Fire Strategy
Fire Strategy
Fire Strategy
PADDINGTON SQUARE LU
STATION BAKERLOO LINE
STATION UPGRADE
Detailed Design Fire Strategy
CONFIDENTIAL
London Underground - Sellar
WSP
WSP House
70 Chancery Lane
London
WC2A 1AF
Phone: +44 20 7314 5000
Fax: +44 20 7314 5111
WSP.com
CONFIDENTIAL
QUALITY CONTROL
2021.01.29
Signature 11:16:10
EXECUTIVE SUMMARY 1
ACRONYMS 4
PROJECT DESCRIPTION 5
SCOPE 7
INTRODUCTION 11
GENERAL 11
BACKGROUND 11
STATION DESCRIPTION 13
GENERAL 13
STATION OPERATOR 15
OBJECTIVES 19
STATION EVACUATION 22
DOORS 37
FINAL EXITS 37
EMERGENCY LIGHTING 38
ESCAPE SIGNAGE 38
BACK-UP POWER 38
COMMUNICATION SYSTEMS AND PROCEDURES 39
FIRE COMPARTMENTATION 40
FIRE STOPPING, FIRE DAMPERS AND CAVITY BARRIERS 41
MATERIALS OF CONSTRUCTION 44
LINING MATERIALS 45
GENERAL 47
GREY LINK 49
STAIR PRESSURISATION 49
MAGNETIC DOOR RELEASE 49
MATERIALS TO BE USED 50
SPRINKLER SYSTEM 51
GENERAL NOTE 51
DETAILS OF EQUIPMENT 52
GENERAL 61
MAINTENANCE PROCEDURES 61
STAFF DUTIES 61
STAFF TRAINING 61
APPENDICES 62
TABLES
Table 1 - Concessions and exemptions required by the proposed design 3
Table 2 – Three-hour boarder and alighters figures for 2041 + 35% 28
Table 3 - Evacuation loads Southbound AM and PM 31
Table 4 - Capacity of Protected Routes from the Platform (Station fire scenario) 33
Table 5: Fire Resistance Ratings 40
Table 6 – Rooms/areas and type of PFE required. 53
Table 7 – Sprinkler pipe losses calculations 103
Table 8 – Hydrant pipe losses calculations 104
Existing non-compliant
TfL LU S1082 A2 3.2.2.2 Concession TfL LU
hydrant coverage on
platforms
TfL S1080 A3 3.14.1.1
Non-compliant evacuation Concession TfL LU
times from incident and
non-incident platforms to
a place of relative safety
Acronym Description
TfL Transport for London
LU London Underground
PRM Persons with Restricted Mobility
SPSG Station Capacity Planning and Guidance
CDM Construction (Design & Management) Regulations: 2015
RRO Regulatory Reform (Fire Safety) Order 2005
SSRR Fire Precautions (Sub-surface Railway Stations) (England) Regulations: 2015
PPM Persons per meter per minute
ASD Aspirating Smoke Detection
CIE Fire Control and Indicating Equipment Panel
DCP Damper Control Panel
HVAC Heating Ventilation Air Conditioning
I/O Input / Output
MCP Manual Call Points
MIOU Multi Input/Output Unit
PA/VA Public Address / Voice Alarm
PCB Printed Circuit Board
PSU Board Supply Unit
Power
SCADA Supervisory Control and Data Acquisition
SOR Station Operations Room
UTS Underground Ticketing System
VFD Vacuum Fluorescent Display
The existing Bakerloo Line station is not compliant with current TfL London Underground Standards with
respects to fire safety. Currently, there is a single means of escape from the platform level, via an escalator
barrel which contains two escalators and a fixed stair. From here, a single narrow stair leads to Praed
Street, a passageway leads to the Lawn Ticket Hall, and a further passageway leads back to the NWR
Paddington Station.
The Paddington Square LU development will provide extension and refurbishment of the ticket hall, and
redesign/allocation of existing and new plant spaces. The existing stair egress from the Ticket Hall to Praed
Street will be removed, with the Ticket Hall entrance relocated to within a retail mall at one level below the
entrance to Paddington Network Rail Station from Arrivals Road (Ticket Hall level is Level B1 of the mall).
Provision of step free access; a secondary means of escape from platform level for ambulant and PRM
(complying with the requirements of TfL1080 A3), and improvement in emergency egress times, have been
prioritised as part of the station layout development.
Due to the proximity of the adjacent Mercure Hotel, a mains sewer, and the running tunnels for the
Bakerloo Line, it is not physically possible to provide a secondary means of escape from the Bakerloo Line
platforms which meets the minimum of 2 m width requirement in the TfL 1080 A3 3.14.4.3.3. Nor is it
possible to provide the required resting areas on alternate landings. Concessions from LU are required for
these.
The final exit for the principle means of escape in the case of fire, is into another demise, at shopping mall
level. This is an unconventional arrangement for a TfL LU station.
To ensure that this means of escape remains safe for escaping passengers, the lease agreement will
contain a number of provisions to protect the rights of TfL LU to confirm that their escape route between
Ticket Hall and street level remains safe throughout the lifetime of the building.
TfL LU staff shall have a right to patrol an area defined in the lease to ensure that the escape route
remains unobstructed and available at all times
The escape route is maintained to the standards required by TfL LU for their own escape routes
The escape route has provision of emergency lighting to the standard required by TfL LU
Maintenance of escalators, lighting and other life safety services along this escape route is to a schedule
as agreed with TfL LU.
The Mall Level B1 (into which the Ticket Hall evacuates, and which provides the secondary means of
escape from basement level) has a restricted fire load. This shall be in compliance with the proposed
additions to the LUL Minimum Requirements in the lease, as provided in Appendix J.
No additional fire load shall be added to the circulation area of the mall without prior agreement of TfL
LU Fire Engineers.
A DDN is provided to show that in the event of a retail mall unit fire, no smoke shall enter or compromise
the escape route from the station. This DDN (appended as Appendix J) describes the CFD modelling
results from two worst case retail fires.
The Fire Strategy for the Mall building reflects the above provisions.
With regards to the above, a section from the Lease Agreement (as supplied by LUL) is provided in
Appendix J.
Figure 2 - Isometric showing interphases with BLL Ticket Hall (on TfL Compliance Fire Plan)
The fire strategy addresses life safety of occupants within the station, and access facilities for the fire and
rescue services. In addition, some of the fire safety features, such as compartmentation, contribute towards
property protection and business continuity.
This report considers the occurrence of a single fire event only; multiple, simultaneous outbreaks of fire are
not considered. Simultaneous fire events in the two demises (station and mall) are not considered. The
strategy does not address a terrorist or multiple arson events.
The Paddington Square development is considered to be functionally independent and separate from the
Bakerloo Line Station, and has independent fire and rescue services access and fire safety systems.
Therefore, this fire strategy only considers the fire separation between the Bakerloo Line Station and the
Paddington Square development. The fire strategy for the Paddington Square development is not within the
scope of this report. However, the fire strategy for the development is considered where it provides the final
means of escape from the Bakerloo Line Ticket Hall to street level.
GENERAL
The Fire Safety Strategy is a necessary part of the design process purposed to demonstrate how works
done on the premises result in fire risks being retained as low as reasonably practicable (ALARP) and
compliant with fire-related legislation.
