White Paper - Exploring Distribution Network Automation
White Paper - Exploring Distribution Network Automation
Distribution
Network
Automation
Automation of the electricity distribution grid provides substantial economic benefits for
utilities and society. Effective fault location and network restoration can in most cases be
converted to an algorithm, enabling the optimisation of network reliability and providing
resilience to network faults.
T
he techniques for achieving distribution network automation Logically, the intent is to maintain uptime of power availability for the
are varied, and whilst the merits of automation can be lauded critical load. Therefore, Recloser 1, the main supply, stays closed. In
as “network modernisation”, carefully considered automation this state, recloser 2 will be normally open (NO), and will see voltage
can create genuine returns for utilities. In the electricity distribution on both sides of the open circuit breaker. If supply 1 fails, Recloser 1
context, Distribution System Automation (DSA) can be summarised can detect this condition and open. Recloser 2 also notes the loss of
as the automation of reclosing (of circuit breakers) and switching supply and commences a countdown timer before closing in Supply
(of load break switches or isolators), with the goal of restoring 2. To prevent back-feeding into Supply 1, the only criteria necessary
power to the largest number of customers in the smallest, safest is for the opening recloser to be faster than the closing one. In this
time interval. This article covers the many Distribution Network case, Recloser 1 should trip on undervoltage before Recloser 2 closes
Automation techniques available to Power Systems engineers. The to restore power. NOJA Power’s OSM Reclosers can be configured
cases explored are: to re-arm their voltage restoration closing function if they opened
1. Simple Automation due to loss of supply, such as the Recloser 1 case mentioned above.
2. Auto Change Over (ACO) with Peer to Peer (P2P) Communications
3. Distributed Automation Benefits:
4. Centralised Automation Primary benefits of this system are simplicity and cost – there are no
5. IEC 61850 for Automation. communications systems necessary to implement the automation,
and only two reclosers to control the switching. The term “Critical
SIMPLE AUTOMATION Load” is also quite broad, not only could the load be a single building
The most elementary case is of an Auto-Changeover Scheme such as a hospital, but this method has been applied for supply to
without peer to peer communications, which is where we begin entire suburbs or towns, where two supply feeders at either ends
to explore the techniques and evaluate their costs, benefits and of the town work in tandem by sensing the voltage presence and
limitations of the simple Auto Changeover Scheme achieved with switching supply on the failure of the main supply.
Reclosers and no communications necessary. This case uses voltage
sensing on both the Supply and Load side of the Autorecloser. Drawbacks
The core issue is if there is a fault between the circuit breakers and the
load, the restoration system will cause an additional close onto the
fault, and hence a reenergisation of the fault site. This is a common
theme for automation schemes that do not have communications,
but if this additional single reclose is tolerable for the scenario then
the simple automation system can be highly effective in improving
network reliability.
Another possible challenge is the training of operations
personnel to understand that opening one circuit breaker,
particularly for line work, can cause another breaker to close
and energise the circuit. In our experience, this is handled well
through signage and interlocks at the controller site. Another
option is to have centralised communications to both devices,
Figure 1 A simple ACO Scheme allowing remote operators to disable the automation before work
commences, but this adds complexity and cost, prompting the a topology with two incomers and one outgoing feeder. This unit
next evolution of distribution network automation: the inclusion can be used to achieve the above scheme in a single product.
of P2P communications for an ACO scheme.
Drawbacks
AUTO CHANGE OVER WITH PEER TO PEER The key drawback of this implementation is the addition of
COMMUNICATIONS communications. In areas where the geographic distance between
Now whilst the basic automation system described above is the the two reclosers becomes large and if communications are
cheapest, most simple system for implementing an automation unreliable, the scheme becomes less effective. However, it remains
scheme, it does have one major drawback: if the fault is in the the most popular simple automation scheme used in the electricity
critical load, without communications the devices will execute at distribution network worldwide.
least one extra close onto the fault.
