Technicalspecification 7
Technicalspecification 7
For
TABLE OF CONTENTS
Sr. Description
No.
1 Scope of Work
4 General Technical & Particular Requirements for Electrical, Instrumentation & Control
Equipment/ Systems
5 Safety Equipment’s/ Requirements and Miscellaneous Items
Contractor
Executive Engineer Page2
Volume II: Technical Specification for
Electrical &Instrumentation Works
1. SCOPE OF WORK:
1.1. The scope of services covers the design, detailed engineering, preparation of
construction drawing, manufacture, acceptance testing at manufacturer’s works or
at any accredited agency, supply, packing, forwarding and delivery from
manufacturer’s works/ place of storage to erection site including transit insurance,
unloading, storage at site, assembly, erection, testing, commissioning &
performance demonstration and handing over along with all necessary spares of
original ratings & specifications on Design, Build& Operatebasis.Inland and
overseas transit insurance, transport, testing at site shall be Contractor scope.
Tender Bill of Quantities and Drawings are for reference purpose only which is the
minimum requirements for the water supply system including raw water Intake,
various Headwork/Sub-Headwork with/ or without water treatment facility as
applicable ;Contractor to ensure that design &equipment’s are as per specification
requirements.
1.2. The Contractor shall prepare design calculations based on parameters/ design
criteria indicated in the specifications. The Contractor shall prepare detailed
engineering and construction purpose drawings to make his/ her own estimate of
ratings & quantities (minimum requirements as per price schedule, technical data
sheets, reference drawings& other relevant details) for entire electrical &
instrumentation systems including all items, systems such as equipment’s, cables/
cabling system, lighting, ventilation, earthling, lightning protection, main & auxiliary
power distribution, instruments, civil works required for completion of Works.
1.3. Contractor shall take due care of the site Seismic conditions while design of all
equipment’s/ components used in entire electrical & instrumentation systems
covered in this specification. Contractor shall furnish list of additional design
parameters considered in design to fulfill above requirement.
1.4. Design and detailed engineering of the materials procured by Contractor is included
in scope. Contractor shall submit design drawings/ calculations of each system
which is included in scope to Purchaser/Purchaser’s representative for final review/
approval. All design documents/ calculations prepared by Contractor shall be as per
ISO documentation i.e. With duly singed by qualified authorities and stamped.
Design documents/ calculations prepared by Sub-Contractors shall be approved by
Contractor and stamped copy of approval along with no-deviation sheet from SUB-
ContractorshallbesubmittedbytheContractortoPurchaser/ Purchaser’s representative
for final review/ approval.
1.6. Contractor shall be solely responsible for any shortages or damages in transit for
his supply scope, handling and/ or in storage of any materials and erection of the
equipment, supply of erection tools at site. Contractor shall ensure that it will not
affect any activity or project schedule. Any demurrage, wharf age and other such
charges claimed by the transporters, railways etc. shall be to the account of the
Contractor.
1.7. Contractor shall identify activities and mile stones of the work forecasted for next
month with optimistic and pessimistic dates of work completion. Contractor shall
prepare program evaluation and review techniques to identify critical path of project
and activity sequences. The project schedule shall be prepared and updated
Contractor
Executive Engineer Page3
Volume II: Technical Specification for
Electrical &Instrumentation Works
fortnightly in MS Project.
1.8. Nothing in this specification shall be constructed to relieve the Contractor of his/ her
responsibilities towards following best engineering practices established in the
country.
1.9. Obtaining approval including load sanction/ release from Himachal Pradesh State
Electricity Board (HPSEB), No Objection Certificates from HPSEB,Electrical
Inspector, relevant government agencies, statutory authority, as applicable is
included in Contractor’s scope.
1.10. All necessary legal fees required for various applications to HPSEB/ Electrical
Inspector, relevant government agencies, statutory authorities shall be paid by the
Purchaser. The HPSEB deposit required to be paid for load sanction/ release shall
also be borne by the Purchaser.
1.12. Even if all components of a system included in this specification are not explicitly
identified and/ or listed herein, these shall be supplied under this contract to ensure
completeness of the system and facilitate proper operation and easy maintenance
of the plant. Any and all other works not indicated above but necessary/ required to
complete the system in all aspects, are included in the Contractor’s scope.
1.13. The Contractorshall include start up spares, essential spares, recommended spares
and a set of special tools necessary for operation, routine maintenance of
equipment supplied for a period as specified in this contract.
1.14. Whether specifically called for or not, all accessories required for normal and
satisfactory operation (as deemed by the Purchaser) of the equipment shall be
considered to be a part of the Contractor’s basic scope of supply and/ or work and
no claims whatsoever, for extra payment on these grounds, will be accepted.
1.15. Contractor should visit site and get him/ her ascertained regarding the scope of
work for the complete Electrical & Instrumentation works before submission of
quote/ offer.
1.16. Contractor’s scope shall include design, engineering, manufacture, supply, testing,
commissioning and handover of following electrical equipment/ systems as per
tender specifications, BOQ, reference drawings and other relevant details as per
the requirements of Engineer-in-charge.
1.16.1. Tariff metering equipments applicable (as per HPSEB requirement) & electric
supply connectionincluding necessary liaison works (Tariff metering equipment &
electric supply connection shall be provided by HPSEB for which necessary liaison
shall be done by the Contractor)
1.16.2. Switchyard Equipment (if required) -Two/ four pole structure (required to receive
incoming 11/ 33 kV power supply from overhead line/ cable and to extend out
required feeders), Bus bars, Isolators (GOD) with operating mechanism, Earth
Switches, Lightning Arrestors, Incoming point of supply Breaker/ Ring Main Units
Contractor
Executive Engineer Page4
Volume II: Technical Specification for
Electrical &Instrumentation Works
outdoor type (required where installed capacity of transformer(s) exceeds 800 kVA/
or as per statutory requirement) & Drop Out Fuses (wherever applicable for
transformer(s) being fed directly from incoming power supply)etcincluding
necessary civil works, fence & gate etc.
1.16.3. Oil type, ONAN, Dyn11, Power/ Distribution Transformer(s) with OCTC/ OLTC +
RTCC, AVR, Marshalling box.
1.16.4. 11/ 6.6 kV Metal Enclosed Switchgears indoor type with Vacuum Circuit Breakers/
Vacuum Contactors/ Load Break Switches fully draw out including necessary
control, metering & relaying devices.HVMotor Starters& necessary Capacitor Banks
as per system requirement.
1.16.5. 415 V Metal Enclosed Switchgears including Power & Motor Control Centre
(PMCC) including Starter Panels, PDBs, Sub DBs, Lighting DBs, Receptacles for
utilities. Local Start/ Stop Push Button Stations shall be provided near those motors
which are not controlled from a Local Console/ Panel.
1.16.6. 415 VCapacitor Banks with control panel consisting of automatic power factor
correction (APFC) relay to improve the plant power factor up to 0.99. APFC panels
shall be provided on both bus sections of the PCC/ MCC.
1.16.7. Cabling system shall consists of various HV/ LV grade, XLPE/ PVC insulated, multi-
stranded Al/ Cu, GI round wire/ flat strip armoured power, control & instrumentation
cables, GI ladder/ perforated type Cable Trays & associated accessories including
support structures.
1.16.8. Provision for continuous monitoring of electrical Power & Energy parameters like
Voltage, Current, Power Factor, Frequency, Kilo Watts, Kilowatt-Hours etc.
1.16.9. Earthing for HV/ LV equipments and lightning protection system for all buildings in
the plant premises. The general design shall be on the basis of following codes and
standards (their latest amendments) in line with design criteria &specification
requirements.
1.16.10. Lighting system for all indoor & outdoor areas of plant(s). The lighting system will be
controlled by lighting panels installed in respective plant/ station areas, which will be
fed from the main lighting DB.
1.16.11. DC System:
a) 24/ 30V or 110V DC in built DC power pack unit shall be provided wherever
applicable.
b) 24/ 30V or 110V DC Battery & Battery Charger (with inbuilt DCDB) shall also be
provided wherever applicable.
Contractor
Executive Engineer Page5
Volume II: Technical Specification for
Electrical &Instrumentation Works
1.17. Contractor’s scope shall also include design, engineering, manufacture, supply,
testing, commissioning and handover of following Instrumentation & control
equipment/ systems as per tender specifications, BOQ, reference drawings and
other relevant details.
1.17.1. Wherever applicable, Programmable Logic Controller (PLC) based control &
monitoring system with HMIshall be implemented, covering the required functional
& operational requirements of the plant involving measurement, control, alarm &
interlocking functions.
1.17.2. All instruments & analysers as required for monitoring/ control/ alarm/ interlocking
functions involved in the process.
1.17.3. All erection hardware and accessories like branch cable trays from field sensors to
Junction boxes & from junction boxes to remote panel/ PLC cabinets, impulse tubes
with fittings & accessories, drain/ vent valves, root valves, cable glands, structural
frames/ supports, expander & reducer etc. as required for complete & proper
installation of the instrumentation & control equipment/ systems.
1.17.4. Instrumentation, control & any other special cables as required for entire system
under Contractor’s scope.
1.17.5. Electronic earth pits, as per applicable standard & also meeting automation
Contractor’s requirement and including supply & laying of earthing cables with
required accessories.
1.17.6. All necessary and supplementary items & equipment required for completeness,
safe & efficient operation of the system, even though these may not have been
mentioned in this specification. Spares & consumables for successful
commissioning, establishment of performance guarantee and five years of trouble-
free & safe operation of the plant.
1.18. Submission of drawings & documentation as specified under ‘’General Technical &
Particular Requirement’’ section for Electrical, Instrumentation & Control equipment/
systems.
1.19. Contractor’s scope shall also include all civil works required for electrical &
instrumentation equipment/ structure such as equipment foundations, indoor &
outdoor trenches, equipment support structures, two pole structures, flow meter
chamber, control rooms, all excavation works including those for earthing, cabling
etc, de-tanking area, soak pits, burnt oil pits, chamber etc.
1.20. It is not the intent to completely specify all details of design and construction herein.
Nevertheless, the Electrical, Instrumentation & Control system shall conform to high
standard of engineering, design and workmanship in all respects and shall be
capable of performing satisfactorily in continuous commercial operation under the
specified environmental conditions.
1.21. Purchaser reserves the right to issue addendum to the technical specification to
indicate modification/ changes in the requirements, if so required at a later date.
1.22. The pumping machinery shall be installed on a base plate designed and
manufactured by the principal manufacturer of the machinery The foundation of the
machinery should be properly designed with proper anchorage. All electrical
Contractor
Executive Engineer Page6
Volume II: Technical Specification for
Electrical &Instrumentation Works
Contractor
Executive Engineer Page7
Volume II: Technical Specification for
Electrical &Instrumentation Works
speed motor
/Pressure/Vacuu IS:3624- Feibig /Bouden
m Gauges 1979
Plant Power Distribution Voltage: 11/ 6.6 kV, 3 Phase, 3 Wire, 50 Hz, AC
Control, Protection & Emergency Lighting: 24/ 30 or 110V, 2 Wire DC (as applicable)
2.2.4. Voltage Variation: 10%, Frequency Variation: 5%and Combined Voltage &
Frequency Variation: 10%
Contractor
Executive Engineer Page8
Volume II: Technical Specification for
Electrical &Instrumentation Works
3.1. GENERAL:
3.1.1. The design criteria, given below has to be followed by the Contractor for designing/
sizing of electrical, instrumentation & controlequipments covered under Contractor’s
battery limits; However it is to be noted by the Contractor that, following this design
criteria does not relieve the Contractor from adherence to the standards, regulatory
requirements & best engineering practices.
3.2.6. Wherever,HV supply (for load demand above 100 kVA/ or as per HPSEB rules
prevailing at that time) is envisaged, 100% stand-by shall be provided for
transformers.All the associated equipments/ accessories shall be provided for
stand-by transformer as well. In normal condition, both the transformers shall feed
their respective bus sections by keeping bus coupler open & in case of failure of
one transformer, the other transformer shall be able to take 100% load with bus
coupler in close position.
3.2.7. The Load losses and No-load losses of transformer shall be within the values given
in IS 1180-2014/ or latest applicable standards.
Contractor
Executive Engineer Page9
Volume II: Technical Specification for
Electrical &Instrumentation Works
3.3.2. Switchgear for all the motor feeders shall be as per Type-2 coordination.
d) Soft Starter – For all low/ medium voltage motors above 75 kW rating.
iv. Bus bars being inside the panel; De- ration for enclosure and ventilation.
vii. Bus bars shall withstand the short time rating of the panel for 1 sec
duration.