The strategy has been prepared to provide assistance to the design team in the fire safety design of the
project. It will also aid in gaining the approval for the station upgrade design from London Underground (the
station operator and infrastructure manager) and the London Fire Brigade.
To improve the worsening capacity issues at the Bakerloo line Ticket Hall of the Paddington station, an
enlarged Ticket Hall and improved access and egress routes are to be relocated within the new Paddington
Square development.
BACKGROUND
The current design proposal is derived from a Consented Scheme which had attained planning consent.
Both Crossrail and TfL have confirmed that the Bakerloo Link Tunnel cannot be considered a means of
escape from platform level.
Due to a lack of tunnel ventilation, and under advice from TfL, it is not preferable to consider immediate
automatic closure of all cross-passage doors at platform level during a fire scenario. There shall be local
door side detection and detection in the escalator barrel adit. Simultaneous detection at both shall close
only the doors with local detection of smoke or heat. Should smoke travel around the platforms to enter the
escalator barrel from the non-incident platform, then that side too shall close by local detection, thus
completing fire separation.
This means that the escalator barrel can be considered a place of relative safety on closure of the fire
doors on the fire affected platforms.
There is insufficient safe holding area off a platform of fire origin to accommodate all passengers who
would be required safe haven. Given this situation, while it is possible to improve station evacuation times,
it is not possible to meet the requirements of TfL S1080 A3 for evacuation from the incident platform in 4
minutes, and to a place of relative safety within 6 minutes. Improvement is made in so far as is possible, on
the understanding that a concession from the TfL S1080 A3 requirement will be needed.
At the request of TfL London Underground, considerable effort was made to ascertain whether an
additional fire separated means of escape could be designed, which would lead from the Ticket Hall directly
to the street, without passing through another demise, in full compliance with S1080 A3.
Four further options were considered; however, these were shown to be either prohibitively expensive to
the project, or unlikely to gain the planning consent as had been awarded to the current design proposal
(Paddington Square LUL Emergency Egress from Ticket Hall Options 0-4). The current design, which
involves escape from the Ticket Hall into the Paddington Square mall prior to accessing street level, is
unconventional, but does meet with known current legislation, and is considered to be the only remaining,
and best available design option. As it does not meet LU Fire Engineering requirements for compliance with
TfL S1080 A3, this escape route requires that a legal agreement be agreed between TfL and the building
owners/occupiers which allows that nothing will be placed within the mall which will negatively affect the
safety of persons egressing from the London Underground Ticket Hall.
GENERAL
Paddington London Underground station comprises of the Bakerloo line (Northbound and Southbound) and
the District & Circle line (Eastbound and Westbound). Access to the station (shown in Figure 2) is:
via Paddington Station “Lawn” (Ticket Hall B), from where the passengers can walk towards either line.
from Praed Street via Ticket Hall A, enabling direct access to the District & Circle Line platforms.
from Praed Street via Ticket Hall C enabling direct access to the Bakerloo line platforms
Current Bakerloo Line emergency egress from platform level is via an escalator barrel consisting of two 1.0
m wide escalators and a 1.2 m wide fixed stair. This barrel exits to the Ticket Hall, from where passengers
escape via a flight of stairs up to Praed Street. This escalator barrel is currently the single means of escape
from platform level. The exit passageways from the Ticket Hall to the Lawn Ticket Hall and back via the
Network Rail station are not designated means of escape.
In the proposed Paddington Square LU development, the existing stair egress from the Ticket Hall to Praed
Street is removed, with the Ticket Hall entrance relocated to within a shopping mall. However, the Bakerloo
line platforms will continue to be served by the existing escalator barrel. The passageway to the Lawn
Ticket Hall will remain, but the passageway to Paddington Network Rail Station will be removed.
The redesigned layout provides for a new firefighting shaft to be located behind the current escalator barrel.
In this new shaft, an additional / escape firefighting stair will be provided for the Bakerloo line platforms.
This new 1.5 m wide stair will also provide a second means of escape, from the Northbound and
Southbound platforms directly to a place of ultimate safety at street level. As it does not meet the TfL LU
S1080 A3 3.14.4.3.3 requirement for a 2 m minimum width on escape stairs, a concession from TfL is
To achieve the above objectives the proposed fire strategy and station design should meet the following:
a) Provide a means of escape in the event of a fire:
b) This shall consider a credible, accidental, single fire event anywhere in the station.
c) Provide adequate means of escape before the conditions become untenable (this includes provisions for
PRM evacuation).
d) Stairs and escalators will be used for means of escape from the platforms. Evacuation lift will be used for
the evacuation of PRM.
e) Provide a means of early fire detection to facilitate the early evacuation of people at risk:
f) Provide a means of raising an alarm.
g) Facilitate a process of a managed station evacuation.
h) Enable early firefighting intervention.
i) Limit the extent of fire spread within the station: fire spread is limited by fire separation and/or provision
of automatic fire suppression as appropriate, to protect the means of escape, but also to minimise
property damage and business interruption.
j) Limit the extent of smoke spread within the station: smoke spread is limited to the incident zone to
protect the means of escape and to minimise the property damage, business and operational
interruption.
k) Minimise the risk of fire spread to and from the retail mall
l) By identifying the premise boundary lines and providing fire separation and/or fire suppression
necessary to limit the risk of fire spread.
m) Provide facilities for the fire-fighting service:
n) By providing fire-fighting vehicles access and designated fire-fighting access routes within the station.
o) By providing water to facilitate fire-fighting operations.
GENERAL
The station evacuation, assessment is carried out in accordance with TfL Category 1 S1080 A3 The
application of fire safety engineering principles to TfL premises, which instructs that the following two fire
scenarios be considered in the safety design of stations:
Train on fire in station;
A fire within the station structure.
Refuge
A refuge point shall be provided within the protected lobbies associated with the evacuation lift, excepting
the final exit level. This clearly marked point shall be in a minimum of 1400 mm x 900 mm.
The refuge point shall be sited such that the flow of other passengers evacuating is not disrupted.
2041+35%
AM 3637 15261 18494 10256
3hr
PM 7490 18728 18494 10216
EVACUATION TIMES
As per the TfL S1080 A3, for a train fire scenario, the evacuation load (train and station occupants) shall be
cleared from the immediate incident platform within 4 minutes and reach a fire-protected route within 6
minutes.
For a fire within the station structure, the affected passenger load shall reach a fire-protected route within 6
minutes.
Passengers are assumed to be in a place of relative safety once they pass through the cross-passage door
from the incident platform to the new stair passageway. It is anticipated that the doors at the bottom of the
existing escalator barrel shall close on local detection, so that on closure, the existing escalator barrel may
be considered a place of relative safety in a station fire scenario.
Evacuation Loads
Table 3 below summarises the evacuation loads for the train on fire and station fire scenarios in the AM
and PM peaks, based on the passenger demand data with an uplift of 35%.
To assess the escape capacity of the cross-passages, escalator barrel and the new stair, the highest
evacuation load for each fire scenario has been used. (See Appendix E for the evacuation calculation
table).
The time taken for the last person to clear the platform and reach the cross-passage is 4.8 minutes, which
is not compliant with compliant with TfL S1080 A3 4.0-minute requirement but is an improvement on the
current evacuation time. A concession will be required.
Time to clear the non-incident platform to a place of relative safety is 7.6 minutes. This evacuation time is
not compliant with TfL S1080 A3, 6.0-minute requirement and will need a concession from TfL.
