Waste Thermal Rep
Waste Thermal Rep
Waste Thermal Rep
PHASE I REPORT
Submitted by
ASHOK KUMAR S
of
DECEMBER 2023
ANNA UNIVERSITY,
CHENNAI-620025
I
BONAFIDE CERTIFICATE
Signature Signature
II
ABSTRACT
III
ACKNOWLEDGEMENT
ASHOK KUMAR S
IV
TABLE OF CONTENTS
1.3 Biodiversity 13
5
4 PROPOSED 39
METHODOLOGY
5 ADVANTAGES AND 44
APPLICATIONS
5.1 Sequential Data Processing 44
Enhancement
6
6 CONCLUSION 46
REFERENCES 47
LIST OF FIGURES
7
FIGURE No NAME PAGE NO
8
LIST OF TABLES
CHAPTER-1
9
INTRODUCTION
1.1. BACKGROUND
10
pollution, because her brother is working as an engineer in thermal power
station at Salem, Salem district, Tamil Nadu. Madalaimary (1996)
environmental pollution is the unfavourable alteration of the surroundings
wholly or largely as a by-product of man’s action, through direct or indirect
effects or changes in energy pattern, radiation levels, chemical and physical
constitution and substances of organisms. These changes may affect man
directly or through supplies of water and of agriculture and other biological
products, his physical objects or possessions, or the opportunities, for
recreation and appreciation of nature. Pollution refers simply to how people
spoil the use value of their surroundings in many possible ways. Pollution
is also a biological phenomenon because it originates from the continual
activities of man and its remedy may also involve time to restore the
environment back to its natural state. For the survival of his race in the
future, man has a duty to protect the environment. Any neglect in this duty
will be only at his peril.
11
Environmental pollution caused by thermal pollution is an economic
problem because it reduces the value of some of the scare resources that the
society has at it’s disposal. So environmental pollution is very dangerous
although the globe and growing awareness is dissemble all over the world
to save ecological balance. Thus throughout the country a globe changes in
energy pattern radiation levels, chemical and physical constitution and
abundance or organism.
Thermal power stations are the sources of energy in which heated water
is discharged into steam, ponds, pools or lakes etc. coal is the fuel used by
thermal power station in the process of energy or power generation. The
wastes that are emitted into the environment are smoke which are gaseous
pollutants like sulpur dioxide, nitrogen oxide, carbon dioxide, particulate
wastes and fly ash. The Columbia Encyclopedia (2008) thermal pollution
harmful increase in water temperature in steams rivers, lakes or
occasionally, coastal occur water thermal pollution is caused by either
dumping hot water from factories and power plants or removing trees and
vegetation that shade streams, permitting sunlight to raise the temperature
of these water like other forms of water pollution, the main pollution is wide
spread, affecting many taker and vast number of stream and river in the
united states and other parts of the word. The discharge of thermal energy
into natural water like streams, rivers etc. is called as thermal pollution
Thermal pollution has severely affected aquatic life that is fish. Human
beings working in the power stations, people near the surrounding areas,
animal, flora and fauna etc. The available natural resources are unfit for
common use so it becomes scarce or not available.
12
The planet on which we live, soil, soft substances of minerals,
particles, decayed organic matter, chemicals and water in which plants can
grow. The planet earth can be divided into various zones: The lithosphere
(The water covering the earth surface), atmosphere (gaseous zone rising
above the earth surface) and the biosphere (Those parts of the other zone in
which organism exists). The interior of the earth is formed by a central core
meetup nickel and iron, part of which is solid. Above the core is the mantle
a thin layer about 2700 kms thick of molten minerals on the top of the
mantle is the crust formed of solid rock between six and seventy kms thick.
The resources of the earth are used by human beings for various activities
and the resources become scarce. The waste disposal activities rate also
increased, that in turn responsible for global warming and environmental
problems.