3.4.2. Capacitor shall be All Poly Propylene (APP), double layer type.
3.4.3. Fixed type capacitor bank, with manual & auto switching and components as
indicated in reference electrical Single Line Diagram(s) shall be provided in each
mains incomer (LV) panel for transformer no load compensation.
3.4.4. For each bus section of the Main LV PCC/ MCC panel, separate APFC panel-
Contractor
Executive Engineer Page10
Volume II: Technical Specification for
Electrical &Instrumentation Works
based on above design criteria to be provided. Other requirements of APFC panel &
its components shall be as per requirement provided in this specification.
3.4.5. Total capacity &capacitor bank sizes shall be as given in Table below:
(*) = Contractor has to calculate the capacitor rating based on the system power
factor (0.85 or actual, whichever is lesser - to be corrected for 0.99. Rating of APFC
panel shall be based on 50% of running load on each bus section & not on the
connected load basis. Number of stages/ steps in a particular APFC panel shall be
decided by the Contractor such that minimum 8 steps & maximum 16 steps shall be
provided in a particular panel.CT changeover scheme when only one transformer is
running to be considered.
Contractor
Executive Engineer Page11
Volume II: Technical Specification for
Electrical &Instrumentation Works
3.5. CABLE SIZING: The Contractor shall ensure that cable and wires associated with
the power distribution and control systems, plant wiring and all other installations
throughout the Works are adequately rated for their use.
3.5.1. The following main aspects shall also be considered while deciding the final size of
the cables-
b) All cables shall be selected to carry the corresponding full load current under
site conditions.
d) Maximum allowable temperature rise under normal full load condition based
on the material of cable insulation (XLPE/ PVC).
e) Maximum short circuit current duration (fault clearing time) and final
temperature of cable during short circuit current flowing through the cable.
f) For Cables emerging from ACB outgoing, fault clearing time shall be
considered as 0.16 second (for Tie feeders if any it shall be 0.5 second)
g) For Cables emerging from MCCB outgoing, fault clearing time shall be
considered as 0.01 second
i) For cable from HV panel outgoing to transformer, fault clearing time shall be
considered as 0.16 second.
j) Cable from transformer secondary to PCC incomer, fault clearing time shall
be 1sec
k) Contractor to note that, the above fault clearing times are minimum to be
considered & fault clearing time shall be considered as per actual relay co-
ordination study.
iv. Depth of cable burial (minimum 750 mm for LT and 900 mm 11kV HV)
Contractor
Executive Engineer Page12
Volume II: Technical Specification for
Electrical &Instrumentation Works
m) Permissible voltage dips at the time of starting the corresponding motor/ load.
Contractor to ensure adherence to the Criteria-2 mentioned above.
n) In running condition, cumulative voltage drop (at 100% rated load) shall not
exceed 5% (measured at load end) for the LV loads.
3.6. ILLUMINATION SYSTEM: Illumination for various indoor & outdoor areas shall be
conforming to the requirements mentioned below:
3.6.1. The illumination levels to be considered for the design of lighting system for various
areas shall be as following. These are the illumination levels achieved at Work
plane. Work plane height shall be considered as 0.76 m from FGL.
Area Illumination Level (Lux) - Average values
3.6.2. Critical lighting shall be designed such that at all junctions, exit passages &
strategic locations the Lux level shall be maintained above 10 Lux. Installite fixtures
with built in battery backup shall be considered.
3.6.3. Lighting design shall be performed using DiaLux Software Version 4.5 or its latest
version/ Original Equipment Manufacturer (OEM) validated software. The Validation
Report along with software and data files shall be acceptable to Purchaser/
Contractor
Executive Engineer Page13
Volume II: Technical Specification for
Electrical &Instrumentation Works
Purchaser’s representative.
a) Maintenance Factor:
i) Outdoor area : 0.6 (0.7 for LED)
ii) Indoor areas : 0.7 (0.8 for LED)
b) Reflectance Factors:
i) Wall : 30%
ii) Ceiling : 10%
iii) Floor : 30%
c) Uniformity (Min. / Avg.) : 50% Minimum for indoor and 30% for outdoor
3.7.1. The safety earthing and lightning protection system will be generally on the basis of
following codes and standards (including their latest editions).
b) IEEE 80 - 2000.
c) IS/ IEC 62305 - 2013: Code of Practice for the protection of buildings and
allied structures against lightning.
3.7.3. Following factors shall be considered for sizing the earthling conductor:
Contractor
Executive Engineer Page14
Volume II: Technical Specification for
Electrical &Instrumentation Works
substation.
3.7.4. Measurement of soil resistivity shall be done using Wenner’sfour (4) electrode
method as described in IS 3043 -1987(Reaffirmed in 2006) including its latest
amendment.
3.7.5. The soil resistivity of the plant area has not yet been measured; the same should be
carried out during detailed engineering by successful Contractor.
3.7.6. After soil resistivity measurement; length of conductor, number of earth electrodes
and no. of test pits shall be finalized based on these design criteria & the
requirements specified in earthling requirements.
3.8.2. The instruments complete with all the necessary mounting accessories shall be
designed to work at the ambient conditions of temperature, humidity, and chlorine
contamination that may prevail
3.8.3. Instruments mounted in field and on panels shall be suitable for continuous
operation of plant. Wherever required, lockable & tamperproof enclosure shall be
provided for all the field mounted instruments.
3.8.4. All electronic components shall be adequately rated and circuits shall be designed
so that change of component characteristics shall not affect plant operation.
3.8.5. The outdoor equipment shall be designed to withstand tropical rain. Wherever
necessary, space heaters, dust and water proof cabinets shall be provided.
3.8.6. Unless otherwise specified, the normal working range of all indicating instruments
shall be between 30% and 70% of the full scale range.
3.8.7. Unless otherwise stated, degree of protection for field mounted electrical and
electronic instruments shall be IP-67. All instruments of submersible type shall be
protected to IP-68.
3.8.8. Unless otherwise stated, overall accuracy of all measurement systems shall be ±1%
or better of the measured value.
3.8.9. Dual redundant SMPS shall be used for powering 24V DC Instrumentation, Control
& Automation equipment’s.
3.8.10. For all the field mounted transmitters, output signal shall be 4-20 mA DC isolated
with HART Protocol (version 6 & above) and field transmitters shall be provided with
the back lit LCD/ LED display.
3.8.11. Electronic instruments shall be of proven design and shall utilize solid state
electronic components, integrated circuits, microprocessors, etc.All digital outputs
from the instruments shall be volt free.
3.8.12. The relay/ switch contacts shall be rated for the voltage of the circuit in which they
Contractor
Executive Engineer Page15
Volume II: Technical Specification for
Electrical &Instrumentation Works
are to be wired.
3.8.13. All indicating meter shall be of the digital type with no moving parts. Zero and span
adjustments shall be provided for all instruments.
3.8.14. After a power failure, when power supply resumes, the instruments and associated
equipment shall start working automatically.
3.8.16. The field instruments i.e. the instruments mounted outside the control panel shall be
mounted at a convenient height of approximately 1.2 meter above grade platform.
3.8.17. The instruments shall be given enough protection against corrosion and all the
wetted parts of the instruments shall be non-corrosive.
3.8.18. All field instruments and cabinets/ panel mounted instruments shall have tag
plates/name plates permanently attached to them.
3.8.19. The performance of all instruments shall be unaffected for the ±10% variation in
supply voltage and ±5% variation in frequency simultaneously.
3.8.20. Unless otherwise specified, double compression glands shall be used for glanding
the cable in field instruments and instrument control panel.
3.8.21. Electromagnetic Flow meter sizing shall be done such that velocity of fluid inside
flow tube should not be less than 0.3 m/s and not generally exceed 3.0 m/s. For
underground installation, Flow Meter Chamber shall be provided.
3.8.23. Online process analyzers shall be of latest technology based and shall be reagent
free.
3.8.25. The monitoring and control system shall be designed & implemented through a
Programmable Logic Controller (PLC) with HMI, covering the required functional &
operational requirements of the plant involving measurement, control, alarm &
interlocking functions.
3.8.26. PLC system selected shall be Open Platform Communications (OPC) compatible.
3.8.27. Input/ Output philosophy for the PLC system shall be as follows:
Contractor
Executive Engineer Page16
Volume II: Technical Specification for
Electrical &Instrumentation Works
Stop Command-1 No
Analog Input:
Speed Feedback (Applicable for VFD driven Pump)-1
No
Vibration Sensor Feedback (Applicable for MV Motor)-
6 Nos
Analog Output:
Speed Reference (Applicable for VFD driven Pump)-1
No
RTD Input:
Windings & DE/ NDE Bearings Temperature
(Applicable for motor having winding and bearing
RTDs )- 8 Nos
b) Pump/ Blower Analog Input:
Pressure Transmitter- 1 No (wherever continuous
Pressure monitoring is required)
Flow Transmitter- 1 No (wherever continuous Flow
monitoring is required)
c) Motorized Valve Digital Input:
Local/ Remote Selector-1 No
Open Feedback- 1 No
Close Feedback- 1 No
Over Load Feedback- 1 No
Torque Switch Feedback-1 No
Digital Output:
Open Command- 1 No
Close Command-1 No
Analog Input:
Position Feedback (Applicable for Modulated Control
Valve)-1 No
Analog Output:
position Reference (Applicable for Modulated Control
Valve)-1 No
d) Breaker Digital Input:
Local/ Remote Selector -1 No
ON Feedback- 1 No
OFF Feedback- 1 No
Master Trip Relay Operated- 1 No
Digital Output:
ON Command- 1 No
OFF Command-1 No
e) Transformer Digital Input:
Oil Level Low Alarm-1 No
Oil Temperature High-1 No
Oil Temperature Very High-1 No
Winding Temperature High- 1 No
Winding Temperature Very high-1 No
Buchholz Alarm-1 No
Buchholz Trip-1 No
Pressure Relief Device Trip -1 No
OLTC Fault-1 No
f) Sump/ Tank Digital Input:
Level Very High-1 No
Contractor
Executive Engineer Page17
Volume II: Technical Specification for
Electrical &Instrumentation Works
Level High -1 No
Level Low-1 No
Level Very Low-1 No
Analog Input:
Level Transmitter- 1 No (wherever continuous Level
monitoring is required)
3.8.28. PLC based control system shall be of latest industrially available configuration. PLC
system shall be provided with Operator& Engineering stations along with a printer,
peripherals & accessories, as required.
3.8.29. Unless otherwise specified, the PLC system shall be provided with hot redundant,
fault-tolerant features, redundancy in processor, power supply modules,
communication modules (I/O bus as well as HMI bus) and communication network,
bumpless switchover from the active system to the standby system in the event of a
fault.
3.8.30. The PLC I/O modules shall be hot swappable, i.e. card changeover, card wiring
removal or communication cable change shall be possible on-line (PLC running)
without causing any process interruption, bump or nuisance trip or any loss of
fidelity during such action.
3.8.31. In case of hot swap of I/O card or card wiring removal, the interruption shall be
limited to the subject card related inputs/ outputs only.
3.8.32. On line PLC programme modification shall be possible without stopping the
processor.
3.8.33. The I/O modules and processors shall be of same family and series. All analog
cards shall be differential type.
3.8.34. I/O modules shall have 3 levels of Isolation- a) Channel to Channel Isolation, b)
Channel to power Isolation & c) Channel to Ground Isolation.
3.8.36. The engineering station forms the focal point of the control system design and acts
as container of the complete control system application.
3.9.1. The electrical Single Line Diagram(s)/ PLC system architecture for water supply
project including raw water intake &various headwork/ sub-headworkwith/ or without
water treatment facility (as applicable) form part of this specification and should be
used for reference purpose only.
3.9.2. The equipment/ switchgear component ratings & requirements shown in the
reference electrical Single Line Diagram(s) are minimum requirements & after
award of contract, Contractor has to get approval for the equipment selection with
the approval for sufficiency calculations.
Contractor
Executive Engineer Page18
Volume II: Technical Specification for
Electrical &Instrumentation Works
Contractor
Executive Engineer Page19
Volume II: Technical Specification for
Electrical &Instrumentation Works
3.10.1. The scope shall be inclusive of supply, installation, testing & commissioning of
power, control and instrumentation cables, cable terminations, cable accessories,
stripping of cable insulation, supplying and fixing of Aluminium lugs for aluminium
cables & tinned plated copper lugs for copper cables and crimping the same to the
conductor, supply and fixing of double compression cable glands including all
labour supply and consumable material required for jointing/ termination. The rate
shall also include the laying of cable in ground/ in cable trays / cleating to structure
etc.