The time to clear the platform area to the escalator barrel in the current Station is circa 10.3 minutes in a
Train on fire scenario. The proposed design is a significant improvement on the existing design.
Holding capacity
passage to new 1 2.4 168 persons
stair
New Stair 1 1.5 84 ppm
Total capacity within protected routes over 6 minutes 672 persons
Table 4 - Capacity of Protected Routes from the Platform (Station fire scenario)
The platform clearance time is 17.5 minutes to a place of relative safety This does not comply with TfL
S1080 A3 requirements. A concession from the TfL S1080 requirement will be needed.
This time is a significant improvement on the existing situation in which there remains only evacuation by
train in a station fire scenario, after the escalator barrel is discounted
.
Direct travel distance is considered to be 2/3 of the actual travel distance and is used when the layout of
the room is unknown.
Actual travel distance is used where the layout of the room is indicated, and in corridors which are
considered free from obstruction. A change in layout from the earlier stage of design has provided that the
actual travel distance for the Plenum Chamber at concourse level is now 16.8m, as shown in Figure 7. The
travel distance is less than 20m and is therefore compliant.
In the unlikely event of a fire in the Plenum Chamber a degree of mitigation for smoke build up is provided
as a portion of the smoke emitted would be naturally vented. The Plenum Chamber roof is open to
atmosphere via the perforated risers in the steps in the above ground realm.
Travel distances within the station Back of House areas are shown in Appendix B.
DOORS
The door leaf of a doorway or exit should, where reasonably practicable, be hung to open in the direction of
escape. The door should always open in the direction of escape from rooms that have an occupant
capacity of more than 60. However, if there is a high fire risk with a potential for a rapid-fire growth, the
doors must open in the direction of escape regardless of the number of occupants.
Doors shall have the same fire rating as the wall in which they are installed, with an additional smoke rating
for all non-lift doors. (FD60s; FD120s)
Doors, including self-closing devices (excluding lift landing doors) protecting openings in refuges or
enclosures to lifts shall be FD60S (tested to BS 476-22) or E60Sa (to BS EN 13501-2).
Lift landing doors shall be FD60 (tested to BS 476-22) or E60 (to BS EN 13501-2 or BS EN 8158).
Doors shall have vision panels where doors on escape routes subdivide corridors or where doors swing
both ways. (BS9999:2017 15.6.5).
All fire doors are to be held open on an automatic release mechanism in accordance with BS EN 1155 or
BS 5839-3, and shall have the appropriate fire safety sign at eye level conforming to BS ISO 3864-1. Even
with doors closed people trying to escape will still be able to open doors and pass through. Due to the
piston effect issues in this station, the cross-passage door leading from platforms to the new protected
corridor and lift/stair should have two magnetic door holders per leaf (one top and one bottom).
FINAL EXITS
Final exits should be apparent to the persons who may need to use them and must remain free from
obstacles at all times. The exits should be sited such that they are clear of any risk from fire or smoke in a
basement (such as the outlets to basement smoke vents, or from openings to transformer chambers,
refuse chambers, boiler rooms, etc).
It is proposed that the escape route from the Ticket Hall shall be via another demise, which is not normal
practice. This route, while not ideal, has been shown to be the most practicable route from this space. To
ensure that this means of escape remains safe for escaping passengers, the lease agreement will contain
a number of provisions to protect the rights of TfL LU to confirm that their escape route between Ticket Hall
and street level remains safe throughout the lifetime of the building.
TfL LU staff shall have a right to patrol an area defined in the lease, between Ticket Hall and street level, to
ensure that the escape route remains unobstructed and available at all times
The escape route is maintained to the standards required by TfL LU for their own escape routes
The escape route has provision of emergency lighting to the standard required by TfL LU
Maintenance of escalators, lighting and other life safety services along this escape route is to a schedule
as agreed with TfL LU.
The Mall Level B1 (into which the Ticket Hall evacuates) has a restricted fire load, with only materials of
limited combustibility within proximity to the escape route.
No additional fire load shall be added to the circulation area of the mall without prior agreement of TfL
LU Fire Engineers.
EMERGENCY LIGHTING
Emergency lighting provides the following functions:
Emergency escape lighting provides illumination of escape routes and signs to assist the occupant in
evacuating the premises;
Emergency safety lighting provides lighting for moving about safely when the occupant do not need to
evacuate the premises immediately;
Standby lighting powered by an alternative power supply provides sufficient lighting to operate the
premises normally in the event of a total failure of the main power supply.
Suitable lighting shall be provided to ensure the safe movement of persons along escape routes to place of
relative or ultimate safety. Emergency escape lighting shall be provided in accordance with BS 5266-1, BS
EN 1838 and LU 1-066 standards.
ESCAPE SIGNAGE
Clearly visible and unambiguous signage is significant for speedy escape, especially in building where a
majority of the occupants might be unfamiliar with the building layout.
Escape signage is provided in accordance with BS 5499-1 on all escape routes and at all emergency exits.
Emergency Do Not Enter (EDNE) signs shall be provided in accordance with S1087. EDNE shall be
located at each of the exit(s) to warn passengers to not enter a station during an emergency evacuation.
The functionality of DNE and associated modification to the panel in the SOR shall be provided by the
Stage 5 installer.
BACK-UP POWER
The back-up power is in the form of an Off-Line Battery Inverter (OLBI), located at Basement level.
All lifts will be provided with dual power (A and B power supplies).
If one power supply fails, the system will switch to the alternative power supply. This is to ensure that the
station systems continue to operate in the event of a primary power supply failure, for life safety purposes.
The secondary supply will have sufficient capacity to keep the following in operation:
Escalators used for means of escape;
Smoke control and pressurisation relief dampers;
Normal lighting and other services within the firefighting shaft;
The fire service communications system;
The emergency voice communications system;
The PA/VA system;
Any powered ventilation or pressurisation system which operates in conjunction with the operational use
of the firefighting shaft;
FIRE COMPARTMENTATION
The architectural plans should be referred to for detailed compartmentation plan. The key
compartmentation principles are as follows:
All public areas are to be separated from non-public areas by fire resisting construction achieving 60
minutes fire resistance;
Back-of-house plant rooms are to be enclosed in a minimum of 60-minutes fire resisting construction;
Air pressurisation system plant rooms are to be enclosed in 120 minutes fire resisting construction
Firefighting shafts are to be enclosed in 120-minutes fire resisting construction. Internal walls may be 60-
minute construction
Transformer rooms are to be enclosed in 120 minutes fire resisting construction
All floors are assumed to be compartment floors, rated to 120 minutes.
Separation of the station from the adjoining mall demise shall be 120-minute fire rated construction.
Any room, if there are S1085 non-compliant materials inside, then 60-minute fire rating is required to
allow concession from S1085.
Table 5 provides the fire resistance rating in terms of load bearing capacity, integrity and insulation for fire
separating walls or floors when tested to the relevant parts of BS 476: E&I only if non-load bearing as noted
in TfL LU S1083 A2 paragraph 3.5.1.
Plant rooms excl. Transformer Rooms, PFR and LEER 60 minutes REI
Figure 10 - Extensive cavity measuring 34.8m in length at Upper Ticket Hall level.
MATERIALS OF CONSTRUCTION
Materials used within the station must comply with the following:
LU Standard 1-085 A3 Fire Safety Performance of Materials; and
The Fire Precautions (Sub-Surface Railway Stations) (England) Regulations 2009.