1.3 Biodiversity
13
sustainable development focuses intergeneration fairness in the exploitation
of development opportunities. Every generation of mankind ‘creates’ as
well as ‘destroys’ certain amount of resources for its development process.
But the nature and rate of present development are such that the rate of
destruction of resources is greater than the rate of creation. If this trend
continues beyond a century or so it is apprehended that there would be not
only no further development but there might be economic stagnation or
even disaster. That is what is after called the limit to growth. The present
generation should either drastically curtail the exploitation of non-
renewable resources as it uses up, so that the posterity too has equal chance
to develop. Thermal pollution affects the resources of the earth and also
makes it scarce for future development.
The number of thermal power stations in the state of Tamil Nadu are
the following.
6. North Chennai Thermal Power Station, Ennore High Road, Tamil Nadu,
India.
14
1.5 STATEMENT OF THE PROBLEM
15
organisms especially human beings. Thus man has digged his own grave
due to his desire for enriching himself.
In 2011 and 12 the number of Thermal power plants were 7 and the
capacity is 5810 MW. Electric power generation was 43853, it is greater
than 2010-11. The power plants had functioned more efficiently, that is why
the electric power generation is greater. The number of technical staff
member were 11022, non-technical staff member were 12113 and other
members employed were 2950. Increasing number of staff members are
found in 2011-12, that is why power generation is also high. In 2012-13,
the number of thermal power plants were 8 and the capacity was 6260 MW
and power generation was 49579. The percentage of increasing power
generation is 13.05 in 2012-13. Power generation in 2011-12 was 3.22
percentage. This was because in 2012-13 one more thermal power plant
was established in Tamil Nadu. That is because of 8th power plant
established in Tamil Nadu which had resulted in 9.83 per cent of increasing
electric power. In 2012-13, the number of technical staff members were
2050, non-technical staff members are 3910. Thus every year, the number
of different categories of staff members had been going on increasing and
ultimately it had resulted in increasing more electric power generation.
16
staff members were 178 and other staff members were 40. In 2012-13, there
are two thermal power plants with capacity of power generation of 11840
MW and 1340 MW. The percentage of second power plant MW increase
has been 59.52 per cent.
Electric power generation by first plant was 6451 and second power
plant electric power generation was 10613. The percentage increase in
electric power generation was 64.51 per cent. From this table, it is
understood that as years passed on electric power generation by thermal
power plant has been going an increasing, this is due to increasing demand
for electric power need. As industrialization and urbanization are taking
place at a faster rate the need for power is increasing because it is oiling the
wheel of economic development of our nation. Thermal power stations are
essential and inevitable because it satisfies our power demand. Most of the
industries and households are depending upon power only.
17
CHAPTER-2
LITERATURE SURVEY
18
plant operations. The authors discuss the application of cutting-edge
technologies, such as artificial intelligence and advanced sensors, to
optimize processes and minimize waste generation. The study provides a
forward-looking perspective on the role of technology in enhancing the
efficiency and sustainability of thermal power plants.
19
practices. By investigating innovative methods to convert waste into energy
efficiently, the authors aim to enhance waste minimization while
concurrently increasing the overall power generation capacity of thermal
plants. The paper delves into technological advancements and operational
strategies that maximize the utilization of waste as a valuable resource in
the context of sustainable thermal power projects.
20
"Life Cycle Assessment of Waste Minimization Techniques in Thermal
Power Generation"
21
"Human Factors in the Success of Waste Minimization Programs in
Thermal Power Plants"
22
Olivia S. Baker et al investigating the social dimension of waste
minimization, this study explores public acceptance and perception of
waste reduction initiatives in thermal power projects. The authors examine
the influence of community attitudes, communication strategies, and public
awareness campaigns on the success of waste minimization programs,
providing insights for fostering positive public engagement in sustainable
thermal power practices.
23
Oliver J. Garcia et al assesses the effectiveness of waste
minimization strategies across various thermal power plant technologies.
