Quiz Submissions - Quiz 2.3

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

9/4/2020 : Quiz Submissions - Quiz 2.

3 - Non-Credit 2019-2020 - Principles Constr Document (CNST-002-O4A) - SAIT

Quiz Submissions - Quiz 2.3


Brandon Gemme (username: 000850759)

Attempt 1
Written: Jun 15, 2020 9:30 PM - Jun 15, 2020 9:32 PM
Submission View

Your test has been submitted successfully.

Question 1 1 / 1 point

A budget is how much money is available to spend.

A) True
B) False

Question 2 0 / 1 point

Describe the difference between a project budget and a construction budget

Project budget is the total budget for a project and includes construction budget,
professional fees, cost of land, rights of way, furnishings, equipment, etc. Construction
budget includes only the cost of construction.

This question has not been graded.

The correct answer is not displayed for Long Answer type questions.

Hide Feedback

A project budget includes total expenditures including the construction budget,


professional fees, land costs, rights of way, etc. A construction budget includes the
costs for construction including contingencies. (M2, L3: Definitions)

Question 3 1 / 1 point

1. List the four principal methods used for estimating project costs.

https://learn.sait.ca/d2l/lms/quizzing/user/quiz_submissions_attempt.d2l?isprv=&qi=887616&ai=6704362&isInPopup=0&cfql=0&ou=383786 1/2
9/4/2020 : Quiz Submissions - Quiz 2.3 - Non-Credit 2019-2020 - Principles Constr Document (CNST-002-O4A) - SAIT

___Order of Magnitude Estimates___ (25 %) ___Square Foot/Metre and Cubic


Foot/Metre Estimates___ (25 %) ___Systems Estimates___ (25 %) ___Unit Price
Estimates___ (25 %)

Attempt Score:2 / 3 - C+
Overall Grade (highest attempt):2 / 3 - C+