Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

2 FRO PVC I To IV

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 163

GOVERNMENT OF TELANGANA

TELANGANA FOREST DEPARTMENT

WORKDONE ESTIMATE & COMPLETION REPORT

Name of the work : Construction of FSO/ Dy.R.O.


Quarter at Suraram Beat of Suraram Section of
Paloncha Range of Paloncha Division, during 2022-
23 under CAMPA - NPV scheme.

Name of the Division : Yellandu


Name of the Range : Komararam
Name of the Section : Polaram
Name of the Beat : Bombai Thanda
Estimate Cost : 30.70 Lakhs
Grant : CAMPA

Forest Range Officer


Komararam
Specification Report
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section
of Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.
Estt. Cost : Rs. 14.00 Lakhs

The work Construction of Sub center at Manikyaram (V) Singareni (M) was Administrativey
Sanctioned vide Proc. No.152/FW-Plg/2015, Dt.09/01/2015., Commissionar of Health and Family Welfare and
Mission Director (NHM) Hyderabad. The work was entrusted to Sri A. Anjaiah, Contractor, H. No.3-119/1,
Karepally X Road, Viswanathpally, Singareni (M) Khammam Dist., in tendering process for a Tender Percentage of
14.99% Less on estimate rates. The work was Technically Santioned vide. TS. No. /2017-18, of SE/TW/WGL,
Dt.05.10.2017. of Superintending Engineer, Tribal Welfare Circle, Warangal.

Accordingly the work was started and completed by the contractor in all aspects and the following
deviations are occured.

1) VRCC M25 Grade corresponding to IS 456 using 20mm size graded machine crushed metal for Footings,
Pedastals & Roof Beams.
2) Filling with Gravel in trenches, sides of foundations and basement with initial lead in layers not exceeding 15cm
thick.
3) Brick Masonry in superstructure with CM (1:8) prop: using second class bricks from approved source having
minimum crushing strength of 40 Kg/Sqcm.
4) Providing & Fixing of Open able Windows with Flymesh made of pre-painted steel as per IS 513 of 0.58 mm
thick galvanized as per IS 277 finish painted with a polyester paint
5) Plastering 20mm thick in two coats with base coat of 16mm thick in CM (1:6) and top coat of 4mm thick in CM
(1:4) dubara sponge finish.
6) Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg of water proof
compound per bag.
7) Flooring with soluble salt porcelain vitrified tiles screen printed and polished of size 600 x 600 mm and
thickness between 8-10 mm 1st quality.
8) Painting to New External Walls with two coats of Plastic Emulsion paint of Asian / Berger / Nerolac / Saicoat /
Endocem or equalent quality of approved brand and shade.
9) White washing two coats with paint grade white lime for wash or equivalent quality to give an even shade
10) Electrification and water supply arrangement items for total building was deviated.
11) Price adjustment done.

The building was completed in all aspects and the work done estimate for the building was
worked out to Rs. 14,35,480.31./-.

An early sanction of the Work done estimate is Solicited.

Err:509
Err:509
GENERAL ABSTRACT
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram
Beat of Suraram Section of Paloncha Range of Paloncha Division,
during 2022-23 under CAMPA - NPV scheme.

Sl. No. Description of Item Amount

1 Construction of FSO Quarter 2292471.29

2 Water Supplay and Sanitor arrangements @11% 252171.84

3 Electrification @9% 206322.42

Sub-Total :: 2750965.55

4 Deduct Tender Premium @3% -82528.97

Sub-Total :: 2668436.58

5 Add GST @12% 320212.39

6 Add Cess @ 1% 26684.37

GRAND TOTAL :: 3015333.34

Forest Range Officer, Forest Divisional Officer,


E.Bayyaram Manuguru,
GENERAL ABSTRACT II
Name of the work : Construction of Ground Floor with R.C.C. at Yeducharlapalli
Venkatapuram

As per As per
Remar
Sl. No. Description of the Item sanction Workdone Excess Less ks
Estimate Estimate
1 2 3 4 5 6 7

1 Construction of FRO Quarter 2766612.00 0.00 0.00 2766612.00


Water Supplay and Sanitor
2 arrangements @7% 193663.00 0.00 0.00 193663.00

3 Electrification @9% 165997.00 0.00 0.00 165997.00

Sub-Total :: 3126272.00 0.00


Deduct Tender Premium
4 @17.06% 0.00 0.00 0.00 0.00

Sub-Total :: 3126272.00 0.00

5 Add GST @18% 375153.00 0.00 0.00 375153.00

6 Add Cess @ 1% 31263.00 0.00 0.00 31263.00

GRAND TOTAL:: 3532688.00 0.00 0.00 3532688.00

As Per Sanction Estimate :: 3532688.00 Exess :: 0.00


As Per Work Done Estimate :: 0.00 Less :: 3532688.00
Difference :: 3532688.00 3532688.00 Excess

Forest Range Officer, Forest Divisional Officer,


Palvancha Palancha
WORKDONE ESTIMATE
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of Paloncha
Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.
Sub Estimate : Compound wall
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1) Earth work excavation for foundations and depositing on bank for all
lifts and with an initial lead of 10m including all operational, incidental,
seigniorage charges, labour charges such as shoring ,sheeting,
planking, strutting, dewatering etc. complete for finished item of work
as per SS - 20 B (APSS 308). for Building Foundation.
Qty. V. P. No. 14 of M. B. No. : 196/C/TW/19-20
For Gate Columns 1 2 1.20 1.20 1.20 3.45
2/Feb/20 3.45 Cum 336.53 1 Cum 1161.02
2) Plain Cement Concrete (1:5:10) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and
conveyance of all materials like cement, sand, coarse aggregate, water
etc. to site, mixing concrete in concrete mixer including seigniorage
charges, sales & other taxes on all materials, all operational, incidental,
and labour charges such as laying and ramming concrete in layers in
position not exceeding 15cm, finishing top surface, curing concrete,
etc., complete for finished item of work. (APSS No. 402).

Qty. V. P. No. 15 of M. B. No. : 196/C/TW/19-20


For Gate Columns 1 2 1.20 1.20 0.15 0.43
5/Feb/20 0.43 Cum Err:509 1 Cum Err:509
3) Vibrated Reinforced Cement Concrete M20 Grade corresponding to IS
456 using 20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales
& other taxes on all materials including all operational, incidental and
labour charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with
minimum cement content @ 380Kgs/Cum from standard suppliers
approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete.
A) Footings
Qty. V. P. No. 16 of M. B. No. : 196/C/TW/19-20
Footings 1 2 1.20 1.20 0.30 0.86
08/Feb/20 0.86 Cum 9302.11 1 Cum 7999.81
B) Columns
Qty. V. P. No. 17 of M. B. No. : 196/C/TW/19-20
Columns 1 2 0.40 0.40 2.40 0.76
08/Feb/20 0.76 Cum 11963.17 1 Cum 9092.00
4) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500
grade as per IS 1786-1979) of different diameters for RCC works,
including labour charges for straightening, cutting, bending to required
sizes and shapes, placing in position with cover blocks of approved
materials and size and tying and lapsplicing with binding wire of 18
SWG, forming grills for reinforcement work as per approved designs
and drawings, including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars including cost
and conveyance of binding wire, cover blocks and all incidental,
operational, laour charges such as cutting, bending placing in position,
tying including sales and other taxes on all materials etc., complete for
finished item of work in all floors. (APSS No.126).

Qty. V. P. No. 15 of M. B. No. : 196/C/TW/19-20 5/Feb/20 88.40 Kg


88.40 Kg
Or in M.T. 0.088 M.T. 63.94 1 MT 5.62
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
5) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks from approved source having minimum crushing strength of 40
Kg/Sqcm. including cost and conveyance of all materials like cement,
sand, bricks, water etc., to site, including seigniorage charges, sales &
other taxes on all materials, all operational, incidental and labour
charges such as mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc., complete for finished item
of work.
Qty. V. P. No. 18 of M. B. No. : 196/C/TW/19-20
CW 1 1 0.60 0.23 1.20 0.16
17/Feb/20 0.16 Cum 6222.35 1 Cum 995.57
6) Supply and fixing of main gate madeout of MS bars of different sizes,
outer frame with a width of 1.20m and height 1.50m including cost and
conveyance of all charges etc., complete.
Qty. V. P. No. 18 of M. B. No. : 196/C/TW/19-20
1 1 - - - 1.00
17/Feb/20 1.00 No.s 16297.72 1 Each 16297.72
6) Plastering 12mm thick in two coats with base coat of 8mm thick in CM
(1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish
including cost and conveyance of all materials like cement, sand, water
etc., to site, seigniorage charges, sales & other taxes on all materials,all
operational, incidental and labour charges such as mixing mortar,
scaffolding charges, lift charges, including cutting of Grooves wherever
necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete for finished item of work. (APSS 901,903 & 904).

Qty. V. P. No. 18 of M. B. No. : 196/C/TW/19-20


For C Wall 1 2 0.60 - 1.20 1.44
1 1 0.60 0.23 - 0.13
Columns 2 4 0.40 - 1.60 5.12
1 1 0.23 - 1.60 0.36
1 1 0.40 - 1.60 0.64
17/Feb/20 7.69 Sqm Err:509 10 Sqm Err:509

Total:- Err:509

Asst. Exe. Engineer Deputy Exe. Engineer Executive Engineer


T.W. Tekulapally T.W.S.D. - Sudimalla T.W.Divn., Bhadrachalam
WORKDONE ESTIMATE
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram
Section of Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV
scheme.
M. B. No. : 141/2019-20
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1) Earth work excavation for foundations and depositing on bank
for all lifts and with an initial lead of 10m including all
operational, incidental, labour charges such as
shoring ,sheeting, planking, strutting, etc. complete for finished
item of work including seigniorage excluding dewatering
charges etc as per SS - 20 B (APSS 308). for building
foundation.
Qty. V. P. No. 1 of M. B. No. : 141/2019-20
Column Pits 1 15 5.50 5.00 4.00 1650.00
1 1 4.50 4.00 4.00 72.00
1722.00 Cuf
Qty. V. P. No. 10 & 11 of M. B. No. : 141/2019-20
CRS walls A3A4-N.S 1 1 15.75 2.00 2.00 63.00
A2A3-N.S 1 1 16.42 2.00 2.00 65.68
A1A2-N.S 1 1 10.58 2.00 2.00 42.32
B1B2-N.S 1 1 2.25 2.00 2.00 9.00
D1D2-N.S 1 1 8.00 2.00 3.00 48.00
C3C4-N.S 1 1 15.50 2.00 3.00 93.00
C2C3-N.S 1 1 10.66 2.00 3.00 63.96
C3C4-N.S 1 1 10.83 2.00 3.00 64.98
B5 to stair case 1 1 8.00 2.00 2.00 32.00
A1B1-W.E 1 1 14.50 2.00 2.00 58.00
B1D1-W.E 1 1 15.33 2.00 2.00 61.32
C1D2-W.E 1 1 2.33 2.00 2.00 9.32
C4B5-W.E 1 1 12.50 2.00 2.00 50.00
B5A4-W.E 1 1 14.50 2.00 2.00 58.00
718.58 Cu.F.
Qty. V. P. No. 78 of M. B. No. : 141/2019-20
Wash Area N.S. 1 2 8.00 2.00 3.00 96.00
W.E 1 1 30.00 2.00 3.00 180.00
276.00 Cu.F.
Total in Cu.Ft :: 2716.58 Cu.Ft
Total in Cu.Mt :: 76.92 Cu.Mt 351.53 1 Cu.Mt 27039.69
2) Excavation in hard rock with blasting prohibited for foumdations
of canel cross drainage and other appurtenant structures and
placing the excavated rock neatly in or stock yard as directed
etc., complete with specified dump area initiated lead up to 50m
and initial lift up to 3m.
Qty. V. P. No. 02 of M. B. No. : 141/2019-20
Pneumatic breaker 9 8 - - - 72.00
72.00 Hrs 235.60 1 Hr 16963.20
Fuel/Energy charges 9 8 - - - 72.00
72.00 Hrs 839.30 1 Hr 60429.60
3) Vibrated Plain Cement Concrete (1:3:6) proportion (cement:
fine aggregate: Coarse aggregate) using 40mm size Hard
Broken Granite (IS383, 1970) machine crushed metal from
approved quarry including cost and conveyance of all materials
like cement, sand, coarse aggregate, water etc. to site, mixing
concrete in concrete mixer including seigniorage charges, sales
& other taxes on all materials, all operational, incidental, and
labour charges such as laying and ramming concrete in layers
in position not exceeding 15cm, finishing top surface, curing
concrete, etc., complete for finished item of work.

Qty. V. P. No. 03 of M. B. No. : 141/2019-20


PCC Under Col. Footings 1 15 5.00 5.00 0.50 187.50
1 1 4.00 4.00 0.50 8.00
195.50 Cu.F.
Qty. V. P. No. 12 & 13 of M. B. No. : 141/2019-20
CRS walls A3A4-N.S 1 1 15.75 1.50 0.50 11.81
A2A3-N.S 1 1 16.42 1.50 0.50 12.32
A1A2-N.S 1 1 10.58 1.50 0.50 7.94
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
B1B2-N.S 1 1 2.25 1.50 0.50 1.69
D1D2-N.S 1 1 8.00 1.50 0.50 6.00
C3C4-N.S 1 1 15.50 1.50 0.50 11.63
C2C3-N.S 1 1 10.66 1.50 0.50 8.00
C3C4-N.S 1 1 10.83 1.50 0.50 8.12
B5 to stair case 1 1 8.00 1.50 0.50 6.00
A1B1-W.E 1 1 14.50 1.50 0.50 10.88
B1D1-W.E 1 1 15.33 1.50 0.50 11.50
C1D2-W.E 1 1 2.33 1.50 0.50 1.75
C4B5-W.E 1 1 12.50 1.50 0.50 9.38
B5A4-W.E 1 1 14.50 1.50 0.50 10.88
117.90 Cu.F.
Qty. V. P. No. 78 of M. B. No. : 141/2019-20
Wash Area N.S. 1 2 8.00 2.00 3.00 96.00
W.E 1 1 30.00 2.00 3.00 180.00
276.00 Cu.F.
Total in Cu.Ft :: 589.40 Cu.Ft
Total in Cu.Mt :: 16.69 Cu.Mt 4724.13 1 Cu.Mt 78845.73
4) Providing High Yield Strength Deformed (HYSD) steel bars (Fe
500 grade as per IS 1786-1979) of different diameters for RCC
works, including labour charges for straightening, cutting,
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and
lapsplicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and
all incidental, operational, laour charges such as cutting,
bending placing in position, tying including sales and other
taxes on all materials etc., complete for finished item of work in
all floors. (APSS No.126).

Qty. V. P. No. 5 of M. B. No. : 141/2019-20 690.88 Kg


Qty. V. P. No. 18 of M. B. No. : 141/2019-20 112.38 Kg
Qty. V. P. No. 27 of M. B. No. : 141/2019-20 778.27 Kg
Qty. V. P. No. 31 of M. B. No. : 141/2019-20 465.77 Kg
Qty. V. P. No. 37 of M. B. No. : 141/2019-20 90.68 Kg
Qty. V. P. No. 48 of M. B. No. : 141/2019-20 1993.76 Kg
Qty. V. P. No. 58 of M. B. No. : 141/2019-20 56.34 Kg
Qty. V. P. No. 62 of M. B. No. : 141/2019-20 66.61 Kg
Qty. V. P. No. 65 of M. B. No. : 141/2019-20 35.76 Kg
Qty. V. P. No. 80 of M. B. No. : 141/2019-20 99.45 Kg
Qty. V. P. No. 83 of M. B. No. : 141/2019-20 247.54 Kg
4637.44 Kg 65.85 1 Kg 305375.42
5) VRCC (1:1½:3)prop nominal mix using 6 to 20mm (SS-5)
graded machine crushed hard granite metal (coarse aggregate)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges, sales &
other taxes on all materials including all operational, incidental
and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel
and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from
standard suppliers approved by the department including
centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Column Footings.

Qty. V. P. No. 06 of M. B. No. : 141/2019-20


Straight 1 15 5.00 5.00 0.50 187.50
1 1 4.00 4.00 0.50 8.00
Taper (average) 1 16 3.16 2.88 1.00 145.61
Total in Cu.Ft :: 341.11 Cu.Ft
Total in Cu.Mt :: 9.66 Cu.Mt 9295.06 1 Cu.Mt 89790.28
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
6) VRCC (1:1½:3)prop nominal mix using 6 to 20mm (SS-5)
graded machine crushed hard granite metal (coarse aggregate)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges, sales &
other taxes on all materials including all operational, incidental
and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel
and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from
standard suppliers approved by the department including
centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Columns.

Qty. V. P. No. 7 of M. B. No. : 141/2019-20


Columns 1 12 1.25 0.75 5.66 63.67
Columns 1 1 0.75 0.75 5.00 2.81
Circular columns 1 3 r = 0.5 13.33
79.81 Cu.F.
Qty. V. P. No. 32 of M. B. No. : 141/2019-20
Columns 1 12 1.25 0.75 10.00 112.50
Circuler Columns 1 3 r=0.50 23.55
Columns stair case supporting 1 1 0.75 0.75 5.00 2.81
138.86 Cu.F.
Total in Cu.Ft :: 218.67 Cu.Ft
Total in Cu.Mt :: 6.19 Cu.Mt 11460.11 1 Cu.Mt 70938.08
7) Filling with useful available excavated earth (excluding rock) in
trenches, sides of foundations and basement with initial lead in
layers not exceeding 15 cm thick, consolidating each deposited
layer by watering and ramming including cost and conveyance
of water to work site and all operational, incidental, labour
charges, hire charges of T & P etc., complete for finished item
of work. APSS No.309 & 310.
Qty. V. P. No. 8 & 9 of M. B. No. : 141/2019-20
Columns pits 1 15 5.50 5.00 4.00 1650.00
1 1 4.00 4.00 4.00 64.00
Deduct PCC -1 15 5.00 5.00 0.50 -187.50
-1 1 4.00 4.00 0.50 -8.00
Deduct Footing -1 15 5.00 5.00 0.50 -187.50
-1 1 4.00 4.00 0.50 -8.00
Deduct Taper -1 16 3.16 2.88 1.00 -145.61
Deduct Column -1 12 1.25 0.75 2.00 -22.50
Deduct circular Column -1 3 r=0.50 - 2.00 -1.57
Deduct Column -1 1 0.75 0.75 2.00 -1.13
1152.19 Cu.F.
Qty. V. P. No. 16 & 17 of M. B. No. : 141/2019-20
CRS walls A3A4-N.S 1 1 15.75 1.50 2.00 47.25
A2A3-N.S 1 1 16.42 1.50 2.00 49.26
A1A2-N.S 1 1 10.58 1.50 2.00 31.74
B1B2-N.S 1 1 2.25 1.50 2.00 6.75
D1D2-N.S 1 1 8.00 1.50 3.00 36.00
C3C4-N.S 1 1 15.50 1.50 3.00 69.75
C2C3-N.S 1 1 10.66 1.50 3.00 47.97
C3C4-N.S 1 1 10.83 1.50 3.00 48.74
B5 to stair case 1 1 8.00 1.50 2.00 24.00
A1B1-W.E 1 1 14.50 1.50 2.00 43.50
B1D1-W.E 1 1 15.33 1.50 2.00 45.99
C1D2-W.E 1 1 2.33 1.50 2.00 6.99
C4B5-W.E 1 1 12.50 1.50 2.00 37.50
B5A4-W.E 1 1 14.50 1.50 2.00 43.50
538.94 Cu.F.
Qty. V. P. No. 79 of M. B. No. : 141/2019-20
Wash Area N.S. 1 2 8.00 2.00 3.00 96.00
W.E 1 1 30.00 2.00 3.00 180.00
276.00 Cu.F.
Total in Cu.Ft :: 1967.13 Cu.Ft
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Total in Cu.Mt :: 55.70 Cu.Mt 31.20 1 Cu.Mt 1737.84
8) Coursed Rubble Stone Masonry in CM (1:3) Prop: including cost
and conveyance of all materials like cement, sand, water etc., to
site, including seigniorage charges, sales & other taxes on all
materials, all operational, incidental charges and labour charges
such as mixing mortar, finishing, curing, etc., complete for
finished item of work. (APSS 901,906)
Qty. V. P. No. 14 & 15 of M. B. No. : 141/2019-20
CRS walls A3A4-N.S 1 1 15.75 1.50 3.33 78.67
A2A3-N.S 1 1 16.42 1.50 3.33 82.01
A1A2-N.S 1 1 10.58 1.50 3.33 52.85
B1B2-N.S 1 1 2.25 1.50 3.33 11.24
D1D2-N.S 1 1 8.00 1.50 3.33 39.96
C3C4-N.S 1 1 15.50 1.50 3.33 77.42
C2C3-N.S 1 1 10.66 1.50 3.33 53.25
C3C4-N.S 1 1 10.83 1.50 3.33 54.10
B5 to stair case 1 1 8.00 1.50 3.33 39.96
A1B1-W.E 1 1 14.50 1.50 3.33 72.43
B1D1-W.E 1 1 15.33 1.50 3.33 76.57
C1D2-W.E 1 1 2.33 1.50 3.33 11.64
C4B5-W.E 1 1 12.50 1.50 3.33 62.44
B5A4-W.E 1 1 14.50 1.50 3.33 72.42
784.96 Cu.F.
Qty. V. P. No. 23 & 24 of M. B. No. : 141/2019-20
CRS walls A3A4-N.S 1 1 15.75 1.50 2.00 47.25
A2A3-N.S 1 1 16.42 1.50 2.00 49.26
A1A2-N.S 1 1 10.58 1.50 2.00 31.74
B1B2-N.S 1 1 2.25 1.50 2.00 6.75
D1D2-N.S 1 1 8.00 1.50 2.00 24.00
C3C4-N.S 1 1 15.50 1.50 2.00 46.50
C2C3-N.S 1 1 10.66 1.50 2.00 31.98
C3C4-N.S 1 1 10.83 1.50 2.00 32.49
B5 to stair case 1 1 8.00 1.50 2.00 24.00
A1B1-W.E 1 1 14.50 1.50 2.00 43.50
B1D1-W.E 1 1 15.33 1.50 2.00 45.99
C1D2-W.E 1 1 2.33 1.50 2.00 6.99
C4B5-W.E 1 1 12.50 1.50 2.00 37.50
B5A4-W.E 1 1 14.50 1.50 2.00 43.50
471.45 Cu.F.
Qty. V. P. No. 79 of M. B. No. : 141/2019-20
Wash Area N.S. 1 2 8.00 1.50 5.50 132.00
W.E 1 1 30.00 1.50 5.50 247.50
379.50 Cu.F.
Total in Cu.Ft :: 1635.91 Cu.Ft
Total in Cu.Mt :: 46.32 Cu.Mt 4159.00 1 Cu.Mt 192644.88
9) VRCC (1:1½:3)prop nominal mix using 6 to 20mm (SS-5)
graded machine crushed hard granite metal (coarse aggregate)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges, sales &
other taxes on all materials including all operational, incidental
and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel
and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from
standard suppliers approved by the department including
centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Plinth Beam.