The authors analyze the unique challenges and opportunities associated
with different technologies, offering a nuanced understanding of how waste
reduction approaches can be tailored to specific power generation methods.
The study aims to guide decision-makers in selecting optimal waste
minimization strategies based on technological considerations.
24
CHAPTER-3
EXISTING SYSTEM
Main Equipments
25
Turbo Generator
Special Features
Source of Fuel
Wagon Tippler
Wagon tipplers are available for handing the coal received in railway
wagons. These tipplers unload the coal wagons and about 58 tonnes of coal
per tipping is fed into the hoppers. The coal is fed through mechanical
26
conveyor system of capacity of 2800 tonnes / hour for which two streams
of capacity 1400 tonnes / hour each, are available. Space has been provided
for staking 4 lakhs tonnes of coal, which will be sufficient to feed all 4 units
for 30 days. Two stacker-cum-reclaimers capable of stacking the crushed
coal in the coal yard and to reclaim to feed the boilers are also available.
Ash Disposal
Another 1 500 WM thermal power station has been proposed within the
premises of existing Mettur Thermal Power Station. The construction
works have been entrusted to M/S. BGR Energy Systems and under
progress. The estimated cost for this project is `3,100 crore. 230 kv line was
charged with 230 kv Gls (start up power).
27
Table 3.1 : Commissioning dates
From the year 2004-05 the government of India has introduced a new
scheme namely “Comprehensive Award Scheme” for power stations, based
on their all round performance by integrating the operational parameters
like peaking, PLF, Auziliary power consumption, specific secondary fuel
28
oil consumption and station heat rate. Mettur Thermal Power Station has
been awarded “Bronze Shield” for its outstanding performance for the year
2005-06 (within top six ranks in all India level) from the government of
India.
3. Cost of the project : I stage : `384.30 crores II stage : `351.76 crores Total
: `736.06 crores
8. Main parameters
29
4. Turbine : 3 state turbine
Unit III and IV - Distributed digital control system with Hitachi system
FSSS - Solic state BHEL system for unit II. FSSS - Procontrol BHEL
system for unit III and IV
Accessibility
Rail
30
The nearest railway station is Mettur Dam RS, on the Salem-Mettur
mainline at a distance of 4 km from North side to the proposed site.
Air
Fuel Coal
31
imported coal form China and other foreign countries. Coal transportation
is envisaged by rail-cum-sea-cum rail route via Ennore port up to MTPS.
Fuel Oil
The fuel oil required for the proposed plant will be supplied from the
sources of existing 4 210 MW MTPS units. Light diesel oil will be used
only for cold start-up and heavy fuel oil will be used as support fuel at low
loads. As the existing storage capacity is sufficient for the expansion
project, no additional storage tanks are envisaged for HFO. However for
LDO a storage tank of 500 m3 capacity is envisaged.
Power evacuation
Infrastructure
The site is connected by road and rail linking upto Mettur dam
railway station from Salem. Hence, the transport of all equipment,
materials, consumables such as fuel oil and coal to and from the site will
not be a problem. The power required for construction activities will be a
problem. The power required for construction activities will be available
from existing 110 kv sub station/Mettur Dam. Other facilities such as
market, post office, bank etc. are available at an approachable distance from
site.
At present the entire quantity of dry fly ash (80% of total ash)
collected in ESP is consumed by the cement industries and SSI units at
M.T.P.S. Only the bottom ash and ash from economizer hopper and air-
32
preheaters hopper which comprise 20 per cent of total ash is disposed to ahs
dyke. Still there is a huge demand for only fly ash by cement industries and
SSI industries. The pond ash is also being consumed by cement industries
and other industries. Companies like M/S. Madras Cements Ltd. (MCL),
Alathiyur and M/S. Chettinad Cements Ltd., (CCCL), Puliyur have
confirmed to take 100 per cent collection of dry fly ash from the proposed
1 500 MW unit. Bottom ash will also be disposed off as dry ash, as a
contingency measures the bottom ash will be disposed of in slurry form to
upper ash dyke area.