The cables shall confirm to the latest applicable standards specified below. In case
of conflict between standards and this specification, this specification shall govern.
a) HV power cables shall conform to 11kV Earthed grade (E), three core,
stranded, Aluminium conductor, screened by extruded semi-conducting
compound, cross-linked poly ethylene (XLPE) insulated, cores screened with
non-magnetic metallic tape laid up with inner and outer extruded PVC sheath
compound Type-ST2 and galvanized steel strip armouring. The cables shall
generally conform to IS 7098-1985 with relevant parts thereof.
Contractor
Executive Engineer Page20
Volume II: Technical Specification for
Electrical &Instrumentation Works
d) All the control cables shall be 1.1kV grade, no. of cores (as per requirement/
application with minimum 2 spare cores for 7C & above) multi-stranded,
Copper conductor, XLPE insulated, extruded inner PVC & outer PVC FRLS
sheath compound type ST2 and galvanized steel round wire armoured.
iii. Provided with inner extruded PVC and outer PVC FRLS sheath of
extruded black PVC compound.
vi. The insulation over the individual conductor core will be colour coded.
g) All the power, control& instrumentation cables used in the Hazardous area
shall be flame proof type suitable for the intended application.
h) Earthing Cable shall be Single core multi-stranded Cu, 1.1 kV grade, XLPE
insulated, un-armoured green coloured outer sheath with yellow strips/ band
cable to be laid in trays, underground, trenches etc. as applicable.
a) All cable cores shall be colour coded throughout their length and shall be so
connected between switchboard, distribution board, plant and accessories,
that the correct sequence or phase colours are preserved throughout the
system.
Contractor
Executive Engineer Page21
Volume II: Technical Specification for
Electrical &Instrumentation Works
3.10.6. Cable Numbering:All cables shall be allocated a unique number which shall be fixed
to each end of the cable using a corrosion resistant label. Necessary loop at both
ends shall be provided for future use and cables of different categories shall be
tagged with the following subscripts and three digit number.
HV power HV-P_ _ _
LV power P_ _ _
Control C_ _ _
Instrumentation I_ _ _
Protection PR_ _ _
Telecommunication T_ _ _
a) Cable Lugs
i. Cable lugs shall be of tinned copper, solder less crimping type for Cu
cables & AL lugs for the AL cables.
ii. The current rating of the lugs shall be same as that of the respective
cable conductors.
iii. Bi-metal strip/ Bi-metallic lug shall be used whenever two different
metals are to be connected together.
iv. Double holes extended neck (long barrel neck) type lugs shall be used
Contractor
Executive Engineer Page22
Volume II: Technical Specification for
Electrical &Instrumentation Works
vi. If termination is done with crimping tool employing crimping die then
forming dies shall be used to make the sector shaped conductor into a
round conductor before crimping the lugs on the conductor. The lug
must not be crimped directly on the sector conductor. Before crimping
the lug, the conductor shall be thoroughly cleaned and special jelly
applied over it to prevent further oxidation.
b) Cable Glands
ii. Double compression type cable glands shall be used. Cable glands
shall be brass casting, machine finished and Nickel-plated to avoid
corrosion and oxidation. Rubber components used in cable gland shall
be of neoprene.
iii. For single core cables, gland shall be with brass ring.
iv. Glands for single core cables shall be constructed from non-magnetic
materials.
vi. Where holes for cable entries are not provided it shall be the
responsibility of the Contractor to mark out and drill such holes. Burrs
and swarf shall be removed, care being taken to ensure that swarf and
filings, etc do not enter the equipment.
vii. For non-hazardous areas cable glands in situations where moisture may
be present shall be double seal weatherproof type, gland shrouds shall
be used and entry shall be sealed.
ix. For hazardous areas, glands conforming to EEE standard shall be used
with double seal and shroud.
i. All the single core cables shall be laid in trefoil formation only.
ii. The grouping & sequencing of three single core cables arranged in
trefoil formation shall be done in such a way to ensure balanced current
distribution.
iii. Trefoil clamp of suitable size & having non magnetic material shall be
used.
Contractor
Executive Engineer Page23
Volume II: Technical Specification for
Electrical &Instrumentation Works
iv. The Trefoil groups shall be held in trefoil clamps at an interval not
exceeding 3.0 meters.
i. Single pair shielded signal/ alarm cables shall be used between field
instruments / switches and junction boxes / local control panels.
iii. Single triad shielded signal cables shall be used between RTD head
and junction boxes/ transmitters/ local control panel mounted
instruments.
iv. For field bus compatible instrument single pair shielded cable shall be
used between instrument to junction box/ local panel and to control
room.
Thermocouple signals
Gas detectors
Contractor
Executive Engineer Page24
Volume II: Technical Specification for
Electrical &Instrumentation Works
viii. Instrument control cables shall be used for valves, feedback of feeders
etc.
ix. The cable design shall generally follow BS 5308 Part-1 for various
cables listed in clause-e as above.
xi. The power and control cables shall be generally as per BS 6346. For
these cables, equivalent IEC/IS specifications are also acceptable.
xiv. Inner and outer sheath/ jacket shall be made of extruded fire retardant,
low smoke, low halogen, low toxic, polymeric compound having physical
properties as per IS-5831-Type ST2.
xv. All cables shall be armoured and suitable for operation when installed
as follows:
In underground ducts
xvi. Running length of the cable shall be printed at least at every 5 metre
interval.
xvii. For Multipair/ multitriad cables, pair identification shall be provided with
numbers at interval of not more than 250 mm as per Contractor’s
standard.
Contractor
Executive Engineer Page25
Volume II: Technical Specification for
Electrical &Instrumentation Works
Contractor
Executive Engineer Page26
Volume II: Technical Specification for
Electrical &Instrumentation Works
Contractor
Executive Engineer Page27
Volume II: Technical Specification for
Electrical &Instrumentation Works
Contractor
Executive Engineer Page28
Volume II: Technical Specification for
Electrical &Instrumentation Works
Contractor
Executive Engineer Page29
Volume II: Technical Specification for
Electrical &Instrumentation Works
Contractor
Executive Engineer Page30
Volume II: Technical Specification for
Electrical &Instrumentation Works
EIA/ TIA 568 A Category 5, 4 pair 0.5 mm2 (24 AWG) solid
conductors, with plastic foil wrapping.
62.5/ 125 micron multimode, graded index, glass silica fibre core,
mechanical protection provided by round galvanized steel armour
with polyester laminated tape layered over inner sheath.
viii. Any other special cables such as co-axial cable or cables with glass
insulation, required for instruments shall also be supplied as per
requirements.
ix. Contractor shall ensure that these cables are armoured type and shall
meet all other requirements specified above, as applicable.
a) Cables shall be supplied in non-returnable wooden drums. The wood used for
construction of the drum shall be properly seasoned and free from defects
and wood preservative shall be applied to the entire drum. All ferrous parts
shall be treated with a suitable rust preventive coating to avoid rusting during
transit or storage.
Contractor
Executive Engineer Page31
Volume II: Technical Specification for
Electrical &Instrumentation Works
the end of the drum or stamped on the metal attached to an end of the drum.
The cable shall be placed on the drum in such a manner that it will be
protected from injury during transit. Each end of the cable shall be firmly and
properly secured to the drum. The drum shall be securely blocked in position
so that the cable will not be displaced during transit. Cable ends shall be
sealed by non-hygroscopic sealing caps.
v. Cable quantity
3.10.10. Tests Before and After Laying of Cables at Site:Following Routine & acceptance
tests on each drums as per IS 10810, IS 7098 standard & other specified relevant
standards shall be performed by the manufacturer and witnessed by Purchaser/
Purchaser’s Representative.
Contractor
Executive Engineer Page32
Volume II: Technical Specification for
Electrical &Instrumentation Works
d) Cables shall be checked for insulation resistance before and after jointing.
The voltage rating of the Megger for cables of different voltage grades shall
be as indicated below.
ii. Continuity test of all the phases, neutral and earth continuity conductor.
i. Type Test: Certificate from independent test house for the following
tests shall be furnished by the Contractor for the FRLS low halogen
sheathed cable.
ii. Routine Test and Acceptance test: Each of the following tests to be
carried out by Contractor during various stages of manufacturing.
Purchaser shall review the related documentations. In addition, the
following test shall be carried out for checking properties of low halogen
FRLS sheathing material.
Contractor
Executive Engineer Page33
Volume II: Technical Specification for
Electrical &Instrumentation Works
Contractor
Executive Engineer Page34
Volume II: Technical Specification for
Electrical &Instrumentation Works
No of Pairs
Temperature Range
g) Cable Gland:
i. Cable glands required for glanding all cables at both ends shall be
supplied by Contractor.
iii. Cable glands shall be of SS 316 and double compression type suitable
for armoured cables.
vi. For all field items and junction box end, NPT threaded cable glands
shall be used and for control room / control panel end, cable glands
shall be ET threaded types.
h) Junction Boxes:
i. In order to make the most economic use of cable tray and trench
capacity, multicore / multipair cabling shall be utilised in order to connect
instrumentation groups by using suitably located junction boxes.
ii. The junction boxes shall have weather protection suitable for the area in
which they are to be installed and for the type of circuit.
iii. They shall be readily accessible for maintenance and clearly labeled.
iv. Junction box shall be constructed of die cast aluminium and provide
degree of protection IP 65.
v. Wires and terminals for the digital and analog signals shall be
segregated within junction boxes.
Contractor
Executive Engineer Page35
Volume II: Technical Specification for
Electrical &Instrumentation Works
i. General information
iii. Cable routing lay out inside and outside the plant with route marker
provided at 30 meter interval.
d) Following Type Tests reports as per relevant standard to be submitted for the
same rating & type of Cables conducted in past for review of Purchaser/
Purchaser’s Representative by the Contractor at the time of inspection &
testing of equipment. Type test reports should be valid and not be older than
the 5 years.
i. Annealing test
Contractor
Executive Engineer Page36
Volume II: Technical Specification for
Electrical &Instrumentation Works
b) Cable trays of ladder and perforated types and the associated accessories
such as coupler plates, tees, elbows etc., shall be fabricated from 14 gauge
(2.0 mm thick) mild steel sheets. Cable tray covers shall be fabricated from 16
gauge perforated (1.60 mm thick) M.S. sheets.
c) The cable trays shall be supplied in standard lengths of 2500 mm and clear
inside widths of trays shall be as follows:
d) Cable trays, accessories and covers shall be painted with one shop coat of
red oxide zinc chromate primer and two site coats of aluminium alkyd paint for
indoor use.
e) For outdoor use, cable trays, accessories and covers shall be either
galvanized or made of aluminium as specifically mentioned in the layout
drawings.
f) For use in corrosive atmospheres both indoors and outdoors, the cable trays,
accessories and covers shall be as per serial no. (e) above.
g) The spacing of rungs for ladder type of trays shall be 250 mm unless
otherwise noted.
h) All finished cable trays and accessories shall be free from sharp edges,
corners, burrs and unevenness.
3.11.1. Scope:
a) The scope includes collection of data, design of the system as per relevant
National/International Standards preparation of layout drawing supply of
earthing conductors, earth electrode, earthing strips installation and approval
to the satisfaction of electrical inspector under this tender specification.
Contractor
Executive Engineer Page37
Volume II: Technical Specification for
Electrical &Instrumentation Works
d) Lightning.
a) The design basis for designing earthing conductor is indicated under design
criteria for electrical system. Earthing system shall be provided for complete
plant i.e. pumping stations, switchyard and all electrical equipments as per the
latest edition including all official amendments and revisions of IS-3043 and
CEA guidelines.
b) All materials and fittings used in the earthing installation shall conform to the
relevant Indian Standards or shall be approved by the Engineer's
representative &HPSEB.
c) Contractor has to carry out soil resistivity test at,at least 4 locations for which
locations shall be provided by Purchaser’s representative. Testing to be done
at each site.
g) The conductor sizes & types shall be as per specified in the Technical
schedules in Volume- II, Section A3. Contractor to note that, the sizes
indicated are minimum required &earthing conductor sizes shall be approved
by the Purchaser/ Purchaser’s representative on the basis of adequacy
calculations submitted by Contractor.
h) The underground joints in the system shall be properly welded or brazed and
the bolted type connection shall be made with structures/ equipments.
Petroleum jelly shall be applied to contact surface of the bolted joints, which
will be covered with bituminous compounded and tapes.
Contractor
Executive Engineer Page38
Volume II: Technical Specification for
Electrical &Instrumentation Works
j) The earthing system shall comprise one or more earth electrodes, earthing
grid or a combination of these in order to obtain the required earth electrode
resistance of less than one (1) Ohms/ or as per IEEE Std 80 -2000.
k) For equipment earthing, two earthing leads will be used if rated voltage of the
equipment is 250 volts & above and one earthing lead will be provided for
equipment rated below 250 volts.
o) For other equipment & area, Earth electrodes shall be of heavy duty
galvanized mild steel of not less than 40 mm NB and minimum 3000 mm long.
