiversity Area) and IBA (Important Bird and Biodiversity Area) are also important
areas for environmental considerations. KBA are areas containing endangered species in
terrestrial/freshwater/marine ecosystems. There are 123 KBAs in Myanmar. Of the 123 KBAs, 35 are
designated as PA and eight have been proposed as PA. IBAs are sites identified as being globally
important for the conservation of bird populations on the basis of an internationally agreed set of
criteria. Of the 123 KBAs, 57 are registered as IBAs in Myanmar.
Table 4.1-2 Existing PAs and KBAs/IBAs around the project area
No. Name, etc. Area, etc. Overview
Moeyungyi Inn is a dam built in 1904 to supply water to a canal connecting
Region: Bago
Name: the Sittaung and Bago rivers. It was designated as "Moeyungyi Wildlife
Region
Moyungyi Sanctuary" on 22nd April 1988, the aim of this being the following: (1) to
Wetland protect the grazing lands of migratory birds, (2) to conduct research on bird
Area:
1 Wildlife species, (3) to ensure the sustainability of watershed ecosystem services, (4) to
25,598 Acres
Sanctuary make effective use of watershed ecosystem services, (6) to raise the public’s
awareness of watershed ecosystems and their importance, (7) to generate
Distance to
Category: public interest and involvement in conservation, and (8) to support ecotourism.
the project
It was identified as Myanmar's First Ramsar Site in 2004. Moyungyi Wildlife
4-1
Transmission Project Preparatory Survey Phase III
4-2
Transmission Project Preparatory Survey Phase III
Usage Guide
Source: Prepared by JICA Survey Team based on the Forest Department of each township; Protected Area coverage information
(2019) and Integrated Biodiversity Assessment Tool (IBAT)
Figure 4.1-1 Location of the PAs around the project area
4-3
Transmission Project Preparatory Survey Phase III
4-4
Transmission Project Preparatory Survey Phase III
Usage Guide
Source: Prepared by JICA Survey Team based on the Forest Department of each township; RF, and PPF Area coverage information
(2019)
Figure 4.1-2 RFs and PPFs around the project area
4-5
Transmission Project Preparatory Survey Phase III
Table 4.1-4 Overview of the topographical characteristics around the project area
Region/State Area Township Overview
Bago township is located at the bottom of the Bago Yoma Range, and the
western part of the township is a highland area covered with forests. The
Bago
township is 21 miles from east to west and 43 miles from north to south, and
Bago Region Bago has an altitude of about 30 m above sea level.
The topography of Waw township is flat-plain surfaces and a lowland area
Waw covered with water in the rainy season. It is situated about 23.8 feet above
sea level.
Kyaik Hto is located 35 feet above sea level with the mountain ranges in the
Kyaik east, south and north, and valleys in the West. The highest mountain is the
Hto Kyaik Htee Yoe mountain in this township, and this is located 36,158 feet
above sea level.
Belin township features a flat-plain surface covered with forest, and it is
Belin
situated about 30 feet above sea level.
Thaton township is located 17.6 feet above sea level, and it has a large
mountain range in the middle of Thaton township, which runs from East to
Thaton
Thaton West. Hills covered by forest can be found in this township, running from
North to South.
Mon State The topography of Paung Township is plain surfaces, except for the
mountains which are located in the middle of the township. It has the Zin
Kyaik mountain, Kalama mountain, Nwar La Bo mountain and Mottama
Paung mountain range, which runs from North to South. Among these mountains,
the Kalama mountain is famous in this township. There are three islands in
Paung Township. One is inhabited, and the other two are uninhabited. Paung
Township is located 24 feet above sea level.
The topography of Kyaik Mayaw Township is bounded by the Gyaing river
Mawla Kyaik basin to the North, Ataran river basin and Taung Nyo mountain range to the
Myaing Mayaw West. They have an elongated shape, from the North-West to the South-
East. This township is situated 18 feet above sea level.
Hpa-an Township is mostly highland, with a percentage of lowland
Hpa- topography. The Zwekabin mountain, which is 2727 feet high, and its
Kayin State Hpa-An
An summit are located 9 miles from the South region of this township. Hpa-an
Township is located 53 feet above sea level.
Source: General Administrative Departments, October 2019
4-6
Transmission Project Preparatory Survey Phase III
Usage Guide
4-7
Transmission Project Preparatory Survey Phase III
4-8
Transmission Project Preparatory Survey Phase III
Usage Guide
4-9
Transmission Project Preparatory Survey Phase III
Per an example of a DPTSC-implemented transmission line project and interviews with MONREC-
ECD, which is the implementing organization for EIAP, no transmission line project has required EIA.
In addition, the JICA National Power Transmission Network Development Project Phase III in
Myanmar was classified as two IEE projects as a result of screening by MONREC-ECD. Since there
is one RF and the total length is about 200km of the planned transmission line route, it is considered
that there is a possibility that EIA will be required as a response on the Myanmar side. In actual fact,
there are many unclear parts because MONREC-ECD will classify the Project. The RF can be
modified through appropriate procedures.
