Medford Garage Final Report 10.15.11
Medford Garage Final Report 10.15.11
Medford Garage Final Report 10.15.11
MassDevelopment Utile, Inc. Nelson\Nygaard Consulting Associates for the City of Medford
Prepared for The City of Medford Mayor Michael J. McGlynn In cooperation with Lauren DiLorenzo, Director Office of Community Development 85 George Hassett Drive Medford, Massachusetts 02155 781-396-5500 www.medford.org Prepared by PROJeCT ManaGeMenT MassDevelopment 160 Federal Street Boston, Massachusetts 02110 617-330-2000 www.massdevelopment.com LeaD COnSuLTanT utile, Inc. architecture + Planning 50 Summer Street Boston, Massachusetts 02110 617-423-7200 www.utiledesign.com TRanSPORTaTIOn COnSuLTanT nelson\nygaard Consulting associates 10 High Street, Suite 903 Boston, Massachusetts 02110 617-521-9404 www.nelsonnygaard.com
Acknowledgements 7 8 10 12 14 17 19 22 33 39 41 43 45 47 50 53 58 62 64 67 69 76 87 88 90 102 115 116 117 119 I. Introduction Executive Summary Study area Methodology Public Participation II. Existing Conditions urban Design Issues existing Parking Issues III. Garage Site Selection Governors Avenue Site Forest Street Site Chevalier Site City Hall Site IV. Parking Management Plan and Recommendations Supply Enhancement Improved Walking Access Parking Zoning and Management Program Pricing Revenues & Costs Signing Plan V. Proposed Garage Site Site Description Site Impacts VI. Garage Studies Design approaches Brick Garage Green Garage VII. Conclusions Garage Traffic and Parking Sustainability 123 124 126 132 134 144 148 156 166 168 VIII. Appendix Bibliography: Previous Studies Property Title Search Memorandum: Possible Permits Required MEPA Threshold Review Environmental Report Overview Structural Review Preliminary Cost Estimating Overview Memorandum: Photovoltaic Panel Specifications Memorandum: Financing the Construction and Operations and Maintenance of a new Garage in Medford Square Memorandum: Overview of Modular Construction Procurement Relevant Building Code excerpts
174
176
Acknowledgements
Prepared for The City of Medford Michael J. McGlynn, Mayor Office of Community Development Lauren DiLorenzo, Director Clodagh Stoker-Long, Economic Development Planner Consultants MassDevelopment, Project Management utile, Inc., architecture and Planning nelson\nygaard Consulting associates, Transportation Planners Harry R. Feldman, Inc., Environmental Engineering KVAssociates, Inc., Cost Estimating Samiotes Consultants, Civil Engineering Simpson Gumpertz & Heger (SGH), Structural Engineering Solar Design Associates, Photovoltaic Consulting
I. Introduction
Executive Summary
The goal of the Medford Garage Feasibility Study was to a) identify the best site, parking capacity, and layout of a new public parking garage, b) propose options for design approaches to the garage, and c) embed the logic of a new parking garage within an overall parking management strategy for the Medford Square downtown core. To arrive at the most informed and compelling recommendations, MassDevelopment and the planning team utile, Inc., and nelson\nygaard Consulting associatesworked closely with Lauren DiLorenzo, Director of the City of Medford Office of Community Development, and sought the feedback of Mayor Michael J. McGlynn, City staff, and Medford community members at several stages during the iterative planning process. Public input was generated through two public meetings and written surveys. The Feasibility Study resulted in five important recommendations: 1. Build a Garage to Accommodate Future Development A four-and-a-half-story parking garage with 178 vehicular spaces and 22 bike spaces should be built on the existing lot between Governors Avenue and Bradlee Road, replacing the 163-space municipal garage formerly on the site. This garage is adequate to meet the future economic development of Medford Square if the garage is part of a larger parking management plan for the Downtown area. The garage will provide parking for existing businesses, for future retail and restaurant establishments, as well as the patrons of the nearby Chevalier Theatre. 2. Forward a Sustainable Agenda in Planning and Design The garage should be a high-quality and architecturally distinctive building that can be considered a contributing visual asset to the Square. The design should be driven by a sustainable agenda and include photovoltaic (solar) panels, adequate natural ventilation and daylighting, bicycle parking, accommodations for electric and shared cars, innovative storm water management, and other sustainable features to make the garage a Zero Net Energy demonstration project in the Commonwealth.
i. introduction
3. Initiate a Comprehensive Parking Management Strategy New parking supply in the western half of the Square, as provided by a new garage, will not alleviate the on-street parking situation, especially if there is a fee to park at the garage. Improved parking management practices are necessary to moderate heavily utilized prime parking areas and incentivize the use of a new garage. A comprehensive parking management strategy for the Downtown area will include tiered pricing for both metered spaces and permits (business and residential), a relaxation of parking time limits, and adequate enforcement. 4. Institute a Pricing Program A demand-responsive priced parking management system in the Square can equitably assure available parking spaces for all user groups, including long-term spaces for employees and convenient front-door spaces for customers. Financing the recommended garage is made much more feasible if such pricing is successfully instituted, providing the City with new sources of revenue. 5. Improve Main Traffic Intersection The five-legged intersection at High, Forest, Salem, Riverside, and Main streets is currently an impediment to pedestrian movement between the east and west halves of Medford Square, effectively splitting the Squares parking supply. With some traffic and public space improvements at this intersection, the overall vehicular level of service would not be negatively impacted, and a civic space could be created at the very heart of the Square. The analysis conducted and recommendations proposed in this Feasibility Study are intended to arm the City of Medford, and the design team they ultimately choose, with the regulatory and technical information necessary to move the design and construction of a new municipal garage forward. The comprehensive appendix to this report is comprised of memos from a host of subconsultants that outline the potential permits that may be required for the garage, environmental conditions on the site, structural implications of various systems, specifications for photovoltaic panel systems, conceptual cost estimates, construction and maintenance financing implications, relevant building code provisions, and an overview of modular construction options. In total, the report provides the future design team with vetted conceptual options for the garage, and the means to engage the project quickly, with City and public support.
10
Study Area
The specific area chosen for the urban design portion of this study constitutes the core of Medford Squares retail and commercial center. It is bounded on the east by Interstate 93, on the south by Route 16, on the west by Powderhouse Road, and on the north by Hall Avenue. Analysis of vehicular activity in the Square focused more tightly on the public (nonresidential) core of the Square in which the majority of through-traffic and public parking occurs. An illustration of both study areas is shown here.
i. introduction
11
12
Methodology
governors Aven ue
LeFt: the proposed garage site is between Governors Avenue and Bradlee Road, just off High Street.
Hig
hs tre
et
bradle
e road
i. introduction
13
14
Public Participation
To help identify needs in and potential improvements to Medford Squares parking system, the team and City held a Parking Open House workshop on March 31, 2010, at Medford City Hall. The open public forum was designed to allow all participants to help identify areas of concern regarding parking in the Square, and to offer suggestions on how to improve the current parking conditions. The Open House included a voting exercise to elicit general parking preferences and small group discussions where comments were made and recorded directly onto large tabletop maps of the Squares parking inventory. The Open House was well-attended by the local business community and nearby residents. All map comments were transferred to illustrations included in this report (see pp. 3031), and all voting results are summarized in the accompanying pie charts (see facing page and p. 29). In addition, a broad public survey was distributed in paper and online that resulted in more than one hundred responses. The workshop and survey results helped target the teams recommendations and provided a valuable users perspective on parking operations. Finally, a Public Meeting was held June 16, 2010, during which the consultant team shared the preliminary analysis and recommendations for parking management strategies, siting and sizing of a municipal parking garage, and conceptual studies for a garage on the Governors Avenue site. The public was invited to comment after the presentation. Some of the public recommendations and suggestions are reflected in this report.
RIGHt: Community members at the Public Meeting on June 16, 2010. FACInG PAGe: Comments from workshop and survey respondents.
9%
West Square Street
19%
27%
33%
Ease of finding a spot
50%
Location
31%
Ease of finding a spot
58%
Location
39%
37%
7%
i. introduction
15
I would be willing to pay to park if I knew I was going to get a convenient space for as long as I wanted to stay. I would run more errands in Medford Square if I knew there would be convenient parking at my destination.
29
I sometimes bypass shopping in Medford Square because I know parking will be hard to find.
I dont mind parking a little further away from my destination if it means I dont have to search for parking.
8
respondents
45
I usually circle for parking because I prefer to park on the street right in front of my destination.
16 3 29 22 39 9
I would like for it to be easier to get to Medford Square by biking or taking transit.
I would like to park only once and walk to all of my destinations when I come to Medford Square.
I do not like the time-limited parking because I find myself wasting time moving a car.
18
City Hall
ABove: Medford Square with the east and West Squares highlighted.
19
20
Pedestrian Experience
In addition to the parking supply issues that influenced the recommendations of the report, the team also weighed several urban design issues including pedestrian walkability, architectural character, and placemaking opportunities. Both sides of the Square have pleasant architectural and streetscape character, but there is a notable lack of pedestrian gathering spaces that would contribute a vibrant walking quality to the Square. The most obvious location for public gathering should be at the center of the Square, currently the most pedestrian-challenged location. A thorough assessment of walking conditions in Medford Square was conducted to evaluate the potential market for a new garage within a 5-minute walk of the target site(s). A number of walking issues were identified and mapped by the consultant team, including obstructions, missing signing and crosswalks, poor sidewalk conditions, difficult sight lines, and areas of higher traffic speeds. As part of the walking inventory, the intersections of High and Main Streets, and High Street and Governors Avenue were determined to be notable barriers to walking in the Square particularly between the East Square and West Square.
FACInG PAGe, toP: Pedestrians near the Salem / Forest intersection with High Street. FACInG PAGe, BottoM LeFt: Colleens on High Street, at the intersection of Governors Avenue in the West Square, is a popular ice cream and sandwich shop. FACInG PAGe, BottoM RIGHt: the five-legged intersection of High Street, Forest Street, Salem Street, Riverside Avenue, and Main Street. LeFt: Pedestrians in the east Square.
21
22
Pow de
Clift
Walter St
Brogan Ave
Englehutt
an
dE x
Rd
Bu
rb
Rd
Rd
Damon Rd
rH
ou s
eR
Cedar Rd
Crocker Rd
Woodrow
Ba
Ave
t Newpor
dg
Ave
er
Summit Rd
Lewis St
Luther
Lincol
Rd
Ce
da
rR
d
Webster St
Webste
r St
Tainter St
nd A ve
Ash
Woo dla
Gree d nR
St
ale A ve
Rd
Terrace Rd
ouse
Pow d
cro
ft S
er H
Tra in
Pilgrim
Rd
Ave
High St
nR
Interv
Oak Blu ff
Founta in Ct
Bo ynto
Fore st S t
W in th ro p St
Schoolhouse Rd
Rural Ave
a T T T Tr in cr f f f of tS t
R R R n Rd
Crest Rd
King Ave
Fulton St
Brookside Pkwy
Wate r
Everett St
Court St
Hall
St
St
Water St
Terell
Rd
Ash land Pl
Allen Ct
Pl Revere
St
Daly Rd
Port e
Che stnu t St
r Rd
Sa
lem
St
Vine St
St
Hadley
en S
Oak
land
Gard
Pl
Bra
dle
St
eR
High
Cr
os
sS
Salem St
Franklin St
Winthrop St
River
St
Mys
M
St
ton Pl
Ma in
Washi ng
Riv
ers
ide
St C
St
South
South
St
Cli
Wes t
pp
er
Sh
ip
Dr
Ave
Lauriat Pl
Da
nie
ls S
Ple
Ma ple Ave
Curt is
Win
ter S
Waln u
t Te
rr
lf S t
Ma
St
nnin
St
Met ca
ut S
Wa ln
Ma
rtin
St
Winth
rk S
Union St
Cla
rop Pl
Jam
es S
Cu
dw o
r th
Park
Emer
St
son S
Av e
Tha
St
Su mm er
gS t
ing
Tou ro
Cott
St
asa
nt S
Ave
Riv
ers
ide
tch
er S
gs S
Bro okin
Swa n St
Tho
ma
sS
pS
sR
thro
Ma rsto nS
ugla
Win
Gou rley
Co
lleg
lS
Core y St
eA ve
mm
Do
Rd
er
St
Ma r
Su
Av e
ine S
Sh
ip
New
YS TI C
RIVER
gto
nS
com b
tic V alle y Pk
93
wy
Wa s
hin
St
My stic e Av
23
86
10 Minute 15 Minute 15 Minute Loading 30 Minute 1 Hour 2 Hours 2 Hour Business Permit 2 Hour Municipal employee Private Residential Business Parking Unregulated Customer Parking Commuter Lot
24
Parking Utilization
Parking utilization counts revealed a significant amount of vacant parking spaces in the Square during the busiest time of parking demand. A utilization rate of 85 percent is considered ideal, and should be the goal of the parking management plan in the Square. In its current state, of the more than 1,300 public spaces in the Square, nearly 500 are vacant at the peak hour of 11AM, resulting in less than 65 percent utilization. Parking on the east side of the square is under 55 percent utilized with more than 300 vacant spaces at peak 11AM accumulation. Parking on the west side of the square is better utilized at 76 percent, but nearly 140 spaces still remain vacant in this area. Unfortunately, the vacant spaces in the Square are in the most remote locations. Key commercial streets are almost entirely full of cars for much of the workdayparticularly High Street, Salem Street, and Riverside Avenue. Governors Avenue is also nearly full during the workday. Similarly, the Governors Avenue surface lot is heavily utilized all day, whereas lots in the eastern half of the Square rarely reach 50 percent occupancy. The commuter lot adjacent to I-93 rarely has cars in it. Spatial analysis of parking patterns throughout the day reveals that most business permit spaces are full before 9AM. Nearly all prime customer-friendly front-door spaces on High, Salem, and Riverside fill up shortly after 9AM. Participants in the Parking Open House (March 31, 2010) indicated that a lot of long-term employee parking occurs at these prime spaces, and the online survey revealed that the vast majority of the Squares employees park in the western half of the square where parking is constrained, while nearly three-quarters of customers only find parking in the eastern half of the Square. It is likely that the customers are forced to park in more distant locations while employees occupy prime spaces. The spatial analysis directly contributed to the demand estimation for a new parking garage. By assessing the utilization rate of parking within the immediate 5-minute walking distance of the target site(s), Nelson\Nygaard evaluated whether demand exceeded available supply sufficiently to warrant new supply in the western half of the Square. For the Governors Avenue site, this assessment revealed an 85 percent utilization rate, which is considered ideal. No new parking is necessary currently, but will be imminently, with the introduction of new businesses along High Street. Given this sites existing high demand for parking, it is a valuable location for a garage, but parking management techniques would need to be implemented within the 5-minute walking distance to ensure it is utilized.
