Site Investigative Report
Site Investigative Report
Site Investigative Report
March 2021
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
SITE INVESTIGATION
WORK PLAN
Tyco Stanton Street Facility
Marinette, Wisconsin
BRRTS No. 02-38-581955
Prepared for:
Tyco Fire Products LP
Christopher S. Peters, PG 1 Stanton Street
Principal Geologist Marinette
Wisconsin 54143
Prepared by:
Arcadis U.S., Inc.
126 North Jefferson Street
Suite 400
Milwaukee
Wisconsin 53202
Benjamin J. Verburg, PE
Principal Engineer Tel 414 276 7742
Fax 414 276 7603
Our Ref:
30015423
Date:
March 22, 2021
arcadis.com
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
CONTENTS
Acronyms and Abbreviations ........................................................................................................................iii
1 Introduction............................................................................................................................................ 1
2 Site Background .................................................................................................................................... 2
2.1 Site Description and History ...................................................................................................... 2
2.2 Previous and Concurrent Investigations Related to PFAS ........................................................ 2
2.3 Geology and Physical Setting.................................................................................................... 3
2.4 Natural and Cultural Resources ................................................................................................ 4
3 General Field Activities ......................................................................................................................... 5
3.1 Access and Utility Clearance ..................................................................................................... 5
3.2 Surveying ................................................................................................................................... 5
3.3 Investigation-Derived Waste...................................................................................................... 5
4 Groundwater.......................................................................................................................................... 6
4.1 Surficial Aquifer Monitoring Well Installations ........................................................................... 6
4.2 Well Development ..................................................................................................................... 6
4.3 Groundwater Monitoring ............................................................................................................ 7
5 Other media........................................................................................................................................... 8
5.1 Soil ............................................................................................................................................. 8
5.2 Surface Water ............................................................................................................................ 8
5.3 Stormwater ................................................................................................................................ 8
5.4 Air .............................................................................................................................................. 8
5.5 Sediment.................................................................................................................................... 9
6 Quality Assurance and Quality Control ............................................................................................... 10
6.1 Special Considerations for PFAS Sampling ............................................................................ 10
6.2 Laboratory Methods and Analysis ........................................................................................... 10
7 Reporting ............................................................................................................................................. 11
8 Anticipated Schedule .......................................................................................................................... 12
9 References .......................................................................................................................................... 13
arcadis.com
i
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
TABLES
Table 1. Proposed Groundwater Monitoring Locations
Table 2. Laboratory Methods and QA/QC Frequency ................................................................................ 10
FIGURES
Figure 1. Site Location
Figure 2. Site Layout
Figure 3. Existing Monitoring Wells and Piezometers
Figure 4. Proposed Groundwater Monitoring Locations
arcadis.com
ii
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
arcadis.com
iii
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
1 INTRODUCTION
On behalf of Tyco Fire Products LP (Tyco), Arcadis U.S., Inc. (Arcadis) prepared this Site Investigation
Work Plan (work plan) to continue investigation of the nature and extent of per- and poly-fluorinated alkyl
substances (PFAS) associated with groundwater at and near the Tyco Stanton Street Facility, located at
1 Stanton Street in Marinette, Wisconsin (the Site; Figure 1). The investigation work described herein is
based on an evaluation of the data collected to date and identification of data gaps.
This work plan builds upon the Near-Term Bedrock Groundwater Evaluation Work Plan (Arcadis 2020c)
that was submitted to the Wisconsin Department of Natural Resources (WNDR) on May 1, 2020. The
objectives of the proposed investigation are to further delineate the nature and extent of PFAS in
groundwater in the vicinity of the Site and to collect additional information about the site geology and
hydrogeology. These data, when combined with the existing data sets, will guide the identification and
evaluation of a focused set of remedial alternatives, if warranted, for the Site.
The investigation activities described herein include:
• Installation of overburden groundwater monitoring wells for measurement of water levels. Note that
this work has already been completed.
• Collection of groundwater samples from existing and newly installed monitoring wells for laboratory
analysis.