Qty. V. P. No. 21 & 22 of M. B. No. : 141/2019-20


Beams A3A4-N.S 1 1 15.75 1.50 0.33 7.80
A2A3-N.S 1 1 16.42 1.50 0.33 8.13
A1A2-N.S 1 1 10.58 1.50 0.33 5.24
B1B2-N.S 1 1 2.25 1.50 0.33 1.11
D1D2-N.S 1 1 8.00 1.50 0.33 3.96
C3C4-N.S 1 1 15.50 1.50 0.33 7.67
C2C3-N.S 1 1 10.66 1.50 0.33 5.28
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
C3C4-N.S 1 1 10.83 1.50 0.33 5.36
B5 to stair case 1 1 8.00 1.50 0.33 3.96
A1B1-W.E 1 1 14.50 1.50 0.33 7.18
B1D1-W.E 1 1 15.33 1.50 0.33 7.59
C1D2-W.E 1 1 2.33 1.50 0.33 1.15
C4B5-W.E 1 1 12.50 1.50 0.33 6.19
B5A4-W.E 1 1 14.50 1.50 0.33 7.18
77.80 Cu.F.
Qty. V. P. No. 28 & 29 of M. B. No. : 141/2019-20
Plinth Beams
N.S - A1A4 1 1 47.58 0.75 1.00 35.69
- B1B5 1 1 51.00 0.75 1.00 38.25
- C1C4 1 1 41.16 0.75 1.00 30.87
- D1D2 1 1 9.58 0.75 1.00 7.19
N.S. 1 1 4.50 0.75 1.00 3.38
N.S. 1 1 4.16 0.75 1.00 3.12
W.E - B1D1 1 1 15.00 0.75 1.00 11.25
1 5 14.50 0.75 1.00 54.38
1 5 12.50 0.75 1.00 46.88
1 1 2.33 0.75 1.00 1.75
232.76 Cu.F.
Qty. V. P. No. 81 of M. B. No. : 141/2019-20
N.S 1 2 8.00 0.75 0.75 9.00
W.E 1 1 30.00 0.75 0.75 16.88
25.88 Cu.F.
Total in Cu.Ft :: 336.44 Cu.Ft
Total in Cu.Mt :: 9.53 Cu.Mt 11677.46 1 Cu.Mt 111286.19
10) Filling Carted Morrum in trenches, sides of foundations and
basement with initial lead in layers not exceeding 15cm thick,
consolidating each deposited layer by watering and ramming
including all operational, incidental, labour charges, seignorage
charges, hire charges of T & P etc., complete for finished item
of work. (APSS NO. 309 & 310).
Qty. V. P. No. 33 of M. B. No. : 141/2019-20
Plinth Beam 1 1 47.58 28.25 5.66 7607.80
1 1 15.00 2.25 5.66 191.03
1 1 5.33 3.83 5.66 115.54
7914.37 Cu.F.
Qty. V. P. No. 81 of M. B. No. : 141/2019-20
1 1 30.00 8.00 4.00 960.00
960.00 Cu.F.
Total in Cu.Ft :: 8874.37 Cu.Ft
Total in Cu.Mt :: 251.29 Cu.Mt 314.65 1 Cu.Mt 79068.40
11) Vibrated Plain Cement Concrete (1:4:8) proportion (cement:
fine aggregate: Coarse aggregate) using 40mm size Hard
Broken Granite (IS383, 1970) machine crushed metal from
approved quarry including cost and conveyance of all materials
like cement, sand, coarse aggregate, water etc. to site, mixing
concrete in concrete mixer including seigniorage charges, sales
& other taxes on all materials, all operational, incidental, and
labour charges such as laying and ramming concrete in layers
in position not exceeding 15cm, finishing top surface, curing
concrete, etc., complete for finished item of work.
Qty. V. P. No. 34 & 35 of M. B. No. : 141/2019-20
Varandah 1 1 15.33 8.00 0.33 40.47
1 1 22.66 12.50 0.33 93.47
1 1 4.58 4.50 0.33 6.80
1 1 9.00 5.00 0.33 14.85
Poojs 1 1 5.00 4.16 0.33 6.86
Kitchen 1 1 12.50 11.33 0.33 46.73
Study/Draiwng 1 1 15.00 11.66 0.33 57.72
Bed Room - I 1 1 15.00 16.00 0.33 79.20
Bed Room - II 1 1 15.00 12.00 0.33 59.40
Toilet - I 1 1 9.00 5.00 0.33 14.85
Toilet - II 1 1 8.00 4.50 0.33 11.88
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
432.23 Cu.F.
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Qty. V. P. No. 81 of M. B. No. : 141/2019-20
Wash area 1 1 28.00 7.25 0.330 66.99
66.99 Cu.F.
Total in Cu.Ft :: 499.22 Cu.Ft
Total in Cu.Mt :: 14.14 Cu.Mt 4466.60 1 Cu.Mt 63157.72
12) VRCC (1:1½:3)prop nominal mix using 6 to 20mm (SS-5)
graded machine crushed hard granite metal (coarse aggregate)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges, sales &
other taxes on all materials including all operational, incidental
and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel
and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from
standard suppliers approved by the department including
centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Roof Beams.

Qty. V. P. No. 38 & 39 of M. B. No. : 141/2019-20


a) Beams
i) Landing Beam 1 1 8.00 0.75 1.00 6.00
ii) Mid landing Beam 1 1 8.00 0.75 1.00 6.00
12.00 Cu.F.
Qty. V. P. No. 49 & 50 of M. B. No. : 141/2019-20
N.S. - A1A4 1 1 50.58 0.75 1.00 37.94
B1B5 1 1 53.58 0.75 1.00 40.19
C1C4 1 1 42.00 0.75 1.00 31.50
D1D2 1 1 9.58 0.75 1.00 7.19
1 4 18.00 0.75 1.00 54.00
1 5 15.50 0.75 1.00 58.13
228.95 Cu.F.
Qty. V. P. No. 59 & 60 of M. B. No. : 141/2019-20
a) tie Beams
N.S 1 4 10.50 0.375 0.33 5.20
1 2 16.00 0.375 0.33 3.96
1 2 9.40 0.375 0.33 2.33
1 2 4.00 0.375 0.33 0.99
1 6 14.50 0.375 0.33 10.77
1 4 5.50 0.375 0.33 2.72
W.E. 1 2 12.50 0.375 0.33 3.09
29.06 Cu.F.
Total in Cu.Ft :: 270.01 Cu.Ft
Total in Cu.Mt :: 7.65 Cu.Mt 10339.27 1 Cu.Mt 79095.42
13) VRCC (1:1½:3)prop nominal mix using 6 to 20mm (SS-5)
graded machine crushed hard granite metal (coarse aggregate)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges, sales &
other taxes on all materials including all operational, incidental
and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel
and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from
standard suppliers approved by the department including
centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Waist Slab.

Qty. V. P. No. 39 of M. B. No. : 141/2019-20


Stair case Slab
i) First flight 1 1 14.00 3.33 - 46.62
ii) Mid landing 1 1 8.75 3.50 - 30.63
77.25 SqF
Qty. V. P. No. 50 of M. B. No. : 141/2019-20
Stair case Slab
i) Second flight 1 1 13.00 3.00 - 39.00
39.00 Sqf
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Total in Sq.Ft :: 116.25 Sq.Ft
Total in Sq.Mt :: 10.80 Sq.Mt 1455.60 1 Sq.Mt 15720.48
14) VRCC (1:1½:3)prop nominal mix using 6 to 20mm (SS-5)
graded machine crushed hard granite metal (coarse aggregate)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges, sales &
other taxes on all materials including all operational, incidental
and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel
and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from
standard suppliers approved by the department including
centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Roof Slab.

Qty. V. P. No. 50 of M. B. No. : 141/2019-20


Roof Slab 1 1 50.58 35.66 - 1803.68
Near steps 1 1 18.00 3.00 - 54.00
Total in Sq.Ft :: 1857.68 Sq.Ft
Total in Sq.Mt :: 172.58 Sq.Mt 1182.85 1 Sq.Mt 204136.25
15) Impervious coat 20mm thick over RCC roof slab surface with
CM(1:3), promixed with 1kg of water proof compound per bag
of cement laid over roof when it is green including cost of all
materials, seigniorage charges, excluding conveyance charges
of materials and including all operational, incidental and labour
charges for mixing mortar, laying, rendering smooth and thread
lining, curing, rounding off junctions of wall and slab etc,,
complete for finished item of work.
Qty. V. P. No. 51 of M. B. No. : 141/2019-20
Terrace Flooring 1 1 50.58 35.66 - 1803.68
1 1 18.00 3.00 - 54.00
Total in Sq.Ft :: 1857.68 Sq.Ft
Total in Sq.Mt :: 172.58 Sq.Mt 4669.87 10 Sq.Mt 80592.62
16) Brick Masonry in superstructure with CM (1:8) prop: using
second class bricks of size 23 x 11 x 7 Cms from approved
source having minimum crushing strength of 40 Kg/Sqcm.
including cost and conveyance of all materials like cement,
sand, bricks, water etc., to site, including seigniorage charges,
sales & other taxes on all materials, all operational, incidental
and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc.,
complete for finished item of work. 9" Brick wall

Qty. V. P. No. 53 to 54 of M. B. No. : 141/2019-20


1 1 10.50 - 10.00 105.00
1 2 4.50 - 10.00 90.00
1 1 12.00 - 10.00 120.00
1 1 15.50 - 10.00 155.00
1 1 11.00 - 10.00 110.00
1 1 21.50 - 10.00 215.00
1 2 14.50 - 10.00 290.00
1 2 12.50 - 10.00 250.00
Deductions :-
w1 -1 1 4.75 4.50 - -21.37
w1 -1 2 7.00 4.50 - -63.00
w2 -1 3 5.00 4.50 - -67.50
w3 -1 2 4.00 4.50 - -36.00
D1 -1 1 7.00 3.00 - -21.00
D2 -1 1 7.00 2.75 - -19.25
V1 -1 3 3.00 2.00 - -18.00
1088.88 SqF
Qty. V. P. No. 92 of M. B. No. : 141/2019-20
Steps at varandah -
East side stair case waist 0.50 4 3.00 - 12.50 75.00
stpes 1 4 12.50 - 0.75 37.50
North side - waist 0.50 4 3.00 - 17.25 103.50
Steps 1 4 17.25 - 0.75 51.75
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
267.75 SqF
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Qty. V. P. No. 97 of M. B. No. : 141/2019-20
N-S 1 1 48.33 - 12.00 579.96
1 1 41.00 - 12.00 492.00
W-E 1 1 13.00 - 11.00 143.00
1 1 15.50 - 12.00 186.00
1 1 30.00 - 12.00 360.00
Deductions :- D1 -1 1 3.00 - 7.00 -21.00
D2 -1 1 2.75 - 7.00 -19.25
W1 -1 1 4.75 - 4.50 -21.37
W1 -1 2 7.00 - 4.50 -63.00
W2 -1 3 5.00 - 4.50 -67.50
W3 -1 2 4.00 - 4.50 -36.00
KW -1 1 4.00 - 3.50 -14.00
V1 -1 3 3.00 - 2.00 -18.00
1500.84 Sqf
Qty. V. P. No. 99 of M. B. No. : 141/2019-20
N-S 1 1 8.00 - 5.66 45.28
1 1 4.50 - 6.00 27.00
1 0.5 16.00 5.66 - 45.28
W-E 1 1 12.83 - 6.00 76.98
- 194.54 Sqf
Total in Sq.Ft :: 3052.01 Sq.Ft
Total in Sq.Mt :: 283.54 Sq.Mt
Total in Cu.Mt :: 65.21 Cu.Mt #NAME? 1 Cu.Mt #NAME?
17) Brick Masonry in superstructure with CM (1:8) prop: using second
class bricks of size 23 x 11 x 7 Cms from approved source having
minimum crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, sand, bricks, water etc., to
site, including seigniorage charges, sales & other taxes on all
materials, all operational, incidental and labour charges such as
mixing cement mortar, constructing masonry, scaffolding charges, lift
charges, curing, etc., complete for finished item of work. 4.5" Brick
wall
Qty. V. P. No. 54 to 55 of M. B. No. : 141/2019-20
NS 1 1 10.50 10.00 - 105.00
1 1 4.50 11.00 - 49.50
1 1 10.50 10.00 - 105.00
1 1 16.00 10.00 - 160.00
1 1 9.40 11.00 - 103.40
1 1 4.00 11.00 - 44.00
WE 1 2 14.50 10.00 - 290.00
1 1 14.50 11.00 - 159.50
1 1 5.50 11.00 - 60.50
1 1 12.50 11.00 - 137.50
1 1 5.50 10.00 - 55.00
Deductions :-
D1 -1 4 3.00 7.00 - -84.00
D2 -1 1 2.75 7.00 - -19.25
D3 -1 3 2.50 7.00 - -52.50
Tie Beams -1 4 10.50 0.33 - -13.86
Tie Beams -1 6 14.50 0.33 - -28.71
-1 2 16.00 0.33 - -10.56
-1 2 9.40 0.33 - -6.20
-1 4 5.50 0.33 - -7.26
-1 2 12.50 0.33 - -8.25
-1 2 4.00 0.33 - -2.64
1036.17 SqF
Qty. V. P. No. 76 of M. B. No. : 141/2019-20
a) Stair case 1 28 3.00 0.83 - 69.72
b) Stair case railing
i) First flight W.E. 1 1 14.75 - 2.80 41.30
1 1 17.75 - 2.80 49.70
N.S. 1 1 1.50 - 2.80 4.20
1 1 7.50 - 2.80 21.00
ii) Second flight W.E. 1 1 12.00 - 2.80 33.60
c) Parapet wall N.S. 1 1 50.50 - 2.80 141.40
1 1 53.50 - 2.80 149.80
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
W.E. 1 2 35.66 - 2.80 199.69
710.41 SqF
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Qty. V. P. No. 85 of M. B. No. : 141/2019-20
1) Kitchen 1 3 - 1.50 2.75 12.37
1 1 - 1.00 3.00 3.00
1 1 - 1.16 5.25 6.09
2) Hall 1 2 - 1.00 5.66 11.32
1 1 - 1.00 6.00 6.00
3) Bed Room - I & II 1 2 - 1.33 6.75 17.95
4) Study Room 1 1 - 1.33 6.75 8.97
1 2 - 0.83 5.50 9.13
74.83 SqF
Qty. V. P. No. 96 of M. B. No. : 141/2019-20
N-S 1 2 12.00 - 11.00 264.00
1 2 29.00 - 11.00 638.00
1 4 4.33 - 11.00 190.52
1 2 9.50 - 11.00 209.00
W-E 1 6 15.33 - 11.00 1011.78
1 4 5.50 - 11.00 242.00
1 2 12.50 - 11.00 275.00
Deductions D1 -1 8 3.00 - 7.00 -168.00
D2 -1 2 2.75 - 7.00 -38.50
D3 -1 6 2.50 - 7.00 -105.00
2518.80 SqF
Total in Sq.Ft :: 4340.21 Sq.Ft
Total in Sq.Mt :: 403.22 Sq.Mt 7737.00 10 Sq.Mt 311971.31
18) Reinforced Cement Concrete M20 Grade Nominal Mix using 6 to
20mm (SS-5) graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh
batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by
the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Lintels.

Qty. V. P. No. 63 of M. B. No. : 141/2019-20


Lintels On Door D1 1 1 3.25 0.75 0.50 1.22
W1 1 1 4.75 0.75 0.50 1.78
W1 1 2 7.25 0.75 0.50 5.44
W2 1 3 5.25 0.75 0.50 5.91
W3 1 2 4.25 0.75 0.50 3.19
KW 1 1 4.25 0.75 0.50 1.59
Total in Cu.Ft :: 19.13 Cu.Ft
Total in Cu.Mt :: 0.54 Cu.Mt 11318.15 1 Cu.Mt 6111.80
19) Reinforced Cement Concrete M20 Grade Nominal Mix
corresponding to IS 456 using 20mm size graded machine
crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., to
site and including Seigniorage charges, sales & other taxes on
all materials including all operational, incidental and labour
charges such as machine mixing, laying concrete, curing
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) including
centering, shuttering, laying concrete, curing etc. complete for
Sunshades / Chajjas for 75mm thick at Fixed end and 50mm
thick at Free end and for a width of 0.60 Mts. etc complete for
finished item of work.

Qty. V. P. No. 64 of M. B. No. : 141/2019-20


D2 1 1 2.75 1.50 - 4.13
W1 1 2 7.25 1.50 - 21.75
W2 1 3 5.22 1.50 - 23.49
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
KW & W3 1 2 4.25 1.50 - 12.75
Total in Sq.Ft :: 62.12 Sq.Ft
Total in Sq.Mt :: 5.77 Sq.Mt 843.12 1 Sq.Mt 4864.80
20) Timber shall be of the kind as specified, may be teak, shisham,
sal, deodar,etc., the timber shall be of best quality, well
seasoned and free from sap knots, warps, cracks and other
defects, all wood work shall be planed and neatly and truly
finished to the exact dimensions. all joints be neat and strong,
truly and accurately fitted and glued before being fitted
together. Chunkhats : The Chunkhats shall be formed and
joined by motise and tenon joint with head wooden pins and
the joints shall be of coated with white lead before being fitted
together.
Qty. V. P. No. 67 of M. B. No. : 141/2019-20
D1 1 5 3.00 - 7.00 105.00
D2 1 2 2.75 - 7.00 38.50
D3 1 3 2.50 - 7.00 52.50
Total in Sq.Ft :: 196.00 Sq.Ft
Total in Sq.Mt :: 18.21 Sq.Mt 5377.94 1 Sq.Mt 97932.29
21) Supplying and fixing of fully glazed non teak wood window with
fan light as per drawing using standard outer frame
38.5x33x21x2.5mm thick and central mullion of size 59(3mm) x
33 (2.5)mm x 25 (3mm) and shutters made of anodized
aluminium z section 24.5 (3mm) x 33 (4mm) x 21 (3mm) using
5mm thick glass fitted with suitable aluminium glazing clips and
rubber beading including supplying and fixing friction hinges
(2no.s per shutter), handle with lock (1no. per shutter),
including cost and conveyance to site of aluminium sections,
glass, rubber beading fixtures etc., including labour charges for
manufacturing window, fixing in position using wooden blocks
and sheet metal screws etc., complete for finished item.

Qty. V. P. No. 68 of M. B. No. : 141/2019-20


W1 1 1 4.75 - 4.50 21.38
W1 1 2 7.00 - 4.50 63.00
W2 1 3 5.00 - 4.50 67.50
W3 1 2 4.00 - 4.50 36.00
KW 1 1 4.00 - 3.50 14.00
Total in Sq.Ft :: 201.88 Sq.Ft
Total in Sq.Mt :: 18.76 Sq.Mt 3756.07 1 Sq.Mt 70463.87
22) Glazed ventilator as per drawing using anodised aluminium
sections of 38.5x33x21x2.50mm thick outer frame and central
mullion of size 59(3mm) x 33 (2.5mm) and shutters with z
section of 33(2.5mm) x 24.5 (3mm) x 21 (3mm) and 5mm thick
plain glass fitted with suitable aluminium glazing be made of
single panel shutter of 25mm thick providing with keyless lock,
100mm aluminium tower clips and rubber beading including
supply and fixing of no.s frictions hinges, 2no.s ISI marked
anodised aluminium tower bolts 75mm long including cost and
conveyance of all materials to site, fixtures in position using
wooden blocks & sheet metals screws etc.,

Qty. V. P. No. 69 of M. B. No. : 141/2019-20


V1 1 3 3.00 - 2.00 18.00
Total in Sq.Ft :: 18.00 Sq.Ft
Total in Sq.Mt :: 1.67 Sq.Mt 4651.86 1 Sq.Mt 7768.61
23) Plastering 12mm thick in two coats with base coat of 9mm thick
in CM (1:6) and top coat of 3mm thick in CM (1:4) dubara
sponge finish including cost and conveyance of all materials like
cement, screened sand, water etc., to site, seigniorage
charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing mortar,
scaffolding charges, lift charges, finishing, including cutting of
Grooves wherever necessary as directed by Engineer - in -
charge, curing, etc., for Uneven Surfaces of Brick Wall
complete for finished item of work. (APSS 901,903 & 904).