25
86
Parking utilization
0-50% 50-75% 75-85% 85-100% 100% West Square east Square Proposed Garage Site the above map shows the average utilization over the course of one weekday, based on data collected by nelson\nygaard in April 2010. In total, Medford Square parking (1,300 spaces total) is under 65 percent utilized. only the Governors Avenue Lot, lower Governors Avenue, and portions of High, Salem, and Riverside streets exceed the desired 85 percent utilization at certain times of day.
26
Medford Square
1,320 Parking Spaces
Medford Square Eastern Square 1320 Parking Spaces 750 Parking Spaces 100%100% 90% 90% 80% 80% Eastern Square 70% 70% 750 Parking Spaces 60% 60%100% 50% 50% 90% 40% 40% 80% 30% 30% 70% 20% 20% 60% 10% 10% 50% 0% 0% 40% AM 7AM 79AM 9AM AM 11AM 13PM 3PM 11 1PM PM 5PM 5PM 30% Eastern Square 20% 750 Parking Spaces 10% 100% 0% 7AM 9AM 11AM 1PM 3PM 5PM 90%
1022 385 538 345 455 355 526 424 606 481 638 744 810 345 398 638 368 385 743 408 761 355 690 424 553 481 329 281 408 368 398 70 329 272 63870 385 345 355 424 481 272
Optimal use
Occupied Vacant Period with most occupied spaces Occupied Vacant Period with most occupied spaces
Optimal use
East Square
368
329
Optimal use
408
398
108 363
339
153
339
153
108
171
176 361
7AM
9AM
11AM
422
1PM
3PM
5PM
80% 70% 60% the above tables demonstrate that parking demand in the east Square is 50% significantly lower throughout the day than demand for parking spaces in the 40% West Square. Midday parking occupancy in West Square approaches 85 percent 30% use, while occupancy in east Square never exceeds 55 percent. 20%
375 363
Parking Occupancies
10% 0%
211
9AM
11AM
1PM
3PM
5PM
281
263
211
1PM
3PM
5PM
281
80% 70% 60% 50% 40% 7AM 9AM 11AM 30% Western Square 20% 570 Parking Spaces
211 375
422
363
263
171 361
West Square
375
422
0% 100% 7AM 9AM 90% 80% Western Square 70% 570 Parking Spaces
108
171
176
263
11AM
1PM
3PM
5PM
272
27
Parking Management
Parking management in the Square today is almost nonexistent. The City has no dedicated enforcement personnel, and the Police Department has public safety duties that limit its ability to enforce parking regulations in the Square. The department dispatches safety personnel to write tickets in the Square only intermittently, and typically in response to complaints. Given the high labor cost associated with enforcing time limits, it is not surprising that many violations are unenforced. Parking Open House participants who work in the Square were aware that violations are rare, and many regular business customers are reported to take advantage of limited enforcement as well. Unfortunately, occasional customers and any new or pass-by customers assume that they can only stay for the posted time limits or risk a parking ticket.
BeLoW LeFt AnD RIGHt: existing on-street parking and signage in the West (left) and east (right) Squares.
28
29
Prim Employees
Cust
9%
West Square Street
33%
27%
9%
19%
27%
33
39%
37%
Ease find a sp
Customers
Employees
3% 7% 33%
Ease of finding a spot Price
Avoid Tow/Ticket
27%
Price
t Square Lot
27%
50%
Location
run more errands in Medford Square if I knew there would be convenient parking at the graphics shown above summarize results gathered from the March 31, 2010, Parking open House and the paper and my destination. online survey distributed to area businesses, customers, and residents.
I Type of Parkingwould
7%
I would Easewilling to pay to park be of Location if I knew finding going to get a I was a spot convenient space for as long as I wanted to stay.
31%
58%
I avoid u because t
29
30
West Square east Square Proposed Garage Site Sources: May 15, 2009, Medford Police Parking inventory; MassGIS; nelson\nygaard; March 31, 2010 Parking open House
a. B. C. D. e.
High Street: Church demand for parking Armory/Medical offices use parking lot CvS is generator of walking traffic for other businesses no way to get to High Street from Main north; will not cross on foot; bus backs up traffic easy-to-find parking
1. 2. 3.
4.
5. 6.
e. f. g. h. i.
Good for all-day parking; should be business parking; needs shuttle and lighting three cars can park in front of Armory if lines are painted three cars can park in front of Rolands if lines are repainted and 1 hydrant is removed (2 hydrants within 15 feet) two cars can park in front of Historical Society Path should be lit and maintained for safety Lot/Garage should be for high turnover; needs to be large; connect garage to Chevalier theatre Zone for nonrush hour parking traffic calming zone 80 to 100 feet for busescould this space be better utilized? Lot needs better signage Place signage for nearby parking Good parking supplyDont take away these lots
31
a
A
c g d
b C
f i h
4 2 3 1 5 8 7 9 11 12 6 10
34
2b
1 2a
Pros
Cons
Historically well-used off High Street (back a layer) two means of entry/exit on mental map of parking options Adjacent to new restaurant / retail Close to Medford Square Medical nexus narrow site Adjacent to existing residential
Pros
Cons
near Chevalier theatre Close to center of Square two means of entry/exit Property acquisition and demolition
Pros
Cons
ease of access off I-93 Ample lot for efficient parking Parking surplus for future development Relatively far from center of Square traffic would need to be rerouted Possibly redundant to Harvard vanguard Garage
2b Chevalier Site
Pros
Cons
35
Four locations in Medford Square were considered as potential sites for the future garage. Of the sites studied, three are located in the West Square, a decision driven by Nelson\Nygaards assessment that the West is closer to reaching the need for extra supply (see pp. 2425 for a more extensive discussion of existing parking utilization rates). Although the project team initially considered the possibility of an underground garage on each of the four sites, preliminary cost estimate studies revealed that subterranean garage construction costs would total, by conservative measures, at least twice as much as equivalent above-grade garage construction. The economic feasibility of an underground garage on any of the considered sites seemed unrealistic based on high projected costs and modest revenue projections. Further study thus focused on above-ground garage options for all four sites. Each site was subject to a rigorous planning assessment; the surrounding building context and the possible entry and exit conditions were considered carefully before a maximum build-out scenario was drafted. This first assessment led to a concise pros and cons list for all four sites, information that ultimately assisted the client and project team in selecting the preferred site for further study. The drafted plans demonstrate a feasible structured parking solution for each parcel under consideration. While only one sitethe Governors Avenue Sitewas developed further, the other three options should be considered viable solutions for future study, should additional structured parking become necessary in the Square.
36
gove
rnors
Aven ue
High stre
et
bra
dle e
ro a
br
oo
ks
La
ne
High s treet
fo re
st
str e
et
br ad lee
ro ad
37
2b Chevalier Site
bradlee road
rive
rsid
e Av enu
ri
ng
ro ad
fo re
st
str ee
38
Level 5
Level 2
Level 1
39
Chevalier theatre
Post Office
The Governors Avenue Site was selected as a candidate for the potential garage for a host of reasons. It was the site of the previous garage (which collapsed in 2005; see pp. 7071), and continues to be a heavily used parking option for employees and customers of the West Square. In this first iteration, later refined, the garage was planned to maximize the site, in a zero-lot-line configuration. This and later options used the 10-foot topographical rise across the site to make use of two entrances, one at Bradlee Road (on the lowest portion of the site), and one at Governors Avenue (at the highest grade). Given the narrow width of the site and changes in the Massachusetts building code, it is impossible to fit an efficient two-bay doubleloaded plan. As a result, the four-and-a-half-floor garage yields 178 to 238 parking spaces, depending on its configuration on the site.
40
Level 2
Subterranean space
Level 1
41
Chevalier theatre
Post Office
87
The Forest Street Site currently hosts a vacant one-story commercial building that would be demolished to accommodate a future garage. Because of considerable grade change across the site (rising from Forest Street to Brooks Lane), this garage has two entrances, one into each level of the garage, and no internal ramping. The main entrance from Forest Street sits as far away from the Salem Street intersection as is possible, and allows for a shallow storefront buffer along the south end of the building. The ground floor is a flat plate of parking that would require minor excavation into the back of the site. The back entrance, accessed from Brooks Lane, leads to another flat plate of parking. The overall benefit of this scheme is its simplicity; also beneficial is its proximity to the Post Office and the Chevalier Theatre.
42
Level 2
Subterranean space
Level 1
43
Chevalier theatre
Post Office
While the Chevalier site does not immediately seem a viable location for a parking structure, two significant characteristics of the site caused it to be included in the study. Like the Forest Street site, its proximity to the under-parked Chevalier Theatre (in this case immediate adjacency), was its primary asset. Additionally, the extreme natural grade rising from Forest Street to Bradlee Road allows for a simple two-plate solution without a costly internal ramping system. Currently, the site is a surface parking lot, fully utilized throughout the day by Post Office employees and visitors to the Square. The main entrance to the ground floor is on Forest Street, and a back entrance to the upper level can be accessed from Bradlee Road. This scheme effectively doubles the number of spaces that can be accommodated on the site.
44
Levels 2-5
Level 1
45
City Hall
This parcel (located behind Medford City Hall) is the only site of the four considered located in the East Square. It was included in this study because it was identified in the 2005 Medford Square Master Plan as a preferred future garage site. Of all of the sites considered, it is the most unhampered by surrounding context; there are no immediately adjacent buildings, and the site itself is ample enough to hold a large, efficient two-bay double-loaded garage. This five-story scheme has one entrance accessed from City Hall Mall. In order to make vehicular access most convenient, City Hall Mall should be re-routed to become a two-way street, which could also allow easier access to the adjacent Harvard Vanguard Garage. Although there is no current need for extra parking supply in this section of the Square, such a garage could be built as a parking bank to encourage future development on nearby underutilized sites.
48
toP: the intersection of High Street, Forest Street, Main Street, Riverside Avenue, and Salem Street. FAR LeFt: Signage on High Street at the intersection with Governors Avenue directs drivers to the existing surface parking lot at the proposed garage site. LeFt, toP AnD BottoM, AnD ABove: Signage in Medford Square.
49
50
Supply Enhancement
In the course of collecting parking inventory information and observing walking conditions, the consultant team observed a number of locations where additional on-street parking could be added. Several locations were already used for parking, even though signs in these locations indicated No Parking. Overall, nearly 80 such spaces were identifiedmostly in the eastern half of the Square. With the planned re-alignment of Clippership Drive resulting in a net loss of 10 spaces, on-street additions elsewhere will see a net gain of approximately 30 spaces in the Squaresimply through the use of paint and signs.
51
+10
additional spaces
~30
86
+2 +2
+3
+7 +7
+8
-10
52
no-park box to allow for emergency vehicle access onto Forest Street
fo r
two-way traffic on Salem Street
High
new pedestrian plazas created on all corners of the intersection, to increase public space and shorten crossing distance
stree t
es
ts tre
et
salem str
eet
rive
rside
Aven ue
ai
st re
et
rin
gr oa
ABove: Reconfiguration of the main intersection would greatly improve the pedestrian experience in the Square by shortening the crossing distance and delay, and would also effectively free up additional parking spaces on the east Square to patrons of the West Square. LeFt: existing condition at the intersection of High Street, Forest Street, Main Street, Riverside Avenue, and Salem Street. FACInG PAGe: the existing Level of Service of the intersection informed the above recommendations.
53
41 41 to 60seconds High to 60 seconds 31 31 to 40 seconds Moderate-High to 40 seconds 21 21 to 30 seconds Moderate to 30 seconds 1010 to 20seconds Moderate-Low to 20 seconds
< seconds <10 10 seconds
Low
for e
st A ven u
High and Main streets intersect with Salem Street, Forest Street, and Riverside Avenue at the core of Medford Square. This five-legged intersection includes medians and islands on two crosswalks, breaking up the pedestrian crossing experience. The intersections signal was timed by the consultant team to calculate average pedestrian delay. While the average amount of pedestrian delay is low (good pedestrian level-of-service) for each individual crosswalk, the cumulative effect of needing to cross as many as three smaller crosswalks to get across the intersectionplus the fact that the maximum delay on each crosswalk is poorresults in a significant barrier to circulation between the east and west sides of the square. Whereas no signal delay would enable the customers of businesses near High Street and Governors Avenue to access the underutilized parking spaces near City Hall with a 5-minute walk, the current signal operation means that a parker near City Hall cannot get across the main intersection in 5 minutes on foot.