Where multiple rods are used they shall be separated by a distance of not
less than the driven length.
p) Each earth electrode pipe shall be welded at the top to a mild steel plate to
which the earthing strips shall be connected.These connections shall each be
housed in individual inspection chamber set which shall project 100 mm
above the finished ground level and shall allow disconnection for testing of
individual electrodes.The chamber shall be permanently marked `Electrical
Earth'.
q) All materials used for the earth electrode installation shall be purpose made
for the application and site conditions and shall be approved by the
Purchaser’s Representative.
r) All civil works, such as excavation, boring, provision of charcoal & salt in
adequate quantity, backfilling for the installation of the earth electrodes and
the earth pit/ inspection pit shall be in the scope of Contractor.
Contractor
Executive Engineer Page39
Volume II: Technical Specification for
Electrical &Instrumentation Works
s) After the earth installation has been completed the Contractor shall
demonstrate to the Purchaser/ Purchaser’s Representative that the resistance
of the electrodes to earth and the continuity of the earth network are within the
limits specified. Any additional earth electrodes and test instruments required
for the tests shall be provided by the Contractor.
iii. The metal sheath of an armoured cable. The sheath shall be bonded to
the metal work of the apparatus and to the apparatus earth bar, if any.
vi. The size of the circuit protective conductor shall be calculated in such a
manner as not to take into consideration the contribution of any other
parallel or fortuitous earth paths.
vii. The armoring of the supply cable shall not form the sole means of
earthing a switchboard or large electrical load.
v) Instrumentation Earth:
ii. If due to the physical size of a control panel more than one instrument
earth bar is required the additional bar shall be connected again with a
single earth connection to the same point as before on the control panel
electrical earth bar. In this fashion all instrument earths shall be
connected radial from the same earth point.
iii. All signal cable screens (analogue and digital) shall be terminated on to
the instrument earth bar. Signal cable screens shall be earthed at the
control panel end only. Screens at the field end shall be tied back and
insulated.
iv. Surge Protector Devices (SPDs) associated with the control and
Contractor
Executive Engineer Page40
Volume II: Technical Specification for
Electrical &Instrumentation Works
a) Each pole of lightning arrestors shall be earthed with separate earth pit.
c) The switchyard fencing shall be earthed at every alternate block and the
switchyard gate shall be earthed with flexible GI wire.
d) All the earthing material with laying etc. shall be included in the scope.
e) The entire plant will have an earth grid laid in trenches/ trays/ buried in the
ground outside. The main earthing grid shall be embedded at a minimum
depth of 600 mm below FGL which shall be connected to earth electrodes.
f) All interconnections of the earthing grid conductors will have welded type
joints except at electrodes with disconnecting facility and at equipment with
bolted connections. All indoor earthing grids will be suitably interconnected to
the external earthing grid.
g) Each steel/ RCC column of the building will be interconnected to the floor-
earthing grid. Steel columns, steel strips / conduits, cable trays etc. will not be
used as earth continuity conductors.
h) Disconnecting type facility shall be provided between Earthing grid & each
earth electrode.
i) All connection between the conductors shall be welded/ brazed type. Metallic
pipe, conduit, structures shall be bonded to lightning protection conductors to
prevent the side flashover. But no metallic pipe, conduit, structure shall be
used as air termination conductor or down conductor.
j) The down conductors shall be fixed with embedded brass posts (on concrete
columns) with nuts & bolts used for fixing the saddle/ clamp (direct drilling of
down comer and fixing with screw shall not be acceptable).
l) The lightning protective conductor shall not be connected with the earthing
above ground however both the systems shall be interconnected below
ground.
m) The earth pits may require boring & drilling in the soil & the same shall be
considered in Contractor’s scope.
Contractor
Executive Engineer Page41
Volume II: Technical Specification for
Electrical &Instrumentation Works
o) Internal earth Bus of each panel shall be connected to both ends to the
earthing system by means of earthing conductor.
t) Metallic conduits and pipes shall be connected to the earthing system unless
specified otherwise.
u) All cable trays will be earthed at minimum two places by suitable sized GI flats
to main earthing system earth conductor. The cable trays shall also be
earthed at a regular interval of not more than 10 meters by 25 x 3 mm GS flat
v) Earthing Pits:
ii. Earthing pits shall be located in ground, which has a reasonable chance
of remaining moist. Arrangement comprising of GI pipe with top funnel
with wire mesh shall be made to facilitate pouring of water to keep
earthing pit wet.
iii. A galvanized iron strip of adequate size (as per calculations) shall be
provided from plate electrode to about ground level to facilitate jointing
with earth conductors. Each earth electrode ending at the pit shall be
connected to suitable linking strips to connect and disconnect the
earthing suitably.
Contractor
Executive Engineer Page42
Volume II: Technical Specification for
Electrical &Instrumentation Works
iv. Earthing chamber shall be of RCC/ brick chamber of 600 mm x 600 mm,
with removable 6 mm thick MS chequered plates. The covers shall have
holes for handling. Earthing pits (chambers) shall be painted Green and
the earth-pit number shall be marked on it.
vii. All earth lead connections shall be as short and direct as possible and
shall be without kink.
viii. The main earth loop in plant area shall be generally routed along
cables. When equipments are located away from main earth loops,
suitable sub-loops shall be run up to them for deriving connections for
individual equipment. The entire earthing system shall fully comply with
the CEA guidelines and requirements.
ix. The Contractor shall have to carry out any changes as desired by the
Electrical inspector or the Engineer in charge, in order to make
installation conforming to the CEA guidelines 2010.
a) The lightning protection system need will be established by calculating the risk
factor value of each building, structure etc. as per procedure given in IS 2309-
1989 and if found necessary the same shall be provided by the Contractor.
3.11.6. Galvanizing:
a) Wherever galvanizing has been specified, the hot dip process shall be used.
The galvanized coating shall be of uniform thickness. Weight of Zinc coatings
for various applications shall not be less than those indicated below
Fabricated Steel
i. Thickness less than 2 mm, but not less than 1.2 mm 340 gms/ sq.m
ii. Thickness less than 5 mm, but not less than 2 mm 460 gms/ sq.m
iii. Thickness 5 mm and over 610 gm/ sq.m
Fasteners
i. Up to nominal size M10 270 gms/ sq.m
ii. Over M10 300 gms/ sq.m
Contractor
Executive Engineer Page43
Volume II: Technical Specification for
Electrical &Instrumentation Works
The Contractor should prepare Layout drawings, after award of contract and before
commencement of work for Purchaser’s approval, showing the location of earthing
grid, electrodes, interconnection grids and earthing leads to various equipment,
down comers, isolating links etc. should be accompanied by design calculations.
3.12.1. Scope
a) The scope of the Contractor shall include design, supply and installation of all
equipment necessary for a complete lighting and receptacle system. The
lighting system includes Lighting fixtures (indoor/ outdoor), lamps, lighting
panels (LP), switchboards, Receptacles, JBs, cables/ wires for lighting/
receptacles, conduits etc. The supply of streetlight/ flood light poles as per IS
2713 or IS 3713 is also included in the Contractor’s scope.
b) The various types of lighting fixtures with lamps shall be installed based on
the mounting arrangement shown in the typical drawings enclosed with the
specification. Installation scope shall include all material to mount the fixtures
in proposed manner.
c) Light control switches, receptacle units with control switch units, lighting wires,
conduits, earth wires and other similar items necessary to complete lighting
system.
d) Lighting fixture supports, street lighting poles and flood light towers/ poles.
Contractor
Executive Engineer Page44
Volume II: Technical Specification for
Electrical &Instrumentation Works
a) It shall be the responsibility of the Contractor to work out a detailed layout for
the complete plant in order to provide the levels of illumination as indicated in
the relevant standards
b) The types of fixtures to be used in various areas are also indicated in the
above mentioned drawing. The Contractor shall be responsible for measuring
the levels of illumination and uniformity after installation and establish
compliance with the specification.
i. Normal A.C Lighting: Normal lighting in all indoor and outdoor areas will
be operated on 230V, 1Phase, 50 HZ A.C supply
Contractor
Executive Engineer Page45
Volume II: Technical Specification for
Electrical &Instrumentation Works
Contractor
Executive Engineer Page46
Volume II: Technical Specification for
Electrical &Instrumentation Works
a) Lighting panels shall be provided in various areas and circuit wiring to the
lighting fixtures shall be made from lighting panels. Lighting panel shall
comprise of Four pole MCB + RCCB (100 mA) for incomer and SP MCB’s for
each outgoing single phase circuits.
b) The wiring for lighting circuits in indoor areas will be done by wires run in GI
conduits. For outdoor lighting, wiring will be done by using armoured cables.
d) For lighting fixtures (Pump room) 1100V grade, 4C x 2.5 sq. mm. PVC
insulated, multistranded copper conductor armoured/ unarmoured cables shall
be used.
e) For lighting fixtures (For Office, electrical room, toilets etc. areas) 1100V
grade, FRLS PVC, multi-stranded Copper conductor wires of area not less
than 1.5 sq mm laid in min. 20 mm dia GI conduit (above false ceiling) shall
be used.
f) For 5/15A decorative sockets (For Office, toilets etc. areas) 1100V grade,
FRLS PVC, multi-stranded copper conductor wires of area not less than 2.5/
4.0 sq. mm. Cu laid in minimum 20 mm dia. GI conduit shall be used.
Contractor
Executive Engineer Page47
Volume II: Technical Specification for
Electrical &Instrumentation Works
g) Wiring shall be concealed in wall below false ceiling with concealed switch
board. Minor civil work like chasing wall, cut outs for conduit, switch board,
Lighting Panel in wall, entries for tray, conduits etc. is in scope.
h) Lighting cable from MLDB to Lighting Panels and Lighting Panels to street
light fixtures, shall be Al conductor, XLPE insulated, armoured, 1.1 KV grade,
laid in cable trays otherwise cleated along the wall/ column/ beam and buried
in the ground.
i) The point wiring for lighting/ receptacle/ exhaust fan/ wall mounted fan/ ceiling
fan shall include conduits, conduit accessories, FRLS PVC insulated
multistranded Copper conductor wires and earthing wires, pull boxes, ceiling
rose, clamps, cleats, hardware, accessories, anchor fasteners etc. It shall
include wiring from lighting panel to switchboard and receptacles &
switchboard to lighting fixtures. Sheet metal switchboard embedded in wall
shall be considered for receptacles and lighting switchboards on wall shall be
considered for lighting.
j) For power sockets in wall/ furniture, PVC switch box of approved make with
switch plate & accessories and 16 Amp piano modular switches and 5/15A
sockets etc. as applicable shall be considered. For all types of point wiring the
receptacles with switches shall be included in the point wiring rate.
l) Decorative socket switchboard consisting of (*) no. of 16A piano switch with
indicator, (*) no. 2/3 pin shuttered socket of 5/15A and metal flush box, 1 no.
white coloured cover plate for (*) module( 4/ 6/ 8/ 12 module).
m) Lighting fixtures and fans will be grouped on the circuit wherever required.
However, separate circuits shall be used for receptacles wiring.
o) All MH fixtures, High bay T5 fixtures, Street Light fixtures shall be controlled
directly from respective Lighting Panels, through MCB.
q) Lighting for staircase shall be controlled with flushed modular switch. The
conduit for main staircase shall be concealed. Lighting for all staircases shall
be with 2 way switch
r) Contractor shall note that any chasing in walls or cutouts or openings such as
fixing of LPs, DBs, switchboards, concealing conduit in wall etc. in walls
required shall be made before plastering of brickwork wherever applicable
Contractor
Executive Engineer Page48
Volume II: Technical Specification for
Electrical &Instrumentation Works
and installation rates quoted shall be inclusive of chasing, cutting & making
the plaster as per standard practice.
s) Lighting for street light fixtures/ flood light fixtures and metal halide fixtures
shall be carried out with cables. The supply of cables, junction boxes, street
light poles & structural steel required for mounting fixtures/ LPs etc. are in the
scope of Contractor. The cable wiring shall include supply & installation of
cable required from LP to the junction box mounted on street lighting pole /
near indoor fixture and also between junction box mounted inside pole/near
indoor fixture to control gear box and same for flood lighting, supply and
installation of all termination accessories such as lugs, cable glands etc. DBO
Contractor’s scope shall also include excavation, preparation of soil bedding,
supply and installation of protection cover, back-filling, supply and installation
of cable route markers etc.
i. Point wiring covers the wiring between a circuit of the lighting panel to
switchboard and then from switchboard to lighting fixtures connected to
that circuit of the lighting panel.
ii. For receptacle circuits point wiring shall cover wiring between circuit of
the lighting panel to receptacles connected to that circuit of the lighting
panel.
iii. The scope of the Contractor shall include the supply, erection, testing
and commissioning of the above LPs/ DB boards for supply of power to
the various sockets required for computers, raw power points etc. The
point wiring rate from these DBs shall include supply of wires, conduits,
cleats/ clamps etc. as may be required and shall be in the scope of
electrical Contractor.
iv. The conduit point wiring rate for exhaust fan shall include conduits/
casing capping, conduit/ casing capping accessories, Switch boards,
PVC insulated wires and earthing wires, pull boxes, ceiling rose,
clamps, cleats, hardware, sheet metal switchboards fabricated out of 16
SWG. sheet steel housing 5 Amp piano switches. It shall include wiring
from EXHAUST FAN DB/ RDB to switchboard & switchboard to exhaust
fan as applicable. Neutral for individual circuit shall be run separate from
DB to individual receptacles.
vi. Required no. of 1-Ph & 3-Ph, industrial receptacles with respective 2P/
4P ELCB (30mA) & 3/ 5 pin plug shall be provided for maintenance
purpose.