Qty. V. P. No. 70-71 of M. B. No. : 141/2019-20


A) Internal 9" brick wall :-
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
N-S 1 1 46.83 - 11.00 515.13
1 1 39.50 - 11.00 434.50
W-E 1 1 12.25 - 11.00 134.75
1 1 14.00 - 11.00 154.00
1 1 28.50 - 11.00 313.50
Deductions :-
D1 -1 1 3.00 - 7.00 -21.00
D2 -1 1 2.75 - 7.00 -19.25
W1 -1 1 4.75 - 4.50 -21.37
W1 -1 2 7.00 - 4.50 -63.00
W2 -1 3 5.00 - 4.50 -67.50
W3 -1 2 4.00 - 4.50 -36.00
KW -1 1 4.00 - 4.50 -18.00
V1 -1 3 3.00 - 2.00 -18.00
1287.76 Sft
Qty. V. P. No. 72 of M. B. No. : 141/2019-20
2) 4.5" Brick walls :-
N-S 1 2 12.00 - 11.00 264.00
1 2 29.00 - 11.00 638.00
1 4 4.33 - 11.00 190.52
1 2 9.50 - 11.00 209.00
1 6 15.33 - 11.00 1011.78
1 4 5.50 - 11.00 242.00
1 2 12.50 - 11.00 275.00
Deductions :-
D1 -1 8 3.00 - 7.00 -168.00
D2 -1 2 2.75 - 7.00 -38.50
D3 -1 6 2.50 - 7.00 -105.00
2518.80 Sft
Qty. V. P. No. 73-74 of M. B. No. : 141/2019-20
B) External 9" Brick walls :-
N-S 1 1 48.33 - 12.00 579.96
1 1 41.00 - 12.00 492.00
1 1 13.00 - 11.00 143.00
1 1 15.50 - 12.00 186.00
1 1 30.00 - 12.00 360.00
Deductions :-
D1 -1 1 3.00 - 7.00 -21.00
D2 -1 1 2.75 - 7.00 -19.25
W1 -1 1 4.75 - 4.50 -21.38
W1 -1 2 7.00 - 4.50 -63.00
W2 -1 3 5.00 - 4.50 -67.50
W3 -1 2 4.00 - 4.50 -36.00
Kw -1 1 4.00 - 3.50 -14.00
V1 -1 3 3.00 - 2.00 -18.00
1500.83 Sft
Total in Sq.Ft :: 5307.39 Sq.Ft
Total in Sq.Mt :: 493.07 Sq.Mt 4327.13 10 Sq.Mt 213357.80
24) Plastering 20mm thick in two coats with base coat of 16mm
thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara
sponge finish including cost and conveyance of all materials like
cement, screened sand, water etc., to site, seigniorage
charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing mortar,
scaffolding charges, lift charges, finishing, including cutting of
Grooves wherever necessary as directed by Engineer - in -
charge, curing, etc., for Uneven Surfaces of Brick Wall
complete for finished item of work. (APSS 901,903 & 904).

Qty. V. P. No. 74 of M. B. No. : 141/2019-20


N-S 1 1 49.25 - 3.00 147.75
1 1 9.75 - 3.00 29.25
1 1 56.00 - 3.00 168.00
W-E 1 1 30.00 - 3.00 90.00
1 1 15.00 - 3.00 45.00
1 1 17.25 - 3.00 51.75
531.75 Sft
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Qty. V. P. No. 77 of M. B. No. : 141/2019-20
a) Stair case 1 28 3.00 0.83 - 69.72
b) Stair case railing
i) First flight W.E. 1 1 14.75 - 2.80 41.30
1 1 17.75 - 2.80 49.70
N.S. 1 1 1.50 - 2.80 4.20
1 1 7.50 - 2.80 21.00
ii) Second flight W.E. 1 1 12.00 - 2.80 33.60
c) Parapet wall N.S. 1 1 50.50 - 2.80 141.40
1 1 53.50 - 2.80 149.80
W.E. 1 2 35.66 - 2.80 199.69
710.41 Sft
Qty. V. P. No. 86 of M. B. No. : 141/2019-20
1) Kitchen 2 3 - 1.50 2.75 24.75
1 2 - 1.00 3.00 6.00
1 2 - 1.16 5.25 12.18
2) Hall 1 2 - 1.00 6.00 12.00
2 2 - 1.00 5.66 22.64
3) Bed Room - 1&2 2 2 - 1.33 6.75 35.91
4) Study Room 1 2 - 1.33 6.75 17.95
2 2 - 0.83 5.50 18.26
149.69 Sft
Qty. V. P. No. 99 of M. B. No. : 141/2019-20
N-S 1 2 8.00 - 5.66 90.56
1 2 4.50 - 6.00 54.00
W-E 2 0.5 16.00 5.66 - 90.56
1 2 12.83 - 6.00 153.96
389.08 Sft
Total in Sq.Ft :: 1780.93 Sq.Ft
Total in Sq.Mt :: 165.45 Sq.Mt 4450.96 10 Sq.Mt 73641.13
25) Reinforced Cement Concrete M20 Grade Nominal Mix using 6 to
20mm (SS-5) graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh
batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by
the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. FOR SHELVES.

Qty. V. P. No. 84 of M. B. No. : 141/2019-20


1) Kitchen N.S. 1 1 11.50 1.66 - 19.09
1 4 11.50 1.25 - 57.50
W.E. 1 1 5.66 1.50 - 8.49
1 2 7.50 1.00 - 15.00
2) Pooja Room 1 2 5.00 1.25 - 12.50
3) Hall N.S. 1 4 5.50 1.00 - 22.00
W.E 1 4 5.00 1.00 - 20.00
4) Bead Room I 1 4 5.50 1.33 - 29.26
5) Bead Room II 1 4 5.50 1.33 - 29.26
6) Study Room N.S. 1 4 4.00 0.83 - 13.28
W.E. 1 4 5.50 1.33 - 29.26
Total in Sq.Ft :: 255.64 Sq.Ft
Total in Sq.Mt :: 23.75 Sq.Mt #NAME? 1 Sq.Mt #NAME?
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
26) Ceiling Plastering 12mm thick in two coats with base coat of
8mm thick in CM (1:5) and top coat of 4mm thick in CM (1:3)
dubara sponge finish including cost and conveyance of all
materials like cement, sand, water etc., to site, seigniorage
charges, sales & other taxes on all materials,all operational,
incidental and labour charges such as mixing mortar, scaffolding
charges, lift charges, including cutting of Grooves wherever
necessary as directed by Engineer - in - charge, finishing,
curing, etc., complete for finished item of work. (APSS 901,903
& 904)
Qty. V. P. No. 75 of M. B. No. : 141/2019-20
Ceiling Plastering 1 1 50.58 35.66 - 1803.68
1 1 18.00 3.00 - 54.00
Circular Pillar Plastering 1 3 - 3.00 10.00 90.00
Total in Sq.Ft :: 1947.68 Sq.Ft
Total in Sq.Mt :: 180.95 Sq.Mt 4327.13 10 Sq.Mt 78299.42
27) Providing and fixing Vetrified ceramic tile full body of size not
less than 18" x 18" 20mm thick base plaster in cement mortor
1:5 (1 Cement : 5 Coarse sand) including a floating cement
slurry including grouting / filling the joints with white cement
slurry mixed with matching pigment, curing cleaning same as
above for skirting in al heights/level.
Qty. V. P. No. 87-88 of M. B. No. : 141/2019-20
1) Verandah : 1 16.25 8.75 - 142.18
2) Liv/Din 1 1 24.00 12.33 - 295.92
1 1 6.92 4.33 - 29.96
(Infront of toilet - I) 1 1 7.33 4.40 - 32.25
3) Pooja 1 1 5.00 3.92 - 19.60
1 2 3.83 1.00 - 7.66
4) Kitchen 1 1 12.40 11.50 - 142.60
5) Study Room 1 1 15.33 11.92 - 182.73
6) Bed Room - I 1 1 15.92 9.83 - 156.49
1 1 6.50 5.50 - 35.75
7) Bed Room - 2 1 1 15.33 12.40 - 190.09
Total in Sq.Ft :: 1235.23 Sq.Ft
Total in Sq.Mt :: 114.76 Sq.Mt 9732.25 10 Sq.Mt 111687.30
28) Providing Skirting to internal walls to 15 cm height and risers of
steps with soluble salt porcelain vitrified tiles screen printed and
polished of size 600 x 600 mm and thickness between 8-10 mm
1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1
to 15) of any colour and finish of make Jhonson & Jhonson,
Kajaria, Nitco, Marbonite, set over base coat of CM (1:5) 12 mm
thick with cement slurry of honey like consistency spread at the
rate of 3.30 kgs per sqm and jointed with white cement paste
mixed with pigment of matching shade to full depth, including
cost of all materials like tiles, cement, sand and water etc.,
complete including seigniorage charges, etc., complete for
finished item of work.

Qty. V. P. No. 89 of M. B. No. : 141/2019-20


1) Verandah : 1 1 12.00 - 0.33 3.96
2) Liv/Din 1 1 64.00 - 0.33 21.12
3) Infront of Toilet -1 1 1 10.66 - 0.33 3.51
4) Kitchen 1 1 42.80 - 0.33 14.12
5) Study Room 1 1 49.49 - 0.33 16.33
6) Bed Room - I 1 1 47.05 - 0.33 15.52
7) Bed Room - 2 1 1 52.46 - 0.33 17.31
Total in Sq.Ft :: 91.87 Sq.Ft
Total in Sq.Mt :: 8.53 Sq.Mt 9678.50 10 Sq.Mt 8255.76
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
29) Dadooing to walls with glazed red or white full body ceramic
wall tiles of size 200 x 300 mm / 245 mm x 325 mm and
thickness 6 mm 1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish in all shades
and designs, any brand as approved by Engineer - in - charge
and set over a base coat of CM (1:5), 12mm thick and neat
cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white
cement paste mixed with pigment of matching shade including
cost and conveyance of all materials like cement, sand, water,
tiles, etc. to site, seigniorage charges, sales and other taxes on
all materials, and all opertional, incidental and all labour charges
such as mixing of cement mortar, laying in position, curing, lift
charges etc., complete for finished item of work in all floors

Qty. V. P. No. 89 of M. B. No. : 141/2019-20


1) Toilet - 1 1 2 7.92 - 6.83 108.18
1 2 4.25 - 6.83 58.05
Deduct Door 1 1 2.50 - 7.00 17.50
2) Toilets - 2 (In Bed Room-1) 1 2 5.00 - 6.83 68.30
1 2 8.83 - 6.83 120.61
Deduct Door -1 1 2.25 - 7.00 -15.75
3) Kitchen 1 1 11.40 - 2.92 33.28
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1 1 1.66 - 2.92 4.84
Deduction at window -1 1 3.83 - 2.16 -8.27
4) Pooja 1 1 3.83 - 6.25 23.93
1 1 4.92 - 6.25 30.75
Total in Sq.Ft :: 441.42 Sq.Ft
Total in Sq.Mt :: 41.01 Sq.Mt 5438.23 10 Sq.Mt 22302.18
30) Supply and fixing of Black Granite stone and set over a base
coat of CM (1:5), 12mm thick and neat cement paste at the rate
of 3.3 Kg/Sqmt. and jointed with white cement paste mixed
with pigment of matching shade including cost and conveyance
of all materials like cement, sand, water, tiles, etc. to site,
seigniorage charges, sales and other taxes on all materials, and
all opertional, incidental and all labour charges such as mixing
of cement mortar, laying in position, curing, lift charges etc.,
complete for finished item of work in all floors
Qty. V. P. No. 92 of M. B. No. : 141/2019-20
At Kitchen 1 1 11.40 1.66 - 18.92
1 1 5.40 1.50 - 8.10
Deduct Wash area -1 1 1.66 1.33 - -2.20
Total in Sq.Ft :: 24.82 Sq.Ft
Total in Sq.Mt :: 2.31 Sq.Mt 36009.58 10 Sq.Mt 8318.21
31) Providing and fixing non skid ceramic tiles for flooring over and
inclusive of 20mm thick base plaster in cement morter 1:5 (1
cement : 5 coarse sand) including a floating cement slurry
including grouting/ filling the joints with white cement slurry
mixed with matching, pigment, curing, cleaning and
leaving/making necessary holes for sanitory connection
complete but including cost of cement and tiles in all
heights/level for skirting complete for finished item of work.
Qty. V. P. No. 93 of M. B. No. : 141/2019-20
1) Toilets - 1 1 1 7.83 4.25 - 33.27
2) Toilets - 2 1 1 8.92 4.92 - 43.88
Total in Sq.Ft :: 77.15 Sq.Ft
Total in Sq.Mt :: 7.17 Sq.Mt 8156.98 10 Sq.Mt 5848.55
32) Painting to new walls with two coats of Asian apex of approved
brand and shade over the base coat of approved white cement
primer making 3 coats in all to give an even shade offer
throughly brushing the surface to remove all dirt and remains of
loose powered materials, all operational, incidental charges
including cost of brushes and all labourcharges etc., complete
for finished item of work as per ss.
Qty. V. P. No. 94 of M. B. No. : 141/2019-20
1) internal 9" brick wall N-S 1 1 46.83 - 11.00 515.13
1 1 39.50 - 11.00 434.50
W-E 1 1 12.25 - 11.00 134.75
1 1 14.00 - 11.00 154.00
1 1 28.50 - 11.00 313.50
1551.88 Sft
Qty. V. P. No. 95 of M. B. No. : 141/2019-20
Deductions :-
D1 -1 1 3.00 - 7.00 -21.00
D2 -1 1 2.75 - 7.00 -19.25
W1 -1 1 4.75 - 4.50 -21.37
W2 -1 2 7.00 - 4.50 -63.00
W2 -1 3 5.00 - 4.50 -67.50
W3 -1 2 4.00 - 4.50 -36.00
KW -1 1 4.00 - 4.50 -18.00
V1 -1 3 3.00 - 2.00 -18.00
-264.12 Sft
Total in Sq.Ft :: 1287.76 Sq.Ft
Total in Sq.Mt :: 119.64 Sq.Mt 1202.75 10 Sq.Mt 14389.70
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
33) Painting to new ceiling with 2 - coats of whiting of approved
quality to give an even shade after throughly brushing the
surface to remove all dirt and remains of loose powdered
materials, including cost and conveyance of all materials to
work site and all operation, incidental labour charges such as
scaffolding, lift charges etc., complete for finished item of work.
Qty. V. P. No. 98 of M. B. No. : 141/2019-20
Ceiling 1 1 50.58 35.66 - 1803.68
1 1 18.00 3.00 - 54.00
Circular cPillars 1 3 - 3.00 10.00 90.00
Total in Sq.Ft :: 1947.68 Sq.Ft
Total in Sq.Mt :: 180.95 Sq.Mt 1202.75 10 Sq.Mt 21763.76
34) Painting to New External Walls with two coats of Polymer Plastic
Emulsion paint of Asian / Berger / Nerolac / Saicoat / Endocem
or equalent quality of approved brand and shade as approved
by the Engineer - in - Charge over base coat of cement primer
water base grade -II exterior making three coats in all to give
an even shade after thoroughly brushing the surface to remove
all loose powdered materials, including cost and conveyance of
all materials, including cost and conveyance of all materials,
cost of brushes, water to site, etc., sales & other taxes, all
operational, incidental and labour charges such as scaffolding
charges, lift charges, curing etc., complete for finished item of
work in all floors for external Walls.(APSS No. 911)

Qty. V. P. No. of M. B. No. : 141/2019-20


External walls :-
N-S 1 1 48.33 - 12.00 579.96
1 1 41.00 - 12.00 492.00
1 1 13.00 - 11.00 143.00
1 1 15.50 - 12.00 186.00
1 1 30.00 - 12.00 360.00
Deductions :-
D1 -1 1 3.00 - 7.00 -21.00
D2 -1 1 2.75 - 7.00 -19.25
W1 -1 1 4.75 - 4.50 -21.38
W1 -1 2 7.00 - 4.50 -63.00
W2 -1 3 5.00 - 4.50 -67.50
W3 -1 2 4.00 - 4.50 -36.00
Kw -1 1 4.00 - 3.50 -14.00
V1 -1 3 3.00 - 2.00 -18.00
1500.83 Sft
Total in Sq.Mt :: 139.43 Sq.Mt #NAME? 10 Sq.Mt #NAME?

Total:- #NAME?

Forest Divisional Officer, Forest Range Officer,


Manuguru, Manuguru,
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section
of Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.
SUB ESTIMATE -Electrification
Sl. Measurements
Description of Item No Qty Units Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
1) Supply and fixing of ISI mark 25mm dia 2mm thick PVC conduit
pipe Sudhakar / Macoplast / Modi make concealed in Roof Slab
with all required acessories including No.14 SWG GI wire for
earth continuity including chiseling the wall wherever necessary ,
including necessary masonery work for light/fan pointand
seperate plug point with teak wood deep box including cost and
conveyance of all materials to site and labour charges, sales tax
etc., complete for finished item of work.
Qty. V. P. No. 51 of M. B. No. : 124/C/TW/19-20
Class Room 1 2 4.45 - - 8.90
1 2 2.35 - - 4.70
Varandah 1 1 7.65 - - 7.65
Drop 1 5 0.30 - - 1.50
12/Jan/22 22.75 Rmt 86.40 /Rmt 1965.60
2) Supply and fixing of ISI mark 25mm dia 2mm thick PVC conduit
pipe Sudhakar / Macoplast / Modi make concealed in wall with all
required acessories including No.14 SWG GI wire for earth
continuity including chiseling the wall wherever necessary ,
including necessary masonery work for light/fan pointand
seperate plug point with teak wood deep box including cost and
conveyance of all materials to site and labour charges, sales tax
etc., complete for finished item of work.
Qty. V. P. No. 52 of M. B. No. : 124/C/TW/19-20
Concealed in wall 1 4 0.45 - - 1.80
" 1 1 2.00 - - 2.00
" 1 1 0.75 - - 0.75
" 1 1 2.50 - - 2.50
12/Jan/22 7.05 Rmt 96.40 /Rmt 679.62
3) Supply and run of 2 of 36/0.3mm (2.5 Sqmm) PVC insulated
flexible copper cable of make Standard / Havells /HPL / Toyoma
in existing PVC conduit pipe circuits, MV Lamp/Security light
points including laboiur charges (Phase, Neutral and earth) and
run of 1 of 1.0 sqmm copper cable for earthing.
Qty. V. P. No. 52 of M. B. No. : 124/C/TW/19-20
1 1 60.00 - - 60.00
12/Jan/22 60.00 Rmt 81.89 /Rmt 4913.40
4) Supplying and wiring with 2 runs of 14/0.3m (1.00 Sq.mm) FRLS
/ HFFR P.V.C. insulated ISI Copper Cable GM/L&T/
RPG/Havells/V-Guard/Power Flex/Polycab/Gold Medal/
Standard /Milion / Vimal/ Suncab/ Paragaon / FortuneArt make in
the existing metallic / non-metallic conduct pipe with 6A 1 Way
flush type switch, Ceiling rose and 3mm thick hylam sheet
covering to switch control box including cost and conveyance of
all materials to site, labour charges and sales tax etc. complete
for finished item of work for light, bell, fan and exhaust fan
points in Non-Residential Buildings.
Qty. V. P. No. 53 of M. B. No. : 124/C/TW/19-20
Tube points 1 6 - - - 6.00
Bulb points 1 4 - - - 4.00
Fan points 1 4 - - - 4.00
12/Jan/22 14.00 No.s 546.30 Each 7648.20
Sl. Measurements
Description of Item No Qty Units Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
5) Supply and transportation of 20W, 2000 lumens, T8,1200mm
length LED tube light, input voltage AC 220 - 260Volts with
PF≥0.9, Surge protection: 2KV,THD<125%, with inbuilt driver
and frosted cover CCT: 3000K - 5700K, minimum CRI≥80,.etc.,
complete Manufacture has to submit LM79,LM80 &
Photobiological Safety Report. Luminaire Performance Complies
to IS10322 (Part 5/Sec 3) & IEC 60598-1,IEC 60529 ISO certified
company.
Qty. V. P. No. 53 & 54 of M. B. No. : 124/C/TW/19-20
Class Room 1 4 - - - 4.00
Varandah 1 2 - - - 2.00
12/Jan/22 6.00 No.s 957.10 Each 5742.60
6) Supply and fixing of Batton Holder/Slanting holder in lieu of
ceiling rose of light point complete with allconnetions and all
labour charges with 40Watt bulb etc., complete for new
installation. Maru Make
Qty. V. P. No. 54 of M. B. No. : 124/C/TW/19-20
1 4 - - - 4.00
12/Jan/22 4.00 No.s 101.20 Each 404.80
7) Supply and errecting Supply of 48" (1200mm) Sweep 5 Star
rated Ceiling Fan without Regulator with 3 blades and double ball
bearings and with condenser AC 250V 50 C/S of 48" 1200mm
sweep completely erected in position without regulator, canopy
down rod up to 301.80 mm in length is provided with
hook/clamps nuts and bolts and 24/02 flexible copper wire etc.,
complete and pointed with lettering by enamil paint the Sr. No.
and date of errection including cost and conveyance of all
materials and labour chargers etc., complete including 4%
tornover tax on cost of all materials for finished item of work.
Qty. V. P. No. 54 of M. B. No. : 124/C/TW/19-20
Class Room 1 4 - - - 4.00
12/Jan/22 4.00 No.s 3445.72 Each 13782.88
8) Supply and fixing of 6A 3/2 pin flush type socket with 6A switch
control of Anchor / Gold medal olive / Million zoom make with ISI
mark on a common switch board with earth continuity including
wire leads, earth connections including cost and conveyance of
all materials to site, labour charges and sales tax etc. complete
for finished item of work
Qty. V. P. No. 55 of M. B. No. : 124/C/TW/19-20
1 2 - - - 2.00
12/Jan/22 2.00 No.s 141.39 Each 282.78
9) Supply and fixing of 16A 3pin / 6A 3pin plug socket with
indicator lamp and 16Amps fuse unit and 16 Amps switch
control (5 in one) of Milltec / Vimal opel / Maru mantero / Starex
smil / CPL make with ISI mark on decolam sheet covered board
including earth continuity including cost and conveyance of all
materials to site, labour charges and sales tax etc. complete for
finished item of work
Qty. V. P. No. 55 of M. B. No. : 124/C/TW/19-20
1 1 - - - 1.00
12/Jan/22 1.00 No.s 313.60 Each 313.60
Sl. Measurements
Description of Item No Qty Units Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
10) Supply and fixing 4 way SPN Distribution board with IP-30
protection of make Standard / Havells / HPL/Toyoma/ C &S
suitable for single phase 40A Double pole Isolator as incomer and
10KA-6-32A range single pole miniature circuit breakers four
numbers (4Nos) as out going with internal connections including
cost and conveyance of all materials to site, labour charges for
surface / flush mounting etc., sales tax complete for finished item
of work.
Qty. V. P. No. 56 of M. B. No. : 124/C/TW/19-20
1 1 - - - 1.00
12/Jan/22 1.00 No.s 4049.81 Each 4049.81
11) Supply and Run of 2 of 6 Sq.mm (7/18) WPSC ISI Aluminium
wire of makes Finolex / Polycab/ Gold Medal /million /Payal/
Power Flex along with No.10 SWG G.I bearer wire through PVC
cleats with all accessories including cost and conveyance of all
materials to site, labour charges and sales tax etc., complete for
finished item
Qty. V. P. of 56
No. work.
of M. B. No. : 124/C/TW/19-20
1 1 30.00 - - 30.00
12/Jan/22 30.00 Rmt 64.46 Rmt 1933.80
12) Providing independent earthing for main switches integrated
circuit cutouts and moters with 40mm dia Medium grade GI Pipe
of TATA/Zenith/GST make of 2.5 m length duly providing 12mm
dia 16 Nos. holes and rewired bolts, nuts and washers,
checknuts, Humepipe ring 18 inches dia, 2 inch thick etc., as per
IS specifications with necessary double GI earth wire NO. 8 SWG
inclkuding filling with equal preparation of salt and charcoal in
layers including cost and conveyance of all materials to site,
labour charges and sales tax etc., complete for finished item of
work.
Qty. V. P. No. 57 of M. B. No. : 124/C/TW/19-20
1 1 - - - 1.00
12/Jan/22 1.00 No.s 4381.56 Each 4381.56