It should be noted that Tyco proactively completed the installation of the overburden groundwater
monitoring wells associated with this work plan in November and December 2020. These wells were
installed during the drilling mobilization to install the shallow bedrock wells proposed in the May 2020
Near-Term Bedrock Groundwater Evaluation Work Plan, which WDNR has not provided comments on to
date. Applicable observations, soil boring logs, well construction logs, and well development logs will be
reported, along with the results of the groundwater sampling event proposed in this work plan, in an
investigation progress report or Site Investigation Report (see Section 7 for additional details related to
reporting). This report is anticipated to be submitted to WDNR in August 2021.
arcadis.com
1
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
2 SITE BACKGROUND
A description of the Site, regional and site-specific geology and hydrogeology, and previously completed
investigation activities is provided in this section.
arcadis.com
2
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
wells/piezometers and the proposed new monitoring wells, and collection of groundwater elevation and
pressure transducer data from select monitoring wells. As mentioned in Section 1, the groundwater
investigation presented in this work plan builds on the May 2020 Near-Term Bedrock Groundwater
Evaluation Work Plan focused on shallow bedrock monitoring wells.
The second and third documents, the Interim Site Investigation Report (Interim SIR; Arcadis 2020d) and
the Conceptual Site Model (CSM; Arcadis 2020e), were submitted to WDNR on June 15, 2020 and
July 15, 2020, respectively. The Interim SIR describes the completed investigations that evaluated the
nature and extent of PFAS in groundwater, soil, and surface water at the Site. The CSM, which was
recommended to be reviewed together with the Interim SIR, includes a discussion of the sources,
transport and exposure pathways, and receptors associated with PFAS at the Site. As of the writing of
this work plan, Tyco has not received comments from WDNR on these documents.
Separate investigations associated with the Tyco Fire Technology Center (FTC) are on-going to evaluate
the distribution of PFAS in groundwater. These investigations include well installation and sampling
locations that may improve understanding of groundwater conditions upgradient of the Site. Data from the
applicable FTC investigation locations will be included, as needed, in an investigation progress report and
Site Investigation Report.
• Fill, present to depths of 5 to 10 feet below ground surface (ft bgs), generally comprising sandy soil,
with saw dust, bricks, and other debris.
• Alluvium, present beneath the fill to approximately 20 ft bgs, typically comprising fine to medium sand,
with localized areas of peat.
• Glacial lake sediments, present beneath the alluvium to approximately 35 ft bgs, primarily comprising
silt, but interbedded with sand and clay.
• Till, typically present 5 to 10 feet above the bedrock surface, comprising a poorly sorted mixture of
clay, silt, sand, and gravel.
arcadis.com
3
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
the lake deposits and bedrock. The depth to the bedrock surface beneath the Site ranges between
approximately 35 and 45 feet, sloping gently to the southeast.
Under natural conditions in the vicinity of the Site, groundwater flow in both the overburden and shallow
bedrock trends generally northeast toward the Menominee River. Within the manufacturing area of the
Site, groundwater flow is controlled by the barrier wall and ongoing groundwater extraction resulting in an
induced inward gradient.
The water table in the vicinity of the Site is typically less than 5 ft bgs, generally occurring within the
shallow fill materials. In the developed portions of the Site, inside the barrier wall, the majority of runoff
from the paved or building-covered surfaces is captured by a storm drainage system designed to limit
recharge within the barrier wall.
arcadis.com
4
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
3.2 Surveying
Newly installed wells were surveyed in January 2021. Surveyed elevations (ground surface, top of well
casing, etc.) are referenced to the North American Vertical Datum of 1988 (NAVD 88), and surveyed
horizontal coordinates are referenced to the State Plane North American Datum of 1983 (NAD 83) –
Wisconsin Central (4802) Zone. Locations have been surveyed to the nearest 0.01 foot (horizontal and
vertical).
arcadis.com
5
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
4 GROUNDWATER
The scope of the proposed groundwater investigation includes 1) installation of monitoring wells in the
surficial aquifer (November/December 2020), and 2) one round of groundwater sampling and water level
gauging of existing and newly installed monitoring wells and piezometers. The groundwater investigation
will be performed as described in this section and the procedures provided in the Draft QAPP (Arcadis
2020b).
The overall objective of the groundwater investigation is to complete delineation of overburden
groundwater containing PFAS. The specific goal is to delineate the extent of PFAS in overburden
groundwater at concentrations exceeding the Wisconsin Department of Health Services (WDHS)
recommended groundwater quality standards, which were provided to the WDNR in November 2020
(Cycle 11).
arcadis.com
6
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
well development continued until up to 10 well volumes had been purged or until the parameters had
stabilized.