Delay GivenTime high pedestrian crossing delay observed at the interthe Pedestrian Noncompliance > 60 seconds Very High sectionseconds High and Main streets, nelson\nygaard began to test of High 41 to 60 intersection improvements that would reduce crossing delays 31 to 40 seconds while30 seconds Moderate vehicular capacity of the intersection. It was 21 to preserving the 10 to 20 seconds determined that re-orienting the Forest Street approach to intersect Low < 10 seconds only with Salem Street could preserve all operations and levels of service while converting the intersection to a standard four-way with shorter crossings and no medians. The solution warrants more detailed evaluation, but models show little change in vehicular delay and notable improvements to pedestrian delay, enabling many more parking spaces that are vacant today to be accessed from Square businesses within a 5-minute walk. Likelihood of
High
stre e
salem
rive
rsid
Ma
in s tre
et
High
stre e
for e
st A ven u
High Street and Governors Avenue safety conditions and crossing delays were also evaluated by the consultant. Simple curb extensions at this location would have a significant safety advantage while Likelihood of noticeably reducing the crossing distance. This would result in lower Pedestrian Level of Service Delay Timedelays and more parking supply within a short walk. crossing Noncompliance
F
> 60 seconds
salem
Very High
rive
rsid
Ma
in s tre
et
41 to 60 seconds High By making improvements to these two intersections, the consultant 31 to 40 seconds Moderate-High D determined that 208 vacant parking spaces would become acces21 to 30 seconds Moderate C sible within a 5-minute walk of the Governors Avenue lot, allowing 10 to 20 seconds Moderate-Low B nearly 90 more cars to be parked nearby before reaching the ideal A < 10 seconds Low 85 percent utilization rate.
54
proposed Delay, accomplished with conceptual intersection improvements shown on previous pages
um Delay
93
Ma
xim
No
D el ay
55
proposed Delay
De la y
No
ax im
um
De la y
93
Clippership Lot
56
1 Create order
3 Create crossings
5 Complete sidewalk
8 Remove poles
14 Remove fencing
57
3 2 5
4 1 7
6 8 10 9 11 12
15 16
14
13
1. 2. 3. 4. 5. 6. 7. 8. 9. 10.
Create order Add wayfinding signage Create crossings Improve sight lines Complete sidewalk Improve sidewalk slope Add curb ramp Remove poles Make no Right on Red Reduce speeds
Reduce speeds Reduce speeds Create crossings Remove fencing Widen median protection; repaint crossings; reconstruct curb and walkway Reconstruct curb and walkway
58
59
Eliminate Time Limits The current time limits are only appropriate for a limited number of parkers in the Square. If demand-responsive pricing is in place, time limits are unnecessary as cost will encourage turnover in time intervals that better match the real needs of those working, visiting, or residing in the Square. Use Multi-Space Meters New payment technologies have dramatically improved the ease of payment, enforcement, and revenue collection for paid parking spaces. Multi-space meters have significantly fewer streetscape impacts, as one unit can serve many spaces. They offer features such as credit card payment, payment by cell phone, remote recharging from different points in the Square, and transmission of space availability information to mobile devices and the internet. A pay-by-space system is recommended with space numbers posted on buildings or curbside. Expand Parking Permit Program Utilizing the same demandresponsive approach that should be implemented for public parking, employees, commuters, and residents should have different tiers of long-term monthly parking available for purchase on a monthly basis. Financial Impact Utilizing the modeled pricing structure, Nelson\Nygaard estimated that surplus annual funds could be generated for the City that would be best directed to improvements in the Square, such as signing, landscaping, and pedestrian or bicycle amenities. Local management of the parking system would result in greater surpluses versus contracting with a private vendor for operations and enforcement.
60
Scenario a
86
Hourly Parking
High-demand Parking $$$ Moderate-demand Parking $$ Long-term Parking $ Free Parking
Permit Parking
Garage Parking West Square $ east Square employee Parking Proposed Garage Site $$ Residential Parking # existing Parking Spaces $ Residential Parking 5PM-8AM weekdays and weekends employee Parking 8AM-5PM weekdays $
61
Scenario B
86
62
Annual Revenue by Hourly Paid Space Total Annual Revenue per $2,606 High-Demand Space Total Annual Revenue per $1,564 Moderate-Demand Space Total Annual Revenue per $1,043 Long-Term Space Revenue at Existing Utilization Rates Total Annual High-Demand $165,000 Parking (77% utilized) Total Annual Visitor Parking (66% $274,000 utilized) Total Annual General Parking $165,000 (51% utilized) Total Annual Hourly $603,000 Paid Parking Revenue Revenue at Target Utilization Rate (85%) Total Annual Customer Parking $182,000 Total Annual Visitor Parking $352,000 Total Annual General Parking $275,000 Total Annual Hourly $809,000 Paid Parking Revenue
63
Monthly Permit Fee Structure Garage Permits (75% of Probable Capacity) Hours of Operation Monthly Fee Employee Permits Hours of Operation Monthly Fee Residential Permits Hours of Operation First Permit (Annually) Second Permit (Annually) Third & Each Additional Permit (Annually)
135 9AM to 5PM $60 525 9AM to 5:30PM $15 N/A 5:30PM to 9AM $10 $30 $100
Annual Parking System Revenues Paid Parking Revenue $603,000 Permit Revenue $185,000 (Optimal Garage Capacity) Enforcement Revenue (Est.) $250,000 Total $1,038,000 Annual Parking System Costs (self-financed) Equipment Service, Maintenance $75,000 (30 pay stations) Personnel $250,000 Total after Maintenance $713,000 and Operations Annual Parking System Costs (privately-financed)* Service Contract Estimate $800,000 Personnel $65,000 Total after Maintenance $173,000 and Operations * The privately financed option is based upon an assump-
Annual Revenue by Permit Total Annual Revenue per Garage $720 Permit Total Annual Revenue per $180 Employee Permit Total Annual Revenue per $10; $30; $100 Residential Permit Annual Permit Revenue Garage Permit Revenue (180 spaces) Employee Permit Revenue (525 permits) Total Annual Permit Revenue $90,720 $94,500 $185,220
tion that private vendors typically offer an annual payment to the municipality in exchange for collecting and retaining all enforcement revenues. The scenario above assumes an annual payment of approximately $250,000 to the municipality ($1,038,000 in revenues, minus this $250,000 payment, reveals the Service Contract Estimate of approximately $800,000). One City staffer at half-time would still be required to manage the relationship with the vendor.
64
Signing Plan
Transitioning from a time-limited enforcement system to a pay-asyou-go unlimited parking system can be very simple to describe to the traveling public. Other than special regulations for buses, loading, or safety clearances, all existing parking regulatory signs can be removed. Simple pay for parking signs can be placed at entry points to each pricing zone, with the only additional signs at the multi-space meters themselves. Adhesive stickers indicating the hourly charge can be placed on signs within certain zones. Such stickers can be replaced easily if the pricing structure changes. Similar barrier signs can be used on residential streets and along streets used for lowrate monthly paid parking.
65
68
offices
bra
dlee
roa d
Residential Building
the Governors Avenue site is currently a 70-space municipal parking lot. As the images suggest, it is almost always filled to capacity.
Hig h
stre e
69
Site Description
The Governors Avenue parking lot, the preferred site for further study, is located immediately adjacent to the center of activity in the west half of Medford Square. The edge dimensions of the trapezoidal parcel are approximately 244 feet to the north, 108 feet to the east, 215 feet to the south, and 115 to the west, resulting in an overall site area of 25,848 square feet. The site is bounded on the east by Bradlee Road and on the west by Governors Avenue. To the immediate north of site, sitting above significant retaining walls, is a five-story brick residential building and a small office building. The southernmost quadrant of the block, facing High Street, is occupied by several retail and restaurant storefronts. Currently, the site is occupied by a sloping 70-space surface parking lot. The topography on the site is notable. From its highest point at the northwest corner of the lot (facing Governors Avenue) to its lowest elevation at its southeast corner (facing Bradlee Road), the site drops approximately 10 feet. The abutting retail storefronts that face onto High Street are all single-story structures, with the exception of Gaffey Funeral Services.
the highest point of the site is on the northwest corner, where the lot meets the residential building. Retaining walls, remnants of the foundation of the previous garage, define this corner.
70
Elevations
Typical Plan
ABove: Drawings of the previous garage, which was demolished in 2005. In discussions with the City and the public during the Parking open House, the team noted generally negative public perception of the previous garages appearance. With a heavy, opaque concrete enclosure, and little natural light or transparency, the design of the garage limited visual connection between inside and outside, and this lack of visibility contributed to a reduced sense of security among many parkers.
71
Previous Garage
From 1983 to 2005, a 164-space, two-and-a-half-level garage existed on the Governors Avenue site. Building and zoning codes in effect during the construction of this garage allowed for much denser occupation of the site than could be achieved in the current regulatory climate. The width of parking stalls was then much narrower than current building code allows, and drive aisles were similarly less generous. Additionally, the garage presented significant barriers to handicapped accessibility: it lacked an elevator to connect all three parking levels, and offered too few designated accessible parking stalls. It is important to note that any contemporary garage on this site would thus not achieve the same density. according to the 2005 Medford Square Master Plan, occupancy of the previous garage was consistently high, reaching 84 percent occupancy in the morning hours and more than 90 percent occupancy in the afternoon hours. In their recent analysis of the site, nelson\ Nygaard observed similarly high occupancy in the current surface lot, which houses approximately 70 cars. The previous garage was demolished in the spring of 2005, after the top floor collapsed.
the previous garage occupied virtually the entire footprint of the site. It was a two-and-a-half-story concrete building with very few openings to allow for ventilation and daylighting.
72
Zero-lot-line building 10
238
spaces
10
15
30 15
178
spaces
73
74
75
once the plans were in place, simple digital massing models of both options were built to test the visual impact of the garage on the site from various perspectives. these perspectives helped the client and design team to arrive at a decision to forward the Partial Site option, as the Full Site Garage was too massive and intrusive in the context. Ultimately, the conceptual design was a refinement of the Partial Site option. In the refined scheme, seen in Section vI of this report, the architecture and massing were adjusted to break down the bulk of the building while maintaining the maximum number of parking spaces. toP: entry to the Partial Site Garage from Governors Avenue. MIDDLe: the Full Site Garage from Governors Avenue. RIGHt: the existing surface lot.
76
Site Impacts
Given that a garage previously occupied the site, and that the site currently hosts a well-used surface lot, it can be inferred that a parking use is compatible with this location. Numerous business owners and customers of the West Square who attended both the Parking Open House and the Public Meeting expressed support for a new garage on this site, for the relief it will offer to the perceived parking deficit in this half of the Square. Among those most likely to utilize the garage are patients and visitors to the nearby medical offices, employees and customers of High Street businesses, and evening patrons of the Chevalier Theatre. Although the Governors Avenue site is zoned as a zero-lot-line parcel, the options forwarded in this study acknowledge the contextual and functional need for setbacks on the southern and northern edges of the site. While the adjacent businesses to the south use their High Street addresses as the primary means of entry and access, these businesses also have secondary or service entries currently accessed from a narrow passageway to the rear of their buildings, directly off of the current parking lot. In addition, the team looked at both the vehicular and visual impact of a new garage on the surrounding streets and buildings. The existing residential and office buildings to the north, which sit very close to the lot line, were carefully considered in the garage massing strategies.
LeFt AnD MIDDLe: Local businesses in Medford Square. ABove: A medical office building at the corner of High Street and Governors Avenue.
77
Chevalier theatre
78
Cheva li theat er re
High/Forest Path
this pathway takes advantage of the already-extant City sidewalks and the pleasant atmosphere of the Square, ultimately offering the most potential activity to the center of the Square. Although it is a few steps longer than the other options, it requires virtually no capital improvements. Wayfinding signage between the garage and Chevalier to highlight this route is the only suggested improvement. this is the recommended pathway.
er oa
dle
bra
High s treet
fo re
st
str ee
79
Brooks Lane Path 805 feet = 0.15 miles = 3 minutes High/Forest Path 957 feet = 0.18 miles = 3.6 minutes
Pedestrian Impacts
the design team initially considered several possible routes between the Governors Avenue site and Chevalier theatre that prioritized, to varying degrees, the shortest route between the two structures, the most visually interesting route, and the path with the least topographic change (and thus the least costly intervention). In order to optimize all of these concerns, the project team arrived at the conclusion that the pedestrian route along High Street and up Forest Avenue maximized efficiency and pedestrian experience while minimizing costs.
80
+33
+28
to navigate the 5-foot difference in grade between the back passageway (33-foot elevation) and the building interiors (28-foot elevation), the existing courtyard space would be re-graded to the 28-foot level, and a stair and accessible ramp would be inserted. BeLoW, LeFt: the rear exit to a local restaurant faces the Governors Avenue site. BeLoW, RIGHt: the existing underutilized pocket of space.
81
Impacts to Access
High Street Buildings: Back entrance
The retail buildings on High Street that back up to the potential garage site are zero-lot-line buildings: they sit exactly on the parcel line. The previous garage on this site was set back approximately three feet to allow for a service passageway between the garage and these buildings. In the massing schemes for the future garage, the new building allows for a more generous five-foot passageway between the garage and the retail buildings. The slope along the passageway length rises gradually from Bradlee Road to Governors Avenue, and with slight grading adjustments, can be fashioned into a handicapped-accessible route from the garage to the rear of the High Street buildings. an existing, underutilized pocket of space in the center of this block can be re-graded to match the floor level of the retail buildings, and a stair and accessible ramp inserted to create a pleasant entry space to access all abutting buildings.