Total:- 46098.65

Asst. Engineer Deputy Exe. Engineer Executive Engineer


T.W. Yellandu T.W.S.D. - Sudimalla T.W.Divn., Bhadrachalam
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section
of Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.
SUB ESTIMATE - Water Supply and Sanitary arrangements
Sl. Measurements
Description of Item No Qty Units Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
1) Supplying & Fixing Orissa Pan 580 mm x 440 mm white glazed
W.C 1st quality ISI marked conforming to IS:2556-Part-3-1981
with "P" or "S" trap Hindware/ Parryware/ Neycer - ISI mark
580 mm x 440mm as approved by the Engineer-in-charge
fixed in brick masonry with necessary ‘S’ trap of water closet,
shall be encased in C.C. (1:2:4) 6" alround well above the
joint, to stop leakage at the joint, cost & conveyance of all
materials and labour charges etc., including sales and other
taxes on all materials complete for finished item of work for all
floors.
Qty. V. P. No. 48 of M. B. No. : 124/C/TW/19-20
For W.C 1 2 - - - 2.00
29/Jan/20 2.00 No.s 1791.75 Each 3583.50
2) Supply and Fixing of Ashirvad/ Ajay/ Astral Flowguard or
equivalent 28.60mm dia CPVC Pipes and Fittings to meet the
requirement of ASTM-D 2846 and are produced in CTS (Copper
Tube Sizes 1/2" ton 2" Ashirvad Flowgurard SDR 11 and SDR
13.5 pipes are made from idential CPVC compounds having the
same physical Properties for Hot and Cold Water (IS
15778:2007).
Qty. V. P. No. 11 & 12 of M. B. No. : 196/C/TW/19-20
1 1 6.30 - - 6.30
1 2 4.35 - - 8.70
1 1 12.00 - - 12.00
1 1 2.00 - - 2.00
1 1 1.90 - - 1.90
1 1 1.00 - - 1.00
29/Jan/20 31.90 Rmt 219.30 /Rmt 6995.67
3) Providing & Placing of RCC Precast rings for water storage tank
with suitable arrangements and making neccesary holes for
inlet and outlet and overflows pipes without fittings and base
supports for tanks.
Qty. V. P. No. 11 of M. B. No. : 196/C/TW/19-20
1000Ltrs 1 1 1000.00 - - 1000.00
29/Jan/20 1000.00 Litrs 8.00 /Litr 8000.00

Total:- 18579.17

Forest Range Officer, Forest Divisional Officer,


Palvancha Manuguru,
WORKDONE ESTIMATE
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of
Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.
M. B. No. :
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1) Earth work excavation for foundations and depositing on bank for all lifts
and with an initial lead of 10m including all operational, incidental,
labour charges such as shoring ,sheeting, planking, strutting, etc.
complete for finished item of work including seigniorage excluding
dewatering charges etc as per SS - 20 B (APSS 308). for building
foundation.
Qty. V. P. No. 1 of M. B. No. :
Column Pits 1 x 11 1.50 1.50 1.80 44.55
1 x 2 1.50 1.50 1.80 8.10
52.65 Cum
Qty. V. P. No. 8 of M. B. No. :
West side walls 1 x 1 14.17 0.45 0.91 5.80
South side walls 1 x 2 8.30 0.45 0.91 6.80
East side walls 1 x 1 15.46 0.45 0.91 6.33
North side walls 1 x 1 4.26 0.45 0.91 1.74
1 x 1 1.21 0.45 0.91 0.49
1 x 1 3.81 0.45 0.91 1.56
Qty. V. P. No. 9 of M. B. No. :
Deduct Columns -1 x 11 0.38 0.23 0.91 -0.87
21.85 Cu.Mt.
Qty. V. P. No. of M. B. No. :
Front side steps 1 x 1 4.00 1.20 0.20 0.96
Right side steps 1 x 1 2.60 1.20 0.20 0.62
1.58 Cu.Mt.
Total in Cu.Mt :: 76.08 Cu.Mt 336.53 1 Cu.Mt 25603.20
2) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine
aggregate: Coarse aggregate) using 40mm size Hard Broken Granite
(IS383, 1970) machine crushed metal from approved quarry including
cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, mixing concrete in concrete mixer
including seigniorage charges, sales & other taxes on all materials, all
operational, incidental, and labour charges such as laying and ramming
concrete in layers in position not exceeding 15cm, finishing top surface,
curing concrete, etc., complete for finished item of work.

Qty. V. P. No. 02 of M. B. No. :


PCC Under Col. Footings 1 x 13 1.50 1.50 0.15 4.388
4.388 Cu.Mt
Qty. V. P. No. 10 of M. B. No. :
West side walls 1 x 1 14.17 0.45 0.15 0.95
South side walls 1 x 2 8.30 0.45 0.15 1.12
East side walls 1 x 1 15.46 0.45 0.15 1.04
Qty. V. P. No. 11 of M. B. No. :
North side walls 1 x 1 4.26 0.45 0.15 0.28
1 x 1 1.21 0.45 0.15 0.08
1 x 1 3.81 0.45 0.15 0.25
Deduct Columns -1 x 11 0.38 0.23 0.15 -0.14
3.58 Cu.Mt
Qty. V. P. No. of M. B. No. :
Septic tank bottom levelling 1 x 1 π/4 (1.30)² 0.15 0.19
0.19 Cu.Mt
Qty. V. P. No. of M. B. No. :
Front side steps 1 x 1 4.00 1.20 0.15 0.72
Right side steps 1 x 1 2.60 1.20 0.15 0.46
1.18 Cu.Mt.
Total in Cu.Mt :: 9.34 Cu.Mt 4976.25 1 Cu.Mt 46468.22
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
3) Vibrated Plain Cement Concrete (1:4:8) proportion (cement: fine
aggregate: Coarse aggregate) using 40mm size Hard Broken Granite
(IS383, 1970) machine crushed metal from approved quarry including
cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, mixing concrete in concrete mixer
including seigniorage charges, sales & other taxes on all materials, all
operational, incidental, and labour charges such as laying and ramming
concrete in layers in position not exceeding 15cm, finishing top surface,
curing concrete, etc., complete for finished item of work.

Qty. V. P. No. 36 & 37 of M. B. No. :


Varandah 1 x 1 3.50 2.31 0.10 0.80
Living/Din 1 x 1 5.56 3.50 0.10 1.946
Pooja 1 x 1 1.82 1.30 0.10 0.236
Kitchen 1 x 1 3.38 2.74 0.10 0.926
Bed Room 1 1 x 1 4.03 4.02 0.10 1.62
Bath 1 1 x 1 2.13 1.21 0.10 0.257
Bath 2 1 x 1 2.05 1.20 0.10 0.24
Bed room 2 1 x 1 4.03 4.02 0.10 1.62
Wash area part 1 1 x 1 3.58 2.28 0.10 0.81
Wash area part 2 1 x 1 4.00 2.28 0.10 0.912
Total in Cu.Mt :: 9.367 Cu.Mt 4607.01 1 Cu.Mt 43153.86
4) Coursed Rubble Stone Masonry in CM (1:3) Prop: including cost and
conveyance of all materials like cement, sand, water etc., to site,
including seigniorage charges, sales & other taxes on all materials, all
operational, incidental charges and labour charges such as mixing
mortar, finishing, curing, etc., complete for finished item of work. (APSS
901,906)
Qty. V. P. No. 12 of M. B. No. :
West side wall 1 x 1 14.17 0.45 0.914 5.83
South side wall 1 x 2 8.30 0.45 0.914 6.82
East side wall 1 x 1 15.46 0.45 0.914 6.36
19.01 Cu.Mt.
Qty. V. P. No. 13 of M. B. No. :
North side wall 1 x 1 4.26 0.45 0.914 1.75
1 x 1 1.21 0.45 0.914 0.49
1 x 1 3.81 0.45 0.914 1.57
Deduct Columns -1 x 11 0.38 0.23 2.60 -2.50
1.31 Cu.Mt.
Total in Cu.Mt :: 20.32 Cu.Mt 4498.24 1 Cu.Mt 91404.24
5) Filling with useful available excavated earth (excluding rock) in trenches,
sides of foundations and basement with initial lead in layers not
exceeding 15 cm thick, consolidating each deposited layer by watering
and ramming including cost and conveyance of water to work site and
all operational, incidental, labour charges, hire charges of T & P etc.,
complete for finished item of work. APSS No.309 & 310.

Qty. V. P. No. 7 of M. B. No. :


total EW forColumns pits 1 x 13 1.50 1.50 1.80 52.65
Deduct Columns -1 x 13 2.74 0.38 0.23 -3.11
Deduct Footing straight -1 x 13 1.50 1.50 0.15 -4.388
Taper -1 x 13 0.95 0.87 0.30 -3.223
PCC Under Col. Footings -1 x 13 1.50 1.50 0.15 -4.388
37.541 Cu.Mt.
Qty. V. P. No. 14 of M. B. No. :
West side wall 1 x 1 14.17 0.45 0.91 5.80
South side wall 1 x 2 8.30 0.45 0.91 6.80
East side wall 1 x 1 15.46 0.45 0.91 6.33
18.93 Cu.Mt.
Qty. V. P. No. 15 of M. B. No. :
North side wall 1 x 1 4.26 0.45 0.91 1.74
1 x 1 1.21 0.45 0.91 0.49
1 x 1 3.81 0.45 0.91 1.56
3.79 Cu.Mt.
Total in Cu.Mt :: 60.26 Cu.Mt 274.72 1 Cu.Mt 16554.90
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
6) Filling with Gravel in trenches, sides of foundations and basement with
initial lead in layers not exceeding 15cm thick, consolidating each
deposited layer by watering and ramming including all operational,
incidental, labour charges, seignorage charges, hire charges of T & P
etc., complete for finished item of work. (APSS NO. 309 & 310).
Qty. V. P. No. 35 of M. B. No. :
Plinth Beam 1 x 1 14.17 8.30 1.52 178.77
1 x 1 3.81 1.21 1.52 7.01
185.78 Cu.Mt.
Deduct Total Qty. of Excavation
Columns pits -52.65
CRS walls -22.75
-75.40 Cu.Mt.
Total in Cu.Mt :: 110.38 Cu.Mt 368.00 1 Cu.Mt 40619.84
7) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Column Footings.

Qty. V. P. No. 05 of M. B. No. :


Straight 1 x 13 1.50 1.50 0.15 4.388
Taper (average) 1 x 13 0.95 0.87 0.30 3.223
Total in Cu.Mt :: 7.611 Cu.Mt 9302.11 1 Cu.Mt 70798.36
8) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Columns.

Qty. V. P. No. 06 of M. B. No. :


Columns upto plinth beam 1 x 13 2.74 0.38 0.23 3.11
3.11 Cu.Mt
Qty. V. P. No. 24 of M. B. No. :
Columns 1 x 11 0.30 0.23 3.00 2.277
Circuler Columns 1 x 2 3.01
5.29 Cu.Mt
Total in Cu.Mt :: 8.40 Cu.Mt 11963.17 1 Cu.Mt 100502.59
9) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Plinth Beam.

Qty. V. P. No. 19 of M. B. No. :


North side Plinth Beam 1 x 1 8.80 0.23 0.30 0.607
West side Plinth Beam 1 x 1 14.17 0.23 0.30 0.98
South side Plinth Beam 1 x 2 7.84 0.23 0.30 1.08
East side Plinth Beam 1 x 1 15.40 0.23 0.30 1.06
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
3.727 Cu.Mt.
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Qty. V. P. No. 20 of M. B. No. :
Internal Plinth Beam
Col 8 to 5 1 x 1 13.48 0.23 0.30 0.93
Col 2 to 7 1 x 2 4.14 0.23 0.30 0.57
1 x 2 3.45 0.23 0.30 0.47
1.97 Cu.Mt.
Total in Cu.Mt :: 5.697 Cu.Mt 11663.03 1 Cu.Mt 66444.28
10) Reinforced Cement Concrete M20 Grade Nominal Mix using 6 to 20mm
(SS-5) graded machine crushed hard granite metal (coarse aggregate)
from approved quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., to site and
including Seigniorage charges, sales & other taxes on all materials
including all operational, incidental and labour charges such as weigh
batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of
work (APSS No. 402) with minimum cement content @ 380Kgs/Cu.F.
from standard suppliers approved by the department including
centering, shuttering, laying concrete, vibrating, curing etc., complete.
For Lintels.

Qty. V. P. No. 43 of M. B. No. :


Main door 1 x 2 1.10 0.75 0.33 0.544
Kitchen entrance of Bed Room 1 x 4 1.10 0.12 0.10 0.052
Bed Room Bath rooms 1 x 2 0.95
0.12 0.10 0.022
Kitchen Door 1 x 1 1.10
0.23 0.33 0.083
Pooja 1 x 1 0.90
0.12 0.10 0.010
Total in Cu.Mt :: 0.711 Cu.Mt 12087.01 1 Cu.Mt 8593.86
11) Reinforced Cement Concrete M20 Grade Nominal Mix corresponding to
IS 456 using 20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and conveyance
of all materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges, sales & other taxes
on all materials including all operational, incidental and labour charges
such as machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of
work (APSS No. 402) including centering, shuttering, laying concrete,
curing etc. complete for Sunshades / Chajjas for 75mm thick at Fixed
end and 50mm thick at Free end and for a width of 0.60 Mts. etc
complete for finished item of work.

Qty. V. P. No. 37 of M. B. No. :


Windows for Kitchen, Hall, Bed
Rooms 1 x 4 1.65 0.70 - 4.62
Windows in Bed ROom1 pooja 1 x 3 1.10 0.70 - 2.31
Windows in Kitchen 1 x 1 1.35
0.70 - 0.945
Total in Sq.Mt :: 7.875 Sq.Mt 1090.21 1 Sq.Mt 8585.40
12) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Roof Beams.

Qty. V. P. No. 32 to 33 of M. B. No. :


West side Roof Beam 1 x 4 10.00 0.23 0.30 2.76
North to south roof Beams 1 x 3 13.41 0.23 0.30 2.77
Beam under stair case mid
landing 1 x 1 2.40 0.23 0.30 0.166
5.696 Cu.Mt.
Qty. V. P. No. 33 of M. B. No. :
Deduct Over lapping beam -1 x 13 0.30 0.20 0.30 -0.234
-0.23 Cu.Mt.
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Total in Cu.Mt :: 5.462 Cu.Mt 11581.80 1 Cu.Mt 63259.79
13) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Roof Slab
125mm thick.

Qty. V. P. No. 33 of M. B. No. :


Roof Slab 1 x 1 10.00
13.41 - 134.10
Total in Sq.Mt :: 134.10 Sq.Mt 1322.94 1 Sq.Mt 177406.25
14) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar,
constructing masonry, scaffolding charges, lift charges, curing, etc.,
complete for finished item of work.
9" Brick wall
Qty. V. P. No. 38 to 40 of M. B. No. :
East wall 1 x 1 10.49 0.23 2.90 6.997
West wall 1 x 1 14.23 0.23 2.90 9.491
North Wall 1 x 1 7.85 0.23 2.90 5.236
South Wall 1 x 1 7.85 0.23 2.90 5.236
1 x 1 1.94 0.23 2.15 0.959
1 x 1 1.17 0.23 2.15 0.579
Deductions in East wall :-
Columns -1 x 3 0.30 0.23 2.90 -0.600
Windows -1 x 2 1.52 0.23 1.42 -0.993
-1 x 1 0.96 0.23 1.42 -0.314
-1 x 1 1.52 0.23 1.10 -0.385
Deductions in west wall :-
Columns -1 x 4 0.30 0.23 2.90 -0.800
-1 x 1 1.54 0.23 1.38 -0.489
-1 x 1 0.93 0.23 1.36 -0.291
Ventilators -1 x 2 0.90 0.23 0.60 -0.248
Deductions in north wall :-
Main door -1 x 1 0.92 0.23 2.17 -0.459
Windows -1 x 2 1.50 0.23 1.42 -0.980
Columns -1 x 1 0.23 0.23 2.90 -0.153
Deductions in south wall :-
Window -1 x 1 1.24 0.23 1.12 -0.319
Kitchen Door -1 x 1 0.87 0.23 2.17 -0.434
Window -1 x 1 0.91 0.23 1.35 -0.283
Columns -1 x 1 0.30 0.23 2.90 -0.200
21.55 Cu.Mt
Qty. V. P. No. of M. B. No. :
Front side steps Step 1 1 x 1 3.95 0.30 0.20 0.24
Step 2 1 x 1 3.95 0.60 0.20 0.47
Step 3 1 x 1 3.95 0.90 0.20 0.71
Step 4 1 x 1 3.95 1.20 0.55 2.61
Right side steps Step 1 1 x 1 2.55 0.30 0.20 0.15
Step 2 1 x 1 2.55 0.60 0.20 0.31
Step 3 1 x 1 2.55 0.90 0.20 0.46
Step 4 1 x 1 2.55 1.20 0.55 1.68
6.63 Cu.Mt
Total in Cu.Mt :: 28.18 Cu.Mt 6222.35 1 Cu.Mt 175345.82
4.5" Brick wall
Qty. V. P. No. 41 to 43 of M. B. No. :
Master Bed Room 1 x 1 4.10 0.12 2.90 1.427
1 x 1 4.13 0.12 2.90 1.437
Children Bed Room 1 x 1 4.13 0.12 2.90 1.437
1 x 1 4.10 0.12 2.90 1.427
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Toilets 1 x 2 2.10 0.12 2.90 1.462
1 x 2 1.15 0.12 2.90 0.800
Wall Between Bed Rooms 1 x 1 2.48 0.12 2.90 0.863
Kitchen 1 x 1 3.44 0.12 2.90 1.197
Puja Room 1 x 1 1.80 0.12 2.90 0.626
1 x 1 1.33 0.12 2.90 0.463
Toilet Under Stair case 1 x 1 1.94 0.12 2.15 0.501
Parapet wall for stair case 1 x 2 4.05 0.12 0.75 0.729
1 x 2 1.80 0.12 0.75 0.324
1 x 1 0.75 0.12 0.75 0.068
Parapet wall over roof slab 1 x 1 46.70 0.10 0.85 3.970
Brick pillars for Parapet wall 1 x 13 0.25 0.16 0.85 0.442
Base for over head tank 1 x 1 1.30 4.30 0.10 0.186
Parapet wall at wash area 1 x 1 4.16 0.12 0.96 0.479
1 x 1 2.50 0.12 0.96 0.288
Deduction for Door in MB -1 x 1 1.00 0.12 2.14 -0.257
Deduction for Door in MB -1 x 1 0.78 0.12 2.18 -0.204
Deduction for Door in CB -1 x 1 1.00 0.12 2.10 -0.252
-1 x 1 0.96 0.12 2.15 -0.248
-1 x 1 0.78 0.12 2.18 -0.204
Deduction for wall b/w BR -1 x 1 0.98 0.12 2.15 -0.253
Deduction for Door of
-1 x 1 0.93 0.12 2.20 -0.246
Kitchen
Deduction for Door of Pooja
-1 x 1 0.80 0.12 2.18 -0.209
Room
Deduction for Door under
-1 x 1 0.84 0.12 2.10 -0.212
Stair case
Total in Sq.Mt :: 16.04 Sq.Mt 6222.35 1 Sq.Mt 99812.72
15) Impervious coat 20mm thick over RCC roof slab surface with CM(1:3),
promixed with 1kg of water proof compound per bag of cement laid over
roof when it is green including cost of all materials, seigniorage charges,
excluding conveyance charges of materials and including all operational,
incidental and labour charges for mixing mortar, laying, rendering
smooth and thread lining, curing, rounding off junctions of wall and slab
etc,, complete for finished item of work.