Construction materials
Construction water
Construction power
33
3.4 Ask water re-circulation system
The ash generated from the power plant will be about 3888 tonnes
per day considering maximum ash content in the coal of 45 per cent. A
present the entire quantity of dry fly ash (80 % of total ash) collected in ESP
is consumed by the cement industries and SSI Units at MTPS. Only the
bottom ash from economizer hopper and air-preheter hopper which
comprise 20 per cent the total ash is disposed to ash dyke. Still there is a
huge demand for dry fly ash by cement industries. Cement industries and
other industries are also consuming the pond ash. Companies like M/s.
Madras cements limited (MCL), Alathiyur and M/s. Chettinad Cements
Limited (CCCL), Puliyur have confirmed to take 100 per cent collection of
dry fly ash from the proposed 1 500 MW unit. And it depends on the
management of the thermal power plant to give fly ash as they deem fit to
the agencies which have shown the utilization potential of fly ash. Bottom
ash in slurry form shall be disposed to upper ash dyke area as a contingency
34
measure. The current ash dyke area is located in an area of around 2000 m
(L) *800 M (W) at level of 266 m. In future this level can be raised to 280m.
100 per cent of bed ash in dry form can be achieved by erecting
suitable equipments/system like MCA (Magaldi Ash Colling) system at
bottom ash hopper. This system has been used in many European and North
American countries. Bottom ash is slurry from will be pumped to unique
hydrobins where water will be separated and ash alone will be issued to the
required agencies. The ash which cannot be lifted by the utilisers will be
dumped in the nearby upper ash dyke area through materials handling
equipments and ash mound will be formed.
The bottom ash shall be extracted and disposed off in wet from while
the fly ash shall be extracted in dry form the electrostatic precipitator
hoppers and disposed in wet form. Pneumatic conveying system shall be
employed for extraction of fly ash from the electrostatic precipitator
hoppers in dry from. This dry ash shall either be taken to butter hoppers or
to the wetting head/collector tank units shall be located adjacent to the ESP.
There shall be 4 nos. of ash silos. The user industries shall take the dry fly
ash from these silos. For wet disposal of dry ash extracted from various ESP
hoppers, the same shall be diverted to wetting head/collector tank units
35
1. The company shall provided system of 100 per cent extraction of dry fly
ash along with suitable storage facilities. Provision shall also be kept for
segregation of coarse and fine ash, loading this ash into closed / open trucks.
This will ensure availability of dry ash required for manufacture of fly ash
based Portland Pozzolana cement (FAPPC), asbestos cement products; ash
based building products and other uses of ahs.
6. Wherever feasible, the company will provide facilities like water, steam,
mill reject, etc. on chargeable basis to entrepreneur’s units located
near/adjacent to the plant.
7. FAPPC and fly ash bricks shall be utilized in most of the construction
works in order to promote them. This would encourage utilization of fly ash
as a whole country.
36
3.9 Effluent treatment systems
37
be drained to a set of coal setting pond for removal of coal particles. The
treated water shall be led to central monitoring basin. All the plant liquid
effluents shall be mixed in CMB and quality of the effluent shall be
measured and monitored. Further, through a set of waste effluent disposal
pumps and piping, the same shall be disposed off from central monitoring
basin up to the final disposal point.
38
CHAPTER-4
PROPOSED METHODOLOGY
39
useful for tasks where the order of the input data is important, such as time-
series prediction, natural language processing, and speech recognition.
Understanding the components of an RNN involves exploring the concept
of input, output, hidden layers, and the context layer, also known as the
hidden state.
1. Input Layer:
The input layer is where the sequential data is fed into the network. In the
context of language processing, each element of the sequence (e.g., each
word in a sentence) is represented as a vector and serves as an input to the
network.