The Fire Precautions (Sub-surface Railway Stations) (England) Regulations 2009 states that “Materials
used in internal construction of premises
8-(1) Any material which is used in the construction of an internal wall or ceiling in any public area must be of
limited combustibility”.
LINING MATERIALS
Subsurface Regulations Requirements
The subsurface regulations require that materials applied to the surface of an internal wall or ceiling should:
“adequately resist the spread of flame over the surface; and
have if ignited either a rate of heat release or a rate of fire growth, which is reasonable in the
circumstances.”
A material can be considered compliant with the above if it meets the requirements as detailed in Table 3
of the SSRR.
GENERAL
This section gives a brief overview of the Fire Detection and Alarm system. For more details on the system,
please refer to the Fire Detection and Alarm Technical Specification, PBLSU-WSP-FRS-B071_Z-SPE-FE-
0002.
A category L1 detection and alarm system shall be provided in Back of House areas, with a Category L5+M
provided in public areas. This to be in accordance with BS 5839: Fire Detection and Alarm Systems for
Buildings Part 1: 2017.
In accordance with BS 5839, automatic fire detection is not provided in rooms 1.004 (Plenum chamber),
2.002 (Ventilation supply plenum) and 3.001 due to significant air flow within these voids.
The fire detection and alarm system will be an analogue addressable detection system incorporating
manual call points, multi-sensor detectors, beacons input/output devices, aspiration systems and damper
control systems.
The main fire control panel (MFCP) will be located in the lobby outside Consolidation Room 3.010 in the
Lower Ticket Hall Level. The MFCP will monitor and control all analogue addressable loops within the
protected areas. There will be two active loops on each system.
In addition to the above, the station will be provided with a voice alarm system to all areas in accordance
with BS 5839-8. An additional fire alarm panel will be located at entrance to the firefighting access shaft.
Manual call points are provided in all back-of-house areas and public areas including platform, basement
levels and ticket hall.
Public Areas: Automatic fire detection is not required in public areas, where a strict regime of materials
control is applied. However, multi-sensor detectors will be provided adjacent to cross passage fire doors
and shutter at main entrance, which are held open during normal operations. The doors/shutter will be
automatically released should both detectors be activated. This will prevent smoke from any train or
platform related incident spreading into the ticket hall and a fire from the ticket hall entering the mall area
(and vice versa) respectively. Cross passage doors shall also be operable by a local key switch and a
manual switch/panel in the Station Operation Room. All Passenger Help Points will be in accordance with
LU Standards and include manual alarm call points. The manual call points within the Ticket Hall area have
been kept to a minimum.
Ceiling voids over 800 mm in depth shall be provided with point detection. These devices shall be placed
such that they are maintainable from access hatches located directly beneath each device. Distribution of
these ceiling void devices is limited to the lower ticket hall level.
Non-public areas: All non-public areas are to be fitted with automatic multi-sensor detection of Type L1
coverage. This detection will be provided in service areas, offices, mechanical plant rooms (including
escalator machinery spaces), electrical plant rooms, and any other accessible non-public areas. Manual
call points will also be installed in these areas.
A summary of the detection provisions is outlined below:
• Multi-sensor detection is provided in all non-public areas of the station to an L1 category;
GREY LINK
The Station fire control panel and the Mall fire control panel will be linked such that a fire output signal from
the Station fire control panel is sent to the Mall fire control panel and vice versa. The grey link will inform
one demise of a fire in the other demise. Upon receiving any single stage alarm notification, the Mall
management would be aware of a potential evacuation from the Station enabling them to action any
management activities required to ensure that the escape routes from the TfL LU Station are unobstructed.
In the event of a first knock activation within the LUL demise, the specified Mall PRM lift will return to the
Concourse Level and its doors will open. This lift will now be out of service and cannot be used until the fire
alert is resolved. This will remove the potential for persons coming down into the flow of passengers
evacuating from the station. Mall staff, having been warned on the Mall fire panel of a first knock indication
in the LUL demise, shall clear persons waiting for the PRM lift at the Mall B1 Level.
In the event of a first detection in the Mall, the station will be informed enabling them to investigate whether
they should engage any proactive management protocols.
STAIR PRESSURISATION
The firefighting shaft is provided with a pressurisation system. This is designed in accordance BS 12101-
06, to Classification B.
A pressurisation override switch shall be provided in Lobby 1.002 at Concourse Level, which is considered
the appropriate location. An additional stair pressurisation override has been requested by TfL LU to be
located in the SOR. For further details, the Fire Detection and Alarm Technical Specification, PBLSU-WSP-
FRS-B071_Z-SPE-FE-0002, should be referred to.
The back of house escape-only stair from basement level is not pressurised.
MATERIALS TO BE USED
The fire detection system includes:
4 Loop Fire Detection Control Panels
Cables FT 120
Cable containment, junction boxes, fixings and labels
Addressable Multi Detectors
Addressable Flashing Beacons
Addressable Sounders Bases
Standard Device Bases
Addressable Manual Call Points
Damper Control Panel
Aspiration Detection
Note: Layouts shown are indicative only and need to be finally designed by a LPS 1040 approved
company.
SPRINKLER SYSTEM
The new town’s main connection installed under the enabling works package will be terminated within the
area allocated for the final position of the new Sprinkler Valve Chamber (SVC) (2.016).
The final detailed scheme will commence from this termination point of the new town’s main within the new
SVC.
The town’s main will be extended to supply a new Wet system control valve set.
This 150mm diameter set will feed via a new main supply routed through the ticket hall to connect to the
existing system covering the protections of the escalators and machine chambers.
This will connect to the existing main at a point outside the entrance to the UMC in room 2/152 (2.013).
Separate distribution pipework routed through the ticket hall to supply sprinkler heads to various rooms as
indicated on the drawings. Each room would have a flow switch and monitored isolating valve on the room
supply interfaced with the fire alarm system. Sprinkler heads in store rooms to be fitted with guards.
The control valve set to be fitted with alarm switches as indicated on the relevant drawing.
These alarms together with any monitored valves to be indicated on the station fire alarm system.
All sprinkler pipework including all bracket components to be fireproof lagged providing a 1-hour rating
when such pipework is routed through a non-sprinkler protected area.
Any false ceiling voids over 800mm in depth within sprinkler protected rooms to have additional protection
provided within the voids.
The systems to be designed in accordance with BS EN 12845 to Ordinary Hazard Group 3 standard.
Layouts shown on the associated drawings are indicative only and need to be finally designed, co-
ordinated and detailed by a LPS 1048 approved company in accordance with TfL Standard 1.081
paragraph 3.3.
All pipework to be Heavy quality galvanised joined by screwed or grooved fittings.
All sprinkler heads to be 68 degree rated fast response type. All sprinkler heads to be fitted with propriety
guards.
Note: Layouts shown are indicative only and need to be finally designed by a LPS 1048 approved
company.
GENERAL NOTE
All sprinkler and hydrant pipe work to be sleeved and fire stopped where it passes through walls, floors,
partitions etc.
Pipework identification tape in accordance with BS 1710 to be fitted to all pipework including directional
arrows and name of service
.
Portable Fire Extinguishers (PFE) for use in LU premises should be manufactured and tested in
accordance with BS EN 3. This standard and BS EN 2 classifies extinguishers in accordance with the fire
risk to which they are suite.