Contractor
Executive Engineer Page49
Volume II: Technical Specification for
Electrical &Instrumentation Works
– Combination
240V, 1-Ph, 50Hz, 3 pin, 15A Industrial receptacles with RCBO (30
mA).
i. General
Variation in supply
Voltage (AC & DC) ±10
Frequency ±5
Combined voltage & ±10
frequency
Design ambient air 500C
temperature
iv. For each type of Luminaries the Contractor shall furnish the utilisation
factor tables to indicate the proportion of the light emitted by the bare
lamps which falls on the working plane.
viii. Fluorescent type Luminaries with more than one lamp shall be provided
with capacitors connected in lead-lag circuit for correction of
stroboscopic effect.
Contractor
Executive Engineer Page50
Volume II: Technical Specification for
Electrical &Instrumentation Works
ix. Each luminaries shall have a terminal block suitable for loop-in, loop-out
and T-off connection by 230/ 415 V, 1 core, FRLS PVC insulated
Copper conductor wires up to 4 sq. mm in size. In outdoor areas the
termination at the luminaries shall be suitable for 1100 V, PVC
insulated, Cu/ Al conductor, armoured cables of sizes up to 6/ 16 sq.
mm conductor. Terminals shall be of stud or clamp type. The internal
wiring should be completed by means of stranded Copper wire of
minimum 1 sq. mm size and terminated on the terminal block. Terminal
blocks shall be mounted with minimum two fixing screws.
v) Earthing
ii. Where separate control gear box is provided for housing the
accessories the same shall be provided with an earthing terminal
suitable for connecting earthing conductor of 12 SWG GI wire.
iii. All metal or metal enclosed parts of the luminaries/control gear box shall
be bonded and connected to the earthing terminal so as to ensure
satisfactory earthing continuity.
w) Painting/ Finish:
iv. The surface shall be scratch resistant and shall show no sign of
cracking or flaking when bent through 90 deg. over 1/2” dia. mandrel.
v. The finish of the luminaries shall be such that no brigHV spots are
produced either by direct light source or by reflection.
vi. External control gear box provided for housing accessories shall be
painted or galvanised.
a) The luminaries shall be provided with CRCA sheet steel mounting rail with
reflector of minimum 20 SWG thicknesses and complete with all control
accessories mounted on it. The finish shall be vitreous enameled.
Contractor
Executive Engineer Page51
Volume II: Technical Specification for
Electrical &Instrumentation Works
d) The distribution of light shall be such that at least 80% of the total luminous
flux from the luminaries shall be in the lower hemisphere.
e) The luminous output of the luminaries with reflector shall not be less than 75%
irrespective of type of reflector used.
b) High and medium bay luminaries shall be with cast aluminium/ stove
enameled housing, anodized aluminium mirror polished reflector, canopy with
eye bolt for suspension, cooling fins. Glass cover shall be provided. The
luminaries shall be suitable for metal halide lamp up to 400 W. The control
gear accessories shall be mounted integral with the luminaries.
c) Low bay luminaries may be with sheet steel/ cast aluminium enclosure, wide
angle distribution type polished reflector, acrylic cover and wire guard
complete with neoprene gaskets, mounting bracket etc. The luminaries shall
be suitable for metal halide lamp up to 125 watts. The control gear
accessories shall be mounted integral with the luminaries.
d) All luminaries used with metal halide lamps shall be of enclosed type.
Contractor
Executive Engineer Page52
Volume II: Technical Specification for
Electrical &Instrumentation Works
b) The housing shall be supported on a cast iron base and capable of being
swivelled in both horizontal and vertical directions and locked in any desired
position.
c) For focussing purposes, knobs, shall be provided along with sector plate
indicating the angle in degrees between 0 and 90 deg. in vertical direction.
d) The Luminaries shall be suitable for single and dual Metal Halide (MH) lamps
of 150W/ 250W/ 400 watts etc. as required. The same shall be mounted in a
separate sheet metal enclosed/ cast aluminium weather proof control gear
box.
e) The luminaries shall be provided with cable gland on the canopy in down ward
direction for cable connection.
f) It shall be possible to adjust the lamp position to achieve wide beam, medium
beam or narrow beam.
g) It shall be possible to replace the lamp from the canopy without opening the
front glass.
a) Fluorescent Luminaries
ii. The luminaries shall be of semi-cut off or non-cut off type, with CRCA
sheet steel housing, vitreous enamelled, plain or corrugated clear acrylic
cover, complete with integral mounted control gear, neoprene gaskets,
side pipe entry or top suspension type.
b) MetalHalide luminaires:
Contractor
Executive Engineer Page53
Volume II: Technical Specification for
Electrical &Instrumentation Works
ii. The luminaries shall have cast aluminium spigot finished with corrosion
proof paint for mounting, opal acrylic or high density polyethylene (HDP)
diffuser bowl, complete with integral mounted control gear, neoprene
gaskets, earthing terminal etc.
d) Bollard Luminaries:
ii. The luminaries shall be of FRP housing, clear acrylic cover, louvers for
directing light downwards and bottom cable entry.
3.12.11. High Mast Flood Light / Flood Light Towers (where applicable):
a) High mast shall be outdoor weather proof type for illumination of main roads
and area lighting, wherever found necessary.
c) The moving platform shall be of steel construction hot dip galvanised and
designed to hold the number of flood light luminaires specified. The control
gear boxes shall be cast aluminium weather proof type mounted on the
moving platform. The moving platform shall be raised or lowered with the help
of winch, pulley system and stainless steel wire ropes. The winch shall be
suitable for hand operation or alternante by electric power.
c) Pump room and Electrical room shall be considered for Emergency lighting.
Contractor
Executive Engineer Page54
Volume II: Technical Specification for
Electrical &Instrumentation Works
a) Reflectors
iii. Reflectors shall be free from scratches or blisters and shall have a
smooth and glossy surface having an optimum light reflecting coefficient
so as to ensure the overall light output specified by the Contractor.
iv. Reflectors shall be readily removable from the housing for cleaning and
maintenance without disturbing the lamps and without the use of tools.
They shall be securely fixed to the housing by means of positive
fastening device of captive type.
ii. Lamp holders for the fluorescent lamps shall be of the spring loaded bi-
pin rotor type. Live parts of the lamps holder shall not be exposed
during insertion or removal of lamp or after the lamp has been taken out.
The lamp holder contacts shall provide adequate pressure on the lamp
cap pins when the lamp is in working position.
iii. Lamp holders for mercury vapour and sodium vapour lamps shall be of
Edison Screw (ES) type.
Contractor
Executive Engineer Page55
Volume II: Technical Specification for
Electrical &Instrumentation Works
iv. The starter holders shall be so designed that they are mechanically
robust and free from any operational difficulties. They shall be capable
of withstanding the shocks met within normal transit, installation and
use.
c) Ballasts:
i. The ballasts shall be designed to have a long service life and low power
loss. The ballasts shall be of the inductive, heavy duty type copper wire
wound, filled with thermosetting, insulating, moisture repellent polyester
compound filled under pressure or vacuum. Ballasts shall be provided
with taps to set the voltage within the range of variation in supply
voltage of ±10% of 240 V. End connections and taps shall be brought
out to a suitable terminal block rigidly fixed to the ballast enclosure.
Ballasts shall be free from hum and such of those which produce hum
shall be replaced by Contractor free of cost.
ii. Ballasts shall be mounted using self locking, anti-vibration fixings and
shall be easy to remove without demounting the fittings. They shall be in
dust tight, non combustible enclosures.
iii. All the luminaries other than Flood Light Fixtures shall have integral
control gear.
iv. All type of fluorescent light fittings shall be provided with high frequency
electronic ballast of proven design with less than 10% THD, fully wired
up to the connector block. The electronic ballast shall be suitable for
operation with input voltage variation between 180-260V to give a
constant light output.
v. All gas discharge/ MH type lamps shall be provided with control gear,
with Copper wound and polyester filled low loss ballast, igniter and PF
correction capacitor.
vii. In Crane bays, lighting fixtures shall be mounted with the minimum 500
mm clearances above overhead crane clearance level as asked by
Crane Manufacturer.
viii. All the outdoor purpose luminaries, including Street light luminaries shall
be with ingress protection of IP 65 minimum.
ix. All the Mid Bay &Highbay fixtures, street light fixtures shall be provided
with the toughened Glass covers.
d) Starters:
Contractor
Executive Engineer Page56
Volume II: Technical Specification for
Electrical &Instrumentation Works
iii. Starters shall have brass contacts and radio interference capacitors.
e) Capacitors:
ii. The capacitors shall be suitable for operation at specified supply voltage
conditions and shall have a value of capacitance so as to correct the
power factor of their corresponding lamps circuit to the extent of 0.95 lag
or better.
f) Lamps:
c) Detailed Room wise Lighting Layout with Type of fixture details, mounting
detail arrangement and Circuit diagram showing phase wise load distribution
and interconnection between switches, fixtures, Lighting panel, receptacles
etc.
d) Conduit layout showing room wise routing of wires from lighting panel to
lighting fixtures covering primary & secondary point wiring, receptacles etc.
e) Internal road Lighting and Area lighting layout with type of mounting details
and fixture details.
Contractor
Executive Engineer Page57
Volume II: Technical Specification for
Electrical &Instrumentation Works
i. Main Lighting distribution board (MLDB) shall have MCCB as incomer &
outgoing feeder with thermal magnetic release for O/L+S/C+E/F
protections.
ii. This MLDB shall feed to different Lighting Panels/ Lighting DBs for
further distribution.
iii. Where ever MLDB is not applicable, lighting feeder of appropriate rating
shall be derived from the local distribution board. This feeder will feed to
local LP catering to lighting requirements of that particular area.
i) Constructional Features:
i. Boards and panels shall be sheet steel enclosed and shall be fully dust
and vermin proof, providing a degree of protection of IP-54 for indoor.
Outdoor panels shall in addition be completely weather-proof with a
sloping canopy for protection against rain and providing a degree of
protection of IP-55. The sheet steel used for frame, frame enclosures,
doors, covers and partitions shall be cold rolled 2.0 mm thick.
ii. The lighting panel for outdoor lighting shall have a programmable timer
for automatic control of lighting along-with contactor, MCB, auto/ manual
selector switch.
iii. All boards and panels shall be provided with hinged doors for access to
equipment. Doors shall be gasketed all round with neoprene gaskets.
iv. A slotted metallic sheet shall be provided inside. Only the MCBs
operating knobs shall project out of the metallic sheet slots for safe
operation and neat appearance. Incomer to lighting panels shall be
provided with Four pole MCB + RCCB
vi. For floor mounting type distribution boards, adequately sized mounting
channels shall be supplied and for wall/column/structure mounting type
panels suitable mounting straps shall be provided.
vii. Adequate interior cabling space and suitable removable cable entry
plates shall be provided for top/bottom entry of cables through glands
and or conduits as required. Necessary number of glands to suit the
specified cable sizes shall be provided. Cable glands shall be screwed
on type and made of brass.
viii. Two earthing terminals shall be provided to suit the earthing conductor.
ix. All sheet steel parts shall undergo rust-proofing process which should
include 7 tank processing. The steel works shall then be painted with
Contractor
Executive Engineer Page58
Volume II: Technical Specification for
Electrical &Instrumentation Works
two coats of Zinc - chromate primer and two coats of final epoxy based
finish paint of colour 63I as per IS 5.
j) Busbars:
ii. Busbars shall be provided with at least the minimum clearances in air as
per applicable standards.
iii. Busbars shall be adequately sized for the continuous current rating such
that the maximum temperature of the busbars, busbar risers/droppers
and contacts does not exceed 85 C under site reference temperature.
iv. The busbars, busbar connections and busbar supports shall have
sufficient strength to withstand thermal and electro-mechanical stresses
of the MCB’s let through/cut-off current associated with the specified
short-circuit level of the system.
vi. The neutral bus of the main 3 phase, 4 wire distribution board shall be
100% of the phase busbars.
i. MCB/ ELCB :
For all the lighting panels RCCBs shall be with 100 mA sensitivity &
for all receptacles RCBO sensitivity shall be 30 mA.
ii. MCCB :
Contractor
Executive Engineer Page59
Volume II: Technical Specification for
Electrical &Instrumentation Works
Potential fuses shall be provided at the tap-off point from the bus
bars for the voltmeters.
v. Indicating Lamps:
Contractor
Executive Engineer Page60
Volume II: Technical Specification for
Electrical &Instrumentation Works
viii. Conduits:
The junction boxes shall be dust and vermin proof and shall be
fabricated from 14 SWG sheet steel and shall be complete with
removable cover plate with gaskets, two earthing terminals each
with nut, bolt and washer. Boxes shall be additionally weather proof.