• Each of the three new overburden monitoring wells installed as part of this work plan.
• Each of four new shallow bedrock monitoring wells installed as proposed in the Near-Term Bedrock
Groundwater Evaluation Work Plan.
• Two existing shallow bedrock monitoring wells located upgradient of the Site on the FTC (PZ-01D
and PZ-04D).
The complete list of proposed monitoring locations is provided in Table 1. Note that monitoring wells
MW049S and MW049M have been included as contingent monitoring locations if MW022S and MW022M
are inaccessible due to high water conditions.
Pressure transducers are present in several existing wells as part of the monitoring program associated
with the USEPA RCRA project. These pressure transducers will be removed from the wells prior to
sampling. Each well in the monitoring event will be gauged using an electronic water level meter. Wells
will also be inspected and redeveloped as needed. Groundwater sampling will be conducted after a
minimum of 2 weeks following redevelopment, if required.
Low-flow sampling procedures will be used for groundwater sampling, using a peristaltic pump and
dedicated down-well disposable tubing. Analytical samples will be collected after groundwater parameters
that are measured with a field probe, including dissolved oxygen, pH, specific conductivity, and oxidation-
reduction potential, are shown to have stabilized at each well. All monitoring wells will be gauged for
depth to the top of water and depth to the bottom of the well.
Samples will be collected for PFAS analysis following the sampling procedures described in the Draft
QAPP (Arcadis 2020b) and the quality assurance/quality control (QA/QC) process described in
Section 6.
arcadis.com
7
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
5 OTHER MEDIA
5.1 Soil
As described in the CSM (Arcadis 2020e), existing soil concentrations are below the WDNR industrial
direct contact residual contaminant level (RCL). It should be noted any potential impacts to groundwater
resulting from soil leaching that occur within the barrier wall will be extracted and treated by the existing
groundwater collection and treatment system 1. Soil concentrations are sufficiently delineated at the Site,
and no additional soil samples will be collected for the site investigation.
5.3 Stormwater
As described in the CSM (Arcadis 2020e), precautions have been taken to prevent PFAS-containing
materials from discharging into the stormwater system. In Building 18 (Figure 2), an internal trench drain
is pumped out, as needed, and is not connected to the stormwater system. Tyco has installed gate valves
at the location of weirs in the sheet pile barrier wall that may be closed to prevent unwanted discharge of
surface water runoff from the site. In addition, Tyco is in the process of planning and implementing
substantial modifications to the stormwater management at the Site, which eliminates underground
conveyance of stormwater, in accordance with the recently issued WPDES permit.
Publicly available surface water sampling data in the Menominee River indicate PFOS and PFOA
concentrations below WDNR surface water quality guidelines, indicating that even if PFAS were present
in stormwater, it is not affecting surface water quality. Stormwater is sufficiently characterized for the site
investigation; therefore, no stormwater samples will be collected for the site investigation.
5.4 Air
As described in the Aerial Deposition Evaluation Report (Arcadis 2020f), there are no outdoor releases of
aqueous film-forming foam at the Site. Aerial transport of PFAS is not believed to have historically
occurred within the Site as no outdoor aqueous film-forming foam testing or firefighter training was
conducted at the Site (Arcadis 2020f).
As such, no air samples will be collected for analysis of PFAS.
1The existing groundwater extraction and treatment system will be upgraded by January 1, 2023 to
comply with the recently issued WPDES permit.
arcadis.com
8
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
5.5 Sediment
As described in the CSM (Arcadis 2020e), the low mass loading of PFAS to surface water and the 2012
and 2013 dredging adjacent to the Site suggest a low possibility for PFAS to be present in sediment at
levels of concern. Therefore, no sediment investigation activities are planned based on previous
investigations related to arsenic at the Site.
arcadis.com
9
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
Matrix Spike/
Matrix Spike Field Duplicate
Matrix Parameter Laboratory Method
Duplicate Frequency
Frequency
arcadis.com
10
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
7 REPORTING
Groundwater sample analytical results will be submitted to the WDNR per Chapter Natural Resources
(NR) 716.14; Wisconsin Administrative Code after completion of the sampling event. Field investigation
information will be communicated to WDNR in a future Site Investigation Report that meets the
requirements detailed in NR716. Note that an investigation progress report may proceed the submission
of the Site Investigation Report if, based on an evaluation of the data, additional investigation is deemed
necessary. The results of the Near-Term Bedrock Groundwater Evaluation Work Plan will also be
provided within an investigation progress report (if this report is needed) and the Site Investigation
Report.
arcadis.com
11
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
8 ANTICIPATED SCHEDULE
A review fee per NR 749 was submitted in September 2020 for this work plan. As previously mentioned,
the original work plan was withdrawn in November 2020, prior to WDNR review. Tyco has routine
conversations with the WDNR and estimates the following schedule based on work already completed
and planned future activities.