In addition to making the passageway wood-clad (a boardwalk), buildingmounted lighting along the passageway and suspended lighting above the new entry space could create a pleasant evening experience for patrons of future restaurants housed in these buildings. exterior seating could also be considered for this space.
82
Vehicular Impacts
A new parking garage in Medford Square of approximately 180 vehicular spaces, and a minimum of 22 bike spaces, can be expected to see a worst-case volume of 110 entering cars in the morning peak hour and 110 existing in the evening peak hour. Utilizing census data and existing vehicle turning movement counts at the intersections of High and Main streets, and High Street and Governors Avenue, the consultant team distributed potential garage traffic through these intersections in each peak hour. The High Street and Main Street intersection processes a significant volume of traffic in each peak hourapproximately 3,000 carsand would be almost entirely unaffected by a new garage adding less than 100 new vehicles in either peak hour to the intersections least congested movements. The High Street and Governors Avenue intersection processes 1,100 cars in the morning peak with a 7-car queue on stop-controlled Governors Avenue, which contributes to a Level of Service (LOS) E. However, the garage would be served by an entrance off of Governors Avenue north of High Street, resulting in no impact to this intersection in the morning. In the evening, the Governors Avenue queue today is only 3 cars on average, but the exiting garage will add up to another 6 cars to this queue. The intersection would drop from a LOS D to LOS E with a 9-car queue extending up Governors Avenue near the garage exit. While a traffic signal at Governors Avenue and High Street would solve this situation, the delay is acceptable for a stop-controlled minor street. It is advisable to observe actual conditions before proceeding with new traffic controls. Nonetheless, this intersection would benefit from improved geometry that would increase driver sight lines compromised today
Level of service C 21-30 Second Delay D 31-40 Second Delay e 41-50 Second Delay % of the cars moving through this intersection, this percent leaves in this direction Illegal turn
ors Ave
existing Operations
PM Peak (All traffic) on average, 3-car queue in the PM peak hours. nelson\nygaard observed 57 cars turning left onto High Street from Governors Avenue. Currently, illegal left turns from Bradlee Road onto High Street cause delays.
nue
20%
govern
er oad
bra
15% D
broo
ks Ln
for e
dle
st s tree
High
stre e
t
25%
salem
t stree
40%
Ma
in
str e
et
83
by cars parked in and close to the intersection. Simple curb extensions clearing cars back as little as ten feet at the corners and removing parked cars from the intersection would allow Governors Avenue motorists to merge into High Street traffic more safely, reducing perceived delay. Furthermore, the curb extensions would greatly improve pedestrian safety and reduce crossing delays, capturing more existing parking spaces within a short walk of the Squares businesses.
Recommendations
With the addition of a 180-space garage in this area of Medford Square, nelson\nygaard recommends the following actions to alleviate the traffic impacts listed below:
1. 1
2 2.
Reversal of Bradlee Road direction in this block will eliminate the threat of illegal left turns. Installation of curb extensions will aid sight lines and reduce crossing delays.
ors Ave
180-space Garage
PM Peak (All traffic) of the cars pulling out of the garage, it is estimated that 22 would turn right, and 71 would turn left. on average, 7-car queue in the PM peak hours. nelson\nygaard estimates 99 cars would turn left onto High Street from Governors Avenue. of cars leaving the garage on Bradlee Road, an estimated 17 would turn right onto High Street. 15%
port e
r ro
ad
20%
govern
dle
broo
ks Ln
bra
for e
st s tree
er oad
High
stre e
t
25%
salem
t stree
40%
Ma
in
str e
et
84
Lan
Governors
Bradlee R
oad
85
88
Design Approaches
Two options for the design approach to the garage were tested to provide two price models and an opportunity for the community to weigh in on two compelling but strongly differentiated approaches. The Brick Garage is modeled on early twentieth-century commercial and mill buildings typical to Massachusetts cities and towns. Each structural module is subdivided into two bays defined by thick pilasters that stretch between the base and the top of the wall. A brick corbel above the upper window head helps make this transition between the pilasters and the upper zone of the facade. Brick spandrels of a slightly darker color define the parapet at each parking level. The brick of the base, pilasters, and top of the wall should closely match that of the neighboring apartment building. The garage option is meant to be timeless in style and look like it was always there. as a result, the building will not call attention to itself, despite its relatively large size. The Brick Garage is supported by a cast-in-place system of concrete columns and beams, and its structure is concealed behind the pilasters and recessed spandrel panels described above. This specific structural system was selected in order to minimize the height of the spandrel condition, thereby allowing the tallest opening possible at each level to support natural ventilation. Specifically, the state building code mandates that 40 percent of the garages total facade area remain free and open in order to avoid the requirement for a costly mechanical ventilation system in the structure. (See the Appendix for relevant excerpts of the Massachusetts State Building Code that define this condition.)
89
The second garage option, the Green Garage, uses natural vegetation rather than a masonry skin to give character and distinction to the garage. To avoid the need for difficult-to-maintain irrigation, the vegetation is planted in the ground around the perimeter of the buildingincluding a vine pocket along the alley on the south side of the garage. Since it will take several years for the ivies to cover the garage, the supporting trellis is intended to be visually interesting in its own right; the slightly canted poles are meant to represent the view through a dense forest. In contrast to the vegetated walls, glass stair lanterns are proposed in the two corners closest to High Street. A mix of glass colors will create a memorable evening landmark as it welcomes visitors to the restaurants in the Medford Square. Because the entire facade is porous and open, the Green Garage meets the Massachusetts Building Codes 40 percent open facade area requirement without having to limit itself to a specific structural logic. The Green Garage employs a different structural strategy than its brick counterpart; this option employs a slender steel frame of columns and girders to support precast concrete double-tee beams. The Green Garage exposes its structure, offering glimpses of itself through the vegetated walls. Such a hybrid structural system is often less expensive than a cast-in-place equivalent, and in many cases can be erected faster since it requires no formwork and is not dependent on favorable weather conditions. Having considered many structural strategies, the design team ultimately chose to pair the two garage schemes with specific structural systems that meet the respective functional and aesthetic goals of each. In forwarding a distinct structural strategy for each scheme, the team was able to explore two varied structural strategies that are conceivably interchangeable. (Please refer to the Appendix for more detailed structural and cost estimating information.)
90
Brick Garage
tHIS PAGe: A brick building on Melcher Street, in the Fort Point neighborhood of Boston. the brick corbeling detail at the top of the final full-height window was a detail that was utilized in the Brick Garage option. FACInG PAGe: this commercial building on the corner of High and Forest streets in Medford Square is an excellent example of early twentiethcentury commercial architecture. the strong vertical pilasters and recessed spandrel panels create depth and visual interest on the facade.
91
92
e gov
rs rno
nu Ave
dl bra
ee
d roa
Hig tre hs et
93
94
95
96
97
98
Bike parking
Storage 460 SF
810 SF
Compact
Floor 1
178 22+
bikes cars
99
open corner to minimize garage scale and provide inviting entry into passageway
Floor 2
100
Floor 5
Floor 4
Floor 3
25
50
100
101
102
Green Garage
103
104
e gov
rs rno
nu Ave
dl bra
ee
d roa
Hig tre hs et
105
Glassy object stair for visual interest and safety entry canopy from Governors Avenue
106
107
108
109
110
Bike parking
Compact
Glass stair for safety and visual interest Green screen entry to handicappedaccessible passageway
Floor 1
180 22+
bikes cars
111
Green screen
Glassy corner stair for safety, visual interest, and to provide an inviting entry into passageway
Floor 2
112
Floor 5
Floor 4
Floor 3
25
50
100
113
$/SF n/a n/a $5.27 $20.55 $15.20 $6.56 $0.38 $3.14 $3.27 $1.68 $0.02 $13.27 $69.33 $5.55 $74.88 $2.25 $77.13 $0.77 $77.90 $7.79 $85.69 n/a $85.69 $39,711.87
vII. Conclusions
116
Garage
Build Garage to Accommodate Future Development A new parking garage in Medford Square is needed to accommodate future development and occupancy of existing vacant space in the western half of the Square, where parking utilization rates within a short walk are already at 85 percent. The eastern half of the Square has hundreds of vacant spaces already.
Locate in the West Square A four-and-a-half-story municipal parking garage should be built on the existing surface parking lot located between Governors Avenue and Bradlee Road. Given the narrowness of the site, this garage will have a capacity of 178 parking spaces and a minimum of 22 bike spaces. This capacity is adequate to meet the future economic development of Medford Square if the garage is part of a larger parking management plan for the Downtown area.
Demand Distinctive Architecture This new garage should be architecturally distinctive, so that it can contribute positively to the ongoing success of Medford Square. Solar panels and other sustainable features should be included in the ultimate design to elevate the garage to ground-breaking status within the Commonwealth.
Vii. conclusions
117
Improve Five-legged Intersection in Medford Square With simple intersection improvements that reduce existing walking delays, the potential to access up to 90 additional vacant spaces exists today, without exceeding 85 percent utilization.
Institute Pricing Program A demand-responsive priced parking management system in the Square can equitably assure available parking spaces for all user groups, including assuring long-term spaces for employees and convenient front-door spaces for customers.
118
Bioswale
Willamette River Park, Portland, Oregon
Bioswales are landscape elements that remove silt and pollution from surface runoff water. Built in 1996, this bioswale in Portland, oregon, captures pollutant runoff and prevents it from entering the Willamette River.
Photovoltaic Trellis
Arizona State University Stadium Parking Structure, Mesa, arizona
this solar panel trellis on top of a stadium parking lot produces approximately 1,425 megawatt hours per year. In addition to producing clean energy, the trellis provides shading for cars on the top level of the garage, and reduces the heat island effect of the structure.
Bicycle Parking
Forest Hills T Station, Boston, Massachusetts
In September 2009, a covered bicycle cage opened at the Forest Hills t Station in Bostons Jamaica Plain neighborhood. the bike cage has space for 100 bikes, it is enclosed by a chain-link fence, lit at night, and is equipped with security cameras.
Vii. conclusions
119
Sustainability
To promote the image of the City of Medford as a forward-thinking municipality, and to capture additional (and varying) funding, it is recommended that the City maximize the number of sustainable features in the new garage. Both garage options include photovoltaic (solar) panels held above the top parking level on a lightweight steel trellis. In an initial analysis of quantities of photovoltaic panels and likely electric load, the garage can strive to be a Zero Net Energy garagethe first of its kind in the Commonwealth of Massachusetts. The solar-collecting structure has been located and dimensioned to be visible from the street, but set back enough from the upper parapet so that it does not dominate the visual image of the garage. In addition to the solar panels, the design team for the garage should also look for sustainable approaches to storm water management and the specification of building systems. Both conceptual plans assumed at least 40 percent openings on the exterior envelope, to ensure that mechanical ventilation will not be necessary, and that daylighting will better contribute to the garages illumination. The parcels open space to the north of the garage structure may be a suitable location for a bioswale and/or a rain garden that can slow the rate of runoff entering the Citys storm water sewer system. If the structure is branded as the Green Garage, it will be a groundbreaking project, bringing positive attention to the City.
120
Car-sharing spaces Car-sharing services are widespread in the Boston area and their use is growing rapidly. Car-sharing spaces in the garage will provide local residents and businesses with an affordable and convenient mode of transportation. Increased use of car sharing services correlates to fewer cars owned and thus fewer cars parked on streets, less traffic congestion., and fewer emissions. electric car recharging stations Fast-charging plugs for electric cars will support those community members who choose to drive emissionsfree vehicles. Bioswale in the gap between garage and northern neighbors
Providing a bioswale along the north edge of the garage will help mitigate the effects of storm water runoff from the garage. Soil and plants in this zone will filter pollutants out of the effluent before it returns to the groundwater supply. Additionally, storm water runoff will also provide any necessary irrigation to the shade-tolerant tree grove in this area.
LeD lighting LeD light bulbs are long-lasting, durable, mercury-free, extremely energy efficient, cost-effective, and do no cause heat build-up. Photovoltaic panels on roof Photovoltaic panels supported on a steel
trellis above the uppermost level of parking will supply the garage with the electricity it needs to light the structure at night and power the parking meter system. Because the garage will supply its own electrical needs through the rooftop solar collection system alone, the structure can strive to become Massachusettss first Zero net energy garage.
40 percent minimum exterior openings on facades openings on the facade will allow daylight and natural ventilation in the garage. According to the Massachusetts building code, the garage will not require mechanical ventilation if at least 40 percent of the exterior is left open, thus greatly lowering the overall energy use of the structure. Plantings Plants provide shade and visual interest. the Green Garages evergreen ivy screen will enliven Downtown Medford and provide a visual barrier between the residential building to the north and the garage. evergreen ivy could also feature on the portion of the Brick Garages solid facade that faces High Street. A grove of shade-tolerant trees lining the area between the garage and neighboring residential building will provide a visual and acoustic buffer.
Vii. conclusions
121
5 6
4 Bioswale
5 LeD lighting
6 Photovoltaic panels
8 Green screen
vIII. Appendix
124
Bibliography
Previous Studies
City of Medford, MA, Parking Advisory Committee Report, prepared by City of Medford Parking Advisory Committee and presented to Mayor Michael J. McGlynn, September 30, 2009. Medford Square Master Plan, prepared by Sasaki associates, Inc., Abramson & Associates, Howard/Stein-Hudson Associates, Inc., and Todreas Hanley Associates, Inc., November 2005. Medford Square and the Mystic River: Reconnection, Revitalization, Redevelopment, prepared by Massachusetts Institute of Technology Department of Urban Studies and Planning, Community Growth and Land Use Planning, Fall 2006. Appendices, Medford Square and the Mystic River: Reconnection, Revitalization, Redevelopment, prepared by Massachusetts Institute of Technology Department of Urban Studies and Planning, Community Growth and Land Use Planning, Fall 2006. Parking Space Count, memo prepared by Sergeant Carroll, Medford Police Department, May 15, 2009.