The boxes shall have provision for wall, column, pole or structure
mounting and shall be provided with cable/conduit entry knock outs,
terminal blocks, and HRC fuses as required.
The boxes shall be painted with one shop coat of red oxide zinc
chromate primer followed by a finishing coat of paint.
Contractor
Executive Engineer Page61
Volume II: Technical Specification for
Electrical &Instrumentation Works
Lighting poles for street lights and flood lights shall be of stepped
tubular steel poles construction as per applicable standard. These
poles shall be coated with bituminous preservative paint on the
inside as well as embedded outside surface. Exposed outside
surface shall be painted with one coat of red lead oxide primer.
After completion of installation two coats of aluminium paint shall be
applied.
Cable entry for street lighting junction boxes shall be from bottom.
Rain water canopy shall be provided at the top for the outdoor JBs.
Terminal strip shall be provided for looping loop out of cables.
Contractor
Executive Engineer Page62
Volume II: Technical Specification for
Electrical &Instrumentation Works
5.1.1. 900 mm wide antiskid insulating mat as per IS 15652 and of reputed make to be
spread in front of the 11kV, 415V switch gear panels & power DBs, DCDB etc.
5.1.3. First aid chart made of cloth for electrical shock treatment printed in English, Hindi
and Gujarati duly framed with front glasses.
5.1.5. HV and LV power supply single line diagrams in adequate sizes approved by
Purchaser/ Purchaser’s representative & in line with the local electrical inspector.
5.1.7. Provision of portable type Class A, B, C, and D type fire extinguishers at various
locations in line with the statutory requirements.
5.2.1. The requirement of hand appliance in switchgear room, electrical equipment room
shall be provided as per Clause 4.0 of Fire Protection Manual by Regional Tariff
Committee, 10th edition 1988.
5.2.2. Water Sealing & Fire Barriers at appropriate locations as specified in this
specifications & good engineering practices.
5.3.1. The enclosures of the control cabinets, junction boxes and Marshalling boxes,
panels etc. to be installed shall provide minimum degree of protection as detailed
here under
a) Installed outdoor – IP 55
b) Installed indoor – IP 54
Contractor
Executive Engineer Page63
Volume II: Technical Specification for
Electrical &Instrumentation Works
5.3.2. The degree of protection shall be in accordance with IS 13947 (Part I)/ IEC 947
(Part I)/ IS 2063/ IEC 529
5.4.2. Gas Classification (Group) – The characteristics of the gas or vapour involved in
relation to the ignition or energy and safe gap data
5.4.3. Temperature Classification- The ignition temperature of the gas or vapour involved
or lowest value of the ignition temperature, if more than one combustible material is
present.
Contractor
Executive Engineer Page64
Volume II: Technical Specification for
Electrical &Instrumentation Works
6.1. GENERAL:
6.1.2. The Contractor shall furnish all supervision, labour, tools, equipment, rigging
materials and incidental materials such as bolts, wedges, anchors, concrete inserts
etc. required to completely install, test and adjust the equipment.
6.1.4. The Contractor shall erect and commission the equipment as per the instructions of
the Purchaser/ Engineer In Charge and shall extend all co-operations to him.
6.1.6. The Contractor shall move all equipment into the respective buildings through
regular doors or floor openings provided specifically for the equipment. The
Contractor shall make his own arrangement for lifting of equipment.
6.1.7. Where assemblies are supplied in more than one section, the Contractor shall make
all necessarymechanical and electrical connections between sections including the
connections between busbars/wires.TheContractorshallalsocarryoutthe
adjustments/alignments necessary for proper operation of the circuit breakers.All
insulators and bushings shall be protected against damage during installation.
Insulators or bushings chipped, cracked or damaged due to negligence or
carelessness shall be replaced by the Contractor at his own expenses.
6.1.8. The Contractor shall take utmost care in handling instruments, relays and other
delicate mechanisms.Wherever the instruments or relays are supplied separately,
they shall be mounted only after the associated control panels have been erected
and aligned. The blocking material/mechanism employed for the safe transit of the
instruments and relays shall be removed after ensuring that the panels have been
completely installed and no further movement of the same would be necessary.Any
damage to relays and instruments shall be immediately reported to the Engineer In
charge.
6.1.9. Equipment furnished with finished coats of paint shall be touched up by the
Contractor if their surface is spoiled or marred while handling.
6.1.10. Foundation work and grouting of fixing bolts or channels for all transformers,
switchgear, motors, and control panels shall be carried out by the Contractor.
Contractor
Executive Engineer Page65
Volume II: Technical Specification for
Electrical &Instrumentation Works
6.3.1. Switchgear control panels shall be installed in accordance with the latest Indian
Standard Code of Practice 10118. The switchgear panels shall be installed on
finished surface or concrete or steel sills. The Contractor shall be required to install
and align any channel sills which form part of the foundations. Tape or compound
shall be applied where called for.The base of outdoor type units shall be sealed in
an approved manner to prevent ingress of moisture.
6.3.2. Following minimum clearances shall be observed while finalizing the HV/ LV panel
layouts-
a) Minimum clearance of 1.0 meter shall be maintained from the rear of the
panel to the nearest wall /structure.
d) For HV metal enclosed, indoor panels, Minimum 1 meter clearance from all
sides & 1.5 meter in the front.
Contractor
Executive Engineer Page66
Volume II: Technical Specification for
Electrical &Instrumentation Works
6.3.3. Emergency Exit doors shall be provided forelectrical room, complying with the
requirements of NBC 2005 latest edition.
6.3.4. After installation of all power and control wiring, the Contractor shall perform
operating tests on all switchgear and panels to verify the proper operation of
switchgear/panels and the correctness of the interconnections between various
items of equipment.This shall be done by applying normal a-c or d-c voltage to the
circuits and operating the equipment. Megger tests for insulation, polarity checks on
the instrument transformers, operation tests on equipment, and installation tests
shall be carried out by the Contractor who shall also make all necessary
arrangements for proper functioning of the equipment.
6.4.1. The Contractor shall install copper/ steel conductors, braids, etc., required for the
system and individual equipment earthing.All work such as cutting, bending,
supporting, painting/coating, drilling, brazing/soldering/welding, clamping, bolting
and connecting onto structures, equipment frames, terminals, rails or other devices
shall be in the Contractor’s scope of work. All incidental hardware and
consumables such as fixing cleats/clamps, anchor fasteners, lugs, bolts, nuts,
washers, bituminous compound, welding rods, anti-corrosive paint as required for
the complete work shall be deemed to be included by the Contractor as part of the
installation work.
6.4.2. The quantities, sizes, material of earthing conductors and electrodes to be installed
as per requirement. Routes of the conductors and locations of electrodes shall be
shown in the earthing layout drawings,which are to be prepared by Contractor&
approved by Purchaser’s representative.
6.4.3. The work of embedment of earthing conductor in RCC floors/walls along with
provision of earth plate inserts/pads/earth risers shall be done by the Contractor
when the floors are cast or during construction of walls. Contractor’s scope of
installation shall also include, laying the conductors in position with 60 mm concrete
cover, making welded connections to inserts/pads/risers above the floor near the
equipments.The embedded conductors shall be connected to reinforcing rods
wherever necessary.
6.4.4. If the tap connections (earthing leads) from the floor embedded main earthing grid
to the equipment are more than 500 mm long then the same shall be embedded in
floor by the Contractor where required, together with associated civil work such as
excavation/chasing, concreting and surfacing.The concrete cover over the
conductor shall not be less than 60 mm.
6.4.5. Installation of earth conductors in outdoor areas, buried in ground, shall include
excavation of earth up to 600 mm deep 450 mm wide, laying of conductors at 600
mm depth, brazing/welding as required, of main grid conductor joints as well as
risers of length 500 mm above ground at required locations and then backfilling
material to be placed over buried conductor shall be free from stones and other
harmful mixtures. Backfill shall be placed in layers of 150 mm, uniformly spread
along the ditch, and tampered utilizing pneumatic tampers or other approved
means. If the excavated soil is found unsuitable for backfilling, the Contractor shall
arrange for suitable material from outside.
Contractor
Executive Engineer Page67
Volume II: Technical Specification for
Electrical &Instrumentation Works
6.4.7. Electrodes shall be installed in constructed earth pits, and connected to main buried
earth grid, The scope of work shall include excavation, construction of the earth pits
including all materials required for construction of earth pits, placing the rod and
fixing test links on those pipe/rod/plate electrodes in test pits and connecting to
main earth conductors.
6.4.8. Installation of lightning conductors on the roofs of buildings shall include laying,
anchoring, fastening and cleating of horizontal conductors,grouting of vertical rods
wherever necessary, laying fastening/ cleating/ welding of the down comers on the
walls/columns of the building and connection to the test links to be provided above
ground level.
6.4.9. Installation of the test links shall include mounting of the same at specified height on
wall/column by suitable brackets and connections of the test link to the earth
electrode.
6.4.10. Whenever main earthing conductor crosses cable trenches, they shall be buried
below the trench floor.
6.4.11. Suitable earth risers shall be provided above finished floor/ ground level. If the
equipment is not available at time of laying of the main earth conductors, the
minimum length of such riser inside the building shall be 200 mm and outdoors shall
be 500 mm above ground level. The risers to be provided shall be marked in project
drawings.
6.4.12. Earth leads and risers between equipment earthing terminals and the earthing grid
shall follow as direct and short a path as possible.
6.4.13. An earthing mat shall be provided under each operating handle of the isolator and
operating mechanism of HV breakers. Operating handle of the isolator and
supporting structure shall be bonded together by a flexible connection and
connected to the earthing grid.
6.4.14. A separate earth electrode bed shall be provided adjacent to structure supporting
lightning arrestors. Each connection shall be as short and as straight as practicable.
For arrestors mounted near transformers, earth conductors shall be located clear off
the tank and coolers.
6.4.15. Wherever earthing conductors passes through walls, galvanized iron/PVC sleeves
shall be provided for the passage of earthing conductor. The pipe ends shall be
sealed by the Contractor by suitable water proof compound.
Contractor
Executive Engineer Page68
Volume II: Technical Specification for
Electrical &Instrumentation Works
b) Test pits with concrete covers shall be provided for periodic testing of earth
resistance. Installation of pipe electrodes in test pits shall be suitable for
watering. The necessary materials required for installation of test pits shall be
supplied and installed by Contractor.The installation work shall also include
civil work such as excavation and connection to main earth grid.
c) Earth pits shall be treated with salt and charcoal. In case found necessary,
then with the approval of Purchaser’s representative,Back fill compound of
suitable composition may be used. Back fill material shall not be water soluble
& shall retain moisture & enhance conduction around electrode.Back fill
compound shall be low resistance & non corrosive earth enhancement
compound which shall provide safe discharge path to fault current &lightening
current.
d) Ohmic value shall be within safe limits & it shall be stable & not fluctuating.
e) Soil, salt and charcoal placed around the electrode shall be finely graded, free
from stones and other harmful mixtures. Backfill shall be placed in layers of
250 mm thick uniformly spread and compacted. If excavated soil is found
unsuitable for backfilling, the Contractor shall arrange for a suitable soil from
outside.
6.5.1. General
a) Lines and grade for trays may be measured from building steel and finished
floor elevations. Change in line or grade, or the addition of offsets by means
of cutting standard tray sections and inserting additional tray fittings to match
with the existing arrangement shall be considered as a normal part of the
work.
b) Where embedded steel inserts in concrete floors/ walls for welding the
supports for cable racks/ trays are not available, Contractor shall provide
suitable anchor fasteners at no extra cost.