Worked examples are given in BS 5306: Part 8, to enable extinguisher provision to be calculated. Under
normal circumstances the provision of extinguishers is made for mixed general fire risk, and a simpler
method of calculating the necessary provision is used, see below.
Requirements for the provision of PFE in LU premises are detailed in LU Cat 2 Standard S2101. This
standard requires that only PFE containing; Water, Aqueous Film Forming Foam (AFFF), or Carbon
Dioxide (CO2) should be used.
Extinguishers containing AFFF, deal very effectively with both Class A and Class B fires, and are preferred,
in most circumstances, to those containing water only. Carbon Dioxide is for use on Electrical type risks.
All extinguishers shall be of the cartridge type only (i.e. not stored pressure type). All extinguishers for LU
use should be capable of meeting the requirements of the electrical conductivity test specified in BS EN 3,
this minimises the risk of injury to the user should the firefighting stream accidentally come into contact with
live electrical equipment.
For most purposes 9 Litre AFFF, and 2 kg CO2, will be the correct sizes of extinguisher, however other
sizes may be required according to the risk, and user needs. The distribution of extinguishers in the area of
the station under the scope of the current project is as follows.
Figure 11: Route of the fire services from Paddington Fire Station to Paddington Square station.
Figure 15 – Demountable Durasteel is used in the soffit above the doors to the lift lobby at Upper
Ticket Hall level as shown highlighted in red.
In the new firefighting access, a repeater panel, an emergency microphone and a pressurisation override
switch will be provided.
It is recommended that the keybox which would aid in opening the door at street level to access the
firefighting lift, is kept in the firefighters plans box.
HYDRANT SYSTEM
A new charged dry dropping main will be provided to replace the existing wet hydrant system currently
supplied by a town’s main.
A four-way breeching inlet shall be positioned at concourse level under the new escalators adjacent to the
ventilation supply room 2.002.
From this point the main supply drops within the lower level of the ventilation supply room immediately
below, at Upper Ticket Hall Level. It is then routed along the corridor and/or plant rooms area to pass into
the existing ticket hall area.
A branch passes across the ticket hall in front of the existing escalators, fitted with a monitored isolating
valve and left in readiness to connect to the existing supply into the UMC entrance (2/152) 2.014 feeding
the existing outlet valve at Ticket Hall Level and the platform outlet valves, at an appropriate time. The
existing pipework to be inspected and tested prior to be coupled to the new works. Should any of this
existing pipework leak or found to be deteriorating then this should be replaced. The main continues into
the Ticket Hall fitted with a further monitored isolating valve. A branch is taken off to the right into the
Cleaners Store 2.009 to drop to below into 3.005 to an outlet valve at low level facing into the new Ticket
Hall 3.018 and rise to an outlet valve at concourse level in the plenum chamber 1.004 facing into corridor
1.002.
All outlet valves recessed into walls to be mounted in a suitably fire rated outlet box.
The main continues across the Ticket Hall to Riser 2 adjacent to lift lobby 2.021, drops to an outlet valve
facing into the lift lobby mounted in a suitably fire rated outlet box, and continues dropping to high level
below within the lift lobby 4.002 at basement level.
A small top-up tank is positioned at high level in Plenum Chamber 1.004 and a supply connected into the
main at upper ticket hall level adjacent to the cleaners Store 2.009 (Water supply to this tank by others.) All
pipework situated in Plenum Chamber 1.004 and room 2.002 to be trace heated and lagged (power
supplies to these by others).
EXTERNAL HYDRANTS
External hydrants are available within 90m of the vehicle access points.
A new hydrant fitted at the top of Arrivals Road during construction phase, shall be retained in the permeant
design.
RENDEZVOUS POINT
Rendezvous point shall remain at the entrance to the District and Circle Line on Praed Street. An
emergency pack, with contents in compliance with BS9999:2017 Annex O shall be kept in a readily
accessible box at that entrance.
GENERAL
LU will be the operator of the station. The LU SOR is located at the LU Ticket Hall.
A management procedure is required that will include responses to fires, the rendezvous point, fire incident
procedures for staff and procedures for the evacuation of all passengers.
MAINTENANCE PROCEDURES
All active and passive fire safety features require systematic checks, servicing and testing as required by
the relevant TfL LU Standards and British Standards. The management systems must ensure that any
changes which affect the fire safety features of the premises are properly recorded and agreed with the
authorities.
Maintained records should include:
A comprehensive set of drawings/fire plans;
The predetermined response plan;
As-built drawings of active and passive fire safety features;
Staff training records;
Service and maintenance records.
STAFF DUTIES
There should be a sufficient number of competent staff on duty at all times to complete the following actions
if a fire is suspected or discovered:
Direct passengers to safe evacuation routes;
Assist with the evacuation of PRMs;
Coordinate with the fire and rescue service and other third parties involved. This includes meeting and
briefing the senior fire officer;
Provide the senior fire officer with drawings showing the location of fire safety features;
Check all public areas are vacated;
Any other actions that are required in the fire response plan.
STAFF TRAINING
The Fire Precautions (Sub-Surface Railway Stations) (England) Regulations 2009, require that all staff are
aware of the fire safety features provided and the response actions expected of them if a fire alarm is
activated or a fire is discovered.
Figure 35 - Final Exit from Protected Corridor (Fire fighters Access) and secondary means of escape
2041+35%
AM 3637 15261 18494 10256
3hr
PM 7490 18728 18494 10216
AM 1665 1230
South bound
PM 1568 1077
AM 2069 1634
South bound
PM 2060 1569
Time
Time to
to Time to Time to
Time Personal place
Exit clear Distance walk clear
Provided width Escape to travel of
Escape element Capacity People the to Exit the incident
(m) (pp/exit/min) clear speed relative
(pp/m/min) exit (m) distance platform
(min) (m/min) safety
(min) (min)
(min)
(min)
Incident Platform 1665
Escalator Barrel 1149
New Stair 516
Platform 38 65.0 1.7
Cross passage doors to
existing barrel 4 80 320 1149 3.6 38 13.0 0.3
Existing Escalator 1 120 120 480 4.0
Existing stair 1.2 56 67.2 269 4.0
Note: persons are assumed to be in a place of relative safety when they have passed through the fire doors into the protected passageway leading to the new stair.
Effect Legend
X - Activate
Cause
Fire Panel Indicators Buzzer & LED notification
Platform level
System fault
Lift Control
- No Action
MCC1
MCC2
MCC3
Spare
Callpoint/Sensor/HSSD System Activated 1st Knock
Escalator chamber P x E G G x x x x x x x x
Escalator chamber P x x G G x x x x x x x x
Manual override Stair pressurisation P I x Note: If the local manual override switch (at Concourse
level) is activated, then the secondary override switch (in
Secondary manual override stair pressurisation (SOR) P x the SOR) will not operate.