Viii. appendix
125
MEDFORD SQUARE
City of Medford, Massachusetts Massachusetts Institute of Technology Department of Urban Studies and Planning Community Growth and Land Use Planning | Fall 2006
126
Viii. appendix
127
128
Viii. appendix
129
130
Viii. appendix
131
132
Memorandum
Medford Garage Feasibility Study
Massachusetts Historical Commission Section 106 review, Determination of effect on Historical properties under MGL Ch9, S.26027C amended by Ch.254 (950CMR 71).
Massachusetts Water Resources Authority Construction Dewatering and Sewage Discharge Permits
Viii. appendix
133
NEPA DEP Oil and Water Separator Permit Underground Storage Tank (UST) Permit (if there is to be any fuel on site) Surface Water and Groundwater Discharge Permits Approval of Plans and Specs pursuant to Federal and State Clean Air Acts (CH. 111) Fuel Utilization Facility Approval (Limited Plan) Notice of Construction or Demolition Sewer Extension/Connection Permit Cross-connection Permit EIS: Environmental Impact Statement **
If there is to be more than 1 acre of disturbance: EPA NPDES SWPPP (National Pollutant Discharge Elimination System / Storm Water Pollution Prevention Plan) *
* Construction Phase Permit, to be obtained by General Contractor of project ** May be required if Federal funds are used to finance the garage construction
Memo prepared by Utile, in collaboration with MassDevelopment and Samiotes Consultants, Inc.
134
This memorandum is to apprise you of potential thresholds that may be exceeded for the abovementioned project requiring a Massachusetts Environmental Policy Act (MEPA) filing. Some of these assumptions regarding the project thresholds are based on plans and data provided by the City of Medford, Utile, Inc, Nelson/Nygaard Consulting Associates and McPhail Associates. MEPA review is not a permitting process. MEPA requires public study, disclosure, and development of feasible mitigation for a proposed project. It does not pass judgment on whether a project is environmentally beneficial, or whether a project can or should receive a particular permit. Those decisions are left to the permitting agencies. MEPA review occurs before permitting agencies act, to ensure that the agencies know the environmental consequences of their actions. MEPA provides the mechanism through which this information collection and mitigation mandate is executed. The primary mechanism is known as an Environmental Impact Report EIR, a lower threshold filing is an Environmental Notification Form (ENF). MEPA empowers the Secretary of Environmental Affairs to oversee the review process. The process is public and encourages comments from the public and from state, regional and local agencies. 301 CMR 11.00 establishes review thresholds that identify categories of Projects or aspects thereof of a nature, size or location that are likely, directly or indirectly, to cause damage to the Environment. Except when the Secretary requires fail-safe review, the review thresholds determine whether MEPA review is required. MEPA review is required when one or more review thresholds are met or exceeded and the subject matter of at least one review threshold is within MEPA jurisdiction.
Environmental Monitor.
MEPA filing deadlines are the 15th and last day of each month to make publication in the next
The following summarizes the thresholds (pertinent to the project) required for MEPA review: 1) Land a) ENF and Mandatory EIR 1. Direct alteration of 50 or more acres of land, unless the Project is consistent with an approved conservation farm plan or forest cutting plan or other similar generally accepted agricultural or forestry practices. 2. Creation of ten or more acres of impervious area.
Samiotes Consultants, Inc. Civil Engineers + Land Surveyors 20 A Street Framingham, MA 01701-4102 T 508.877.6688 F 508.877.8349 www.samiotes.com
Viii. appendix
135
Page 2 Preliminary MEPA threshold review June 17, 2010 Governors Ave. Garage / Medford
b) ENF and Other MEPA Review if the Secretary So Requires 1. Direct alteration of 25 or more acres of land, unless the Project is consistent with an approved conservation farm plan or forest cutting plan or other similar generally accepted agricultural or forestry practices. 2. Creation of five or more acres of impervious area. 3. Conversion of land held for natural resources purposes in accordance with Article 97 of the Amendments to the Constitution of the Commonwealth to any purpose not in accordance with Article 97. 4. Conversion of land in active agricultural use to nonagricultural use, provided the land includes soils classified as prime, state-important or unique by the United States Department of Agriculture, unless the Project is accessory to active agricultural use or consists solely of one single family dwelling. 5. Release of an interest in land held for conservation, preservation or agricultural or watershed preservation purposes. 6. Approval in accordance with M.G.L. c. 121A of a New urban redevelopment project or a fundamental change in an approved urban redevelopment project, provided that the Project consists of 100 or more dwelling units or 50,000 or more sf of non-residential space. 7. Approval in accordance with M.G.L. c. 121B of a New urban renewal plan or a major modification of an existing urban renewal plan.
b) ENF and Other MEPA Review if the Secretary So Requires 1. Alteration of designated significant habitat. 2. Greater than two acres of disturbance of designated priority habitat, as defined in 321 CMR 10.02, that results in a take of a state-listed endangered or threatened species or species of special concern.
The project site is not within a designated significant habitat or a Priority Site of Rare Species Habitats according to the latest Natural Heritage Map.
3) Wetlands, Waterways and Tidelands a) ENF and Mandatory EIR 1. Provided that a Permit is required: a. alteration of one or more acres of salt marsh or bordering vegetating wetlands; or b. alteration of ten or more acres of any other wetlands. 2. Alteration requiring a variance in accordance with the Wetlands Protection Act. 3. Construction of a New dam. 4. Structural alteration of an existing dam that causes an Expansion of 20% or any decrease in impoundment Capacity. 5. Provided that a Chapter 91 License is required, New non-water dependent use or Expansion of an existing nonwater dependent structure, provided the use or structure occupies one or more acres of waterways or tidelands.
The project does not meet the EIR thresholds for Wetlands, Waterways and Tidelands
b) ENF and Other MEPA Review if the Secretary So Requires 1. Provided that a Permit is required:
136
Page 3 Preliminary MEPA threshold review June 17, 2010 Governors Ave. Garage / Medford
alteration of coastal dune, barrier beach or coastal bank; alteration of 500 or more linear feet of bank along a fish run or inland bank; alteration of 1,000 or more sf of salt marsh or outstanding resource waters; alteration of 5,000 or more sf of bordering or isolated vegetated wetlands; New fill or structure or Expansion of existing fill or structure, except a pile-supported structure, in a velocity zone or regulatory floodway; or f. alteration of one half or more acres of any other wetlands. 2. Construction of a New roadway or bridge providing access to a barrier beach or a New utility line providing service to a structure on a barrier beach. 3. Dredging of 10,000 or more cy of material. 4. Disposal of 10,000 or more cy of dredged material, unless at a designated in-water disposal site. 5. Provided that a Chapter 91 License is required, New or existing unlicensed non-water dependent use of waterways or tidelands, unless the Project is an overhead utility line, a structure of 1,000 or less sf base area accessory to a single family dwelling, a temporary use in a designated port area, or an existing unlicensed structure in use prior to January 1, 1984. 6. Construction, reconstruction or Expansion of an existing solid fill structure of 1,000 or more sf base area or of a pile-supported or bottom-anchored structure of 2,000 or more sf base area, except a seasonal, pile-held or bottom-anchored float, provided the structure occupies flowed tidelands or other waterways.
a. b. c. d. e.
The project is under the ENF threshold for Wetlands, Waterways, and Tidelands. The work proposed is not in a Velocity Zone or Regulatory Floodway according to the latest FEMA maps.
4) Water a) ENF and Mandatory EIR 1. New withdrawal or Expansion in withdrawal of: a. 2,500,000 or more gpd from a surface water source; or b. 1,500,000 or more gpd from a groundwater source. 2. New interbasin transfer of water of 1,000,000 or more gpd or any amount determined significant by the Water Resources Commission. 3. Construction of one or more New water mains ten or more miles in length. 4. Provided that the Project is undertaken by an Agency, New water service to a municipality or water district across a municipal boundary through New or existing pipelines, unless a disruption of service emergency is declared in accordance with applicable statutes and regulations.
Viii. appendix
137
Page 4 Preliminary MEPA threshold review June 17, 2010 Governors Ave. Garage / Medford
7. Non-bridged stream crossing 1,000 or less feet upstream of a public surface drinking water supply for purpose of forest harvesting activities.
138
Page 5 Preliminary MEPA threshold review June 17, 2010 Governors Ave. Garage / Medford
The project does not meet the EIR thresholds for Traffic.
b) ENF and Other MEPA Review if the Secretary So Requires 1. Unless the Project consists solely of an internal or on-site roadway or is located entirely on the site of a nonroadway Project: a. construction of a New roadway one-quarter or more miles in length; or b. widening of an existing roadway by four or more feet for one-half or more miles. 2. Construction, widening or maintenance of a roadway or its right-of-way that will: a. alter the bank or terrain located ten more feet from the existing roadway for one-half or more miles, unless necessary to install a structure or equipment; b. cut five or more living public shade trees of 14 or more inches in diameter at breast height; or c. eliminate 300 or more feet of stone wall. 3. Expansion of an existing runway at an airport. 4. Construction of a New taxiway at an airport. 5. Expansion of an existing taxiway at Logan Airport. 6. Expansion of an existing terminal at Logan Airport by 100,000 or more sf. 7. Expansion of an existing terminal at any other airport by 25,000 or more sf. 8. Construction of New or Expansion of existing air cargo buildings at an airport by 100,000 or more sf. 9. Conversion of a military airport to a non-military airport. 10. Construction of a New rail or rapid transit line for transportation of passengers or freight. 11. Discontinuation of passenger or freight service along a rail or rapid transit line. 12. Abandonment of a substantially intact rail or rapid transit right-of-way. 13. Generation of 2,000 or more New adt on roadways providing access to a single location. 14. Generation of 1,000 or more New adt on roadways providing access to a single location and construction of 150 or more new parking spaces at a single location. 15. Construction of 300 or more new parking spaces at a single location.
The proposed project at this stage does not appear to meet the traffic threshold. The proposed parking garage will provide approximately 110 additional parking spaces (existing 70 spaces / proposed 180 spaces) to the site. According to Nelson/Nygaard (the traffic consultant for the study) by assuming a rough worst case scenario where 60% of the traffic arrives during peak hours, we can estimate an average daily trip. By assuming a typical value; where 10% of the average daily trips contributes to the peak traffic flow, they estimated the increase in average
Viii. appendix
139
Page 6 Preliminary MEPA threshold review June 17, 2010 Governors Ave. Garage / Medford
daily trips to be 660. Since this estimate only amounts to 2/3rds the required threshold, it appears that the project will fall under the filing threshold. Once again based upon the traffic consultants input, a key point in this preliminary estimate is that parking garages dont create trips, their surrounding land uses do. Real numbers would need full 48-hr tube counts at the driveways, plus an inflation factor for the new garage, backed up by real land use data. The surrounding buildings will govern the daily trips for the proposed parking garage. Additional investigation with actual 48-hour parking counts may be needed to determine a more conclusive judgment. Existing and proposed parking summaries are included in the Parking Management Plan / Recommendations section of the Feasibility Study Report.
7) Energy a) ENF and Mandatory EIR 1. Construction of a New electric generating facility with a Capacity of 100 or more MW. 2. Expansion of an existing electric generating facility by 100 or more MW. 3. Construction of a New fuel pipeline ten or more miles in length. 4. Construction of electric transmission lines with a Capacity of 230 or more kv, provided the transmission lines are five or more miles in length along New, unused or abandoned right of way.
140
Page 7 Preliminary MEPA threshold review June 17, 2010 Governors Ave. Garage / Medford
A parking garage should not be generating solid waste anywhere near the thresholds.
10) Historical and Archaeological Resources a) ENF and Mandatory EIR. None
b) ENF and Other MEPA Review if the Secretary So Requires Unless the Project is subject to a Determination of No Adverse Effect by the Massachusetts Historical Commission or is consistent with a Memorandum of Agreement with the Massachusetts Historical Commission that has been the subject of public notice and comment: 1. demolition of all or any exterior part of any Historic Structure listed in or located in any Historic District listed in the State Register of Historic Places or the Inventory of Historic and Archaeological Assets of the Commonwealth; or 2. destruction of all or any part of any Archaeological Site listed in the State Register of Historic Places or the Inventory of Historic and Archaeological Assets of the Commonwealth.
b) ENF and Other MEPA Review if the Secretary So Requires Any Project within a designated ACEC, unless the Project consists solely of one single family dwelling.
Viii. appendix
141
Page 8 Preliminary MEPA threshold review June 17, 2010 Governors Ave. Garage / Medford
Promulgation of New or revised regulations, of which a primary purpose is protecting against Damage to the Environment, that significantly reduce: 1. standards for environmental protection; 2. opportunities for public participation in permitting or other review processes; or 3. public access to information generated or provided in accordance with the regulations. We hope these responses will allow you to narrow your preliminary MEPA review of this project. If there are other thresholds that are tripped, this would require State agencies to review the filing if a permit were being applied for (for example if a curb cut permit from MassHighway was required). If you have any comments or questions regarding this memo, please do not hesitate to call either Steven Buff (ext 16) or myself at (508) 877-6688 ext. 13.
Enc.
srg: P:\Projects\2010\10013.00 Governors Ave Garage Medford\Documents\10013.00 MEPA Threshold Review Memo.doc
142
Viii. appendix
143
144
The complete environmental report can be found on the CD enclosed in this final report.