Contractor
Executive Engineer Page69
Volume II: Technical Specification for
Electrical &Instrumentation Works
6.5.2. Cable Trays: All the cable tray shall be hot dipped galvanized with minimum
galvanization thickness as per mentioned in this specifications.
a) Cable tray shall be of perforated sheet steel with formed flanges and of
minimum thickness not less than 1.25 mm for trays up to 100 mm width, not
less than 1.5 mm for trays from 100 mm to 150 mm width and not less than
2.0 mm for trays from 150 mm to 300 mm width.
b) All the cable trays above 300 mm width shall be of ladder type with minimum
thickness of 2.5 mm.
c) Cable tray for use in areas where chlorine gas may be present shall be
constructed from U-PVC or GRP. Cable tray supports shall be of a compatible
finish with the associated cable tray.
d) All cable trays tees, intersection units, bends, turns and sets shall be
prefabricated (made by the manufacturer) and shall be of a matching design
to the main section of cable tray.
e) Tray shall only be joined by couplers supplied by the manufacturers. The joint
shall be secured in accordance with the manufacturer’s instructions.
g) Wherever possible, cable trays shall be installed in full lengths without cutting.
Should it be necessary to cut or drill a length of tray, the bared ends or
damaged section of the tray shall immediately be given a coat of zinc rich cold
galvanized paint. All site manufactured accessories, supports and metal
fittings required to ensure correct installation of the cable trays shall be
similarly treated.
h) All cables shall be firmly secured to the tray using purpose made saddles, as
approved by the Purchaser’s Representative, together with proprietarynylon
fasteners and/or cable cleats. Following installation of cables, the tray shall
remain rigidly supported and the deflection of any section shall not exceed 15
mm at mid span. All brackets and tray work shall be suitable for withstanding
a temporary weigh of 125 kgs.
i) Cable trays shall not be cut to allow the passage of cables through the
surfaces of the tray
j) The sizing of the cable tray shall provide a minimum of 20% spare capacity.
k) The tray shall be run at least 300 mm clear of plumbing and mechanical
services.
Contractor
Executive Engineer Page70
Volume II: Technical Specification for
Electrical &Instrumentation Works
l) Bends in the installation shall take account of the minimum bending radii of
cables to be installed.
m) All the cable trays shall be supplied with cable tray supports (of adequate
size) at no more than 1.2 meter interval.
n) Other cable tray details & cabling system shall be as per typical drawings
attached with the specifications.
a) Cable trunking shall be manufactured from mild steel of not less than 1.25 mm
and shall be hot dipped galvanized. The Contractor shall ensure that the size
of the trunking is adequate for the number of cables to be installed together
with 50% spare capacity and shall in any case be 50 mm x 50 mm minimum
size.
c) The trunking shall have two return flanges for rigidity. Where necessary,
additional strengthening straps shall be fitted internally. The cover shall
overlap the trunking and be made of the same gauge. Fixing screws for
covers shall be recessed and be of the self retaining `quick fix' type. All
bends, tees and intersections shall be of the gusset type and shall, wherever
possible, be purpose made by the manufacturer and of a matching design to
the main trunking.
d) Cables shall be retained in the trunking when the cover is removed by means
of straps. Internal connecting sleeves shall be fitted across joints in the
trunking and earth continuity ensured by bonding each section of trunking to a
continuous earth wire.
i) Cable and conduit/ trunking runs shall be determined by the Contractor and
agreed by the Purchaser’s Representative before any work is started. The run
shall be at least 300 mm clear of plumbing and mechanical services.
Contractor
Executive Engineer Page71
Volume II: Technical Specification for
Electrical &Instrumentation Works
6.6.1. General:
b) Cables shall be installed in such a way that the minimum bending radii are not
reduced when installed or during installation. Cables shall not be installed in
ambient temperatures below that recommended by the cable manufacturer.
g) In order to make economic use of the cable support system, cables shall be
arranged in groups of 50 mm maximum overall diameter. These groups shall
be securely tied to the cable support system at intervals not exceeding 900
mm for horizontal runs and 300 mm intervals on vertical runs.
h) In order to make the most economic use of cable tray and duct capacity,
multicore cabling shall be utilized in order to connect instrumentation groups
by using suitably located sub-distribution junction boxes. The junction boxes
shall be suitable for the area in which they are to be installed and for the type
of circuit. They shall be readily accessible for maintenance and clearly labeled
junction boxes shall be constructed of die cast Aluminium and provide degree
of protection IP 65.
Contractor
Executive Engineer Page72
Volume II: Technical Specification for
Electrical &Instrumentation Works
j) Cables shall be laid in a manner such that any electrical interference between
cables shall not have a detrimental effect on the life and operation of Plant.
k) Where practical a separate cable support system shall be provided for power
and non-power cables. Where this is not practical a separation as per
indicated in above table shall be maintained between power and non-power
cables when run on the same support system.
l) Heavy duty galvanized iron cable tray and ladder racking shall be used for
cable support systems. FRP/ GRP cable support systems shall be used in
areas used for the storage and handling of chlorine. These systems shall be
used to route cables around walls and within cable trenches. Cables shall be
securely fixed to the support systems. Bundling of cables shall be permitted
where allowance for this practice has been made in sizing the cables.
c) Cables shall be laid in accordance with layout drawings and cable schedule
which shall be prepared by Contractor and submitted for approval.
d) All cable routes shall be carefully measured and cables cut to the required
lengths, leaving sufficient amount for the final connection of the cable to the
terminals on either end.
e) Various cable lengths cut from the cable reels shall be carefully selected to
prevent undue wastage of cables.
f) A loop of 1.0 meter shall be left near each field instrument before terminating
the cable.
g) Cables shall be complete uncut lengths from one termination to the other.
i) All cables shall be identified close to their termination point by cable numbers
as per cable interconnection schedules.
j) Identification tags shall be securely fastened to the cables at both the ends.
l) The Contractor shall take the actual measurement of the cables and the
associated accessories such as cable trays, conduits etc required at site, prior
to the placement of order on the cables.
Contractor
Executive Engineer Page73
Volume II: Technical Specification for
Electrical &Instrumentation Works
c) The bottom of the cable trench shall be freed of sharp stones and such like
and 75 mm of sieved sand laid below the cable. After cable laying 75 mm of
sieved sand shall be laid above the cable. For HV cables sand bedding shall
be of 150 mm & cables shall be covered with half round Hume pipes of twice
the diameter of cable.
e) Warning tape shall be laid a minimum of 200 mm above the protective covers.
b) The Contractor shall ensure that sufficient draw-in points have been provided
and that adequate room has been allowed for installation of cables.
Drawstrings shall be provided in all ducts to enable additional cables to be
installed when required.
c) Where cables pass in or out of any duct entries into or within buildings such
entries, together with any spare ducts shall be sealed against the ingress of
moisture by means of duct stoppers and bituminous compounds or by any
other method approved by the Purchaser’s Representative. The stopper shall
have a fire resistance of at least 30 minutes. Single core cables in trefoil
formation shall pass through the same duct and shall not be separated.
However, for two different trefoil formations, they shall be laid in separate
ducts.
Contractor
Executive Engineer Page74
Volume II: Technical Specification for
Electrical &Instrumentation Works
b) A space factor of 40% shall not be exceeded, but in any case conduit of less
than 20 mm diameter shall not be permitted. The tubing shall be perfectly
smooth inside and out and free from flaws and imperfections of any kind. Both
ends of every length of tubing shall be properly reamed with all sharp edges
removed before erection.
d) Where conduits are greater than 25 mm, straight through joint boxes shall be
of the trough type. Where conduit and/ or fittings are attached to equipment
casings, the material or case of the casing shall be tapped for a depth of not
less than 10 mm or male bushes and flanged couplings shall be used.
e) Heavy hexagonal lock nuts shall be used at all positions where running joints
are required and care shall be taken to ensure that they seat firmly and evenly
on to the mating faces of coupling or other adjacent accessories. All junction
boxes, draw-in boxes, and inspection fittings, shall be so placed that the
cables can be inspected and, if necessary, withdrawn and re-wired throughout
the life of the installation.
f) Generally not more than two bends or offsets or one coupling will be permitted
without a suitable inspection accessory. Fish wires shall not be left in conduits
after erection. The whole of the installation shall be arranged for a loop-in type
of system with joints being carried out at switches, isolators, etc. Intermediate
joints in the cable will only be allowed by arrangement with the Purchaser/
Purchaser’s Representative.
g) Ends of conduits which are liable to be left open for any length of time during
building operations shall be plugged to prevent the ingress of dirt, cement,
etc. and covers, either temporary or permanent, shall be fitted on all boxes.
h) Generally, conduits shall not cross expansion joints of buildings, but where
they cannot be installed in any other manner then a flexible conduit shall be
used across the expansion joint. A total 150 mm movement shall be allowed.
Contractor
Executive Engineer Page75
Volume II: Technical Specification for
Electrical &Instrumentation Works
b) Exposed threads and places where galvanizing has been damaged shall be
cleaned and then painted with two coats of an approved metallic zinc based
paint. This treatment shall be applied as the work proceeds.
b) At least 15 mm cover shall be allowed for finishes over the conduit. Where
this cover cannot be maintained then expanded metal shall be fitted with the
conduit. Conduit cast into reinforced concrete floors shall be fixed to the steel
reinforcing with binding wire and the conduit boxes filled with expanded
polystyrene or enclosed in a plastic bag to prevent the ingress of concrete
when poured. Where possible, the conduit boxes shall be fixed to shuttering
to give a flush finish.
c) Conduit installed in voids, false ceilings, and other concealed routes shall be
installed as specified for the surface conduits. Wiring shall be carried out after
the false ceiling or permanent ducts have been completed. Conduit installed
in floors shall be sealed against ingress of moisture.
a) All cable hangers, clips, cleats and saddles shall be of an approved type and
appropriate to the type and size of cable installed. Their spacing shall be such
as to ensure a neat appearance and prevent sagging of the cables at all times
during their installed life.
Contractor
Executive Engineer Page76
Volume II: Technical Specification for
Electrical &Instrumentation Works
b) In shallow trenches used for electrical services only, cables may be laid in a
neat and orderly manner on the floor of the trench. One layer only shall be
allowed. Additional cables shall be installed on the walls of the trench in an
acceptable manner & such a way that, in no case the distance between two
different types of cable shall not be less than the separation distance
tabulated above.
c) Where the trench is shared by other services, cables shall be installed on the
walls of the trench in an acceptable manner & such a way that, minimum
separation distance of 300mm shall be maintained.
e) Cable trenches & cable installation shall be in accordance with the attached
typical cabling system drawings.
f) Where other services are present the cables shall be segregated from them
by separation distances as mentioned above and wherever possible kept
above `cold' wet services. Cables should not be run if at all possible above or
in close proximity to `hot' services.
g) The cabling shall be installed in such a manner as to allow access to the other
services for normal maintenance without disturbance of the electrical
installation
Contractor
Executive Engineer Page77
Volume II: Technical Specification for
Electrical &Instrumentation Works
plastic covered conduit, and a separate earth core linking the box to the
equipment.
vii. Where single core cables are glanded to or pass through cabling plates
the gland plate or cabling plate shall be constructed of non-magnetic
material.
i. Through joints shall only be allowed with the approval of the Purchaser’s
Representative. Where such joints are necessary in thermoplastic and
elastomeric cables, the cables shall be jointed with epoxy or acrylic
resin cold setting compound, which has been premeasured and pre-
packed ready for use. The boxes shall preferably be of split, moulded
plastic type with filling vents for compound. Bonding straps shall be
fitted with armour clamps across the joint and inspected by the
Purchaser/ Purchaser’s Representative prior to filling the box with
compound. Wrapped pressure type joints will not be accepted.
a) Ties and strapping shall be suitable for securing cable and cable groups to
cable tray or ladder. They shall be resistant to chemical and marine corrosion.
Plastic coated metal ties used in order to obtain corrosion resistance shall not
be acceptable. Nylon ties shall be resistant to the effects of ultra-violet light
and shall be self-extinguishing.
b) Large single cables shall be secured with cable clamps or cable cleats.
At each end of each cable, in a uniform and visible position a label shall be fixed on
the cable in accordance with the cable schedule. Labels shall be made of PVC and
shall be indelibly marked to the approval of the Purchaser’s Representative. The label
shall be retained using proprietary nylon strips passing through two fixing holes at
either end of the label. If the cable gland is not normally visible, then the label shall be
fixed inside the panel by means of screws.