• Field Activities:
o November/December 2020: Installation of select monitoring wells and development.
Note: this work has been completed.
o April 2021: Groundwater monitoring of identified offsite monitoring wells and piezometers and
select onsite monitoring wells.
• Reporting:
o April/May 2021: Groundwater sample analytical results submittal per NR 716.14.
o August 2021: Depending on the results of the investigation, an investigation progress report, or a
NR 716 Site Investigation Report, whichever is applicable, will be submitted to WDNR. This report
will be submitted after completion of all field activities proposed in this work plan and the Near-
Term Bedrock Groundwater Investigation Work Plan. This report will provide a summary of the
data collected, an evaluation of data, contour and cross-section figures, and a discussion of
remaining data gaps, as applicable.
In the event the schedule is affected by weather, access, or other factors, WDNR will be provided with an
updated schedule.
arcadis.com
12
SITE INVESTIGATION WORK PLAN - STANTON STREET FACILITY
9 REFERENCES
Arcadis. 2018a. Revised Site Investigation Work Plan, Tyco Fire Technology Center Site, 2700 Industrial
Parkway, Marinette, Wisconsin, BRRTS No. 02-38-580694. April 20.
Arcadis. 2018b. Summary of Groundwater Sampling, Ansul Inc., Stanton Street Facility, Marinette,
Wisconsin, EPA ID: WID006125215. June 21.
Arcadis. 2020a. Summary of Soil and Groundwater Sampling, Tyco Stanton Street Facility, Marinette,
Wisconsin, BRRTS No. 02-38-581955. February 4.
Arcadis. 2020b. Draft Quality Assurance Project Plan, Tyco Per- and Polyfluoroalkyl Substances (PFAS)
Site Investigation and Private Well Sampling Activities, Marinette, Wisconsin. April 15.
Arcadis. 2020c. Near-Term Bedrock Groundwater Evaluation Work Plan, Tyco Stanton Street Facility,
1 Stanton Street, Marinette, Wisconsin, BRRTS No. 02-38-581955. May 1.
Arcadis. 2020d. Interim Site Investigation Report, Tyco Stanton Street Facility, Marinette, Wisconsin,
BRRTS No. 02-38-581955. June 15.
Arcadis. 2020e. Conceptual Site Model, Tyco Stanton Street Facility, Marinette, Wisconsin, BRRTS
No. 02-38-581955. July 15.
Arcadis. 2020f. Aerial Deposition Evaluation Report, Tyco Fire Products, Stanton Street Facility,
Marinette, Wisconsin, BRRTS No. 02-38-581955. July 16.
Arcadis. 2020g. Supplemental Site Investigation Work Plan, Tyco Fire Products, Fire Technology Center,
Marinette, Wisconsin, BRRTS No. 02-38-580694. August 17.
WDNR. 2020. Letter from David Neste of WDNR to Jeff Danko of Johnson Controls, Inc. and Scott Wahl
of Tyco Fire Products LP Regarding Review and Response to JCI and Tyco Submittal of Draft
Investigation Report of the Southern Area Groundwater Evaluation Efforts. BRRTS No. 02-38-