Viii. appendix
145
146
Viii. appendix
147
148
Structural Review
Viii. appendix
149
11 June 2010
Ms. Alyson Tanguay Utile, Inc. 50 Summer Street Boston, MA 02210 Project 100520 1. Governors Avenue Garage, Medford, MA
BACKGROUND
You asked Simpson Gumpertz & Heger Inc. (SGH) to meet to review a proposed parking garage at the above-noted location and to provide a narrative on structural system and durability options for the proposed garage. This letter is a summary of parking garage durability considerations, structural options for the garage, a recommended structural system, and recommended durability options. 2. DURABILITY OF PARKING STRUCTURES
Parking deck slabs in cold climates are exposed to significant quantities of deicing salts brought into the garage by vehicles. Salt-laden water from melting snow and ice permeates the top surface of the slab. Cracks allow salt-laden water to permeate the slab more quickly. Open joints and through-slab cracks allow salt-laden water to flow through the slab where it then permeates the underside of the slab and substructure elements in the vicinity of the leaking cracks and joints. The alkalinity and high electrical resistivity of concrete normally provide excellent protection against reinforcing bar corrosion. However, chlorides from salts break down this protection and establish electrical potentials which result in corrosion of the reinforcing steel. The corrosion produces corrosion products (rust) which have a much greater volume that the original, stable metal. This expansion of the rust produces bursting tensile stresses within the concrete, causing delamination and eventually spalling of the concrete over the reinforcing steel. In parking structures exposed to deicing salts, the chloride concentration at the depth of the reinforcing steel increases with time. There exists a threshold chloride level above which corrosion begins in the presence of oxygen and moisture, and with further ingress of chlorides and moisture, the corrosion continues an ever-increasing rate. The permeability of the concrete, the amount of concrete cover the reinforcing steel, and the presence or absence of other durability measures can greatly affect the time for the initiation of corrosion. Scaling, which is the disintegration of the mortar portion of the concrete due to freezing and thawing while critically saturated, is another common problem in parking structures. Scaling eventually results in exposure of the coarse aggregate and pitting of the slab surface. Standing
150
-2-
11 June 2010
water and the associated use of deicing salts exacerbate scaling damage by increasing the rate of freeze-thaw cycling. A well-distributed system of entrained air voids maximizes concretes resistance to freeze-thaw damage. Entrained air voids can prevent or reduce damage to concrete by providing expansion space for free water in the concrete as it expands upon cooling and freezing. 2.1 Minimum Durability Features Recommended by ACI
ACI 362.1R-97 Guide for the Design of Durable Parking Structures gives recommendations for the minimum level of corrosion protection for parking structures. ACI 362 defines five exposure zones representing different conditions of exposure to freezing water and salts: three general exposures and two coastal exposures. The general exposures are defined as follows: Zone I: Mild exposure where freezing is rare and salt is not used. Zone II: Moderate exposure areas where freezing occurs but deicer salts are rarely or never used. Zone III: Severe exposure areas that are commonly exposed to freezing and deicer salts.
The Governors Avenue garage is located in Zone III. For cast-in-place, non-prestressed/posttensioned concrete structures with Zone III exposure, ACI 362 recommends the following minimum durability measures: 2 in. of clear cover over the reinforcing steel in the top of the slab (reducible to 1-1/2 in. if corrosion inhibitor or epoxy coated reinforcement is used). A maximum water-cement ratio of 0.40. Application of vehicular-traffic-bearing waterproofing.
Adequate drainage is also a necessary feature for durability. There must be an appropriate number of drains and a minimum slope to drain of 1/4 in./ft. Drains should be located at anticipated areas of maximum vertical displacement of the slab. 2.2 Durability Features for the Governors Avenue Garage
Since the parking decks of the garage are intended to serve a diverse population and are located in a densely populated area, major structural repairs involving removal and replacement of large portions of the decks will be not only an operational hardship but also very costly. Therefore, it is sensible to maximize the time to major structural repairs by including other corrosion protection measures in addition to the minimum durability requirements recommended by ACI 362. We suggest the consideration of the following corrosion protection alternates, listed in order of increasing protection:
Viii. appendix
151
-3-
11 June 2010
Alternate 1 2 in. of cover over top reinforcement, maximum water/cement ratio of 0.40, epoxy coated reinforcement in the top of the slab (including beam top steel and stirrups), and vehicular-traffic-bearing membrane. Alternate 2 2 in. of cover over top reinforcement, maximum water/cement ratio of 0.40, epoxy coated reinforcement in the top of the slab (including beam top steel and stirrups) ,and corrosion inhibitor. Alternate 3 2 in. of cover over top reinforcement, maximum water/cement ratio of 0.40, all reinforcement epoxy coated, and corrosion inhibitor.
All of the alternates include 2 in. cover over top reinforcement, maximum water/cement ratio of 0.40, and epoxy coated top reinforcement, which together should provide excellent long-term protection to the top reinforcement. The intent of the vehicular-traffic-bearing waterproofing in Alternate 1 is to control leakage, which is a nuisance (stained cars) and can cause corrosion of the reinforcement in the bottom of slabs, and beams and in the columns in the vicinity of the leaking cracks and joints. The corrosion inhibitor in Alternate 2 is intended to provide additional protection to the epoxy coated steel at defects in the coating and to provide protection to the non-epoxy coated reinforcement at leaking cracks and joints. The epoxy coating on the bottom reinforcement in Alternate 3 is intended to provide additional protection to that reinforcement at leaking cracks and joints. Because vehicular-traffic-bearing membrane is prone to wear and to leakage at cracks and joints that reflect through the membrane, they can require frequent and costly maintenance. Consequently, we exclude the membrane from Alternates 2 and 3, which have other measures for protecting the bottom reinforcement at cracks and joints. Without membrane waterproofing, control of nuisance leakage will require diligent maintenance of sealant in cracks and joints. Membrane waterproofing can always be installed in the future if maintenance of sealant becomes intolerable. We do not consider a roof over the garage to be a cost-effective measure to protect the garage from the effects of weather. The cost associated with the additional structure necessary is generally better expended on durability measures in the initial construction and ongoing maintenance. 3. 3.1 STRUCTURAL SYSTEMS Background
Structural systems commonly used for parking garages fall into the three general categories: Cast-in-place, non-prestressed/non-post-tensioned concrete. These structures are usually either entirely cast-in-place structures or cast-in-place concrete slabs on steel frames.
152
-4-
11 June 2010
Precast prestressed concrete. These structures are usually precast prestressed double tees on either concrete or steel frames. The flanges of the tees can serve as the riding surface (pretopped) or can be covered with a cast-in-place concrete topping. Cast-in-place, post-tensioned concrete. These structures are usually one-way post-tensioned slabs spanning between post-tensioned beams supported on cast-in-place concrete columns. Two-way systems without beams are also possible.
Each system category has general advantages and/or disadvantages in terms of both structural function and durability as described below: Cast-in-place, non-prestressed/non-post-tensioned concrete structures: In the Boston construction market, this is the most typical type of concrete construction. Cast-in-place slabs can be combined with a structural steel frame. More capable than precast systems at accommodating unique geometry. Not as capable as the other systems of accommodating the large span-to-depth ratios that are usually desirable in parking structures. These structures are prone to cracking which results in leakage and deterioration of both the deck and substructure elements.
Precast prestressed concrete double tees: More capable of accommodating large span-to-depth ratios. Since it is cast in a plant, precast concrete is usually of better quality (durability) than cast-in-place concrete; this is less of an advantage for systems that include a cast-in-place concrete topping. Both the topped and pretopped systems rely on sealant joints between tees and elsewhere to control leakage and therefore can be prone to leakage and deterioration unless the joints are diligently maintained. The depth of double tees usually prohibits their use in depth-constrained applications. Double tees are at least twice as deep as cast-in-place garage systems. Double tees can span significantly longer distances than cast-in-place concrete systems. For this particular project, the spans of precast double tees would afford the designer the option of eliminating interior columns. The range of enclosure options is limited; precast facade panels are the most typical enclosure/facade.
Cast-in-place post-tensioned concrete: Can accommodate larger span-to-depth ratios. Slabs are typically thinner than conventionally cast-in-place concrete. Post-tensioning minimizes cracking and thereby controls leakage and related deterioration. Post-tensioning effects are reduced by the restraint provided by shear walls.
Viii. appendix
153
-5-
11 June 2010
End anchorages in post-tensioned concrete systems require special detailing and coordination for facade connections.
Each system category generally has advantages and/or disadvantages in terms of constructability as described below: Cast-in-place concrete: Requires formwork, shoring, and reshoring. Cast-in-place slabs on steel frames require much less, if any (metal from deck), formwork.
Precast prestressed double tees: Eliminates shoring and formwork. Eliminates on-site concrete placement for pretopped systems.
Post-tensioned concrete: Requires formwork. Monitoring of the concrete strength for readiness for stressing is critical. The stressing operation.
3.2
The cast-in-place concrete, two-way structural system is the most appropriate choice for the following reasons. The disadvantages of post-tensioning extra construction activity (post-tensioning), special detailing requirements, restraint of creep shortening, and the potential vulnerability of the post-tensioning anchorages in the foundation walls far outweigh the advantage of improved crack control. The pretopped double tee system can not resist the high diaphragm forces and will be prone to leakage due to reliance on the large length of sealant joints for leakage control. The topped double tee system will require a thick and highly reinforced concrete topping to resist diaphragm forces and will be prone to leakage due to reliance on the large length of sealant joints for leakage control. The double tee system will be too deep a structural system. Cast-in-place concrete slabs on steel framing may require fireproofing and special corrosion protection of the steel such as galvanizing.
154
-6-
11 June 2010
The current architectural plans for the garage indicate the following: Ramp 27 ft single span between columns transverse to the direction of travel. 29 ft continuous spans between columns parallel to the direction of travel. Approximate slope of 12%.
During final design, it is reasonable to expect these spans to increase/decrease between 1 and 3 ft. The proposed slab geometry listed below can accommodate this range of spans for cast-in-place concrete flat plate construction. Parking deck: 15 ft 26 ft 15 ft, three span condition between columns transverse to the direction of travel. 29 ft continuous spans between columns parallel to the direction of travel. This slab is presumed to be nominally flat with pitch of 1/4 in./ft (minimum) to drains.
Typical parking garage column bay spacing, without site or other constrictions, is typically in this range. During final design, it is reasonable to expect these spans to increase/decrease between 1 and 3 ft. The proposed slab geometry listed below can accommodate this range of spans for cast-in-place concrete flat plate construction. Cost efficiency is developed by reducing floor-to-floor height. This reduces the required area of vertical formwork, reduces the area of facade, and reduces the lateral loads the structure must resist due to lower weight and lower height. For planning, floor-to-floor height between 8.5 ft and 10ft should be considered for this garage. The final heights will depend on entry clear height requirements for emergency vehicles, type and size of signage, type and location of lighting, location and path of drain bodies and pipes, etc. For the size and spans of the Governors Avenue garage, we recommend that the following member geometry be considered for any construction budget estimates. Cast-in-place concrete flat slabs: 11 in. 12 in. thick slabs #6 steel reinforcing bars at 10 in. o/c, both ways, top and bottom. Decon stud rails shear heads at columns.
Typical column size: 20 in. x 20 in. square columns. Alternately, 14 in. x 32 in. rectangular columns.
Viii. appendix
155
Ms. Alyson Tanguay Project 100520 Lateral load resistance: Sincerely yours,
-7-
11 June 2010
10 in. thick, cast-in-place concrete shear walls. 24 in. x 24 in. wall boundary elements (integral columns). Assume three walls in each direction of the garage; final locations to be coordinated.