Contractor
Executive Engineer Page78
Volume II: Technical Specification for
Electrical &Instrumentation Works
c) The minimum depth for laying of underground cable route markers shall be as
per indicated in the typical drawings attached with this tender.
a) The Contractor shall install, test and commission the cables specified in the
specification. Cables shall be laid directly buried in earth, on cable racks, in
built up trenches, on cable trays and supports, in conduits and ducts or bare
on walls, ceiling etc. as per drawings, which are to be prepared by
Contractor& approved by Purchaser’s representative.Contractor’s scope of
work includes unloading, laying, fixing, jointing, bending, and termination of
the cables & all related accessories. The Contractor shall also supply the
necessary materials and equipment required for jointing and termination or
the cables.
b) All apparatus, connections and cable work shall be designed and arranged to
minimize risk of fire and any damage which might be caused in the event of
fire. Wherever cables pass through floor or wall openings or other partitions,
suitable bushes of an approved type shall be supplied and put into position by
the Contractor.
c) Standard cable grips and reels shall be utilized for cable pulling. If unduly
difficult pulling occurs, the Contractor shall check the pull required and
suspend pulling until further procedure has been approved by the Engineer’s
Representative. The maximum pull tension shall not exceed the
recommended value for the cable measured by the tension dynamometer. In
general, any lubricant that does not injure the overall covering and does not
set up undesirable conditions of electrostatic stress or electrostatic charge
may be used to assist in the pulling of insulated cables in conduits and ducts.
d) After pulling the cable, the Contractor shall record cable identification with
date pulled neatly with waterproof ink in linen tags. Identification tags shall be
attached securely to each end of each cable with non-corrosive wire. The said
wire must be non-ferrous material on single conductor power cable. Tags
shall further be attached at 10 meter intervals on long runs of cables on cable
trays and in pull boxes. Cable and joint markers and RCC warning covers
shall be provided wherever required.
e) Sharp bending and kinking of cables shall be avoided. The bending radius for
various types of cables shall not be less than those specified below:
Contractor
Executive Engineer Page79
Volume II: Technical Specification for
Electrical &Instrumentation Works
ii. 1.1 kV, XLPE insulated, multicore : 12 times the overall dia of
the cablearmoured cables
iii. (If shorter radius appears necessary, no bend shall be made until
clearance and instructions have been received from the Purchaser/
Engineer in charge)
g) Where groups of HV, LV and control cables are to be laid along the same
route, suitable barriers to segregate them physically shall be provided.
h) Where cables cross roads and water, oil, gas or sewage pipes, the cables
shall be laid in reinforced spun concrete or steel pipes. For road crossings
the pipe for the cables shall be buried at no less than one meter depth.
i) Cables laid in ground shall be laid on a 75 mm riddled earth bed. The cables
shall then be covered on top and at their sides with riddled earth of depth of
about 150 mm. This is then gently filled up to a depth of about 100 mm above
the top of uppermost cable to provide bedding for the protective cable covers
which are placed centrally over the cables. The protective cable covers for LV
cables may be of earthenware and for HV cables of reinforced concrete. The
RCC covers shall have one hole at each end, to tie them to each other with GI
wires to prevent displacement. The trench is then backfilled with the
excavated soil and well rammed in successive layer of not more than 300 mm
in depth, with the trenches being watered to improve consolidation wherever
necessary. To allow for subsidence, it is advisable to allow a crown of earth
not less than 75 mm in the centre and tapering towards the sides of the
trench.
j) In each cable run some extra length shall be kept at a suitable point to enable
one or two straight through joints to be made, should the cable develop a fault
at a later date.
k) Cables on cable racks, on cable trays and conduits shall be formed to avoid
bearing against edges of trays, racks, conduits or their supports upon entering
or leaving trays, racks or conduits. Cables shall be racked or laid directory into
cantilevered cable trays where practicable, but in some cases it may be
necessary that cables are pulled or threaded into trays. To facilitate visual
tracing, cables in trays shall be laid only in single layers and unnecessary
crossing of cables shall be avoided. Cables on trays shall finally be clamped
in an approved manner.
l) Cable splices will not be permitted except where permitted by the Purchaser/
Purchaser’s Representative. Splices shall be made by Contractor for each
type of wire or cable in accordance with the instructions issued by cable
manufacturer’s and the Engineer’s Representative. Before splicing, insulated
cables shall have conductor insulation stepped and bound or penciled for
recommended distance back from splices to provide a long leakage path.
After splicing, insulation equal to that on the spliced conductors shall be
applied at each splice.
Contractor
Executive Engineer Page80
Volume II: Technical Specification for
Electrical &Instrumentation Works
n) At cable terminal points where the conductor and cable insulation will be
terminated, terminations shall be made in a neat, workmanlike and approved
manner by men specialized in this class of work.
p) When control cables are to be fanned out and cabled together with cord, the
Contractor shall make connections to terminal blocks, and test the equipment
for proper operation before cables are corded together. If there is any
question as to the proper connection, the Contractor shall make a temporary
connection with sufficient length of cable so that the cable can be switched to
another terminal without splicing. After correct connections are established
through operating the equipment, cables shall be cut to their correct lengths,
connected to terminals in the specified manner, and corded together where
necessary to hold them in place in a workmanlike manner.
q) Cable seals shall be examined to ascertain if they are intact and that cable
ends are not damaged. If the seals are found to be broken the cable ends
shall not be jointed until after due examination and testing by the Purchaser/
Purchaser’s Representative.Before jointing is commenced, insulation
resistance of both sections of cables to be jointed shall be checked by
megger.
r) After installation and alignment of motors, the Contractor shall complete the
conduit installation, including a section of flexible conduit between motor
terminal box and trench/ tray. The Contractor shall install and connect the
power, control and heater supply cables as per equipment manufacturer’s
drawings.
s) Metal sheath and armour of the cable shall be bonded to the earthing system
of the station.The size of conductor for bonding shall be appropriate with the
system fault current.
c) Lighting panels
Contractor
Executive Engineer Page81
Volume II: Technical Specification for
Electrical &Instrumentation Works
e) Point wiring
h) Maintaining equipment/ materials during storage and being responsible for the
equipment/ material until they are handed over to Purchaser.
Code for practice for interior illumination (Part-1) : IS: 3646/ BS: 8206
electrical work
Contractor
Executive Engineer Page82
Volume II: Technical Specification for
Electrical &Instrumentation Works
Primary point wiring covers the wiring between a circuit of the lighting
panel to the junction box of the first lighting fixture/receptacle unit and
between junction boxes of the subsequent lighting fixture connected to
that circuit of the lighting panel. In some cases where there are junction
boxes, the primary point covers the wiring between junction box and the
first lighting fixture/receptacle unit in that circuit.
i. The point wiring shall include supply of necessary materials for the
conduit wiring such as galvanized rigid steel conduit, galvanized M.S.
fixing saddles with spacer plates, nylon/fiber fixing plugs, galvanized
M.S. fixing screws, 12 SWG galvanized steel earthing wire, FRLS PVC
insulated Copper conductor wires, control switches and pulling,
termination of the earthing/ FRLS PVC insulated wires as required,
installation of control switches, drilling holes in brick walls/RCC roof
slabs for taking the wiring conduits and refinishing and any other
works/material necessary for making point wiring complete in all
respects.
ii. Wires used for conduit point wiring of lighting fixtures/ceiling fans, 5A
receptacles and receptacles above 15A shall be 1.1 kV grade, FRLS
PVC insulated, single core, multistranded Copper conductor wires of
sizes not less than 1.5 sq. mm and 2.5 sq. mm respectively. Wires shall
conform to IS: 694 and shall bear the ISI mark.
Contractor
Executive Engineer Page83
Volume II: Technical Specification for
Electrical &Instrumentation Works
ii. Contractor shall plan and cut the cables in such a way that there is no
wastage and no cable jointing is required in any run. However, should
any joint become necessary the same shall be provided by the
Contractor and a joint marker shall also be provided at no extra
cost.Earthing of street light pole/flood light tower, lighting fixtures, etc.
are included under Contractor scope.
ii. Drilling holes in brick/RCC wall and roof for taking cable or conduit,
sealing and refinishing with cement plaster.
6.7.5. Outdoor Lighting (Street and Flood Lighting):The following shall be deemed to be
included as part of the installation work for outdoor lighting point wiring.
a) Installation of multicore/ single core cables between LDB and junction box
mounted on street light pole/flood lighting tower, from junction box to metal
enclosed control gear box.
b) Supply and installation of crimping type cable lugs, double compression type
cable glands at each junction box and fixture, termination, testing and
commissioning of cables.
c) Contractor’s scope shall also include excavation and preparation for buried
cables. Supply and installation of route markers, supply and installation of
HDPE/Hume pipes for road crossing shall also be included in the scope of
installation of point wiring.
Contractor
Executive Engineer Page84
Volume II: Technical Specification for
Electrical &Instrumentation Works
f) Contractor shall plan and cut the cables in such a way that there is no
wastage and no cable jointing is required in any run. However, should any
joint become necessary, the same shall be provided by the Contractor and
joint marker shall also be provided at no extra cost.
g) Earthing of street light pole/flood light tower, lighting fixtures, control gear
boxes, junction boxes, etc. are also included in the scope of installation of
point wiring. Contractor shall earth street light pole/flood light poles and
junction box with 25x3 mm G.S. flat tap off from the 25x3 mm M.S. flat
earthing grid along the street lighting included in scope. The Contractor shall
interconnect earthing grid to plant main earthing grid at first and last pole of
each feeder circuit and at one intermediate pole.
h) Installation of lighting Poles and Towers for Outdoor Lighting (Street and
Flood Lighting)-
i. Work includes supply and installation of street light poles and flood light
towers including associated junction boxes with fuses, links and
terminals for junction boxes and junction boxes near each flood light
fixtures.
ii. All street light poles and towers shall be painted with one shop coat of
red oxide oil primer followed by two coats of aluminium alkyd paint.
6.7.6. Installation of Lighting Distribution Board, Lighting Panels (AC & DC), 230 V, AC 1-
Ph Distribution Boards.
Installation of above items shall include necessary foundation channels, bolts/ nuts,
etc. for grouting lighting distribution boards, iron brackets/ grouting brackets,
bolts/nuts for wall/ column mounted panels and associated civil works.
6.7.7. Details of work requirements are covered in lighting installation notes and details
and typical drawings which form the part of specification. Any changes, if
necessary due to site conditions/requirements shall be carried out after obtaining
approval of Purchaser/ Purchaser’s Representative. The changes carried out shall
be marked clearly in the layout drawings by Contractor and ‘AS BUILT DRAWING’
shall be prepared by the ‘Contractor’ and this shall be forwarded to Purchaser’s site
/ design office.
a) Wiring
i. Wiring shall be carried out strictly as per project drawings and technical
specification.All exposed conduit wiring shall have provision for easy
inspection. Where cable wiring is specified cable shall be cleated on to
the wall as close to the ceiling as possible. In all types of wiring due
consideration shall be given for neatness and appearance.
Contractor
Executive Engineer Page85
Volume II: Technical Specification for
Electrical &Instrumentation Works
R - Phase - Red
Y - Phase - Yellow
B - Phase - Blue
N –Neutral - Black
b) There shall be a circuit breaker on each live conductor of supply mains at the
point of entry.
d) Receptacles and lighting fittings in general shall be fed from different Circuits.
Five amps receptacles for toilet or small rooms can be fed from the lighting
circuit with proper isolating arrangement.
e) Each final sub-circuit from a lighting panel shall be controlled by a single pole
switch connected to the live conductor.
f) For long conduit wiring runs, inspection/ pull boxes shall be provided at
intervals not exceeding 10 meter. Such facilities shall also be provided at
conduit bends.
a) All receptacles and switches to be installed in offices and control rooms shall
be flush mounted within the wall and those in other areas shall be wall or
column mounted.
b) Ceiling roses shall not embody fuse terminals as an integral part.For voltages
exceeding 250 volts, a ceiling rose or any similar attachment shall not be
used.
c) All exposed metal parts of the plug, when the plug is in complete engagement
with the socket outlet, shall be in effective electrical connection with the
earthing pin.
Conduits and fittings shall be earthed by 12 SWG GI wires run along the length of
the conduit and secured by means of suitable clamps efficiently fastened to conduit
tip. To achieve perfect electrical continuity, the conduits shall be bonded effectively
on either end of a coupling and other joints.
a) Conduits shall be earthed at the ends adjacent to switch boards at which they
originate or otherwise at the earth clip, clamp or gland, in effective electrical
contact with the conduit.
Contractor
Executive Engineer Page86
Volume II: Technical Specification for
Electrical &Instrumentation Works
b) For outdoor lighting poles & mast 8 SWG GI earth wire shall be run buried in
ground at a depth of 600 mm along-with lighting cables and shall be
terminated up to the junction box on the pole and 12 SWG wire shall be taken
up to the pole fitting. In case of lighting poles where the main earth grid is far
away from the pole, local pits shall be provided for pole earthing.
Contractor
Executive Engineer Page87