4-10
Transmission Project Preparatory Survey Phase III
Table 4.1-8 Overview of this Project in line with JICA Guidelines for Environmental
and Social Considerations (2010)
Category Contents Overview of this Project
(6) Power transmission and distribution lines Technically, large-scale involuntary
1. Illustrative List of
involving large-scale involuntary resettlement, resettlement and large-scale
Sensitive Sectors
large-scale logging, or submarine electrical cables deforestation can be avoided.
(1) Large-scale involuntary resettlement Technically, (1) Large-scale
(2) Large-scale groundwater pumping involuntary resettlement and (4)
(3) Large-scale land reclamation, land Large-scale logging can be avoided.
2. Illustrative List of development, and land clearing The Project does not have any
Characteristics (4) Large-scale logging activities related to (2) Large-scale
groundwater pumping, or (3) Large-
scale land reclamation, land
development, and land clearing.
(1) National parks, nationally-designated
protected areas (coastal areas, wetlands, areas for
ethnic minorities or indigenous peoples and
No direct alterations are expected for
cultural heritage, etc. designated by national
protected areas, cultural heritage, or
governments)
key areas of biodiversity conservation
(2) Areas that are thought to require careful
(KBA). Although the project passes
consideration by the country or locality
through one RF, it is a reserved forest
1) Primary forests or natural forests in tropical
for commercial/local supply/water
3. Illustrative List of areas
collection protection under national
Areas 2) Habitats with important ecological value (coral
law and this can be modified through
reefs, mangrove wetlands, tidal flats, etc.)
related procedures. In addition, it will
3) Habitats of rare species that require protection
not modify vulnerable areas, such as
under domestic legislation, international treaties,
areas where soil erosion is likely to
etc.
occur and areas where desertification
4) Areas in danger of large-scale salt
tends to occur.
accumulation or soil erosion
5) Areas with a remarkable tendency towards
desertification
Note: The numbers listed correspond to the numbers listed in Appendix 3 of the JICA Guidelines for Environmental and Social
Consideration Guidelines (2010).
Source: Prepared by JICA Survey Team based on the JICA Guidelines for Environmental and Social Considerations (2010)
The Gayang River is situated at a distance of about 1.7 km north-east from the north-east corner of
4-11
Transmission Project Preparatory Survey Phase III
Figure 4.2-1 Satellite Photo of the Proposed Substation Site and Surrounding Area
Count of properties
Properties were identified and counted using satellite photos mainly taken in December 2018 (Table
4.2-1, Figure 4.2-2).
The site consisted of rice paddies. Scattered trees were counted at about 34.
The square shapes within the site are expected to be artificial roofs, and the several of them are
found on site depending on the photos. The size of the roofs is small at about 4 m on one side, compared
to about 10 m on one side in the village houses. The structures are, therefore, probably seasonal huts
for resting and storage.
4-12
Transmission Project Preparatory Survey Phase III
Satellite Photo Analysis of the Proposed Route for the 500 kV Transmission
Line Between Phayargy and Mawlamyaing Substations
The proposed route for the transmission line between Phayargy and Mawlamyaing Substations was
studied using satellite photos of the surrounding area collected from Google Earth.
It was found that the route passes mainly rice paddies and rubber plantations. Structures are located
within the ROW (30 m one side) at a few locations. In the detailed study for the tower locations, it
will be possible to ensure those structures are not included in the ROW and avoid impacts (Table 4.2-2,
Figure 4.2-3).
Advice for the detailed study on the ROW location covers the following 4 points.
1. Minimize the clearance of productive rubber trees. Where clearance cannot be avoided,
adequate counter measures such as compensation will be implemented.
2. In areas susceptible to flooding or inundation, areas with soft soil, or areas that may be affected
by cyclones, the towers must be well-designed to be resilient to those conditions, and the lines
must be monitored closely so that electrical accidents and black-outs are avoided.
3. Impacts on farmland, paddies, residential structures, schools, religious facilities, and other
public infrastructure must be minimized. Where the impacts cannot be avoided, adequate
counter measures such as compensation will be implemented.
Table 4.2-2 Study of the Proposed Route for the 500 kV Transmission Line Between
Phayargy and Mawlamyaing Substations
PM PM State Prominent environment Significant features
Start End Paddies Rubber Woodland Other
1 2 Bago X X
2 3 Bago X
3 4 Bago X X X Sand quarries
4 5 Bago X Canal
4-13
Transmission Project Preparatory Survey Phase III
4-14
Transmission Project Preparatory Survey Phase III
4-15
Transmission Project Preparatory Survey Phase III
4-16
Transmission Project Preparatory Survey Phase III
4-17