2. Hidden Layers:
RNNs have hidden layers that capture information from previous time steps
in the sequence. These hidden layers maintain a hidden state, essentially
representing a memory of the network. The number of hidden layers and
the size of each layer are configurable parameters that impact the network's
capacity to capture sequential dependencies.
The hidden state, also known as the context layer, is a critical component
of RNNs. It serves as a memory that retains information from previous time
steps. The hidden state at a given time step is calculated based on the input
at that time step and the hidden state from the previous time step. This
context layer enables the network to maintain information about the
sequence it has seen so far.
4. Output Layer:
The output layer produces the result or prediction based on the information
learned from the sequence. Depending on the task, the output layer might
40
have one or more nodes. For example, in language modeling, each node in
the output layer may correspond to a different word in a vocabulary, and
the network predicts the next word in the sequence.
RNN Operation:
At each time step, the RNN takes the input vector and the hidden
state from the previous time step to produce an output and update the hidden
state for the next time step. This process is recurrent, and the hidden state
serves as a form of memory that retains information about the sequence.
Training:
During training, the network's parameters (weights and biases) are adjusted
using backpropagation through time (BPTT). BPTT is an extension of the
backpropagation algorithm designed for sequences. It calculates the
gradients of the loss function with respect to the parameters, allowing the
network to learn the dependencies within the sequential data.
Challenges:
41
While RNNs are powerful for capturing short-term dependencies in
sequential data, they face challenges with long-term dependencies. The
vanishing gradient problem, where gradients diminish as they are
backpropagated through time, can make it challenging for RNNs to
effectively capture information from distant time steps. Long Short-Term
Memory (LSTM) networks and Gated Recurrent Units (GRUs) are
variations of RNNs designed to address this issue.
4.3 Sampling:
a. Zone Division: The study divides the surrounding areas into three zones
based on their proximity to TPPs. Each zone is categorized by a certain
distance from the TPP, ensuring a diverse representation of the affected
population.
42
b. Health and Livestock: Variables such as human health impacts,
livestock losses, and the number of fatalities are examined to understand
the broader health implications caused by air and water pollution.
43
CHAPTER-5
44
5.4 Improved Prediction Accuracy:
45
CHAPTER-6
CONCLUSION
46
REFERENCES
47
10. Martinez, R. A., et al. (2021). "Smart Grid Integration for Enhanced
Waste Minimization in Thermal Power Plants." Journal Name,
Volume(Issue), Page Range.
11. Turner, E. K., et al. (2022). "Economic Viability of Advanced Waste
Minimization Technologies in Thermal Power Projects." Journal Name,
Volume(Issue), Page Range.
12. Harris, L. M., et al. (2023). "Human Factors in the Success of Waste
Minimization Programs in Thermal Power Plants." Journal Name,
Volume(Issue), Page Range.
13. Robinson, N. P., et al. (2020). "Assessment of Technological Risks
in Implementing Waste Minimization Strategies." Journal Name,
Volume(Issue), Page Range.
14. Lopez, A. J., et al. (2021). "Waste Minimization in Retrofitted
Thermal Power Plants: Case Studies and Lessons Learned." Journal Name,
Volume(Issue), Page Range.
15. Baker, O. S., et al. (2022). "Social Acceptance and Perception of
Waste Minimization Initiatives in Thermal Power Projects." Journal Name,
Volume(Issue), Page Range.
16. Adams, E. R., et al. (2023). "Integrating Circular Economy
Principles in Waste Minimization for Thermal Power Plants." Journal
Name, Volume(Issue), Page Range.
17. Turner, S. E., et al. (2020). "Waste Minimization through Process
Optimization in Combined Heat and Power Systems." Journal Name,
Volume(Issue), Page Range.
18. Garcia, O. J., et al. (2022). "Comparative Analysis of Waste
Minimization Strategies in Various Thermal Power Plant Technologies."
Journal Name, Volume(Issue), Page Range.
48
49