Sprinkler Activation
System Activated P x x x E G G x x x x x x x x x x x x x x x x x
System Tamper P x
User Activity
Maintenance P I I I I I I I I I I I I I I I I I I I I I I I I I I
Weekly Test P I I I
System Fault
System fault P x
Doo
Statement of distribution pipe losses between the various design points and the installation valves
System: Wet Sprinkler system – Flow rate 1000L/min
Hazard Group: Ordinary Group 3
Contract Name: Paddington Square Upgrade
1 2 3 4 5 6 7
Run of distribution pipe from Pipe Pipe No of Equiv. Total Pressure loss at design flow rate
valves to design point dia. length bends length
length Pipe Static head Difference
and
losses gain
tees
mm m m m mbar mbar mbar
Basement - Storeroom 150 26 4 8 34 34
4.010
100 8 1 6 14 56
80 43 8 13 56 896
986
600 386
90
0 90
System: Dry Fire Hydrant Main – Flow rates 1500 & 750 L/min
Contract Name: Paddington Square Upgrade
1 2 3 4 5 6 7
Run of distribution pipe from Breeching inlet at Pipe Pipe No of bends Equiv. Total length Pressure loss at design flow rate
Concourse Level to outlet valve dia. length and tees
length Flow Loss Static head Difference
gain
Ticket Hall – Upper Level 150 53 20 40 93 1500 93
Connection to existing system - existing room
2.014
93 200
-107
Ticket Hall Upper Level: Lobby 2.021 150 58 23 53 111 1500 111
100 3 4 11 14 750 42
153
400 -247
Ticket Hall Lower Level: Lobby 3.017 150 67 26 75 142 1500 142
100 3 2 8 11 750 33
175 700 -525
Concourse Level - Stair 2 150 67 26 75 142 1500 142
100 8 1 2 10 750 30
65 3 3 3 11 750 286
458
0 458
Basement Level: Lobby – 4.002 150 65 26 75 140 1500 140
100 18 6 15 33 750 99
239 1000 -761
INTRODUCTION
The Paddington Square development will include a two-storey retail mall below the street level. This
technical note is intended to summarise the discussions/agreements that have taken place during the
design process of the retail mall of the Paddington Square development and its interface with LU and
provides a synopsis of the Retail Mall considerations for future reference as follows:
1. LU interface
2. Sprinkler protection coverage
LU INTERFACE
The entrance route to LU station is provided via escalators/stairs from open public realm at concourse level
entrance to reach the ticket hall at B1 level.
Figure 1 and Figure 2 show the proposed entrance to LU station.
Figure 1: 3D view showing the entrance to LU station from the open public realm.
www.wsp.com
Figure 2: 3D view showing the escalators at B1 level connecting to the open public realm.
To accommodate LU requirements the proposed entrance/egress route contains design provisions within
the Retail Mall fire strategy. The following sections summarise the requirements and provisions of the Retail
Mall with regards to satisfying LU.
The entrance route to LU Ticket Hall (up to the line of the demise) is considered part of the open Public
Realm space due to its direct openness to outside over a large volume of weather covered spaces. See
Figure 4 below.
Figure 4 Part of the retail mall is connected to outside
CFD STUDY
As part of the Retail Mall fire strategy a CFD study was carried out to demonstrate that the mall escape
route from LU ticket hall via the retail mall is kept clear smoke if a fire breaks out within the deemed worst-
case fire incident in retail unit 15, adjacent to the egress route. Figure 5 shows the location of retail unit 15.
Subsequent meetings with LU resulted in an additional fire scenario being considered and a CFD study for
retail unit 2 (shown in Figure 5) was carried out with the following visibility results;
Longitudinal Section along mall Transverse Section thru unit
The CFD study results show that tenable conditions are expected in the retail mall and therefore the
entrance/egress route from LU station in the event of fire within a retail unit.
Note: A standalone CFD report has been produced for the benefit of LU to accommodate their request to
consider a fire in retail unit 02.
EVACUATION PROCEDURES
The simultaneous evacuation of the LU station and Retail mall is not a required fire evacuation scenario
and as such is not considered in the fire strategy design; the spaces are fire separated by a 120 minutes
fire rated curtain line at B1 level, hence considered as separate fire compartments and different entities
under separate management and evacuation methodologies.
The fire alarm strategy for the Concourse and B1 levels is defined in the fire strategy as simultaneous,
albeit this will be done only on a genuine “double knock” fire detection activation condition.
Given that the Retail mall will be a managed space the illustrated evacuation matrix is considered in the fire
strategy to ensure unnecessary disruption for minor incidents and only evacuate on a confirmed fire
condition when deemed necessary. The fire strategy also highlights the requirement for management level
in section 17 of the fire strategy report. Evacuation procedures will need to be put in place once the building
is occupied under RRO (Regulatory Reform (Fire Safety) Order) enforcements.
Figure 9: Fire activation and alarm sequence
The proposed material achieves B-s1-d0 European classification and therefore meets Building Regulations
requirements. As shown in Figure 10, the proposed stretched ceiling at B1 level is located at the
designated area where LU requirements are considered. However, WSP consider that the proposals are
acceptable based on the following:
• No fire load is expected as it is a circulation space used as egress/access to LU station.
• As fire load is restricted the risk of fire would not occur directly below the stretched ceiling to cause
ignition of the material.
• In the unlikely event of the proposed material igniting, the thickness of the material would cause to
burn through rapidly and not significant enough to cause fire to spread to the adjacent Class 0
ceiling
FALSE CEILING
In order to allow the smoke extract system to perform as per the design intent it is necessary to create a
smoke reservoir and prevent smoke spilling into the mall. The suspended ceiling in each retail unit will need
to be at least 25% ‘open’ to allow smoke to rise through the ceiling, into the void from where it can be
extracted. The details of the openings in the ceiling will be provided by the fit-out teams but could take the
form of slots, coffers or other types of perforations, which ensure an even distribution of the openings is
achieved.
INTAKE AIR DUCTWORK TO THE RETAIL UNIT AT RETAIL MALL
As part of the shell-and-core, an enclosure to the landlord ventilation system is provided as shown below.
Once tenants provide the fit-out, they will be able to connect the landlord opening or remove the landlord
enclosure and provide a damper in the ductwork at the connection point.
Figure 14: Intake air ductwork connection within the retail units.
PADDINGTON SQUARE LU
Emergency Egress from Ticket Hall Options 0 - 4
CONTENTS
EXECUTIVE SUMMARY 1
1. INTRODUCTION 2
2. EXISTING MEANS OF ESCAPE 3
3. OPTION 0 AS FEASIBILITY REPORT OPTION 5A 4
4. OPTION “1” EVACUATION CORRIDOR WITHIN RETAIL SPACE 6
5. OPTION “2” EVACUATION CORRIDOR WITHIN LUL DEMISE 10
6. OPTION “3” EVACUATION VIA EXISTING PRAED STREET CORRIDOR 14
7. OPTION “4” EVACUATION VIA MECHANICAL LIFT 17
8. PLANNING CONTEXT 24
9. BUDGET ESTIMATE 25
10. CONCLUSION 26
11. APPENDIX A – DDN EMERGENCY EGRESS TICKET HALL & PLANT ROOM 27
EXECUTIVE SUMMARY
This document has been prepared to provide LUL with further substantiation that the Feasibility Report
Option 5a design and associated LU fire strategy provides the optimum solution reducing associated
risks to ALARP when considered within the constraints of the development and against alternative
layouts and escape strategy options.
The Bakerloo Line station has not been significantly enhanced since its opening in 1913 and a number
of previous schemes to ameliorate the worsening capacity issues have been proposed over the last
two decades, however these proposals have been hampered by the physical constraints of the site
such as LU infrastructure issues including running tunnels, escalator barrel, main sewer, existing
services, road network, adjacent buildings and main line Paddington Station including Arrivals Road.