580694. May 27.
arcadis.com
13
TABLES
1
Table 1
Proposed Groundwater Monitoring Locations
Site Investigation Work Plan
Tyco Stanton Street Facility
Marinette, Wisconsin
Depth to Bottom of
Depth to Top Top of Casing Top of Screen General
Bottom of Screen
Well ID Area of Screen Elevation Elevation Description / Site
Screen Elevation
(feet bgs) (feet) (feet amsl) Setting
(feet bgs) (feet amsl)
MW003D Stanton Street 45 50 587.29 542.29 537.29 On-site, bedrock
MW003M Stanton Street 30 35 587.24 557.24 552.24 On-site, overburden
MW003S Stanton Street 10 20 586.40 576.40 566.40 On-site, overburden
MW008M Stanton Street 25 30 583.12 558.12 553.12 On-site, overburden
MW013D Stanton Street 45 50 588.69 543.69 538.69 On-site, bedrock
MW013M Stanton Street 30 33 587.91 557.91 555.30 On-site, overburden
MW013S Stanton Street 5 15 588.21 583.21 573.21 On-site, overburden
MW021M Stanton Street 30 35 586.93 556.93 551.93 On-site, overburden
MW021S-R Stanton Street 6 16 586.17 580.17 570.17 On-site, overburden
MW022M Stanton Street 30 35 584.34 554.34 549.34 On-site, overburden
MW022S Stanton Street 10 20 584.30 574.30 564.30 On-site, overburden
MW032S Stanton Street 7 17 588.33 581.33 571.33 On-site, overburden
MW040D Stanton Street 38 43 582.67 544.67 539.67 On-site, bedrock
MW040M-R Stanton Street 20 25 582.42 562.42 557.42 On-site, overburden
MW041S Stanton Street 5 15 582.93 577.93 567.93 On-site, overburden
MW044S-R Stanton Street 5 15 583.96 578.96 568.96 On-site, overburden
MW049M* Stanton Street 10 20 584.37 574.37 564.37 On-site, overburden
MW049S* Stanton Street 30 35 584.01 554.01 549.01 On-site, overburden
MW054S Stanton Street 10 20 587.66 577.66 567.66 On-site, overburden
MW100D Stanton Street 52 57 584.11 532.11 527.11 On-site, bedrock
MW102D Stanton Street 50 55 588.49 538.73 533.81 On-site, bedrock
MW102M Stanton Street 28 33 588.43 560.70 555.49 On-site, overburden
MW102S Stanton Street 8 17 588.71 581.00 571.31 On-site, overburden
MW104S Stanton Street 8 18 589.14 581.14 571.14 On-site, overburden
MW108D Stanton Street 48 53 586.29 538.29 533.29 On-site, bedrock
MW108S Stanton Street 8 18 586.51 578.51 568.51 On-site, overburden
MW109D Stanton Street 48 53 584.59 536.28 531.28 On-site, bedrock
MW125D-60 Stanton Street 50 60 596.03 546.03 536.03 Off-site, bedrock
MW125M-35 Stanton Street 30 35 596.26 566.26 561.26 Off-site, overburden
MW125S-20 Stanton Street 10 20 596.16 586.16 576.16 Off-site overburden
MW126D-40 Stanton Street 30 40 597.79 567.79 557.79 Off-site, bedrock
MW126S-20 Stanton Street 10 20 598.06 588.06 578.06 Off-site overburden
MW127D-85 Stanton Street 75 85 595.83 520.83 510.83 Off-site bedrock
PZ-01D FTC 64 69 606.23 542.73 537.73 Bedrock, FTC
PZ-04D FTC 69 74 607.86 539.36 534.36 Bedrock, FTC
PZ-28-14 Stanton Street, FTC 9 14 594.76 585.76 580.76 Off-site, overburden
PZ-28-54 Stanton Street, FTC 49 54 594.81 545.81 540.81 Off-site, overburden
PZ-28-75 Stanton Street, FTC 65 75 594.29 529.29 519.29 Off-site, bedrock
Notes:
Bold indicates monitoring well is outside the containment wall
Vertical Datum: North American Vertical Datum (NAVD) 1988
amsl = above mean sea level
bgs = below ground surface
MW = monitoring well
PZ = piezometer
*Contingent wells if MW022S and MW022M are not accessible.
Page 1 of 1
FIGURES
1
SITE LOCATION
WISCONSIN
City: Minneapolis/Citrix Div/Group: IMDVC Created By: Last Saved By: MSMiller
0 2,000 4,000
T:\_ENV\TYCO\MXD\01282021\SiteLocation.mxd 1/28/2021 12:20:22 PM
Feet
SITE LOCATION
TYCO Marinette, WI
FIGURE
1
NOTES:
1. TOPOGRAPHIC MAP SOURCE: COPYRIGHT:© 2013 NATIONAL GEOGRAPHIC
SOCIETY, I-CUBED, ACCESSED JANUARY 2021.
