Conbextra P
Conbextra P
Conbextra P
Uses Specification
For pumped or free flow grouting, it can be used in a wide Performance specification
range of applications:
All grouting, where shown on the drawing, must be carried
! As a heavy duty support beneath machine base plates out with a prepackaged cement based product which is
iron-free and chloride-free. It shall be mixed with clean water
! Stanchion bases
to the required consistency. The plastic grout must not bleed
! Ideal for horizontal ducts or segregate.
If these are to be removed after the grout has hardened, they The selected water content should be accurately measured
should be treated with a thin layer of grease. into the mixer. The total contents of the Conbextra P bag should
be slowly added and continuous mixing should take place for
Formwork
5 minutes. This will ensure that the grout has a smooth even
The formwork should be constructed to be leakproof as consistency.
Conbextra P is free flowing grout. This can be achieved by
Placing
using foam rubber strip, or mastic sealant, beneath the
constructed formwork and between joints. Place the grout within 20 minutes of mixing to gain full benefit
of the expansion process.
In some cases it is practical to use a sacrificial semi-dry sand
and cement formwork. The formwork should include outlets Conbextra P can be placed in thicknesses of up to 40 mm in a
for pre-soaking. single pour when used as an underplate grout.
When using Conbextra P as an underplate grout, the gap width Any bolt pockets must be grouted prior to grouting between
and fluid head should be designed to ensure that the grout will the substrate and the base plate.
flow through the gap as a continuous front. The gap thickness
Continuous grout flow is essential. Sufficient grout must be
should be in the range of 5 to 40mm.
prepared before starting. The time taken to pour a batch must
Unrestrained surface area be regulated to ensure adequate timing for the preparation of
the next one.
This must be kept to a minimum. Generally the gap width
between the perimeter formwork and the plate edge should Pouring should be from one side of the void to eliminate any
not exceed 75 mm on the pouring side and 25 mm on the air or pre-soaking water becoming trapped under the
opposite side. It is advisable, where practical, to have no gap baseplate. It is advisable to pour the grout across the shortest
at the flank sides. distance of travel. The grout head must be maintained at all
times so that a continuous grout front is achieved.
Conbextra P - Page 2 of 4
Conbetra P*
On completion of the grouting operation, exposed areas should It is suggested that, for temperatures above 35°C, the following
be thoroughly cured. This should be done by the use of guidelines are adopted as good working practice:
Concure*† curing membrane or continuous application of water
(i) Store unmixed material in a cool (preferably temperature
and/or wet hessian.
controlled) environment, avoiding exposure to direct
Cleaning sunlight.
Conbextra P should be removed from tools and equipment (ii) Keep equipment cool, arranging shade protection if
with clean water immediately after use. Cured material can be necessary. It is especially important to keep cool those
removed mechanically, or with Fosroc Acid Etch*†. surfaces of the equipment which will come into direct
contact with the material itself.
Sampling procedure
(iii) Try to eliminate application during the hottest times of the
All sampling procedures for Conbextra P are to be conducted
day and in direct sunlight.
within the confines of a temperature controlled laboratory. The
reactive agents within Conbextra P do not permit site sampling (iv) Make sufficient material, plant and labour available to ensure
and transport. The procedure for sampling is to be as follows: that application is a continuous process.
1) A full and unopened bag of Conbextra P to be selected from (v) Water (below 20°C) should be used for mixing the grout
the batch allocated for site use and despatched to the prior to placement.
testing laboratory.
Limitations
2) The Conbextra P shall be mixed in the laboratory following
the instructions listed on the product data sheet. - Grouts should not be placed in any unrestrained situation,
i.e. base plate plinths, etc. Failure to comply may lead to
3) All sampling shall be conducted using 100mm cube
crack development in the grout.
moulds, the use of 150mm cube moulds being prohibited.
4) When mixed, the Conbextra P shall be poured into release Technical support
agent treated 100mm cube moulds in two lifts of 50mm
Fosroc offers a comprehensive technical support service to
each with a 60 second interval between pours. The
specifiers, end users and contractors. It is also able to offer
Conbextra P shall not be tamped but gentle tapping of the
on-site technical assistance, an AutoCAD facility and dedicated
cube mould is permitted to promote the release of air.
specification assistance in locations all over the world.
5) Fill three 100mm cube moulds with the Conbextra P for
each curing time interval specified. Mould filling should be Estimating
completed within 20 minutes of the end of the mixing cycle.
Supply
The filled moulds should be stacked three high on top of
Conbextra P : 25 kg bags
each other to provide conditions of restraint. The top mould
should be restrained either with a weighted metal plate or Yield
an empty cube mould. Conbextra P : 17.5 litres/ 25 kg bag (approx.)
6) The cubes should be stored at a 20°C+ 2°C temperature Allowance should be made for wastage when estimating
for 24 hours in the laboratory. After 24 hours the cubes are quantities required.
to be demoulded and placed in a water curing tank
maintained at a 20°C+ 2°C temperature. The cubes are Storage
then to be cured in accordance with BS1881.
Conbextra P has a shelf life of 12 months if kept in a dry store
7) Cubes are to be crushed in calibrated compression testing in sealed bags. If stored in high temperature and high humidity
apparatus with a rate of loading not exceeding 180kN per locations the shelf life may be reduced.
minute. Types of cube fracture are to be recorded. Three
cubes are to be crushed for each curing time interval
specified. Results are to be calculated and issued as an
average.
Conbextra P - Page 3 of 4
Conbextra P*
! fluid micro-concretes
Important note
Fosroc products are guaranteed against defective materials and manufacture and are sold subject to its standard
Conditions for the Supply of Goods and Service. All Fosroc datasheets are updated on a regular basis. It is the user’s
responsibility to obtain the recent version. Refer to www.fosroc.com.
Head Office
Al Gurg Fosroc telephone: (+9714) 2039699 fax: (+9714) 2859649 email: agf@fosroc.com
LLC Regional offices
Abu Dhabi, Al Gurg Fosroc telephone: 673 1779 fax: 673 1449 email: abudhabi@fosroc.com
Post Box 657, Dubai Bahrain, YBA Kanoo telephone: 17735454 fax: 17732828 email: bahrain@fosroc.com
United Arab Emirates Kuwait, Boodai telephone: 4817618 fax: 4832124 email: kuwait@fosroc.com
Oman, Al Amana telephone: 24815080 fax: 24817554 email: oman@fosroc.com
www.fosroc.com
Qatar, Tadmur telephone: 4500607 fax: 4500543 email: qatar@fosroc.com
UAE/0223/06/F