This report seeks to demonstrate that the scheme now being progressed provides the optimum
solution within the constraints for an extension to the existing ticket hall in an extremely space
restricted environment.
The Feasibility Report Option 5a design provides for significant improvements including:
· Congestion relief at peak hours
· Improves station operation
· Provides step free access from street to platforms
· Improves evacuation provision during emergency situations
· Optimises passenger flows and improves on passenger journey times
· Improves wayfinding of customers and improves cross-flows
· Provides new dedicated means of escape from platform
· Improves Customer experience
· Provides PRM evacuation from platform level.
The details are contained in the Feasibility Report Option 5a design for Paddington Square London
Underground Bakerloo Line which includes for designated means of escape, in a fire emergency, from
the newly extended Ticket Hall through the retail mall for passengers.
Despite the design and fire strategy contained in the above report, London Underground Fire
Engineers have expressed concern at proposals to provide a means of escape from the ticket hall
which passes through another demise. Whilst recognising these concerns it should be noted that this
provision is compliant with standards and guidance on providing a means of escape and provides the
safest and best solution in the context of the highly complex consented scheme. Access through and
across this demise is also governed by lease arrangements securing LUL rights.
As an existing station, there is very limited scope underground for bringing new exits to the surface.
There are spatial restrictions caused by the new fire-fighters shaft, the Mercure Hotel basement, and
a retaining wall. There are further restrictions as to where such an exit might breach the surface due
to the requirement to keep Arrivals Road permanently available for emergency vehicle and
maintenance access for Paddington Station and the Hilton Hotel. Similar vehicular restrictions apply
to the area around the Mercure Hotel.
As well as the existing Feasibility Design Report 5A design (Option 0), this report provides further
consideration of 4 options.
For option 0 it is considered the risks associated with the proposed exits are ALARP. A further 4
options have also been considered (1-4) and are included within this review. Each of these options
carry significant cost and planning permission noncompliance, without reducing the risk to passengers
in a station fire.
A commentary on the Planning context and the associated impacts of the 4 options has been included
in this document. It concludes that after carefully considering all the options (0-4), option 0, evacuation
via the shopping mall, provides the most viable and effective means of escape from the Bakerloo Line
Ticket Hall.
Options 1-4 would be perceived by Westminster City Council (WCC) as a ‘retrograde’ step in terms of
the quality of the public realm. The public realm was considered a fundamental public benefit of the
approved development, meaning any change will be sensitive and closely scrutinised by WCC, and
they are very keen to maintain to maximum permeability and pedestrian flow throughout the
development.
The options all involve addition of structures in relatively sensitive areas where pedestrian flow is likely
to be high as people move into/through the site and to/from the underground station and retail mall.
Any additional structures or intrusions into the public realm would therefore be very likely to be resisted
by WCC.
LUL have been granted a 999yr lease (virtual freehold) of the new ticket hall which includes all relevant
access provisions required for operations, maintenance, and emergencies including fire. The lease
includes escape routes which form a right of way over the public realm or retained premises to give
appropriate ability to maintain safe operations at all times.
A summary of the anticipated CAPEX and OPEX costs associated with the various options discussed
has also been provided. This includes an estimated value loss of circa [£7.8M] reported against
Options 1 and 2.
In considering the additional 4 options it should be clear that the numbers considered for evacuation
are the numbers of persons who can enter the Ticket Hall per minute from the escalator barrel
(187ppm). All others are considered to escape safely via the new stair. This is identical for each option
and identical to Option 0. This report confirms that the route to safety for these 187 ppm under option
0 is direct, immediate, substantially the most cost-effective option, and meets with planning consent.
Option 1 – will carry a minimum CAPEX cost of £1,400,000 including the provision for a new lift.
However, there is a significant loss of value of circa £7,800,000. Additionally, LUL will have to carry
out calculations associated with their own potential costs.
Option 2 – will carry a minimum CAPEX cost of £825,000. There is a significant loss of value of circa
£7,800,000. Additionally, LUL will have to carry out calculations associated with their own potential
costs.
Option 3 – will carry a minimum CAPEX costs of circa £700,000. This would include costs to modify
the existing structure, associated MEP and structural works at surface. The cost associated with
relocating new plant and equipment currently allocated within this space and the associated design
fees have yet to be assessed and are therefore excluded due to lack of information. Additionally, LUL
will have to carry out calculations associated with their own potential costs.
Option 4 – will carry a minimum CAPEX costs of £950,000. This would include costs to modify the
existing structure, associated MEP and structural works at surface. The cost associated with
relocating new plant and equipment currently allocated within this space and the associated design
fees have yet to be assessed and are therefore excluded due to lack of information. Additionally, LUL
will have to carry out calculations associated with their own potential costs.
We believe that Option 0 continues to offer the safest practical solution within the context of the
constraining environment and given the key constraints of neighbouring structure, planning consent
and viability we believe the alternative Options 1-4 remain are unviable and would deliver a retrograde
step in relation to fire safety.
3.1 GENERAL
Escape from platform level requires that 187 ppm exit via the escalator barrel into the ticket hall.
3.2 ROUTE
This option provides an egress route from the station Ticket Hall via the mall (which is not enclosed
or shut), rather than direct to surface level.
The main entrance will be closed by a fire shutter in the event of a fire. Emergency exit will be via a
fire door to the side of this shutter. The fire door will be 2.4m wide, with an exit capacity of 192 ppm.
All passengers leaving the escalator barrel will flow freely through the fire door to open air. Of the
means of escape options considered this route offers the shortest time route to a place of relative
safety.
The mall escalators as shown below are situated immediately outside the proposed fire door and are
open to the external environment. LUL have legal access rights of this area.
Option 0 Plans
4 OPTION “1” EVACUATION CORRIDOR WITHIN RETAIL SPACE
4.1 GENERAL
Escape from platform level requires that 187 ppm exit via the escalator barrel into the ticket hall.
4.2 ROUTE
This option considers a new LUL dedicated fire rated corridor in front of the shopping mall step free
access lift. This option has several issues which impact on the scheme as identified within the
Feasibility Design Report number PAD-WSP-ML-00-RP-DM-0001(P03). Exit from the ticket hall into
the new corridor is via the 2.4m fire door adjacent to the fire curtain.
The pinch point within the corridor is 2.0m wide, which has an exit capacity of 160ppm, 27ppm would
be required to use the new stair in order to maintain a steady flow through the station. This does not
comply with TfL S1371 requirements to maintain at least two separate escape routes through the
station. Alternatively, the evacuation time will be increased elevating risk to passengers.
2m Pinch point
5 OPTION “2” EVACUATION CORRIDOR WITHIN LUL DEMISE
5.1 GENERAL
Escape from platform level requires that 187 ppm exit via the escalator barrel into the ticket hall.
5.2 ROUTE
This option comprises a new fire rated corridor within the LUL demise with the loss of the allocated
place of safety adjacent to the gate line, staff toilet area, and electrical cupboard. These rooms and
areas will need to be relocated elsewhere within the proposed footprint.
The pinch point within the corridor is 2.0m wide, which has an exit capacity of 160ppm, 27ppm would
be required to use the new stair in order to maintain a steady flow through the station. This does not
comply with TfL S1371 requirements to maintain at least two separate escape routes through the
station. Alternatively, the evacuation time will be increased elevating risk to passengers. Introduction
of Structure at Concourse – Urban Realm Area
· through the station. This route would cause confusion / congestion during an evacuation in the
ticket hall.