Qty. V. P. No. 34 of M. B. No. :


Terrace Flooring 1 x 1 10.00
13.41 - 134.10
Total in Sq.Mt :: 134.10 Sq.Mt 429.14 1 Sq.Mt 57547.67
16) Plastering 20mm thick in two coats with base coat of 16mm thick in CM
(1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish
including cost and conveyance of all materials like cement, screened
sand, water etc., to site, seigniorage charges, sales & other taxes on all
materials, all operational, incidental and labour charges such as mixing
mortar,scaffolding charges, lift charges, finishing,including cutting of
Grooves wherever necessary as directed by Engineer - in - charge,
curing, etc., for Uneven Surfaces of Brick Wall complete for finished
item of work. (APSS 901,903 & 904)

Qty. V. P. No. 68 of M. B. No. :


West side wall 1 x 1 14.17 - 1.50 21.25
South side 1 x 1 8.30 - 1.50 12.45
East side 1 x 1 15.46 - 1.50 23.19
North side 1 x 1 3.81 - 1.50 5.71
62.60 Sq.Mt
Qty. V. P. No. of M. B. No. :
Front side steps face 1 x 4 3.95 0.30 - 4.74
Front side steps 1 x 4 3.95 - 0.18 2.84
Front side steps face 1 x 4 2.50 0.30 - 3.00
Front side steps 1 x 4 2.50 - 0.18 1.80
12.38 Sq.Mt
Total in Sq.Mt :: 74.98 Sq.Mt 387.62 1 Sq.Mt 29063.75
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
17) Plastering 12mm thick in two coats with base coat of 9mm thick in CM
(1:6) and top coat of 3mm thick in CM (1:4) dubara sponge finish
including cost and conveyance of all materials like cement, screened
sand, water etc., to site, seigniorage charges, sales & other taxes on all
materials, all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, finishing, including cutting of
Grooves wherever necessary as directed by Engineer - in - charge,
curing, etc., for Uneven Surfaces of Brick Wall complete for finished
item of work. (APSS 901,903 & 904).

A) Internal 9" brick walls :


Qty. V. P. No. 48 to 55 of M. B. No. :
North side 1 x 1 4.22 - 3.15 13.293
Deduct windows -1 x 1 1.52 - 1.30 -1.976
West side 1 x 1 4.20 - 3.15 13.230
Deduct window -1 x 1 1.52 - 1.30 -1.976
South side 1 x 1 4.22 - 3.15 13.293
Deduct Doors -1 x 1 0.96 - 2.05 -1.968
-1 x 1 0.80 - 1.90 -1.520
East side 1 x 1 4.20 - 3.15 13.230
Deduct door -1 x 1 0.96 - 2.05 -1.968
North side 1 x 1 1.87 - 3.15 5.890
Deduct door -1 x 1 0.96 - 2.05 -1.968
West side 1 x 1 2.50 - 3.15 7.875
South side 1 x 1 2.00 - 3.15 6.300
Deduct door -1 x 1 0.96 - 2.05 -1.968
East side 1 x 1 2.45 - 3.15 7.717
Deduct entrance -1 x 1 0.96 - 2.05 -1.968
South side wall 1 x 1 4.21 - 3.15 13.261
Deduct window -1 x 1 0.90 - 1.32 -1.188
West side wall 1 x 1 4.25 - 3.15 13.387
Deduct window -1 x 1 0.90 - 1.32 -1.188
North side wall 1 x 1 4.13 - 3.15 13.009
Deduct door -1 x 1 0.80 - 1.90 -1.520
-1 x 1 0.96 - 2.05 -1.968
East side wall 1 x 1 4.10 - 3.15 12.915
South side wall 1 x 1 2.05 - 3.15 6.457
North side wall 1 x 1 2.05 - 3.15 6.457
Deduct Bath room door -1 x 1 0.80 - 1.90 -1.520
East side wall 1 x 1 1.20 - 3.15 3.780
West side wall 1 x 1 1.15 - 3.15 3.622
Deduct Ventilator 1 x 1 0.89 - 0.59 0.525
South side wall 1 x 1 2.05 - 3.15 6.457
Deduct Bath room door -1 x 1 0.80 - 1.90 -1.520
North side wall 1 x 1 2.05 - 3.15 6.457
East side wall 1 x 1 1.20 - 3.15 3.780
West side wall 1 x 1 1.15 - 3.15 3.622
Deduct Ventilator -1 x 1 0.89 - 0.59 -0.525
Hall Plastering
North side wall 1 x 1 3.43 - 3.15 10.804
Deduct main door -1 x 1 0.90 - 2.05 -1.845
Window -1 x 1 1.46 - 1.37 -2.000
West side wall 1 x 1 7.10 - 3.15 22.365
Deduct entrance -1 x 1 0.96 - 2.05 -1.968
East side wall 1 x 1 5.50 - 3.15 17.325
Deduct Doors -1 x 1 1.52 - 1.37 -2.082
South side wall 1 x 1 1.80 - 3.15 5.670
1 x 1 1.50 - 3.15 4.725
Deduct Kitchen door -1 x 1 0.96 - 2.05 -1.968
Pooja Room
Pooja room Out side 1 x 1 1.33 - 3.15 4.189
Deduct door -1 x 1 0.76 - 2.03 -1.542
Nort side wall 1 x 1 1.75 - 3.15 5.512
East side wall 1 x 1 1.19 - 3.15 3.748
Deduct window -1 x 1 0.92 - 1.36 -1.251
South side wall 1 x 1 1.75 - 3.15 5.512
West side wall 1 x 1 1.19 - 3.15 3.748
Deduct Pooja Door -1 x 1 0.76 - 2.03 -1.542
Kitchen Room
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
North sidewall 1 x 1 3.42 - 3.15 10.773
Deduct Door -1 x 1 0.96 - 2.02 -1.939
West side wall 1 x 1 2.70 - 3.15 8.505
South side wall 1 x 1 3.44 - 3.15 10.836
Deduct Door -1 x 1 0.96 - 2.02 -1.939
Window -1 x 1 1.20 - 1.50 -1.800
East side wall 1 x 1 2.69 - 3.15 8.473
Deduct Window -1 x 1 1.50 - 1.04 -1.560
Total in Sq.Mt :: 250.56 Sq.Mt 375.17 1 Sq.Mt 94004.47
B) External 9" brick wall :-
Qty. V. P. No. 44 to 47 of M. B. No. :
North side wall 1 x 1 3.70 - 3.15 11.655
Deduction : Door -1 x 1 0.90 - 2.05 -1.845
windows -1 x 1 1.46 - 1.37 -2.000
O/s wall 1 x 1 1.28 - 3.15 4.032
Deduction : Door -1 x 1 0.90 - 2.05 -1.845
O/s wall 1 x 1 4.63 - 3.15 14.584
Deduction window -1 x 1 1.52 - 1.30 -1.976
West side wall 1 x 1 14.25 - 3.15 44.887
Deduction windows -1 x 1 1.52 - 1.30 -1.976
Ventilators -1 x 2 0.90 - 0.60 -1.080
Windows -1 x 1 0.90 - 1.32 -1.188
South side wall 1 x 1 8.10 - 3.15 25.515
Deductions Windows -1 x 1 0.90 - 1.32 -1.188
Kitchen Door -1 x 1 0.87 - 2.07 -1.800
Windows -1 x 1 1.20 - 1.05 -1.260
Wash are CW 1 x 1 2.50 1.40 - 3.500
Inner side 1 x 1 2.38 0.97 - 2.308
Top side 1 1 2.30 0.13 - 0.299
South side wall outer 1 x 1 8.10 1.40 - 11.340
inner 1 x 1 7.97 0.97 - 7.730
top side 1 x 1 7.97 0.13 - 1.036
West side wall inner 1 x 1 1.05 1.95 - 2.047
East side wall 1 x 1 10.45 - 3.15 32.917
Deduct windows -1 x 2 1.52 - 1.37 -4.164
window -1 x 1 0.93 - 1.37 -1.274
window -1 x 1 1.52 - 1.05 -1.596
Total in Sq.Mt :: 138.66 Sq.Mt 375.17 1 Sq.Mt 52020.32
18) RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire
mesh & nominal reinforcement as directed by Engineer-in-charge with
dubara sponge finishing, including cost & conveyance of all materials to
site, seigniorage charges, sales & other taxes on all materials,
operational & incidental, cost and conveyance of cement, wire mesh,
water to work site, centering, scaffolding and form work, lift charges
etc., complete for finished items of work but excluding cost of steel & its
fabrication charges, for finished item of work. (APSS No.403&903).

Qty. V. P. No. 56 to 57 of M. B. No. :


Portico 1 x 1 0.44 - 0.45 0.198
1 x 1 4.03 - 0.45 1.813
1 x 1 0.54 - 0.45 0.243
Drop wall North side 1 x 1 5.42 - 0.45 2.439
1 x 1 0.96 - 0.45 0.432
West side 1 x 1 13.60 - 0.45 6.120
South side 1 x 1 0.914 - 0.45 0.411
1 x 1 8.229 - 0.45 3.703
East Side 1 x 1 13.50 - 0.45 6.075
Total in Sq.Mt :: 21.43 Sq.Mt 1716.63 1 Sq.Mt 36794.25
19) Ceiling Plastering with CM(1:3) Prop: 12mm thick in single coat spong
finish including cost and conveyance of all materials like cement, sand,
water etc., to site, including seigniorage charges, sales & other taxes on
all materials, all operational, incidental charges and labour charges such
as mixing mortar, finishing, curing, etc., complete for finished item of
work. (APSS 901,906).
Qty. V. P. No. of M. B. No. :
1 x 1 13.60 10.00 136.00
Total in Sq.Mt :: 136.00 Sq.Mt 133.81 1 Sq.Mt 18198.16
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
20) Plain Cement Concrete M15 grade nominal mix (1:2.5:5) proportion
(cement: fine aggregate: Coarse aggregate) using 40mm, 20mm, 10mm
size Hard Broken Granite (IS383, 1970) Machine Crushed metal from
approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, including seigniorage
charges, sales & other taxes on all materials, all operational, incidental
and labour charges such as mixing concrete in Concrete Mixer, laying,
curing concrete, etc., complete for finished item of work (APSS No. 402)
Steps.

Qty. V. P. No. 37 of M. B. No. :


1 x 16 0.80 0.24 0.18 0.55
Total in Cu.Mt :: 0.55 Cu.Mt 5463.37 1 Cu.Mt 3004.85
21) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade
as per IS 1786-1979) of different diameters for RCC works, including
labour charges for straightening, cutting, bending to required sizes and
shapes, placing in position with cover blocks of approved materials and
size and tying and lapsplicing with binding wire of 18 SWG, forming grills
for reinforcement work as per approved designs and drawings, including
cost and conveyance of steel bars, including all wastages such as
overlaps, couplings, chairs, spacer bars including cost and conveyance of
binding wire, cover blocks and all incidental, operational, laour charges
such as cutting, bending placing in position, tying including sales and
other taxes on all materials etc., complete for finished item of work in all
floors. (APSS No.126).

Qty. V. P. No. 3 of M. B. No. : 173.33 Kg


Qty. V. P. No. 4 of M. B. No. : 490.00 Kg
Qty. V. P. No. 18 of M. B. No. : 495.234 Kg
Qty. V. P. No. 22 of M. B. No. : 418.85 Kg
Qty. V. P. No. 23 of M. B. No. : 67.58 Kg
Qty. V. P. No. 29 of M. B. No. : 1035.06 Kg
Qty. V. P. No. 26 to 31 of M. B. No. : 841.00 Kg
3521.05 Kg 63.943 1 Kg 225146.76
22) Flooring with adanga Marbles of I st quality of size not exceeding 0.457
x 0.457m laid over CC Flooring bed set over 20mm thcik CM(1:8) drop
kase coat and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed
with white cement paste mixed with pigment of matching shade
including cost and conveyance of all materials like cement, sand, water,
tiles, etc. to site, seigniorage charges, sales and other taxes on all
materials, and all opertional, incidental and all labour charges such as
mixing of cement mortar, laying in position, curing, lift charges etc.,
complete for finished item of work in all floors.

Qty. V. P. No. 58-59 of M. B. No. :


1) Hall 1 x 1 5.50 3.45 - 18.98
1 x 1 1.60 1.60 - 2.56
2) Pooja Room 1 x 1 1.75 1.19 - 2.08
3) Kitchen Room 1 x 1 2.70 3.45 - 9.32
4) Master Bed Room 1 x 1 4.28 4.23 - 18.10
5) Children Bed Room 1 x 1 4.21 4.20 - 17.68
6) Bed Rooms area 1 x 1 2.52 1.90 - 4.79
7) Varandah 1 x 1 2.56 3.48 - 8.91
Total in Sq.Mt :: 82.42 Sq.Mt 988.47 1 Sq.Mt 81469.70
23) Timber shall be of the kind as specified, may be teak, shisham, sal,
deodar,etc., the timber shall be of best quality, well seasoned and free
from sap knots, warps, cracks and other defects, all wood work shall be
planed and neatly and truly finished to the exact dimensions. all joints
be neat and strong, truly and accurately fitted and glued before being
fitted together. Chunkhats : The Chunkhats shall be formed and joined
by motise and tenon joint with head wooden pins and the joints shall be
of coated with white lead before being fitted together.

Qty. V. P. No. 80 of M. B. No. :


1 x 6 0.96 - 2.05 6.00
Total in Sq.Mt :: 6.00 Each 15254.00 1 Each 91524.00
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
24) Providing and fixing 30mm thick Solid panel PVC door shutter consisting
of frame made out of M.S. tubes of 19 gauge thickness and size of
19mm x 19mm for stiles, & 15mm x 15mm for top & bottom rails. M.S.
frame shall have a coat of steel primers of approved make and
manufacture. M.S. frame shall be covered with 5mm thick heat molded
PVC ‘C’ channel of size 30 x 50mm forming stiles, and 5mm thick, 75mm
wide PVC sheets for top rail, lock rail & bottom rail on either side, and
10mm (5mm x 2) thick, 20mm wide cross PVC sheet as gap insert for
top rail & bottom rail. Paneling of 5mm thick PVC sheet to be fitted in
the M.S. frame welded / sealed to the stiles & rails with 30mm wide x
5mm thick PVC sheet beading on either side, and joined together with
solvent cement adhesive etc. An additional 5mm thick PVC strip of
20mm width is to be stuck on the interior side of the ‘C’ Channel using
PVC solvent adhesive. Complete as per direction of Engineer-in-charge,
manufacturer’s specification & drawing for finished item of work

Qty. V. P. No. 81 of M. B. No. :


Bath rooms door 1 x 2 0.80 - 1.90 3.04
Pooja Room Door 1 x 1 0.76 - 2.03 1.54
Toilet under stair case 1 x 1 0.84 - 2.10 1.76
Total in Sq.Mt :: 6.34 Sq.Mt 2493.00 1 Sq.Mt 15805.62
25) Supplying and fixing fully glazed anodized aluminium hinged type
window with fan light as per drawing using standard outer frame
38.5x33x21x2.5mm thick and central mullion of size
59(3mm)x33(4mm)x21(3mm) using 5mm thick, glass fitted with suitable
aluminium glazing clips and rubber beading including supplying and
fixing friction hinges (2np.s per shutter), handle with lock(1 no. per
shutter), incl cost and conveyance to site of aluminium sections, glass
rubber beading, fixtures etc., including labour charges for manufacturing
window, fixing in position using wooden blocks and sheet metalscrews
etc., complete for finished item of work.

Qty. V. P. No. 82 of M. B. No. :


Hall window 1 x 1 1.46 - 1.37 2.00
Bed Room 2 1 x 2 1.52 - 1.30 3.95
Bed Room 1 1 x 2 0.90 - 1.32 2.37
Hall 1 x 2 1.52 - 1.37 4.16
Kitchen window 1 x 1 1.20 - 1.50 1.80
1 x 1 1.04 - 1.50 1.56
Total in Sq.Mt :: 15.84 Sq.Mt 6417.00 1 Sq.Mt 101645.28
26) Glazed ventilator as per drawing using anodised aluminium sections of
38.5x33x21x2.50mm thick outer frame and central mullion of size
59(3mm) x 33 (2.5mm) and shutters with z section of 33(2.5mm) x 24.5
(3mm) x 21 (3mm) and 5mm thick plain glass fitted with suitable
aluminium glazing be made of single panel shutter of 25mm thick
providing with keyless lock, 100mm aluminium tower clips and rubber
beading including supply and fixing of no.s frictions hinges, 2no.s ISI
marked anodised aluminium tower bolts 75mm long including cost and
conveyance of all materials to site, fixtures in position using wooden
blocks & sheet metals screws etc.,

Qty. V. P. No. 83 of M. B. No. :


Ventilators 1 x 2 0.89 - 0.59 1.05
Pooja Room 1 x 1 0.90 - 1.36 1.22
Total in Sq.Mt :: 2.27 Sq.Mt 4246.00 1 Sq.Mt 9638.42
27) Painting to new walls with 2 coats of water proof cement paint of
apporved brand and shade as approved by the Engineer - in - Charge
over a base coat of approved cement primer grade II exterior making
three coats in all to give an even shade after thourughly brushing the
surface to remove all dirt and remains of loose powdered materials,
including cost and conveyance of all materials, cost of brushes, water to
site, etc., sales & other taxes, all operational, incidental, labour charges
etc. complete for finished item of work as per SS 912 for internal walls.
A) Internal walls :-
Qty. V. P. No. 72 to 79 of M. B. No. :
BED ROOM 2
North side 1 x 1 4.22 - 3.15 13.293
Deduct Window -1 x 1 1.52 - 1.30 -1.976
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
West side 1 x 1 4.20 - 3.15 13.230
Deduct window -1 x 1 1.52 - 1.30 -1.976
South side 1 x 1 4.22 - 3.15 13.293
Deduct Door -1 x 1 0.96 - 2.05 -1.968
Door (Bath) -1 x 1 0.80 - 1.90 -1.520
East side 1 x 1 4.20 - 3.15 13.230
Deduct Door -1 x 1 0.96 - 2.05 -1.968
Open area NS 1 x 1 1.87 - 3.15 5.890
Deduct Bed Room Door -1 x 1 0.96 - 2.05 -1.968
West side 1 x 1 2.50 - 3.15 7.875
South side 1 x 1 2.00 - 3.15 6.300
Deduct BR Door -1 x 1 0.96 - 2.05 -1.968
East side 1 x 1 2.45 - 3.15 7.717
Deduct : Entrance -1 x 1 0.96 - 2.05 -1.968
BR 1 South side wall 1 x 1 4.21 - 3.15 13.261
Deduct window -1 x 1 0.90 - 1.32 -1.188
West side wall 1 x 1 4.25 - 3.15 13.387
Deduct window -1 x 1 0.90 - 1.32 -1.188
North side wall 1 x 1 4.13 - 3.15 13.009
Deduct Bath room door -1 x 1 0.80 - 1.90 -1.520
Bed Room Door -1 x 1 0.96 - 2.05 -1.968
East side wall 1 x 1 4.10 - 3.15 12.915
Bed Room 2 S wall 1 x 1 2.05 - 1.10 2.255
North side wall 1 x 1 2.05 - 1.10 2.255
Deduct Door -1 x 1 0.80 - 1.90 -1.520
East side wall 1 x 1 1.20 - 1.10 1.320
West side wall 1 x 1 1.15 - 1.10 1.265
Deduct ventilator -1 x 1 0.89 - 0.59 -0.525
Bath room 1 S wall 1 x 1 2.05 - 1.10 2.255
Deduct Door -1 x 1 0.80 - 1.90 -1.520
North sidewall 1 x 1 2.05 - 1.10 2.255
East side wall 1 x 1 1.20 - 1.10 1.320
West side wall 1 x 1 1.15 - 1.10 1.265
Deduct ventilator -1 x 1 0.89 - 0.59 -0.525
Hall North side 1 x 1 3.43 - 3.15 10.804
Deduct main door -1 x 1 0.90 - 2.05 -1.845
Windows -1 x 1 1.46 - 1.37 -2.000
West side 1 x 1 7.10 - 3.15 22.365
Deduct BR Entrance -1 x 1 0.96 - 2.05 -1.968
East side 1 x 1 5.50 - 3.15 17.325
Deduct windows -1 x 1 1.52 - 1.37 -2.082
South side 1 x 1 1.80 - 3.15 5.670
1 x 1 1.50 - 3.15 4.725
Deduct Kitchen door -1 x 1 0.96 - 2.05 -1.968
Pooja room west wal 1 x 1 1.33 - 3.15 4.189
Deduct door 1 x 1 0.76 - 2.03 1.542
North side wall 1 x 1 1.75 - 3.15 5.512
East side wall 1 x 1 1.19 - 3.15 3.748
Deduct window -1 x 1 0.92 - 1.36 -1.251
South side wall 1 x 1 1.75 - 3.15 5.512
West side wall 1 x 1 1.19 - 3.15 3.748
Deduct Pooja Door -1 x 1 0.76 - 2.03 -1.542
Kitchen Room N S Walls 1 x 1 3.42 - 3.15 10.773
Deduct Kitchen Door -1 x 1 0.96 - 2.02 -1.939
West side wall 1 x 1 2.70 - 3.15 8.505
South side wall 1 x 1 3.44 - 1.85 6.364
Deduct Door -1 x 1 0.96 - 2.02 -1.939
East side wall 1 x 1 2.69 - 1.85 4.976
Total in Sq.Mt :: 221.55 Sq.Mt 193.32 1 Sq.Mt 42829.66
B) External walls :-
Qty. V. P. No. 69 to 71 of M. B. No. :
North side 1 x 1 3.70 - 3.15 11.655
Deduct Door -1 x 1 0.90 - 2.05 -1.845
Window -1 x 1 1.46 - 1.37 -2.000
Bed Room Outer wall 1 x 1 1.28 - 3.15 4.032
Deduct Door -1 x 1 0.90 - 2.05 -1.845
Bed Room outer wall 1 x 1 4.63 - 3.15 14.584
CRS+plinth Beam 1 x 1 4.63 - 1.50 6.945
Deduct Window -1 x 1 1.52 - 1.30 -1.976
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
West side wall 1 x 1 14.25 - (3.15+1.50) 66.26
Deduct Bed Room Window -1 x 1 1.52 - 1.30 -1.976
Ventilators -1 x 2 0.90 - 0.60 -1.080
Windows -1 x 1 0.90 - 1.32 -1.188
South side wall 1 x 1 8.10 - 3.15 25.515
CRS+plinth Beam 1 x 1 8.10 - (1.50+1.40) 23.49
Deduct window -1 x 1 0.90 - 1.32 -1.188
Door -1 x 1 0.87 - 2.07 -1.800
window -1 x 1 1.20 - 1.05 -1.260
Est side wall 1 x 1 2.50 - 2.90 7.250
9" wall+CRS 1 x 1 10.49 - (3.15+1.50) 48.78
Deduct Window 1 x 2 1.52 - 1.37 4.164
Window 1 x 1 0.93 - 1.37 1.274
Window 1 x 1 1.52 - 1.05 1.596
199.387 Sq.Mt
Qty. V. P. No. of M. B. No. :
West side wall 1 x 1 14.17 - 1.50 21.25
South side 1 x 1 8.30 - 1.50 12.45
East side 1 x 1 15.46 - 1.50 23.19
North side 1 x 1 3.81 - 1.50 5.71
62.60 Sq.Mt
Total in Sq.Mt :: 261.99 Sq.Mt 108.16 1 Sq.Mt 28336.51
28) Painting to new walls with 2 coats of water proof cement paint of
apporved brand and shade as approved by the Engineer - in - Charge
over a base coat of approved cement primer grade II exterior making
three coats in all to give an even shade after thourughly brushing the
surface to remove all dirt and remains of loose powdered materials,
including cost and conveyance of all materials, cost of brushes, water to
site, etc., sales & other taxes, all operational, incidental, labour charges
etc. complete for finished item of work as per SS 912 for internal walls.