I:\BOS\Projects\2010\100520.00-GARG\WP\001MHJohnson-L-100520.00.pad.doc
156
6/30/2010
ITEM 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 Sitework and Utilities Demolition Foundations Superstructure (Cast-in-Place Concrete) Exterior Envelope Interior Finishes Equipment/Specialties Elevator Sprinkler Plumbing HVAC Electrical and Photovoltaics Subtotal General Conditions (8%)
TOTAL
$84,000 $14,450 $446,480 $1,884,620 $1,288,660 $433,510 $31,060 $257,200 $264,300 $136,150 $1,500 $1,084,900 $5,926,830 $474,146 $6,400,976 $192,029 $6,593,006 $65,930 $6,658,936 $665,894 $7,324,829 Not Included $7,324,829 Cost/Parking Space
n/a n/a $5.51 $23.27 $15.91 $5.35 $0.38 $3.18 $3.26 $1.68 $0.02 $13.39 $71.96 $5.76 $77.71 $2.33 $80.04 $0.80 $80.84 $8.08 $88.93 n/a $88.93 $41,150.73
Subtotal
Subtotal
Subtotal
1
Final report october 15, 2010
Estimate for:
Viii. appendix
157
MassDevelopment
Governors Avenue Garage
Medford , MA Brick Garage Option
6/14/10
Ref Dwgs: Conceptual drawings by Utile Inc., undated Gross Sq Ft: 81,000 SF
ITEM 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Sitework and Utilities: Water Service Storm Drain Tie-in Electric Service Tie-in Sidewalks at Perimeter Including Subbase Wood Boardwalk with Footings Reset Existing Curbs Trees and Shrubs Stormwater Retention System Street Lighting Subtotal Demolition:
QUANTITY UNIT
UNIT COST
TOTAL
$ $ $ $ $ $ $
84,000.00
15 Strip Existing Parking Lot 16 Remove Existing Light Poles and Utility Poles 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 Subtotal Foundations: General Excavation Backfill - General Gravel fill under slab (12") Miscellaneous Trenching for Piping Dispose of Overburden to Unlined Landfill Miscellaneous Dewatering Spread Footings and Strip Footings Frost Wall Perimeter Retaining Wall and Footing Slab on Grade Elevator Pit Subtotal Superstructure: Concrete Formwork: - Columns (18" x 24") - Shear Walls (12") - Flat Slabs (10") Ready Mix Material w/ Corrosion Inhibitor and Place Rebar Furnish and Install: - Columns ( 400#/ea) - Shear Walls ( 10#/sf) - Flat Slabs ( 7#/sf) Concrete Slab Finishing
allow $
cy cy cy lf cy allow cy cy cy sf allow
$ 6.00 $ 8.00 $ 30.00 $ 15.00 $ 25.00 $ 10,000.00 $ 460.00 $ 440.00 $ 520.00 $ 6.00 $ 10,000.00
$ $ $ $ $ $ $ $ $ $ $ $
24,600.00 12,000.00 20,400.00 6,000.00 65,000.00 10,000.00 36,800.00 25,080.00 150,800.00 85,800.00 10,000.00 446,480.00
$ $ $ $ $ $ $ $
2
158
MassDevelopment
Governors Avenue Garage
Medford , MA Brick Garage Option
Ref Dwgs: Conceptual drawings by Utile Inc., undated Gross Sq Ft: 81,000 SF
ITEM 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 Concrete Testing and Inspection Steel Support (Galv.) for Photovoltaics (allow 6#/sf) Elevator - Miscellaneous Metals Concrete Landings at Elevator/Stairs Subtotal Exterior Envelope: Glass Curtainwall Stair Cladding Relieving Angles Loose Lintels at Corbelled Header Precast Sills Precast Headers Precast Cap at Top Spandrel Stainless Steel Metal Frames (at masonry openings) Steel Railings at North Elevation - Painted CMU False Columns CMU Spandrel Back-up CMU Elevator Hoistway Waterproof CMU and Concrete at Brick and Stone Brick Veneer Stone Base (3 sides) Canopy at Exits to Street (Glass and Steel) Doors - Hollow Metal Caulking and Flashings for Masonry Subtotal Interior Finishes: Stairs- Metal Pan with Concrete Fill Stair Railings Railings at Vehicle Ramps Electric Room - CMU and Door CMU Walls at Storage Metal Door and Frame at Storage Painting of Stair Pans and Stair Rails Traffic Deck Coating Concrete Sealer Paint Railings at Ramps Paint CMU at Elevator Shaft Subtotal Equipment/Specialties: Photovoltaic System Gutters
1,680 860 300 1,340 960 430 97 600 740 5,400 3,025 15,840 15,260 580 720 2 15,840
sf lf lf lf lf lf ea lf sf sf sf sf sf sf sf pr sf
$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $
70.00 50.00 20.00 70.00 60.00 70.00 900.00 90.00 20.00 18.00 20.00 3.00 32.00 60.00 60.00 2,500.00 0.50
$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $
117,600.00 43,000.00 6,000.00 93,800.00 57,600.00 30,100.00 87,300.00 54,000.00 14,800.00 97,200.00 60,500.00 47,520.00 488,320.00 34,800.00 43,200.00 5,000.00 7,920.00 1,288,660.00
$ $ $ $ $ $ $ $ $ $ $
6,000.00 6,000.00 80.00 8,000.00 18.00 1,800.00 1,000.00 3.50 0.50 10.00 2.00
$ $ $ $ $ $ $ $ $ $ $ $
48,000.00 48,000.00 40,000.00 8,000.00 11,160.00 1,800.00 8,000.00 257,950.00 2,000.00 5,000.00 3,600.00 433,510.00 2
allow $ 10,000.00
10,000.00
3
Final report october 15, 2010
Estimate for:
Viii. appendix
159
MassDevelopment
Governors Avenue Garage
Medford , MA Brick Garage Option
6/14/10
Ref Dwgs: Conceptual drawings by Utile Inc., undated Gross Sq Ft: 81,000 SF
ITEM 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 Bike Racks Signage Fire Extinguishers and Brackets Parking Space Striping Parking Controls - Gates, Card Reader, Loop Detectors Subtotal Elevator: 5 - Stop Machine Roomless 12 Month Maintenance Subtotal Sprinkler: Main Service/Check Valve Sprinkler Heads and Distribution Fire Pump Subtotal Plumbing: Deck Drainage Slab on Grade Drainage Gas/Sand Seperator Subtotal HVAC: Storage Room - Unit Heater Subtotal Electrical: Main Electric Service Lighting - Covered Levels Lighting - Upper Level and Upper Ramp Exterior Lighting Miscellaneous Convenience Power Fire Alarm Automatic Venting Damper for Elevator Hoistway Emergency Battery Pack Lighting - Stairwells Power for Elevators Power to Parking Controls Security Systems Photovoltaic System
QUANTITY UNIT
UNIT COST
TOTAL
1 10 178
$ $ $
$ $
7,500.00 256,800.00
264,300.00
66,700 14,300 1
sf sf allow
$ $ $
$ $ $ $
ea
1,500.00
$ $
1,500.00 1,500.00
$ 25,000.00 $ 2.50 $ 3.00 $ 10,000.00 $ 2,500.00 $ 1.00 $ 3,000.00 $ 350.00 $ 7,500.00 $ 2,000.00 $ 6.00
$ $ $ $ $ $ $ $ $ $ $
25,000.00 160,500.00 50,400.00 10,000.00 12,500.00 81,000.00 3,000.00 3,500.00 15,000.00 4,000.00 720,000.00 3
160
Estimate for:
MassDevelopment
Governors Avenue Garage
Medford , MA Brick Garage Option
Ref Dwgs: Conceptual drawings by Utile Inc., undated Gross Sq Ft: 81,000 SF
QUANTITY UNIT
UNIT COST
TOTAL
Subtotal
1,084,900.00
note: Mechanical ventilation costs are not included in the cost estimate for the Brick Garage because it qualifies as as open Garage per State Building Code and thus can be naturally ventilated. Please see Relevant Building Code excerpts in the Appendix for further explanation.
Viii. appendix
161
ITEM 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 Sitework and Utilities Demolition Foundations Superstructure (Steel with Precast Double-Tees Exterior Envelope Interior Finishes Equipment/Specialties Elevator Sprinkler Plumbing HVAC Electrical and Photovoltaics Subtotal General Conditions (8%)
TOTAL
$84,000 $14,450 $431,980 $1,684,850 $1,246,730 $537,700 $31,100 $257,200 $268,300 $137,650 $1,500 $1,088,400 $5,783,860 $462,709 $6,246,569 $187,397 $6,433,966 $64,340 $6,498,306 $649,831 $7,148,136 Not Included $7,148,136
n/a n/a $5.27 $20.55 $15.20 $6.56 $0.38 $3.14 $3.27 $1.68 $0.02 $13.27 $69.33 $5.55 $74.88 $2.25 $77.13 $0.77 $77.90 $7.79 $85.69 n/a $85.69 $39,711.87
Subtotal
Subtotal
Subtotal
Cost/Parking Space
1
162
MassDevelopment
Governors Avenue Garage
Medford , MA Green Garage Option
Ref Dwgs: Conceptual drawings by Utile Inc., undated Gross Sq Ft: 82,000 SF
ITEM 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Sitework and Utilities: Water Service Storm Drain Tie-in Electric Service Tie-in Sidewalks at Perimeter Including Subbase Wood Boardwalk with Footings Reset Existing Curbs Trees and Shrubs Plantings for Green Screen Stormwater Retention System Street Lighting Subtotal Demolition:
QUANTITY UNIT
UNIT COST
TOTAL
1 allow $ 10,000.00 1 allow $ 10,000.00 1 allow $ 10,000.00 900 sf $ 6.00 1,100 sf $ 30.00 400 lf $ 14.00 1 allow $ 10,000.00 in Exterior Envelope Not Included Excluded
$ $ $ $ $ $ $
84,000.00
16 Strip Existing Parking Lot 17 Remove Existing Light Poles and Utility Poles 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 Subtotal Foundations: General Excavation Backfill - General Gravel fill under slab (12") Miscellaneous Trenching for Piping Dispose of Overburden to Unlined Landfill Miscellaneous Dewatering Spread Footings and Strip Footings Set Column Base Plates Frost Wall Perimeter Retaining Wall and Footing Slab on Grade Elevator Pit Subtotal Superstructure: Steel Columns and Girders (allow 9#/sf) Precast Double Tee Decking - 60' Span Precast Double Tee Decking - 26' Span Caulking of Double-Tees
allow $
cy cy cy lf cy allow cy ea cy cy sf allow
$ 6.00 $ 8.00 $ 30.00 $ 15.00 $ 25.00 $ 10,000.00 $ 460.00 $ 200.00 $ 440.00 $ 500.00 $ 5.00 $ 10,000.00
$ $ $ $ $ $ $ $ $ $ $ $ $
24,600.00 12,000.00 20,400.00 6,000.00 65,000.00 10,000.00 36,800.00 5,600.00 25,080.00 145,000.00 71,500.00 10,000.00 431,980.00
tons sf sf lf
$ $ $ $
$ $ $ $
2
Final report october 15, 2010
Estimate for:
Viii. appendix
163
MassDevelopment
Governors Avenue Garage
Medford , MA Green Garage Option
6/14/10
Ref Dwgs: Conceptual drawings by Utile Inc., undated Gross Sq Ft: 82,000 SF
ITEM 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 Precast Plant Testing and Inspection Steel Support (Galv.) for Photovoltaics (allow 6#/sf) Elevator - Miscellaneous Metals Concrete Landings at Elevator/Stairs Subtotal Exterior Envelope: Glass Curtainwall Stair Cladding Premium for Colored Glass (assume 50%) Metal Soffiting at Curtainwall Precast Spandrel Panels with Thin Brick Veneer/Precast C Inserts and Attachments for Precast Panels to Structure Railings at North Elevation - Painted Green Screen Metal Grid System: - Galvanized Horizontal Tube Supports (assume 6x3x1/4) - Galvanized Outrigger Attachements for Vertical Membe - Galvanized Vertical Pipe (assume 3" diameter) - Stainless Steel Mesh and Cables - Installation of Mesh and Cables - Misc touch up of galvy and re-tightening Plantings for Green Screen CMU at Elevator Hoistway Waterproof CMU and Concrete at Brick and Stone Brick Veneer at Elevator Brick Base (3 sides) Canopy at Exit to Street (Glass and Steel) Doors - Hollow Metal Caulking and Flashings for Masonry and Precast Panels Subtotal Interior Finishes: Stairs- Metal Pan with Concrete Fill Stair Railings Railings at Vehicle Ramps and North Electric Room - CMU and Door CMU Walls at Storage Metal Door and Frame at Storage Painting of Stair Pans and Stair Rails Paint Exposed Structural Steel Traffic Deck Coating Concrete Sealer Paint Railings at Ramps Paint CMU at Elevator Shaft
UNIT COST $ $ $ $ $
3,520 1,760 360 4,870 1 600 23,000 500 46,000 15,000 15,000 1 1 3,025 1,810 1,230 580 360 2 6,680
$ 70.00 $ 10.00 $ 50.00 $ 30.00 $ 25,000.00 $ 90.00 $ 4.50 $ 300.00 $ 3.50 $ 8.00 $ 2.50 $ 10,000.00 $ 5,000.00 $ 20.00 $ 3.00 $ 32.00 $ 30.00 $ 60.00 $ 2,500.00 $ 0.50
$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $
246,400.00 17,600.00 18,000.00 146,100.00 25,000.00 54,000.00 103,500.00 150,000.00 161,000.00 120,000.00 37,500.00 10,000.00 5,000.00 60,500.00 5,430.00 39,360.00 17,400.00 21,600.00 5,000.00 3,340.00 1,246,730.00
$ $ $ $ $ $ $ $ $ $ $ $
6,000.00 6,000.00 80.00 8,000.00 18.00 1,800.00 1,000.00 0.70 3.50 0.50 10.00 2.00
$ $ $ $ $ $ $ $ $ $ $ $
48,000.00 48,000.00 89,600.00 8,000.00 11,160.00 1,800.00 8,000.00 47,390.00 257,950.00 2,000.00 12,200.00 3,600.00
3
164
MassDevelopment
Governors Avenue Garage
Medford , MA Green Garage Option
Ref Dwgs: Conceptual drawings by Utile Inc., undated Gross Sq Ft: 82,000 SF
ITEM 87 88 Subtotal 89 90 Equipment/Specialties: Photovoltaic System Gutters 91 Bike Racks 92 Signage 93 Fire Extinguishers and Brackets 94 Parking Space Striping 95 Parking Controls - Gates, Card Reader, Loop Detectors 96 97 Subtotal 98 Elevator: 99 5 - Stop Machine Roomless 100 12 Month Maintenance 101 102 Subtotal 103 104 Sprinkler: 105 Main Service/Check Valve 106 Sprinkler Heads and Distribution 107 Fire Pump 108 109 Subtotal 110 111 Plumbing: 112 Deck Drainage 113 Slab on Grade Drainage 114 Gas/Sand Seperator 115 116 Subtotal 117 118 HVAC: 119 Storage Room - Unit Heater 120 121 Subtotal 122 123 Electrical: 124 Main Electric Service 125 Lighting - Covered Levels 126 Lighting - Upper Level and Upper Ramp 127 Exterior Lighting 128 Miscellaneous Convenience Power 129 Fire Alarm 130 Automatic Venting Damper for Elevator Hoistway
QUANTITY UNIT
UNIT COST
TOTAL
537,700.00
1 10 180
allow $ 10,000.00 None allow $ 15,000.00 ea $ 250.00 spcs $ 20.00 Not Included
$ $ $ $
$ $
7,500.00 260,800.00
268,300.00
67,700 14,300 1
sf sf allow
$ $ $
$ $ $ $
ea
1,500.00
$ $
1,500.00 1,500.00
$ $ $ $ $ $ $
4
Final report october 15, 2010
Estimate for:
Viii. appendix
165
MassDevelopment
Governors Avenue Garage
Medford , MA Green Garage Option
6/14/10
Ref Dwgs: Conceptual drawings by Utile Inc., undated Gross Sq Ft: 82,000 SF
ITEM 131 132 133 134 135 136 137 138 Emergency Battery Pack Lighting - Stairwells Power for Elevators Power to Parking Controls Security Systems Photovoltaic System Subtotal
note: Mechanical ventilation costs are not included in the cost estimate for the Green Garage because it qualifies as as open Garage per State Building Code and thus can be naturally ventilated. Please see Relevant Building Code excerpts in the Appendix for further explanation.