· Corridor would mean a loss of commercial space at both Ticket hall and Concourse Area
(157.6sqm’s)
2m Pinch point
6 OPTION “3” EVACUATION VIA EXISTING PRAED STREET
CORRIDOR.
6.1 GENERAL
Escape from platform level requires that 187 ppm exit via the escalator barrel into the ticket hall.
6.2 ROUTE
This route considers the utilisation of the existing Praed Street corridor, stairs and exit as the dedicated
means of escape. The stairs within this corridor are 2.1m wide, with an exit capacity of 117ppm.
In an evacuation scenario 117ppm will be able to flow freely from the ticket hall via the Praed street
exit to a place of ultimate safety. This will leave a build-up of 70ppm within the ticket hall. This will
create an increase in the evacuation time and therefore a less safe option than option 0. Twenty eight
ppm could be accommodated in the 2.0m wide new stair (this will not be compliant with TfL S1371 as
above). However, this would still leave a build-up of 42 ppm within the ticket hall and an increase in
evacuation time. Risk is increased in this option whether the new stair is used or not.
The existing staircase width does not accommodate the numbers exiting from the escalator barrel.
The existing design does not provide sufficient exit capacity in a fire scenario.
The entrance is very close to the new stair so that escape is partially in the same direction.
7.1 GENERAL
Escape from platform level requires that 187 ppm exit via the escalator barrel into the ticket hall.
7.2 ROUTE
This route considers the utilisation of the existing Praed Street corridor as the dedicated means of
escape. It would exit at street level via a mechanically operated lift stair. This form of evacuation is
used as a means of escape on other developments but will be novel to London Underground. This
option is complex and will require product approval together with substantial civil alterations.
In an evacuation scenario 117ppm will be able to flow freely from the ticket hall via the Praed street
exit to a place of ultimate safety. This will leave a build-up of 70ppm within the ticket hall. This will
create an increase in the evacuation time and therefore a less safe option than option 0. Twenty eight
ppm could be accommodated in the 2.0m wide new stair. (this will not be compliant with TfL S1371
as above). However, this would still leave a build-up of 42 ppm within the ticket hall and an increase
in evacuation time. Risk is increased in this option whether the new stair is used or not.
In addition to the issues outlined above, it should be noted that WCC’s expectation is that the
building and public realm has now been developed to an advanced stage of design following grant
of planning permission in 2017. At this stage, they may therefore be reluctant to introduce further
changes which have quite significant implications for design and use of the public realm and could
be seen to diminish one of the key public benefits of the scheme previously approved.
· Amend the Agreed Planning Consent and submit to Westminster City Council for Consent (which
may be not be granted and or challenged)
· Impact to Urban Realm, secured area required (bollards or similar)
· Impact to Urban Realm whilst in operation and testing
· Planning support to emphasise the impact this option on the urban realm intention.
Viability
It should be noted that the changes associated with this option will breach our financing agreements.
In the current market it is very difficult to secure debt finance to develop speculative buildings such as
this therefore there is a significant risk that this option will halt the overall project and delivery of the
station improvements.
Notwithstanding the issues outlined above in the event any of the options were progressed, WCC
would seek to understand why this level of change, which has quite significant implications for design
and use of the public realm, is only being realised and addressed now despite the fact that the detailed
design has been in place and reviewed by both Sellar and TfL/LUL over several years.
9 COMMERCIAL SUMMARY
The following initial budget estimates have been provided by the Gardiner & Theobald cost team.
These estimates have been based on limited design information and should be considered as order
of magnitude budget estimates only and subject to further verification:
Option 1 CAPEX £1.4 million £7.8M (value loss)
Option 2 CAPEX £825,000 £7.8 (value loss)
Option 3 CAPEX £700,000 (OPEX tbc)
Option 4 CAPEX £975,000 (OPEX tbc)
The above costs are exclusive of OH&P, Preliminaries, Design and Procurement Risk Fees, VAT, all
associated OPEX, adaption of dry falling main, re-provision of lost space, bomb blast protection.
There is currently no allowance for any associated programme impact and associated costs including
potential delay to project completion and the scheme opening date. This is currently hard to quantify
however estimated to be well in excess of £10 million
At present £250k allowed for the lift in option 4. This will require research as it is a specialist item and
will require back rams etc. in case of main failure.
10 CONCLUSION
All of the Options noted above are able to provide a means of escape, however the viability of each
option differs by the constraints imposed by the nature of the existing station geography which in turn,
depending in the option, will impact the development.
Options 1- 4 impact the proposed development significantly with discipline designs being reworked in
detail to assess the validity and impact not only in terms of Quality, Time and Cost but to the viability
of the development. These options would also impose more responsibility on London Underground
with additional assets owned or leased to London Underground, additional assets for London
Underground to maintain and upgrade when necessary thus increasing the whole life costs for this
station.
The development as it stands currently meets Westminster City Council’s Public Realm Strategy
Principles, meeting The Westminster Code a set of ten rules and has Planning Consent. Options 1 –
4 would require in some way impact on these rules and necessitate minor material amendment to the
planning permission which is a potentially time consuming process. This would represent a potentially
significant risk, and we anticipate that the principle of additional structures in the public realm would
be resisted by WCC. It is contrary to design and public realm principles which have been developed
with WCC over several years of pre-application discussion, and which were strongly welcomed by
officers and stakeholders.
Options 1 and 2 are costed to figures in excess of 7million pounds which creates a significant risk to
the project. Neither of these options significantly decreases risk to life safety and thus cannot be
considered the ALARP solution.
Options 3 and 4 are costed at figures up to 1 million pounds, with no appreciable reduction in risk to
life safety for this investment. Additionally, option 3 and 4 are unlikely to win planning consent which
would have serious programme implications.
Upon careful consideration of all the Options 0-4 detailed above it is still believed that Option 0,
evacuation via the shopping mall, provides the most viable and effective secondary means of escape
from the Bakerloo Line Ticket Hall in the event of an evacuation. The specific details surrounding this
Option have already been documented and issued to all parties. For further reference please see
Document PAD-WSP-DDN-STN-FI-0004 Emergency Egress from Plantroom & Ticket Hall.
WSP House
70 Chancery Lane
London
WC2A 1AF
wsp.com
CONFIDENTIAL
Project: PADDINGTON SQUARE LU BAKERLOO LINE STATION UPGRADE
Signature Date
Prepared by Ally Mamgain 29/01/2021
Approved by I endorse this deliverable as the designated technical authority for the relevant
engineering discipline and am accredited to do so.
<Name>
Accredited Assurer
Approved by I confirm that this deliverable meets the requirements of the relevant Pathway Product
Description and that all consultation comments have been addressed to the satisfaction
of consultees.
<Name>
Project Manager
Document History
Revision Date Summary of changes
P01 15/05/2020 Detailed Design Submission
I confirm that sufficient evidence has been provided to assure me that the safety and
technical risks associated with the project works have been identified and adequately
mitigated.
Signature Date
<Name>
Project Manager
Signature Date
<Name>
I confirm that this project has been designed in accordance with applicable LU
standards (except for agreed concessions), Railway Safety Principles and Guidance
(except for agreed deviations), and other relevant standards. There is auditable
documentary evidence demonstrating this design, agreed concessions and deviations.
Signature Date
<Name>