Qty. V. P. No. 64 of M. B. No. :


Ceiling 1 x 1 13.60 10.00 - 136.00
Total in Sq.Mt :: 136.00 Sq.Mt 193.32 1 Sq.Mt 26291.52
29) Dadooing to walls with glazed red or white full body ceramic wall tiles of
size 200 x 300 mm / 245 mm x 325 mm and thickness 6 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any
colour and finish in all shades and designs, any brand as approved by
Engineer - in - charge and set over a base coat of CM (1:5), 12mm thick
and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with
white cement paste mixed with pigment of matching shade including
cost and conveyance of all materials like cement, sand, water, tiles, etc.
to site, seigniorage charges, sales and other taxes on all materials, and
all opertional, incidental and all labour charges such as mixing of cement
mortar, laying in position, curing, lift charges etc., complete for finished
item of work in all floors

Qty. V. P. No. 61 to 62 of M. B. No. :


Bath Rooms 1 x 2 2.05 2.05 - 8.41
1 x 2 1.20 2.05 - 4.92
Deduct Door -1 x 1 0.80 1.90 - -1.52
Ventilator -1 x 1 0.89 0.59 - -0.52
Bath Room 2 1 x 2 2.05 2.05 - 8.41
1 x 2 1.20 2.05 - 4.92
Deduction Door -1 x 1 0.80 1.90 - -1.52
Ventilators -1 x 1 0.89 0.59 - -0.52
Kitchen Room : East Side 1 x 1 2.69 1.30 - 3.49
Deduct Kitchen Window -1 x 1 1.50 1.04 - -1.56
South side 1 x 1 2.34 1.30 - 3.04
Deduct Kitchen Window -1 x 1 1.20 1.50 - -1.80
Total in Sq.Mt :: 25.75 Sq.Mt 777.37 1 Sq.Mt 20017.28
30) Providing and fixing non skid ceramic tiles for flooring over and inclusive
of 20mm thick base plaster in cement morter 1:5 (1 cement : 5 coarse
sand) including a floating cement slurry including grouting/ filling the
joints with white cement slurry mixed with matching, pigment, curing,
cleaning and leaving/making necessary holes for sanitory connection
complete but including cost of cement and tiles in all heights/level for
skirting complete for finished item of work.
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Qty. V. P. No. 60 of M. B. No. :
1) Bath Room- 1 1 x 1 2.05 1.2 - 2.46
2) Bath Room - 2 1 x 1 2.05 1.2 - 2.46
Total in Sq.Mt :: 4.92 Sq.Mt 775.71 1 Sq.Mt 3816.49
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
SUPPLYMENTARY ITEM
31) Brick Masonry in superstructure with CM (1:8) prop with Flyash Cement
solid blocks of size 290 x 225 x 140 mm, for manufacturing of flyash
solid blocks using flyash of 80 kgs, cement of 15 kgs. Gypsum of 5 kgs.
and stone dust with a compresive strength not lessthan 50 kg/sqm
including cost and conveyance of all materials, labour charges,
seiniorage charges, scaffolding and curing etc., for Superstructure
Walls.
Qty. V. P. No. 13 of M. B. No. :
West side wall 1 x 1 14.170.45 1.82 11.60
South side wall 1 x 2 8.300.45 1.82 13.59
East side wall 1 x 1 15.460.45 1.82 12.66
North side wall 1 x 1 9.280.45 1.82 7.60
Total in Cu.Mt :: 45.45 Cu.Mt 6010.50 1 Cu.Mt 273177.23
32) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Waist Slab
150mm thick.

Qty. V. P. No. 25 of M. B. No. :


Stair case Slab

From Ground Level to Landing 1 x 1 3.45 0.98 0.12 0.405


Only mid landing 1 x 1 1.27 0.95 0.12 0.144
From Landing to Roof Level 1 x 1 1.70 0.95 0.12 0.193
0.742 Cu.Mt
Total in Sq.Mt :: 4.95 Sq.Mt 1455.60 1 Sq.Mt 7205.22
33) Providing Skirting to internal walls to 15 cm height and risers of steps
with soluble salt porcelain vitrified tiles screen printed and polished of
size 600 x 600 mm and thickness between 8-10 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any
colour and finish of make Jhonson & Jhonson, Kajaria, Nitco, Marbonite,
set over base coat of CM (1:5) 12 mm thick with cement slurry of honey
like consistency spread at the rate of 3.30 kgs per sqm and jointed with
white cement paste mixed with pigment of matching shade to full depth,
including cost of all materials like tiles, cement, sand and water etc.,
complete including seigniorage charges, etc., complete for finished item
of work.

Qty. V. P. No. 65 to 67 of M. B. No. :


1) HALL North Side 1 x 1 3.73 - 0.1016 0.38
Deduct Door -1 x 1 0.90 - 0.1016 -0.09
West side 1 x 1 7.36 - 0.1016 0.74
Deduct Entrance -1 x 1 0.96 - 0.1016 -0.10
East side 1 x 1 5.50 - 0.1016 0.56
South Side 1 x 1 2.10 - 0.1016 0.21
2) Pooja Room N Side 1 x 1 1.75 - 0.10 0.175
South Side 1 x 1 1.75 - 0.10 0.175
East side 1 x 1 1.19 - 0.10 0.12
West side 1 x 1 1.19 - 0.10 0.12
Deduct Door -1 x 1 0.76 - 0.10 -0.076
3) Kitchen N Side 1 x 1 0.93 - 0.10 0.093
East 1 x 1 0.35 - 0.10 0.035
1 x 1 2.16 - 0.10 0.216
South 1 x 1 0.22 - 0.10 0.022
1 x 1 0.85 - 0.10 0.085
West side 1 x 1 2.50 - 0.10 0.250
4) Bed Room N Side 1 x 1 3.16 - 0.10 0.32
East side 1 x 1 (4.10+0.15) - 0.10 0.43
South side 1 x 1 4.21 - 0.10 0.42
West side 1 x 1 4.25 - 0.10 0.43
1 x 1 0.22 - 0.10 0.02
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
5) Bed Room North 1 x 1 4.22 - 0.10 0.422
South 1 x 1 3.10 - 0.10 0.310
East 1 x 1 3.10 - 0.10 0.310
West 1 x 1 4.20 - 0.10 0.420
6) Area bw Bed rooms 1 x 1 (0.84+0.09) - 0.10 0.100
South 1 x 1 0.35+1.16) - 0.10 0.100
East 1 x 1 (0.22+0.85) - 0.10 0.100
West 1 x 1 2.50 - 0.10 0.250
Total in Sq.Mt :: 6.547 Sq.Mt 977.30 1 Sq.Mt 6398.38
34) Supply and fixing of Black Granite stone and set over a base coat of CM
(1:5), 12mm thick and neat cement paste at the rate of 3.3 Kg/Sqmt.
and jointed with white cement paste mixed with pigment of matching
shade including cost and conveyance of all materials like cement, sand,
water, tiles, etc. to site, seigniorage charges, sales and other taxes on all
materials, and all opertional, incidental and all labour charges such as
mixing of cement mortar, laying in position, curing, lift charges etc.,
complete for finished item of work in all floors

Qty. V. P. No. 63 of M. B. No. :


East 1 x 1 1.95 0.50 - 0.98
1 x 1 1.82 0.50 - 0.91
Total in Sq.Mt :: 1.89 Sq.Mt 36009.58 10 Sq.Mt 6805.81
35) Reinforced Cement Concrete M20 Grade Nominal Mix corresponding to
IS 456 using 20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and conveyance
of all materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges, sales & other taxes
on all materials including all operational, incidental and labour charges
such as machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of
work (APSS No. 402) including centering, shuttering, laying concrete,
curing etc. complete for Side Walls of 100mm thick.

Qty. V. P. No. of M. B. No. :


Septic tank side wall 1 x 1 π/4 (1.30²-1.20²) 2.70 0.53
Top cover 1 x 1 π/4 (1.30²) 0.10 0.13
Bottom portion 1 x 1 π/4 (1.30²) 0.15 0.20
Total in Sq.Mt :: 0.86 Sq.Mt 3855.40 1 Sq.Mt 3321.57
36) Supply and fixing of M.S.Grill of size with outer angular frame of rolled
steel equal angle of ISA 2525 of size 25mm x 25mm x 4mm welded with
safety bars of 10mm square rods at 150mm centre to centre horizontally
and verticlally including red oxide primer of grade-I quality, sales and
other taxes, cost and conveyance of all materials to site, all labour
charges and fixing in position etc., complete for finished item of work.

Qty. V. P. No. of M. B. No. :


Hall window 1 x 1 1.46 - 1.37 2.00
Bed Room 2 1 x 2 1.52 - 1.30 3.95
Bed Room 1 1 x 2 0.90 - 1.32 2.37
Hall 1 x 2 1.52 - 1.37 4.16
Kitchen window 1 x 1 1.20 - 1.50 1.80
1 x 1 1.04 - 1.50 1.56
Total in Kgs :: 15.84 Sq.Mt 1506.00 1 Kgs 23855.04

Total:- 2292471.29

Forest Range Officer, Forest Divisional Officer,


E.Bayyaram Manuguru,
COMPLETION REPORT
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of Paloncha Range of Paloncha Division,
during 2022-23 under CAMPA - NPV scheme.
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
1 2 3 4 5 6 7 8 9 10 11

1) Earth work excavation for foundations and


depositing on bank for all lifts and with an initial
lead of 10m including all operational, incidental,
labour charges such as shoring ,sheeting,
73.580 Cu.Mt 336.53 1 Cu.Mt 24762.00 76.08 Cu.Mt 336.53 1 Cu.Mt 25603.20 841.20 0.00
planking, strutting, etc. complete for finished item
of work including seigniorage excluding
dewatering charges etc as per SS - 20 B (APSS
308). for building foundation.
2) Vibrated Plain Cement Concrete (1:3:6) proportion
(cement: fine aggregate: Coarse aggregate) using
40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry
including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to
site, mixing concrete in concrete mixer including 8.350 Cu.Mt 4976.25 1 Cu.Mt 41552.00 9.34 Cu.Mt 4976.25 1 Cu.Mt 46468.22 4916.22 0.00
seigniorage charges, sales & other taxes on all
materials, all operational, incidental, and labour
charges such as laying and ramming concrete in
layers in position not exceeding 15cm, finishing
top surface, curing concrete, etc., complete for
finished item of work.

3) Vibrated Plain Cement Concrete (1:4:8) proportion


(cement: fine aggregate: Coarse aggregate) using
40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry
including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to
site, mixing concrete in concrete mixer including
seigniorage charges, sales & other taxes on all 9.03 Cu.Mt 4607.01 1 Cu.Mt 41597.00 9.37 Cu.Mt 4607.01 1 Cu.Mt 43153.86 1556.86 0.00
materials, all operational, incidental, and labour
charges such as laying and ramming concrete in
layers in position not exceeding 15cm, finishing
top surface, curing concrete, etc., complete for
finished item of work.
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
4) Coursed Rubble Stone Masonry in CM (1:3) Prop:
including cost and conveyance of all materials like
cement, sand, water etc., to site, including
seigniorage charges, sales & other taxes on all
45.549 Cu.Mt 4498.24 1 Cu.Mt 204890.00 20.32 Cu.Mt 4498.24 1 Cu.Mt 91404.24 0.00 113485.76
materials, all operational, incidental charges and
labour charges such as mixing mortar, finishing,
curing, etc., complete for finished item of work.
(APSS 901,906)
5) Filling with useful available excavated earth
(excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not
exceeding 15 cm thick, consolidating each
deposited layer by watering and ramming
including cost and conveyance of water to work 73.579 Cu.Mt 274.72 1 Cu.Mt 20214.00 60.26 Cu.Mt 274.72 1 Cu.Mt 16554.90 0.00 3659.10
site and all operational, incidental, labour charges,
hire charges of T & P etc., complete for finished
item of work. APSS No.309 & 310.

6) Filling with Gravel in trenches, sides of


foundations and basement with initial lead in
layers not exceeding 15cm thick, consolidating
each deposited layer by watering and ramming
37.320 Cu.Mt 368.00 1 Cu.Mt 13735.00 110.38 Cu.Mt 368.00 1 Cu.Mt 40619.84 26884.84 0.00
including all operational, incidental, labour
charges, seignorage charges, hire charges of T &
P etc., complete for finished item of work. (APSS
NO. 309 & 310).
7) VRCC (1:1½:3) prop nominal mix using 6 to
20mm (SS-5) graded machine crushed hard
granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all
materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine 7.82 Cu.Mt 9302.11 1 Cu.Mt 72745.00 7.61 Cu.Mt 9302.11 1 Cu.Mt 70798.36 0.00 1946.64
mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges
for finished item of work (APSS No. 402) with
minimum cement content @ 380Kgs/Cu.F. from
standard suppliers approved by the department
including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Column
Footings.
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
8) VRCC (1:1½:3) prop nominal mix using 6 to
20mm (SS-5) graded machine crushed hard
granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all
materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
mixing, laying concrete, curing etc.,complete but 4.560 Cu.Mt 11963.17 1 Cu.Mt 54603.00 8.40 Cu.Mt 11963.17 1 Cu.Mt 100502.59 45899.59 0.00
excluding cost of steel and its fabrication charges
for finished item of work (APSS No. 402) with
minimum cement content @ 380Kgs/Cu.F. from
standard suppliers approved by the department
including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Columns.

9) VRCC (1:1½:3) prop nominal mix using 6 to


20mm (SS-5) graded machine crushed hard
granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all
materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
mixing, laying concrete, curing etc.,complete but 5.61 Cu.Mt 11663.03 1 Cu.Mt 65395.00 5.70 Cu.Mt 11663.03 1 Cu.Mt 66444.28 1049.28 0.00
excluding cost of steel and its fabrication charges
for finished item of work (APSS No. 402) with
minimum cement content @ 380Kgs/Cu.F. from
standard suppliers approved by the department
including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Plinth Beam.
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
10) Reinforced Cement Concrete M20 Grade Nominal
Mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate)
from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including Seigniorage charges, sales &
other taxes on all materials including all
operational, incidental and labour charges such as 0.640 Cu.Mt 12087.01 1 Cu.Mt 7763.00 0.71 Cu.Mt 12087.01 1 Cu.Mt 8593.86 830.86 0.00
weigh batching, machine mixing, laying concrete,
curing etc.,complete but excluding cost of steel
and its fabrication charges for finished item of
work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering,
shuttering, laying concrete, vibrating, curing etc.,
complete. For Lintels.
11) Reinforced Cement Concrete M20 Grade Nominal
Mix corresponding to IS 456 using 20mm size
graded machine crushed hard granite metal
(coarse aggregate) from approved quarry
including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage
charges, sales & other taxes on all materials
including all operational, incidental and labour 6.70 Sq.Mt 1090.21 1 Sq.Mt 7304.00 7.88 Sq.Mt 1090.21 1 Sq.Mt 8585.40 1281.40 0.00
charges such as machine mixing, laying concrete,
curing etc.,complete but excluding cost of steel
and its fabrication charges for finished item of
work (APSS No. 402) including centering,
shuttering, laying concrete, curing etc. complete
for Sunshades / Chajjas for 75mm thick at Fixed
end and 50mm thick at Free end and for a width
of 0.60 Mts. etc complete for finished item of
work.
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
12) VRCC (1:1½:3) prop nominal mix using 6 to
20mm (SS-5) graded machine crushed hard
granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all
materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
mixing, laying concrete, curing etc.,complete but 4.78 Cu.Mt 11581.80 1 Cu.Mt 55332.00 5.46 Cu.Mt 11581.80 1 Cu.Mt 63259.79 7927.79 0.00
excluding cost of steel and its fabrication charges
for finished item of work (APSS No. 402) with
minimum cement content @ 380Kgs/Cu.F. from
standard suppliers approved by the department
including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Roof Beams.

13) VRCC (1:1½:3) prop nominal mix using 6 to


20mm (SS-5) graded machine crushed hard
granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all
materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine 117.32 Sq.Mt 1322.94 1 Sq.Mt 155207.00 134.10 Sq.Mt 1322.94 1 Sq.Mt 177406.25 22199.25 0.00
mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges
for finished item of work (APSS No. 402) with
minimum cement content @ 380Kgs/Cu.F. from
standard suppliers approved by the department
including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Roof Slab
125mm thick.
14) Brick Masonry in superstructure with CM (1:8)
prop: using second class bricks of size 23 x 11 x 7
Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost
and conveyance of all materials like cement, sand,
bricks, water etc., to site, including seigniorage 0.00 0.00
charges, sales & other taxes on all materials, all
operational, incidental and labour charges such as
mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc.,
complete for finished item of work.
9" Brick wall 25.10 Cu.Mt 6222.35 1 Cu.Mt 156181.00 28.18 Cu.Mt 6222.35 1 Cu.Mt 175345.82 19164.82 0.00
4.5" Brick wall 9.38 Sq.Mt 6222.35 1 Sq.Mt 58366.00 16.04 Sq.Mt 6222.35 1 Sq.Mt 99812.72 41446.72 0.00
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
15) Impervious coat 20mm thick over RCC roof slab
surface with CM(1:3), promixed with 1kg of water
proof compound per bag of cement laid over roof
when it is green including cost of all materials,
seigniorage charges, excluding conveyance
charges of materials and including all operational, 133.17 Sq.Mt 429.14 1 Sq.Mt 57147.00 134.10 Sq.Mt 429.14 1 Sq.Mt 57547.67 400.67 0.00
incidental and labour charges for mixing mortar,
laying, rendering smooth and thread lining,
curing, rounding off junctions of wall and slab
etc,, complete for finished item of work.
16) Plastering 20mm thick in two coats with base coat
of 16mm thick in CM (1:6) and top coat of 4mm
thick in CM (1:4) dubara sponge finish including
cost and conveyance of all materials like cement,
screened sand, water etc., to site, seigniorage
charges, sales & other taxes on all materials, all
operational, incidental and labour charges such
as mixing mortar,scaffolding charges, lift charges, 42.05 Sq.Mt 387.62 1 Sq.Mt 16301.00 74.98 Sq.Mt 387.62 1 Sq.Mt 29063.75 12762.75 0.00
finishing,including cutting of Grooves wherever
necessary as directed by Engineer - in - charge,
curing, etc., for Uneven Surfaces of Brick Wall
complete for finished item of work. (APSS 901,903
& 904)