LEGEND:
SLURRY WALL
Me
no
NOTES:
m in
ee
1. ROAD DATA SOURCE: OPEN STREET MAP, ACCESSED FALL 2017.
Riv
2. SERVICE LAYER CREDITS: SOURCE: ESRI, MAXAR, GEOEYE,
e
EARTHSTAR GEOGRAPHICS, CNES/AIRBUS DS, USDA, USGS,
GROUNDWATER r AEROGRID, IGN, AND THE GIS USER COMMUNITY.
TREATMENT BLDG 14
BLDG 41
BLDG 42
BLDG COAL
71 DOCK
AREA
BUILDING 36
BLDG 43
BLDG 40 TURNING
BASE
AREA
BUILDING 29
BLDG
69
FORMER
LIP
SALT
ET S
VAULT
E
STR
IGTH
ER E
BUILDING 59
WETLANDS
M
FOR
AREA
City: Minneapolis/Citrix Div/Group: IMDVC Created By: Last Saved By: MSMiller
0 275 550
SITE LAYOUT
FIGURE
2
Me 4th
no
Av LEGEND:
en
m in ue
ee Wells
Avenu
Riv e
!
P EXTRACTION WELL OR TEST WELL
e r @
A MONITORING WELL - SHALLOW OR PEAT
GROUNDWATER MONITORING WELL - INTERMEDIATE
TREATMENT
MW045M @
A
e
nu
BUILDING MW041S
MW003M MW045S
MONITORING WELL - DEEP (BEDROCK)
ve
MW041M @
A
lA
MW121S
MW008M
l MW003D MW041D
Ha
MW117M
C
B PIEZOMETER
MW117D MW118D
MW122S
MW118M APPROXIMATE SITE PROPERTY BOUNDARY
MW003S MW118S
Eggne MW032M SHEET PILE WALL
r Street MW107M
MW032S
@
A
@
@ MW107D SLURRY WALL
@A
Ri
@ A
A MW031S
@
A A
ve
@ &
MW106S A MW108M MW031M
rs
MW106D @MW-067S
!
A
P @
A
@
A A
&
id
MW108D EW-13
@
A
@
A
@
A
e
MW106M
et
BT-02 !
P @A
A
Av
@ MW115P
tre
MW123S
en
EW-7
S MW009M MW117S @
A MW115S
n
ue
an
MW124S MW020M
TW-1
Vi
MW108S
M @
A MW009S
ne
A MW030S MW116P
t d
MW105M A
re
e in
tre
@ MW029M
et
g MW040M A
@
@ MW105S
A MW116S
MW-068S
S to @
A MW029S
n
EW-14
sin
EW-6 MW044S
St MW007S
PA@
A
@
on
MW030M
et
re MW105D EW-5 !
P MW044M EW-4 !
et
isc
MW103S
Golden C
MW042S
re
MW007M
o urt MW120S
St
W MW103M MW042D MW114S EW-3 @ A
A
St
& !
P
MW042M MW120M
y
NOTES:
ep
TW-2 @
A
El
MW043S MW114M
@
A
he
MW034S @
A
ee Stre et
MW104S MW011M MW052S EW-9 A
@
A
@
A @
AP @
! A 1. ROAD DATA SOURCE: OPEN STREET MAP, ACCESSED FALL 2017.
r
on
@
A @
A
St MW104M MW002M-R MW034M !
P
MW011S MW053S MW002S-R
@
A @
A 2. SERVICE LAYER CREDITS: SOURCE: ESRI, MAXAR, GEOEYE,
n @ AA
@ MW109D
io MW002S A @
is MW054S MW109M EARTHSTAR GEOGRAPHICS, CNES/AIRBUS DS, USDA, USGS,
iv @ @
A
A A @
A @ P
A @
A AEROGRID, IGN, AND THE GIS USER COMMUNITY.
D
MW059M EW-10 MW109S !
@@A
A @ MW035M !
P
@
A @
A
C
B
MW059S
MW062S MW002M @
A BT-01 @
A !
P
@
A
@
A 3. WELLS PZ2875, MW127D85, MW125 CLUSTER, AND MW126 PAIR
MW012S MW035S @
A
@
A @
A WERE INSTALLED IN NOVEMBER/DECEMBER 2020.
PZ-27-12 MW126S-20 MW062M
MW046M MW046S !
P
@
A
ue MW126D-40 A
Newberry Aven
&
& MW113S @
MW046D
A
@
A @
A
A
@ MW047S
EW-11 @
@
A
MW063M MW063S MW113M MW047M @
A A
MW013S MW102D MW001M MW036M MW047D @!