The primary reason being that the Normally Open (NO) recloser DISTRIBUTED AUTOMATION - AUTOMATING RING
has limited scope to detect if there was a downstream fault while it NETWORKS WITHOUT COMMUNICATIONS
was open, as the fault current is not flowing through the NO recloser. Our first example demonstrating Smart Grid Automation without
It will then close onto the fault to attempt supply restoration, before communications is a concept that can be applied to the broader
tripping on protection itself. grid, with some forethought of the scenarios of network switching
that are likely to occur. When considering the design of reliable
Solving the Close-Onto-Fault Scenario: distribution networks, the “Ring” type network topology is
Simply, to stop closing onto faults, the reclosers need to be able to commonly used.
inform each other of fault passage, blocking the automation when a
downstream fault occurs. This Peer to Peer communications scheme
is so common in Recloser applications, that NOJA Power’s OSM
Recloser system has a dedicated ACO function designed to achieve
this as standard.
In this case, Recloser 2 now has reverse power flow to standard Whilst 250ms is conservative by modern recloser standards (150ms
operation. Therefore, the use of directional protection becomes grading is comfortably reliable with modern equipment), it does
essential to provide grading. Under normal system configuration, limit the number of protective devices that can be switched in.
Recloser 2 is the furthest from the substation, closest to the tie Unless the devices switched in are Sectionalisers.
point. If supply 2 fails, it becomes the 2nd closest to the substation, If we consider the case of figure 3, but let’s assume a more
with 3 other downstream devices. In the case above, it becomes the conservative grading margin of 300ms with a 1 second substation
furthest recloser from the substation – each case requiring its own breaker time, we can only fit 3 protective reclosers in before the
protection grading. substation would trip. Under system normal, this would be easily
A quick reminder, Protection grading is the coordinated handled, but adding the two extra reclosers during an automation
configuration of tripping responses so that protection devices operation (R3 and R2), a race condition will be created if a fault
coordinate with each other to ensure the minimum zones are occurs between R1 and R2.
impacted by faults. In this case, we have three protection scenarios But if R2 is configured to operate as a sectionaliser in the reverse
we need to account for in our grading. We’ll use Recloser 2’s settings current flow direction, its response becomes determinate and it can
as our reference, although this simple situation analysis should be be graded with the rest of the system. R2 then acts as a normal
applied to all devices in the scheme for confirming settings. recloser in the System Normal and Supply 2 Failure cases, but under
the Supply 1 Failure case it will allow fault passage and open in the
dead time of the upstream breaker. By having the Recloser act as a
SCENARIO DIAGNOSIS CONSIDERATIONS sectionaliser in the reverse power flow condition, we can be assured
that the risk of mal-grades are mitigated.
Smart Grid Automation achieved using distributed logic based
System Normal Fastest tripping Can be automatically
on voltage presence is a highly reliable, cost effective method of
device, furthest switched to take
from the substation on the load implementing the smart grid. Without needing communications,
up to Recloser it is possible to effectively re-switch the network to isolate faults,
5. Therefore, and in this article we explored some of the technical considerations
Overcurrent and required for designing protection settings for these automatic
ratings need to allow switching networks. By using a scenario method, evaluating the
for load, and graded
up to R5
required protection settings becomes generally straightforward,
with a few constraints based on the amount of load that could
plausibly be added. These are generally considered when ring mode
Supply 2 Fails 2nd device in chain Need to grade with networks are designed originally, however it is worth revisiting the
R3, R4 and R5,
protection settings when developing an automation scheme.
USING IEC 61850 IN AUTOMATION For further information, contact NOJA Power or visit
Whilst IEC 61850 is traditionally considered confined to larger www.nojapower.com.au
substations, IEC61850 Generic Object Oriented Substation Event
(GOOSE) Messaging has niche applications in achieving DSA when
applied to distributed pole mounted switchgear.