17) Plastering 12mm thick in two coats with base coat


of 9mm thick in CM (1:6) and top coat of 3mm
thick in CM (1:4) dubara sponge finish including
cost and conveyance of all materials like cement,
screened sand, water etc., to site, seigniorage
charges, sales & other taxes on all materials, all
operational, incidental and labour charges such 0.00 0.00
as mixing mortar, scaffolding charges, lift charges,
finishing, including cutting of Grooves wherever
necessary as directed by Engineer - in - charge,
curing, etc., for Uneven Surfaces of Brick Wall
complete for finished item of work. (APSS 901,903
& 904).
A) Internal 9" brick walls : 252.92 Sq.Mt 375.17 1 Sq.Mt 94889.00 250.56 Sq.Mt 375.17 1 Sq.Mt 94004.47 0.00 884.53
B) External 9" brick wall :- 138.66 Sq.Mt 375.17 1 Sq.Mt 52834.00 138.66 Sq.Mt 375.17 1 Sq.Mt 52020.32 0.00 813.68
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
18) RCM facia 5cm thick in CM (1:3) for drop walls,
fins with rabbit wire mesh & nominal
reinforcement as directed by Engineer-in-charge
with dubara sponge finishing, including cost &
conveyance of all materials to site, seigniorage
charges, sales & other taxes on all materials, 68.75 Sq.Mt 1716.63 1 Sq.Mt 118026.00 21.43 Sq.Mt 1716.63 1 Sq.Mt 36794.25 0.00 81231.75
operational & incidental, cost and conveyance of
cement, wire mesh, water to work site, centering,
scaffolding and form work, lift charges etc.,
complete for finished items of work but excluding
cost of steel & its fabrication charges, for finished
item of work. (APSS No.403&903).
19) Ceiling Plastering with CM(1:3) Prop: 12mm thick
in single coat spong finish including cost and
conveyance of all materials like cement, sand,
water etc., to site, including seigniorage charges,
sales & other taxes on all materials, all 108.82 Sq.Mt 133.81 1 Sq.Mt 14561.00 136.00 Sq.Mt 133.81 1 Sq.Mt 18198.16 3637.16 0.00
operational, incidental charges and labour charges
such as mixing mortar, finishing, curing, etc.,
complete for finished item of work. (APSS
901,906).
20) Plain Cement Concrete M15 grade nominal mix
(1:2.5:5) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm, 20mm, 10mm
size Hard Broken Granite (IS383, 1970) Machine
Crushed metal from approved quarry including
cost and conveyance of all materials like cement, 0.96 Cu.Mt 5463.37 1 Cu.Mt 5245.00 0.55 Cu.Mt 5463.37 1 Cu.Mt 3004.85 0.00 2240.15
sand, coarse aggregate, water etc. to site,
including seigniorage charges, sales & other taxes
on all materials, all operational, incidental and
labour charges such as mixing concrete in
Concrete Mixer, laying, curing concrete, etc.,
complete for finished item of work (APSS No. 402)
21) Providing High Yield Strength Deformed (HYSD)
steel bars (Fe 500 grade as per IS 1786-1979) of
different diameters for RCC works, including
labour charges for straightening, cutting, bending
to required sizes and shapes, placing in position
with cover blocks of approved materials and size
and tying and lapsplicing with binding wire of 18
SWG, forming grills for reinforcement work as per
approved designs and drawings, including cost 4027.91 Kg 63.94 1 Kg 257555.00 3521.05 Kg 63.94 1 Kg 225146.76 0.00 32408.24
and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of
binding wire, cover blocks and all incidental,
operational, laour charges such as cutting,
bending placing in position, tying including sales
and other taxes on all materials etc., complete for
finished item of work in all floors. (APSS No.126).
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
22) Flooring with adanga Marbles of I st quality of size
not exceeding 0.457 x 0.457m laid over CC
Flooring bed set over 20mm thcik CM(1:8) drop
kase coat and neat cement paste at the rate of
3.3 Kg/Sqmt. and jointed with white cement paste
mixed with pigment of matching shade including
cost and conveyance of all materials like cement, 83.29 Sq.Mt 988.47 1 Sq.Mt 82327.00 82.42 Sq.Mt 988.47 1 Sq.Mt 81469.70 0.00 857.30
sand, water, tiles, etc. to site, seigniorage
charges, sales and other taxes on all materials,
and all opertional, incidental and all labour
charges such as mixing of cement mortar, laying
in position, curing, lift charges etc., complete for
finished item of work in all floors.
23) Timber shall be of the kind as specified, may be
teak, shisham, sal, deodar,etc., the timber shall
be of best quality, well seasoned and free from
sap knots, warps, cracks and other defects, all
wood work shall be planed and neatly and truly
finished to the exact dimensions. all joints be neat 6.00 Each 15254.00 1 Each 91524.00 6.00 Each 15254.00 1 Each 91524.00 0.00 0.00
and strong, truly and accurately fitted and glued
before being fitted together. Chunkhats : The
Chunkhats shall be formed and joined by motise
and tenon joint with head wooden pins and the
joints shall be of coated with white lead before
being fitted together.
24) Providing and fixing 30mm thick Solid panel PVC
door shutter consisting of frame made out of M.S.
tubes of 19 gauge thickness and size of 19mm x
19mm for stiles, & 15mm x 15mm for top &
bottom rails. M.S. frame shall have a coat of steel
primers of approved make and manufacture. M.S.
frame shall be covered with 5mm thick heat
molded PVC ‘C’ channel of size 30 x 50mm 4.750 Sq.Mt 2493.00 1 Sq.Mt 11842.00 6.34 Sq.Mt 2493.00 1 Sq.Mt 15805.62 3963.62 0.00
forming stiles, and 5mm thick, 75mm wide PVC
sheets for top rail, lock rail & bottom rail on either
side, and 10mm (5mm x 2) thick, 20mm wide
cross PVC sheet as gap insert for top rail &
bottom rail. Paneling of 5mm thick PVC sheet to
be fitted in the M.S. frame welded / sealed to the
stiles & rails with 30mm wide x 5mm thick PVC
sheet beading on either side, and joined together
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
25) Supplying and fixing fully glazed anodized
aluminium hinged type window with fan light as
per drawing using standard outer frame
38.5x33x21x2.5mm thick and central mullion of
size 59(3mm)x33(4mm)x21(3mm) using 5mm
thick, glass fitted with suitable aluminium glazing
clips and rubber beading including supplying and
fixing friction hinges (2np.s per shutter), handle 15.390 Sq.Mt 6417.00 1 Sq.Mt 98758.00 15.84 Sq.Mt 6417.00 1 Sq.Mt 101645.28 2887.28 0.00
with lock(1 no. per shutter), incl cost and
conveyance to site of aluminium sections, glass
rubber beading, fixtures etc., including labour
charges for manufacturing window, fixing in
position using wooden blocks and sheet
metalscrews etc., complete for finished item of
work.
26) Glazed ventilator as per drawing using anodised
aluminium sections of 38.5x33x21x2.50mm thick
outer frame and central mullion of size 59(3mm) x
33 (2.5mm) and shutters with z section of
33(2.5mm) x 24.5 (3mm) x 21 (3mm) and 5mm
thick plain glass fitted with suitable aluminium
glazing be made of single panel shutter of 25mm 1.62 Sq.Mt 4246.00 1 Sq.Mt 6879.00 2.27 Sq.Mt 4246.00 1 Sq.Mt 9638.42 2759.42 0.00
thick providing with keyless lock, 100mm
aluminium tower clips and rubber beading
including supply and fixing of no.s frictions hinges,
2no.s ISI marked anodised aluminium tower bolts
75mm long including cost and conveyance of all
materials to site, fixtures in position using wooden
blocks & sheet metals screws etc.,
27) Painting to new walls with 2 coats of water proof
cement paint of apporved brand and shade as
approved by the Engineer - in - Charge over a
base coat of approved cement primer grade II
exterior making three coats in all to give an even
shade after thourughly brushing the surface to
remove all dirt and remains of loose powdered
materials, including cost and conveyance of all
materials, cost of brushes, water to site, etc.,
sales & other taxes, all operational, incidental,
labour charges etc. complete for finished item of
work as per SS 912 for internal walls.
A) Internal walls :- 252.92 Sq.Mt 193.32 1 Sq.Mt 48894.00 221.55 Sq.Mt 193.32 1 Sq.Mt 42829.66 0.00 6064.34
B) External walls :- 140.83 Sq.Mt 108.16 1 Sq.Mt 15232.00 261.99 Sq.Mt 108.16 1 Sq.Mt 28336.51 13104.51 0.00
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
28) Painting to new walls with 2 coats of water proof
cement paint of apporved brand and shade as
approved by the Engineer - in - Charge over a
base coat of approved cement primer grade II
exterior making three coats in all to give an even
shade after thourughly brushing the surface to 108.82 Sq.Mt 193.32 1 Sq.Mt 21036.00 136.00 Sq.Mt 193.32 1 Sq.Mt 26291.52 5255.52 0.00
remove all dirt and remains of loose powdered
materials, including cost and conveyance of all
materials, cost of brushes, water to site, etc.,
sales & other taxes, all operational, incidental,
labour charges etc. complete for finished item of
work as per SS 912 for internal walls.
29) Dadooing to walls with glazed red or white full
body ceramic wall tiles of size 200 x 300 mm /
245 mm x 325 mm and thickness 6 mm 1st
quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish
in all shades and designs, any brand as approved
by Engineer - in - charge and set over a base coat
of CM (1:5), 12mm thick and neat cement paste
at the rate of 3.3 Kg/Sqmt. and jointed with white 20.16 Sq.Mt 777.37 1 Sq.Mt 15672.00 25.75 Sq.Mt 777.37 1 Sq.Mt 20017.28 4345.28 0.00
cement paste mixed with pigment of matching
shade including cost and conveyance of all
materials like cement, sand, water, tiles, etc. to
site, seigniorage charges, sales and other taxes
on all materials, and all opertional, incidental and
all labour charges such as mixing of cement
mortar, laying in position, curing, lift charges etc.,
complete for finished item of work in all floors
30) Providing and fixing non skid ceramic tiles for
flooring over and inclusive of 20mm thick base
plaster in cement morter 1:5 (1 cement : 5 coarse
sand) including a floating cement slurry including
grouting/ filling the joints with white cement
slurry mixed with matching, pigment, curing, 3.780 Sq.Mt 775.71 1 Sq.Mt 2932.00 4.92 Sq.Mt 775.71 1 Sq.Mt 3816.49 884.49 0.00
cleaning and leaving/making necessary holes for
sanitory connection complete but including cost of
cement and tiles in all heights/level for skirting
complete for finished item of work.
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
31) Providing Skirting to internal walls and Risers of
Steps to 15 cm height with Polished shabad /
Tandur stone minimum 15 to 18 mm thick of size
(0.254M x0.254M) length equal to flooring stones,
set over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency spread at 9.330 Sq.Mt 535.72 1 Sq.Mt 4998.00 0.00 4998.00
the rate of 3.30 kgs per sqm and jointed with
white cement paste mixed with pigment of
matching shade to full depth, including cost of all
materials like tiles, cement, sand and water etc.,
complete including seigniorage charges, etc.,
complete for finished item of work.
32) Providing anti termite treatment as per IS 6315
(Part-2) 2001 (pre-constructional chemical
treatment measures) along the internal & external
vertical faces of the columns, plinth beams,
basement and top surface of the basement filling
below flooring bed as per the specified procedure
confirming to IS 6315 (Part-2) 2001 and other
relevent approved specification duly using
Chlorpyriphos / Lindane emulsifiable concentrate
20% with 1% concentration @ 7.5 Liters/sqm of 118.820 Sq.Mt 152.00 1 Sq.Mt 18061.00 0.00 18061.00
the vertical surface & 5.0 Liters/sqm of the
horizontal surface of the substructure to a depth
of 500mm around columns & 300mm deep
around plinth beams, basements & floor filling
area including excavation channel along the wall
& rodding etc & cost & conveyane of all materials
to the site, cost of labour for spraying, rodding etc
complete for finished item of work as per the
approval of the Engineer-in-Charge.
Supplymentary Items
31) Brick Masonry in superstructure with CM (1:8)
prop with Flyash Cement solid blocks of size 290 x
225 x 140 mm, for manufacturing of flyash solid
blocks using flyash of 80 kgs, cement of 15 kgs.
Gypsum of 5 kgs. and stone dust with a
compresive strength not lessthan 50 kg/sqm 45.45 Cu.Mt 6010.50 1 Cu.Mt 273177.23 273177.23 0.00
including cost and conveyance of all materials,
labour charges, seiniorage charges, scaffolding
and curing etc., for Superstructure Walls.
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
32) VRCC (1:1½:3) prop nominal mix using 6 to
20mm (SS-5) graded machine crushed hard
granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all
materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine 4.95 Sq.Mt 1455.60 1 Sq.Mt 7205.22 7205.22 0.00
mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges
for finished item of work (APSS No. 402) with
minimum cement content @ 380Kgs/Cu.F. from
standard suppliers approved by the department
including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Waist Slab
150mm thick.
33) Providing Skirting to internal walls to 15 cm height
and risers of steps with soluble salt porcelain
vitrified tiles screen printed and polished of size
600 x 600 mm and thickness between 8-10 mm
1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish
of make Jhonson & Jhonson, Kajaria, Nitco,
Marbonite, set over base coat of CM (1:5) 12 mm 6.547 Sq.Mt 977.300 1 Sq.Mt 6398.380 6398.38 0.00
thick with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and
jointed with white cement paste mixed with
pigment of matching shade to full depth, including
cost of all materials like tiles, cement, sand and
water etc., complete including seigniorage
charges, etc., complete for finished item of work.
34) Supply and fixing of Black Granite stone and set
over a base coat of CM (1:5), 12mm thick and
neat cement paste at the rate of 3.3 Kg/Sqmt.
and jointed with white cement paste mixed with
pigment of matching shade including cost and
conveyance of all materials like cement, sand, 1.89 Sq.Mt 36009.58 10 Sq.Mt 6805.81 6805.81 0.00
water, tiles, etc. to site, seigniorage charges, sales
and other taxes on all materials, and all
opertional, incidental and all labour charges such
as mixing of cement mortar, laying in position,
curing, lift charges etc., complete for finished item
of work in all floors
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
35) Reinforced Cement Concrete M20 Grade Nominal
Mix corresponding to IS 456 using 20mm size
graded machine crushed hard granite metal
(coarse aggregate) from approved quarry
including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage
charges, sales & other taxes on all materials 0.86 Sq.Mt 3855.40 1 Sq.Mt 3321.57 3321.57 0.00
including all operational, incidental and labour
charges such as machine mixing, laying concrete,
curing etc.,complete but excluding cost of steel
and its fabrication charges for finished item of
work (APSS No. 402) including centering,
shuttering, laying concrete, curing etc. complete
for Side Walls of 100mm thick.
Sl. As Per Sanction Estimate As Per Workdone Estimate Difference Remark
No. Description of item s
Qty. Unit Rate Per Amount Qty. Unit Rate Per Amount Excess Less
36) Supply and fixing of M.S.Grill of size with outer
angular frame of rolled steel equal angle of ISA
2525 of size 25mm x 25mm x 4mm welded with
safety bars of 10mm square rods at 150mm
centre to centre horizontally and verticlally
including red oxide primer of grade-I quality, sales 15.84 Sq.Mt 1506.00 1 Kgs 23855.04 23855.04 0.00
and other taxes, cost and conveyance of all
materials to site, all labour charges and fixing in
position etc., complete for finished item of work.

TOTAL :- 2014359.00 2292471.29

38) Water Supplay and Sanitor arrangements @11% 221579.00 252171.84 30592.84 0.00

39) Electrification @9% 181292.00 206322.42 25030.42 0.00

2417230.00 2750965.55

40) Deduct Tender Percentage at 3% Less 0.00 -82528.97 0.00 82528.97

Total :- 2417230.00 2668436.58

41) Add GST@12% 290068.00 320212.39 30144.39 0.00

42) Add Cess @ 1.00% 24172.00 26684.37 2512.37 0.00

GRAND TOTAL :- 2731470.00 3015333.34 633042.80 349179.46

As Per Sanction Estimate :: 2731470.00 Exess :: 633042.80


As Per Work Done Estimate :: 3015333.34 Less :: 349179.46
Difference :: -283863.34 -283863.34

Forest Range Officer, Forest Divisional Officer,


E.Bayyaram Manuguru,
SEIGNIOREGE CALICULATION CHART
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of Paloncha
Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.

Sl. Amount
No. Description of Item Qty Per Rate/Per
1 2 3 4 9
1 Earth work excavation for foundations and
Earth 76.08 Cum 30.00 1 Cum 2282.40
depositing on bank for all lifts and with an initial
lead of
2 Plain 10m Concrete
Cement including (1:4:8)
all operational,
proportionincidental,
(cement: Metal Err:509 Cum 75.00 1 Cum Err:509
seigniorage
fine charges,
aggregate: labour
Coarse chargesusing
aggregate) such 40mm
as shoring
size Sand Err:509 Cum 40.00 1 Cum Err:509
Hard Broken Granite (IS383, 1970)
3 Vibrated Reinforced Cement Concrete M20 Grade machine
crushed metal from
corresponding to IS approved
456 usingquarry
20mmincluding cost
size graded
machine
A) Footingscrushed hard granite metal (coarse Metal 6.85 Cum 75.00 1 Cum 513.74
aggregate) from approved quarry including cost Sand 3.42 Cum 40.00 1 Cum 136.99
B) Pedastals Metal 7.56 Cum 75.00 1 Cum 567.06
Sand 3.78 Cum 40.00 1 Cum 151.21
C) Columns Metal 54.23 Cum 75.00 1 Cum 4067.61
Sand 27.12 Cum 40.00 1 Cum 1084.69
D) Plinth Beam Metal 18.29 Cum 75.00 1 Cum 1371.60
Sand 9.14 Cum 40.00 1 Cum 365.76
E) Roof Beam Metal 5.13 Cum 75.00 1 Cum 384.54
Sand 2.56 Cum 40.00 1 Cum 102.54
F) Roof Slab 115mm Thick Metal 11.42 Sqm 75.00 1 Sqm 856.82
Sand 5.71 Sqm 40.00 1 Sqm 228.48
G) Lintels Metal 8.43 Cum 75.00 1 Cum 632.27
Sand 4.22 Cum 40.00 1 Cum 168.60
H) Sunshades Metal 0.31 Sqm 75.00 1 Sqm 23.04
Sand 0.15 Sqm 40.00 1 Sqm 6.14
4 Providing impervious coat to exposed RCC roof slab
Sand 0.00 Sqm 40.00 10 Sqm 0.00
surface with CM(1:3), 20mm thick with 1kg of water
proof compound
5 Filling with Gravelper bag of cement
in trenches, sides oflaid over roof
foundations
Gravel 134.10 Cum 30.00 1 Cum 4023.00
when it is green including cost
and basement with initial lead in layers not of all materials,
exceeding
6 Brick Masonry 15cmin thick, consolidating
superstructure with each deposited
CM (1:8) prop:
x 7 Cms all Sand 0.00 Cum 40.00 0.00
1 Cum
layer second
using by watering andof ramming
class bricks size 23 x 11 including
from approved source having minimum crushing
7 Plastering to even surface of walls with CM
strength of 40 Kg/Sqcm. including cost and Sand 0.90 Sqm 40.00 10 Sqm 3.60
(1:4)prop: 12mm thick in single coat sponge finish
including cost
8 Plastering 20mm andthick
conveyance
in two coatsof allwith
materials
base coatlike
Sand 1.33 Sqm 40.00 10 Sqm 5.32
cement,
of 16mm sand,thick inwater etc., and
CM (1:6) to top
site,coatseigniorage
of 4mm
9 thick
CeilinginPlastering
CM (1:4)with dubara
12mm sponge
thick infinish
singleincluding
coat in
Sand 0.34 Sqm 40.00 10 Sqm 1.36
cost and
CM (1:4)conveyance
sponge finish of all materials
includinglikecostcement,
and
conveyance
10 Flooring of all
with materials
soluble salt like cement,vitrified
porcelain sand, water
tiles
Sand 0.00 Sqm 40.00 10 Sqm 0.00
etc., to printed
screen site, including seigniorage
and polished of sizecharges,
600 x 600 salesmm &
and thickness
11 Providing Skirtingbetween
to internal 8-10
wallsmmto 151st cm quality
height
Sand 4.29 Sqm 40.00 10 Sqm 17.14
conforming to IS:13711, IS:13712,
and risers of steps with soluble salt porcelain IS:13630 (Parts
vitrified tiles screen printed and polished of size 600
x 600 mm and thickness between 8-10 mm 1st Total:- Err:509

Asst. Exe. Engineer Deputy Exe. Engineer Executive Engineer


T.W. Tekulapally T.W.S.D. - Sudimalla T.W.Divn., Bhadrachalam
1 Supply and fixing of 18guage M.S.Plain sheet DOOR of size 1.25M x 2.30M ( Double shutters )with outer
angular frame of rolled steel equal angle ISA 4040 of size 40mm x40mm x 6mm and with MS Hold fasts 6nos
with Double shutter Frame of angle ISA 3535 of size 35mm x35mm x4mm in between 2nos 25mm x25mm x 4
L angle section back side of shutter alround MS FLAT Patty 90x2mm with 18 guage MS Sheet welded with
required fixtures such as M.S.Powder coated tower bolts I.S. 204 150 mm long 2 Nos, M.S.Powder coated Butt
Hinges IS 205 125 mm long 6Nos., M.S.Powder coated handles IS 208 125mm long 2 Nos,M.S.Powder coated
Aldrops 300mm long 2nos and including Red oxide primer of grade-I quality, sales and other taxes ,cost and
conveyance of all materials to site, all labour cahrges etc.,complete for finished item of work.