A
@
A P @
A
@
MW102S MW001S
MW036S MW100D
@A
A @
A
@
A
Le wis Street MW033M-R
MW037S MW100S MW048S @
A
@
A!
P A !
P
@
A
@
MW013M
A
@
A MW102M
MW037M MW100M @
MW033S MW048M @
A
A
Grant Stree t
EW-1 MW019S
et
MW049M
St
MW064M MW050S
MW049S @
A
@
A
ok
t
MW050M
e
MW064D MW022M
Wells Stree t
Co
re
eet
MW066S MW101S
r Str
St
@
@
A
A
Wate MW066M MW021M
Sherman Street n
Pr to
M
an
es er
MW021S-R
et
MW064S EW-8
co ry MW061S
St
re
MW022S
tt m EW-2
St
St an M MW060S
re St ai
w
MW061M
Pierce Avenue
MW038S
e n
llo
t re
D:\Tyco_Stanton\2021-01\Figure 3 Existing Monitoring Wells and Piezometers.mxd 1/29/2021 1:17:14 PM
MW004M
et St
fe
re MW060M MW039S
d
e
Thomas Stree t
MW004S
t
Od
MW039M
Oakes Street
Terr MW038M
ac e Av
enu
e
MW125D-60 &
Church Stree t
& MW125S-20
& A
A
MW125M-35
Colfa x Street
Carney Avenue
City: Minneapolis/Citrix Div/Group: IMDVC Created By: Last Saved By: MSMiller
Carn
reet
ey B
o ul ev
ard
t
8th S
reet
et
reet
tre
St
0 300 600
9th S
7th
t
6th S
Shore Drive
reet
Eliza
beth MARINETTE, WISCONSIN
Aven
t
t
PZ2875
ue
5th S
e
C
B
C
B
PZ-28-14 PZ-28-54 MW127D-85
Logan Avenue A
&
TYCO Stanton St, Marinette, WI
in
Miller Street M
ot
AND PIEZOMETERS
tS
et
tre
Lincol n Stre
et
Po
Mary Street in FIGURE
3
t St
re
et
Me
no
m in LEGEND:
ee
5th Avenue
Riv
ge
e
MONITORING WELL OR WELL CLUSTER
id
4th
@
A
r
Br
Av
en
te
u e
a
st
C
B PIEZOMETER
ert
In
SLURRY WALL
MW003M MW003D
@
A
@
A
MW003S MW041S
r ee
t @
A
St
n
an
M
MW040D MW008M
@
A MW108D
@
A
@
A
t
ee
MW108S NOTES:
S tr
MW040M-R @
A
Ely
MW049S @
@ WERE INSTALLED IN NOVEMBER/DECEMBER 2020.
A
A
ok
t
Co
re e
MW022M
St
@
A
n
to
Wa te MW022S
Pr M r Str e
er e
et
es r t
re
co ym
St
t tS an
w
t re St
lo
et re
el
et
df
Od
Tho ma s Stre et
City: Minneapolis/Citrix Div/Group: IMDVC Created By: Last Saved By: MSMiller
Main
Church Stre et
S tre
et
MW125D-60 & Terr
ac
Colfax Street
AA& MW125S-20 e Av
e nu
e
MW125M-35
t e
S tr e 0 300 600
et
et
S tr e
8th
S tr e
9th
6th
Carn
et
ey B GRAPHIC SCALE IN FEET
S tr e
o u le
v ard
7th
et
et
S tre
Shore Dri ve
S tr e
TYCO STANTON STREET FACILITY
10 th
4th
MARINETTE, WISCONSIN
et
et
S tre
S tre
et
Garfield Ave nue
S tr e
in
3rd
Pe rn
Eliza
TYCO Stanton St, Marinette, WI
5th
b eth
PROPOSED GROUNDWATER
Av e
nu e
PZ-28-14
C
B
C
B
C
B
PZ-28-54 MW127D-85 MONITORING LOCATIONS
Log an Ave nue PZ-28-75 A
&
FIGURE
4
Miller Street M
ot
tS
t re
et
Arcadis U.S., Inc.
126 North Jefferson Street
Suite 400
Milwaukee, Wisconsin 53202
Tel 414 276 7742
Fax 414 276 7603
www.arcadis.com