166
Memorandum
The Parking Garage proposed for Medford center between Governors Avenue and Bradlee Road is expected to be optimally energy efficient and may provide its own power production through photovoltaics (PV) mounted on a trellis above the top floor parking deck. There appears to be sufficient area to provide a PV system that could offset the expected loads of the garage given a number of early stage assumptions.
The utility for the site is National Grid, and they have indicated that there should be no project. The energy produced on site will offset any that is consumed by the facility utility provided electricity and renewable energy generated kilowatt hours. Energy Budget
significant constraints to the interconnection of a 100-150kWdc PV system as part of this through the Massachusetts Net-Metering laws, which provide a one for one credit between
lighting and natural ventilation, should not require significant energy. Lighting loads are expected to be the major consumption, along with attendant kiosk heating and cooling, and minor loads due to elevator and other equipment. Given an area of roughly 82,000sf, approximately 410,000kBtu/yr or 120,000kWh/yr. Design Considerations
Parking garages of the type proposed, incorporating significant open air design for day-
and a rough energy load goal of less than 5kBtu/sf/yr, the garage is estimated to consume
and 120kWdc, and oriented towards True south in a shade-free area. Depending upon the tilt angles and row spacing required, as well as the efficiency of the modules installed, the system will likely require between 8,000 and 15,000sf of roof area. Since only about 7,750sf of area is available, it is recommended that a low 5-20 slope system be installed. Using a low tilt angle will reduce production but increase available area (due to less row shading). Alternatively, a high tilt angle will increase production per panel installed, but
take up more space. For the Medford Garage, it is recommended that a rain, ice and snow onto cars and customers. Cost of the System
collection (roof or gutter) system be included under the PV system to avoid snow dropping
The cost for construction of the PV equipment of an array is around $6-7/Watt fully
installed. This does not include the supporting trellis proposed on the garage. This rate is considered reasonable for a system of this size, complexity, and aesthetic requirement. This amounts to approximately $6-700,000 total.
box242,harvard,massachusetts014510242 (978)4566855www.solardesign.com
Viii. appendix
167
The Department of Energy estimates that the annual maintenance costs for PV systems to typically required every 10-12 years, and costs are currently about $0.40/W or $40,000 for a 100kW system. Funding Opportunities range between $0.005 and $0.02 per kWh for a typical system. Inverter replacement is
Operations
For a nonprofit or government agency, there are limited number of external funding
options for renewable energy projects; 1) state production incentives, 2) grants loans and donations, and 3) private ownership arrangements. A comprehensive data base of state and federal incentives can be found at .
http://www.dsireusa.org/incentives/index.cfm?re=1&ee=1&spv=0&st=0&srp=1&state=MA 1) For system owners, the primary financial incentive in MA is based upon production.
Every megawatt-hour (MWh) of energy produced by the PV system can be sold, traded, or donated as a solar Renewable Energy Certificate or sREC, anticipated to be between $300 and $600/MWh. The Medford garage array will produce roughly 120 carbon-free MWh as useful energy for the facility and city.
each year for the life of the system that can provide between $36,000 - $72,000/yr, as well 2) Grants for renewable energy are typically focused on disadvantaged areas. The current state grant program, the Green Communities Act from the MA DOER, is not currently accepting new applications (http://www.mass.gov/energy/greencommunities), but may
consider special projects for urban developments in need. Alternatively, renewable energy costs over time.
loans or Clean Renewable Energy Bonds (CREBs) may also be available to help distribute the 3) Medford may also consider a Power Purchase Agreement, or PPA with a 3 rd party for-
profit firm that can take advantage of federal and state tax incentives as well as production and sell the clean energy at a rate discounted from the utility rates. Typically PPAs are aimed at large systems only, and 100kW may be below the current market threshold. Recommended Consultants incentives. The 3rd party would then install, own and operate the PV system on the garage,
For the design of the PV systems, it is recommended that the City of Medford engage an Electrical Engineering firm with a minimum of 5 years experience in photovoltaic system design and application.
box242,harvard,massachusetts014510242 (978)4566855www.solardesign.com
168
Memorandum
Financing the Construction and Operations and Maintenance of a New Garage in Medford Square
MEMORANDUM
Lauren DiLorenzo Rhonda Spector and Robert Kaye Richard Henderson, Rebecca Sullivan, Ken Goode, and Ann Pierce Financing the Construction and Operations and Maintenance of a New Garage in Medford Square September 20, 2010
The most likely option for financing the cost associated with the construction of a garage at Governors Avenue in Medford Square appears to be either a tax exempt revenue bond or general obligation bond issued by the City of Medford. There also may be opportunities for some small grants for the project, as well as the possibility of either grants or subsidies for photovoltaics for the project.
Revenue Bonds The City of Medford has several borrowing options to finance a City garage. The first option would be to issue a tax exempt revenue bond backed by parking receipts. To do this type of financing, the City would need to commit garage and on-street parking revenues equal to a multiple of the projected debt service (multiple varies by project). Investors will look to a parking finance study to verify what revenues are projected to be available. It is possible that additional analysis may be required to verify potential revenue for a bond issuance. Interest rates are traditionally higher for a tax exempt revenue bond than a general obligation financing, but the City might have more flexibility in structuring the bond. The analysis provided indicates there may be insufficient revenue from parking to support a revenue bond issuance.
Viii. appendix
169
General Obligation Bonds The second borrowing option would be to issue a tax exempt general obligation bond backed by the full faith and credit of the City. The City could issue in the traditional form of tax exempt bonds, issue a Build America Bond (taxable bond with subsidy from the Federal government) or apply for Recovery Zone Economic Development Bond (RZEDB) financing, which is a better version of Build America Bonds, with an increased subsidy of 45% vs. 35%. Tax exempt bonds or Build America Bonds can be issued without any state approvals. For a Recovery Zone Economic Development Bond allocation, the City would need to apply to the Executive Office of Housing and Economic Development (EOHED). The best place to start exploring any bond related financing options would be with the Citys financial advisor, First Southwest.
170
Grant Opportunities In recent years, the only garages that have received grants have been on the States Transportation Improvement Plan (TIP) and have been related to intermodal facilities. It is possible, however, that grants for economic development may be available for this project. A summary of grant opportunities is presented here: State Growth District Initiative City must be designated a growth district in order to be eligible PWED funds above-ground infrastructure improvements, not parking garages; $1- 2M maximum award; requires 2:1 private to public match ratio; application is due June 30, 2010. CDAG funds below-ground infrastructure improvements, not parking garages and there is a low-income/workforce affordable housing requirement; $1-2M maximum award; requires 2.5:1 private to public dollar and 2:1 CDAG to public dollar match ratios; rolling application, first submit Notice of Intent to Apply. Federal ARRA (Stimulus) funds were applied to the statewide TIP for highway and bridge improvements; although some funds were applied to TIP-related/approved parking garage construction in cities where the garage supported a transit center or intermodal facility, generally, parking garages are an ineligible use of funds. EDA (Economic Development Administration) requires private investment/job creation; commercial/retail projects are not eligible; EDA is reluctant to support parking garage construction. Photovoltaics The attached financial analysis assumes the cost of photovoltaics is included in the total construction budget that would be paid for out of bond proceeds. The City could reduce the funds needed through grants available through the Massachusetts Clean Energy Centers Commonwealth Solar programs. www.commonwealthsolar.org Another alternative for funding photovoltaics would be a Power Purchase Agreement with a private firm. Under a Power Purchase Agreement, a private company would lease an area for photovoltaics on the garage. The private company will purchase, install and maintain the photovoltaics and provide energy to the public facility. If there is any electricity in excess of what is needed for the facility, that excess is sold to the local utility company. The private company benefits from any tax credits that are available for photovoltaics as well as from the sale of excess electricity. Initially, the City would receive a utility bill similar to one they would have had without the photovoltaics, and then, after the private firm makes back its investment and sees a return, for less or nothing depending upon the contract with the private company.
Viii. appendix
171
Potential Financing Scenarios The attached potential financing scenarios use estimates for the cost of the garage and for photovoltaics as presented in the feasibility study. An estimated cost for on-street pay stations is added to come up with an overall parking capital requirement. This estimate does not include costs identified in the feasibility study for traffic circulation changes or improvements to the Forest/Salem/High/Riverside intersection identified in the study. A table of potential interest rates and debt service coverage is then provided to identify the range of revenue that could be needed to service the debt for associated with the capital costs. Debt service coverage is determined based on the level of certainty the bond issuer associates with the identified repayment revenue source. The estimates for on-street parking revenues in and around Medford Square, garage operations, maintenance and for revenue related employees are all based upon estimates derived from the feasibility study. The parking rates provided in the study have not been approved by the City and will require further policy study and feasibility confirmation before any parking rates are implemented. The first scenario assumes a tax-exempt revenue bond at an interest rate of 4.5% and a debt service coverage ratio of 1.75. The estimated income is short of the coverage required. Coverage could be adequate if assumed staffing expenses are covered by other City revenues. Scenario 2 assumes a 20-year G.O Bond at 4.0%, with no debt service coverage needed as the full faith and credit of the city is behind the bond. The estimated revenue easily exceeds the debt service required.
172
Brick Version
All estimates are preliminary and assume, among other things, pricing in feasiblity study which has not been approved by the City Paid parking Revenue Permit Revenue Enforcement Revenue $ $ $ $ $ $ $ $ $ 603,000 185,000 250,000 1,038,000 122,337 75,000 197,337 840,663 840,662 1
Memorandum from MassDevelopment
Net Annual proceeds available for debt service and coverage requirements Income required for debt service coverage Net
MassDevelopment
Viii. appendix
173
Net Annual proceeds available for debt service Income required for debt service coverage Net
MassDevelopment
174
Memorandum
Viii. appendix
175
OVERVIEW OF MODULAR CONSTRUCTION PROCUREMENT As the parking garage project moves forward into a preliminary design and cost estimating phase, one option is to consider potential savings in time and money that may be realized by utilizing modular construction. Massachusetts General Laws chapter 149, sections 44A-M govern contracts for the construction of public buildings. Although the statutes do not define the term building, court decisions have indicated that the word is to be taken in its common and ordinary sense. If a structure has walls and a roof and enclosed space that is to be used for some purpose, it is a building. 1 While the proposed Medford Square municipal parking garage has yet to be designed, it is reasonable to anticipate that the structure will have walls, a roof (or lower levels with a ceiling or roof), enclosed spaces such as staircases, elevators, a storage room and/or retail space, electrical systems, and fire protection systems, etc., all to be used and occupied by people parking within it. Therefore, the proposed garage will likely be considered a building. The City may elect to follow chapter 149 procedures to deliver the project by using a design-bidbuild process. However, M.G.L. chapter 149, s. 44E(4) permits a public agency to procure modular buildings by following an alternative procurement process. Using this alternative method of procurement may result in the delivery of a completed project while achieving significant savings in time and money. A modular building is one which is predesigned or units of a predesigned building which are assembled and equipped with internal plumbing, electrical or similar systems prior to movement to the site where the units are attached to each other and the building is affixed to a foundation and connected to external utilities. A parking garage that is predesigned and mostly manufactured off site (such as a concrete beam and slab design) and then delivered to the site for assembly would likely be considered a modular building, however, specific details of a proposed design would need to be reviewed and analyzed before a conclusion can be reached. The modular procurement process varies from the design-bid-build process in several respects. Rather than competitively selecting a designer to prepare detailed plans and specifications for the construction, the awarding authority issues a request for proposals (RFP) for modular construction that describes the project requirements in detail. Respondents to the RFP submit proposals to provide a predesigned building meeting the requirements set forth in the RFP. Proposals are then evaluated according to a competitive evaluation process by individuals designated by the awarding authority. Additional information regarding procuring modular construction can be found in M.G.L. chapter 149, s. 44E as well as in Designing and Constructing Public Facilities, Comm. of Mass. Office of the Inspector General, Section VIII. (Fall 2005.)
See Designing and Constructing Public Facilities, Comm. of Mass. Office of the Inspector General, Section V. (Fall 2005.)
176
The excerpts of the Massachusetts State Building Code included on the following pages deal with the classification of parking garages and egress requirements for each garage type. Specifically, the excerpts highlight the relevant sections that define an Open Garage, a facility that does not require mechanical ventilation or enclosed egress stairs. each scenario illustrated in this report can be classified as an Open Garage.
Viii. appendix
177
178
Viii. appendix
179
180
Viii. appendix
181