DOOR SIZE : 1.05 X 1.98


AREA OF DOOR 2.079 Sqmts.
THEORITICAL REQUIREMENT
1 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 4040 - 40mm x 40mm x6mm
Verticals(L -Angle) 2 1.98 3.96

Horizontals(L-Angle) 2 1.05 2.1

Hold Fasts 6 0.23 1.38


7.44 RM
Equivalent Weight 3.50 Kgs/RM
Total Weight 7.44 3.50 26.04 Kgs.
2 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 3535 - 35mm X35mm X 4mm
Verticals(L -Angle) 4 1.930 7.72
Horizontals(L-Angle) 4 0.500 2
9.720 RM
Equivalent Weight 2.10 Kgs/RM
Total Weight 9.72 2.10 20.41 Kgs.
3 INNER SHUTTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 2525 - 25mm X25mm X
4mm
Horizontals(L-Angle) 4 0.500 2
2.000 RM
Equivalent Weight 1.40 Kgs/RM
Total Weight 2.00 1.40 2.8 Kgs.
4 18 Gauge MS Sheet
Area of Sheet 2 0.500 0.376 0.376 Sqm
Equivalent Weight 9.80 Kgs/Sqmt.
Total Weight 0.376 9.80 3.68 Kgs.
5 MS FLAT Patty 19x2
all round 1 5.86 5.86 RM
Equivalent Weight 0.30 Kgs/RM
Total Weight 5.86 0.30 1.76 Kgs.
6 DATA for Red Oxide Primer
Cost of Red Oxide GRADE-I Quality 0.6 142.00 85.20
Painter 1st class 0.21 515.00 108.15
Painter 2nd class 0.49 405.00 198.45
TOTAL Rs. 391.80 /10 Sqm.
ABSTRACT QUANTITY RATE AMOUNT
1 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL 26.04 Kgs 45.00 /Kg 1171.80
ANGLE ISA 4040 -40mmx40mmx6mm
2 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL 20.41 Kgs 45.00 /Kg 918.45
ANGLE ISA 3535 - 35mm X35mm X 4mm
3 INNER SHUTTER ANGULAR FRAME OF ROLLED STEEL 2.80 Kgs 45.00 /Kg 126.00
EQUAL ANGLE ISA 2525 - 25mmx25mmx4mm
4 18 Gauge MS Sheet 3.68 Kgs 44.00 /Kg 161.92
5 10mm square rods safety bars 1.76 Kgs 44.00 /Kg 77.44
6 DATA for Red Oxide Primer 6.24 Sqmts. 391.80 /10 Sqmts. 244.37
FIXTURES:
6 100mm Long MS Powder Coated Butt Hinges 6 Nos. 38.00 /Each 228.00
8 125mm Long MS Powder Coated Handles 2 Nos. 34.00 /Each 68.00
8 MS Aldrop 300 mm long 2 Nos. 181.00 /Each 362.00
10 Labour Charges for Fabrication of Steel Window 54.69 Kgs 24.00 /Kg 1312.56
11 Labour charges for Fixing of Window 54.69 Kgs 4.00 /Kg 218.76
4889.30
12 Agency Allowance @ 25% on fixing charges on 1531.32 382.83
Or Say per Each 5272.13
13 Add 13.615% Overhead& Contractors profit 0.00
5272.13
1 Supply and fixing of 18guage M.S.Plain sheet DOOR of size 0.90M x 2.13M ( Double shutters )with outer
angular frame of rolled steel equal angle ISA 4040
DOOR of SIZE
size 40mm
: x40mm
0.90 x 6mm
X and
2.13with MS Hold fasts 6nos
AREA OF WINDOW 1.917 Sqmts.
THEORITICAL REQUIREMENT
1 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 4040 - 40mm x 40mm x6mm
Verticals(L -Angle) 2 2.13 4.26
Horizontals(L-Angle) 2 0.9 1.8

Hold Fasts 6 0.23 1.38


7.44 RM
Equivalent Weight 3.50 Kgs/RM
Total Weight 7.44 3.50 26.04 Kgs.
2 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 3535 - 35mm X35mm X 4mm
Verticals(L -Angle) 4 2.080 8.32
Horizontals(L-Angle) 4 0.425 1.7
10.020 RM
Equivalent Weight 2.10 Kgs/RM
Total Weight 10.02 2.10 21.04 Kgs.
3 INNER SHUTTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 2525 - 25mm X25mm X
4mm
Horizontals(L-Angle) 4 0.425 1.7
1.700 RM
Equivalent Weight 1.40 Kgs/RM
Total Weight 1.70 1.40 2.38 Kgs.
4 18 Gauge MS Sheet
Area of Sheet 2 0.425 0.376 0.320 Sqm
Equivalent Weight 9.80 Kgs/Sqmt.
Total Weight 0.320 9.80 3.13 Kgs.
5 MS FLAT Patty 19x2
all round 1 5.86 5.86 RM
Equivalent Weight 0.30 Kgs/RM
Total Weight 5.86 0.30 1.76 Kgs.
6 DATA for Red Oxide Primer
Cost of Red Oxide GRADE-I Quality 0.6 105.00 63.00
Painter 1st class 0.21 350.00 73.50
Painter 2nd class 0.49 300.00 147.00
TOTAL Rs. 283.50 /10 Sqm.
ABSTRACT QUANTITY RATE AMOUNT
1 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL 26.04 Kgs 44.50 /Kg 1158.78
ANGLE ISA 4040 -40mmx40mmx6mm
2 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL 21.04 Kgs 44.50 /Kg 936.28
ANGLE ISA 3535 - 35mm X35mm X 4mm
3 INNER SHUTTER ANGULAR FRAME OF ROLLED STEEL 2.38 Kgs 44.50 /Kg 105.91
EQUAL ANGLE ISA 2525 - 25mmx25mmx4mm
4 18 Gauge MS Sheet 3.13 Kgs 44.00 /Kg 137.72
5 10mm square rods safety bars 1.76 Kgs 44.00 /Kg 77.44
6 DATA for Red Oxide Primer 5.75 Sqmts. 283.50 /10 Sqmts. 163.04
FIXTURES:
6 100mm Long MS Powder Coated Butt Hinges (188) 6 Nos. 33.00 /Each 198.00

8 125mm Long MS Powder Coated Handles (193) 2 Nos. 25.00 /Each 50.00
8 MS Aldrop 300 mm long 204 2 Nos. 134.00 /Each 268.00

10 Labour Charges for Fabrication of Steel Window ( page298) 54.35 Kgs 21.00 /Kg 1141.35
11 Labour charges for Fixing of Window (81 bmm-v-15 350) 54.35 Kgs 3.50 /Kg 190.23
4426.75
12 Agency Allowance @ 25% on fixing charges on 1331.58 332.89
4759.64
13 Add 14% Overhead& Contractors profit 666.35
5425.99
1 Supply and fixing of 18guage M.S.Plain sheet DOOR of size 0.90M x 1.98M with outer angular frame of rolled
steel equal angle ISA 3535 of size 35mm x35mmDOOR x 6mm
SIZE :and with0.90
MS Hold
X fasts 6nos with Double shutter
1.98
AREA OF WINDOW 1.782 Sqmts.
THEORITICAL REQUIREMENT
1 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 3535 - 35mm x 35mm x6mm
Verticals(L -Angle) 2 1.98 3.96

Horizontals(L-Angle) 2 0.9 1.8

Hold Fasts 6 0.23 1.38


7.14 RM
Equivalent Weight 2.10 Kgs/RM
Total Weight 7.14 2.10 14.99 Kgs.
2 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 2525 - 25mm X25mm X 4mm
Verticals(L -Angle) 4 1.930 7.72
Horizontals(L-Angle) 4 0.425 1.7
9.420 RM
Equivalent Weight 1.40 Kgs/RM
Total Weight 9.42 1.40 13.19 Kgs.
3 18 Gauge MS Sheet
Area of Sheet 2 0.425 0.376 0.320 Sqm
Equivalent Weight 9.80 Kgs/Sqmt.
Total Weight 0.320 9.80 3.13 Kgs.
4 MS FLAT Patty 19x2
all round 1 5.56 5.56 RM
Equivalent Weight 0.30 Kgs/RM
Total Weight 5.56 0.30 1.67 Kgs.
5 DATA for Red Oxide Primer
Cost of Red Oxide GRADE-I Quality 0.6 142.00 85.20
Painter 1st class 0.21 515.00 108.15
Painter 2nd class 0.49 405.00 198.45
TOTAL Rs. 391.80 /10 Sqm.
ABSTRACT QUANTITY RATE AMOUNT
1 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL 14.99 Kgs 36.50 /Kg 547.14
ANGLE ISA 4040 -35mmx35mmx6mm
2 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL 13.19 Kgs 36.50 /Kg 481.44
ANGLE ISA 2525 - 25mm X25mm X 4mm
3 18 Gauge MS Sheet 3.13 Kgs 36.50 /Kg 114.24
4 DATA for Red Oxide Primer 5.35 Sqmts. 391.80 /10 Sqmts. 209.46
FIXTURES:
5 125mm Long MS Powder Coated Butt Hinges TBSC-P.II-11 3 Nos. 34.00 /Each 102.00
6 150mm Long MS Powder Coated Handles TBSC-P.III-06 1 Nos. 50.00 /Each 50.00
7 MS Aldrop 300 mm long TBSC-P.IV-09 2 Nos. 181.00 /Each 362.00
8 Labour Charges for Fabrication TBSC-T.I-16 32.98 Kgs 26.00 /Kg 857.48
9 Labour charges for Fixing TBSC-T.I-17 32.98 Kgs 4.00 /Kg 131.92
2855.67
10 Agency Allowance @ 25% on fixing charges on 989.40 247.35
3103.02
11 Add 13.615% Overhead& Contractors profit 422.48
3525.50

2 Supply and fixing of 18guage M.S.Plain sheet DOOR of size 0.75M x 1.83M with outer angular frame of rolled
steel equal angle ISA 3535 of size 35mm x35mmDOOR x 6mm
SIZE :and with0.75
MS Hold
X fasts 6nos with Double shutter
1.83
AREA OF WINDOW 1.373 Sqmts.
THEORITICAL REQUIREMENT
1 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 3535 - 35mm x 35mm x6mm
Verticals(L -Angle) 2 1.83 3.66

Horizontals(L-Angle) 2 0.75 1.5

Hold Fasts 6 0.23 1.38


6.54 RM
Equivalent Weight 2.10 Kgs/RM
Total Weight 6.54 2.10 13.73 Kgs.
2 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 2525 - 25mm X25mm X 4mm
Verticals(L -Angle) 4 1.780 7.12
Horizontals(L-Angle) 4 0.350 1.4
8.520 RM
Equivalent Weight 1.40 Kgs/RM
Total Weight 8.52 1.40 11.93 Kgs.
3 18 Gauge MS Sheet
Area of Sheet 2 0.350 0.376 0.263 Sqm
Equivalent Weight 9.80 Kgs/Sqmt.
Total Weight 0.263 9.80 2.58 Kgs.
4 MS FLAT Patty 19x2
all round 1 4.96 4.96 RM
Equivalent Weight 0.30 Kgs/RM
Total Weight 4.96 0.30 1.49 Kgs.
5 DATA for Red Oxide Primer
Cost of Red Oxide GRADE-I Quality 0.6 142.00 85.20
Painter 1st class 0.21 515.00 108.15
Painter 2nd class 0.49 405.00 198.45
TOTAL Rs. 391.80 /10 Sqm.
ABSTRACT QUANTITY RATE AMOUNT
1 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL 13.73 Kgs 36.50 /Kg 501.15
ANGLE ISA 4040 -35mmx35mmx6mm
2 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL 11.93 Kgs 36.50 /Kg 435.45
ANGLE ISA 2525 - 25mm X25mm X 4mm
3 18 Gauge MS Sheet 2.58 Kgs 36.50 /Kg 94.17
4 DATA for Red Oxide Primer 4.12 Sqmts. 391.80 /10 Sqmts. 161.32
FIXTURES:
5 125mm Long MS Powder Coated Butt Hinges TBSC-P.II-11 3 Nos. 34.00 /Each 102.00
6 150mm Long MS Powder Coated Handles TBSC-P.III-06 1 Nos. 50.00 /Each 50.00
7 MS Aldrop 300 mm long TBSC-P.IV-09 2 Nos. 181.00 /Each 362.00
8 Labour Charges for Fabrication TBSC-T.I-16 29.73 Kgs 26.00 /Kg 772.98
9 Labour charges for Fixing TBSC-T.I-17 29.73 Kgs 4.00 /Kg 118.92
2597.98
10 Agency Allowance @ 25% on fixing charges on 891.90 222.98
2820.96
11 Add 13.615% Overhead& Contractors profit 384.07
3205.03

3 Supply and fixing of 18guage M.S.Plain sheet DOOR of size 1.22M x 2.10M with outer angular frame of rolled
steel equal angle ISA 3535 of size 35mm x35mmDOOR x 6mm
SIZE :and with1.22
MS Hold
X fasts 6nos with Double shutter
2.10
AREA OF WINDOW 2.562 Sqmts.
THEORITICAL REQUIREMENT
1 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 3535 - 35mm x 35mm x6mm
Verticals(L -Angle) 2 2.10 4.2

Horizontals(L-Angle) 2 1.22 2.44

Hold Fasts 6 0.23 1.38


8.02 RM
Equivalent Weight 2.10 Kgs/RM
Total Weight 8.02 2.10 16.84 Kgs.
2 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 2525 - 25mm X25mm X 4mm
Verticals(L -Angle) 4 2.050 8.2
Horizontals(L-Angle) 4 0.585 2.34
10.540 RM
Equivalent Weight 1.40 Kgs/RM
Total Weight 10.54 1.40 14.76 Kgs.
3 18 Gauge MS Sheet
Area of Sheet 2 0.585 0.376 0.440 Sqm
Equivalent Weight 9.80 Kgs/Sqmt.
Total Weight 0.440 9.80 4.31 Kgs.
4 MS FLAT Patty 19x2
all round 1 6.44 6.44 RM
Equivalent Weight 0.30 Kgs/RM
Total Weight 6.44 0.30 1.93 Kgs.
5 DATA for Red Oxide Primer
Cost of Red Oxide GRADE-I Quality 0.6 121.00 72.60
Painter 1st class 0.21 515.00 108.15
Painter 2nd class 0.49 405.00 198.45
TOTAL Rs. 379.20 /10 Sqm.
ABSTRACT QUANTITY RATE AMOUNT
1 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL 16.84 Kgs 45.00 /Kg 757.80
ANGLE ISA 4040 -35mmx35mmx6mm
2 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL 14.76 Kgs 45.00 /Kg 664.20
ANGLE ISA 2525 - 25mm X25mm X 4mm
3 18 Gauge MS Sheet 4.31 Kgs 45.00 /Kg 193.95
4 DATA for Red Oxide Primer 7.69 Sqmts. 379.20 /10 Sqmts. 291.45
FIXTURES:
5 100mm Long MS Powder Coated Butt Hinges 3 Nos. 33.00 /Each 99.00
6 125mm Long MS Powder Coated Handles 1 Nos. 25.00 /Each 25.00
7 MS Aldrop 300 mm long 2 Nos. 134.00 /Each 268.00
8 Labour Charges for Fabrication 37.84 Kgs 22.00 /Kg 832.48
9 Labour charges for Fixing 37.84 Kgs 4.00 /Kg 151.36
3283.24
10 Agency Allowance @ 25% on fixing charges on 983.84 245.96
3529.20
11 Add 13.615% Overhead& Contractors profit 480.50
4009.70
2 Supply and fixing of 18guage M.S.Plain sheet WINDOWof size 0.92M x 1.22M with outer angular frame of
rolled steel equal angle ISA 4040 of size 40mm x40mm x 6mm and inner shutter angular frame of rolled steel
equal angle ISA 2525 of size 25mm x25mm x4mm and rolled steel Tee Bars 40mmx40mmx6mm one number
horizontally and vertically at the centre of ther window also welded with fixtures such as M.S.Powder coated
tower bolts I.S. 204 100mm long 4Nos, M.S.Powder coated Butt Hinges IS 205 100mm long 8Nos.,
M.S.Powder coated handles IS 208 125mm long 4Nos,M.S.Powder coated Wind appliances 4No, safety rods
of 10 mm square rods at 100mm centre to centre to welded horizontally to full width of window including Red
oxide primer of grade-I quality, sales and other taxes ,cost and conveyance of all materials to site, all labour
cahrges etc.,complete for finished item of work.

WINDOW SIZE : 0.92 X 1.22


AREA OF WINDOW 1.12 Sqmts.
THEORITICAL REQUIREMENT
1 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 4040 - 40mm x 40mm x6mm
Verticals(L -Angle) 2 1.22 2.44
Verticals(Tee Bar) 1 1.22 1.22
Horizontals( L Angle) 2 0.92 1.84
Horizontal( Tee bar) 1 0.92 0.90
Hold Fasts 4 0.23 0.92
7.32 RM
Equivalent Weight 3.50 Kgs/RM
Total Weight 7.32 3.50
25.62 Kgs.
2 INNER SHUTTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 2525 - 25mm X25mm X 4mm
Verticals 12 0.663 7.956
Horizontals 12 0.441 5.292
13.25 RM
Equivalent Weight 1.40 Kgs/RM
Total Weight 13.25 1.40 18.55 Kgs.
3 18 Gauge MS Sheet
Area of Sheet 12 0.663 0.441 3.509 Sqm
Equivalent Weight 9.80 Kgs/Sqmt.
Total Weight 3.509 9.80 34.38 Kgs.
4 10mm square rods safety bars
14 0.90 12.60 RM
Equivalent Weight 0.78 Kgs/RM
Total Weight 12.60 0.78 9.83 Kgs.
5 DATA for Red Oxide Primer
Cost of Red Oxide GRADE-I Quality 0.6 142.00 85.20
Painter 1st class 0.21 480.00 100.80
Painter 2nd class 0.49 370.00 181.30
TOTAL Rs. 367.30 /10 Sqm.
ABSTRACT QUANTITY RATE AMOUNT
1 OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL 25.62 Kgs 45.00 /Kg 1152.90
ANGLE ISA 4040 -40mmx40mmx6mm
2 INNER SHUTTER ANGULAR FRAME OF ROLLED STEEL 18.55 Kgs 45.00 /Kg 834.75
EQUAL ANGLE ISA 2525 - 25mmx25mmx4mm
3 18 Gauge MS Sheet 34.38 Kgs 44.00 /Kg 1512.72
4 10mm square rods safety bars 9.83 Kgs 44.00 /Kg 432.52
5 DATA for Red Oxide Primer 3.37 Sqmts. 367.30 /10 Sqmts. 123.68
FIXTURES:
6 100mm Long MS Powder Coated Butt Hinges TBSC-P.II-10 8 Nos. 23.00 /Each 184.00
7 100mm Long MS Powder Coated Tower Bolts TBSC-P.I-14 4 Nos. 26.00 /Each 104.00
8 125mm Long MS Powder Coated Handles TBSC-P.III-05 4 Nos. 34.00 /Each 136.00
9 Wind appliances M.S.Powder coated 4 Nos. 30.00 /LS 120.00
10 Labour Charges for Fabrication TBSC-T.I-16 88.38 Kgs 24.00 /Kg 2121.12
11 Labour charges for Fixing TBSC-T.I-17 88.38 Kgs 4.00 /Kg 353.52
7075.21
12 Add 13.615% Overhead& Contractors profit 0.00
Or Say per Each 7075.21
PRICE ADJUSTMENT

Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of
Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.

Sl. No. Description Item Amount

1 Price Adjustment for Cement Err:509

2 Price Adjustment for Steel 18911.00

Total Err:509

Asst. Exe. Engineer Deputy Executive Engineer Executive Engineer


T.W. Yellandu T.W.S.D. - Sudimalla T.W.Divn., Bhadrachalam
PRICE ADJUSTMENT FOR CEMENT
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of Paloncha Range of Paloncha Division,
during 2022-23 under CAMPA - NPV scheme.
To be paid
Cement Cement Cement Rate as Increase / Operatinal
Used Amount for
Sl. Date of Page Work done Requirme Rate as per per BOC during % of Decrease Rate Operatinal Percentage
Description of Item MB. No. Cement Variation of
No. Recording No. Qty in Cum nt in Agreement the month per Variation of Cement per Percentage over sanction
in MT Rates in
Kg/Cum per MT MT MT amount
Cement
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 PCC(1:5:10) 30-Dec-99 124/C/TW 2 4.39 129.60 0.569 5600 5600 0.00 0 0.00 0.00 0.00
2 PCC(1:5:10) 30-Dec-99 124/C/TW 7 3.58 129.60 0.464 5600 5600 0.00 0 0.00 0.00 0.00
3 PCC(1:5:10) 7-Dec-21 124/C/TW 32 7.54 129.60 0.977 5600 5700 1.79 100 0.00 0.00 0.00
4 PCC(1:5:10) 7-Dec-21 124/C/TW 35 1.40 129.60 0.181 5600 5700 1.79 100 0.00 0.00 0.00
6 VRCC M20 for Footings 30-Dec-99 124/C/TW 4 7.61 400.00 3.044 5600 5600 0.00 0 0.00 0.00 0.00
8 VRCC M20 for Pedastals Err:509 124/C/TW 4 Err:509 400.00 Err:509 5600 5600 0.00 0 0.00 0.00 Err:509
9 VRCC M20 for Columns 30-Dec-99 124/C/TW 4 3.110 400.00 1.244 5600 5600 -1.82 0 0.00 0.00 0.00
10 VRCC M20 for Columns 30-Dec-99 124/C/TW 10 5.29 400.00 2.116 5600 5600 -1.82 0 0.00 0.00 0.00
11 VRCC M20 for Columns 8-Nov-21 124/C/TW 19 0.11 400.00 0.044 5600 5800 -1.82 200 0.00 0.00 0.00
12 VRCC M20 for Plinth Beam Err:509 124/C/TW 10 Err:509 400.00 Err:509 5600 5600 0.00 0 0.00 0.00 Err:509
13 VRCC M20 for Roof Beams Err:509 124/C/TW 24 Err:509 400.00 Err:509 5600 5800 3.57 200 0.00 0.00 Err:509
VRCC M20 for Roof Slab 115
14 Err:509 124/C/TW 24 Err:509 46.00 Err:509 5600 5800 3.57 200 0.00 0.00 Err:509
mm thick
15 VRCC M20 for Lintals 18-Nov-21 124/C/TW 19 0.93 400.00 0.372 5600 5800 3.57 200 0.00 0.00 0.00
17 VRCC M20 for Sunshades Err:509 124/C/TW 19 Err:509 24.00 Err:509 5600 5800 3.57 200 0.00 0.00 Err:509
18 Brick Masonary (1:8) Err:509 124/C/TW 11 Err:509 18.00 Err:509 5600 5600 0.00 0 0.00 0.00 Err:509
19 Brick Masonary (1:8) Err:509 124/C/TW 16 Err:509 18.00 Err:509 5600 5800 3.57 200 0.00 0.00 Err:509
20 Brick Masonary (1:8) Err:509 124/C/TW 20 Err:509 18.00 Err:509 5600 5800 3.57 200 0.00 0.00 Err:509
21 Brick Masonary (1:8) 7-Dec-21 124/C/TW 33 7.47 18.00 0.134 5600 5700 1.79 100 0.00 0.00 0.00
25 Plastering 12 mm single coat 30-Dec-99 124/C/TW 39 21.43 7.20 0.154 5600 5700 1.79 100 0.00 0.00 0.00
26 Plastering 20 mm Two Coats 30-Dec-99 124/C/TW 41 15.84 5.75 0.091 5600 5700 1.79 100 0.00 0.00 0.00
27 Ceiling Plastering 12 mm single coat 30-Dec-99 124/C/TW 38 74.98 7.20 0.540 5600 5700 1.79 100 0.00 0.00 0.00
31 Flooring with vitrified tiles Err:509 124/C/TW 45 Err:509 7.46 Err:509 5600 5700 1.79 100 0.00 0.00 Err:509
32 Providing skirting to iternal walls 30-Dec-99 124/C/TW 46 6.55 9.06 0.059 5600 5700 1.79 100 0.00 0.00 0.00
35 Providing improvise coat 30-Dec-99 124/C/TW 25 134.10 10.08 1.352 5600 5800 3.57 200 0.00 0.00 0.00

Total : Err:509

Asst. Exe. Engineer Deputy Executive Engineer Executive Engineer


T.W. Yellandu T.W.S.D. - Sudimalla T.W.Divn., Bhadrachalam
PRICE ADJUSTMENT FOR STEEL

Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of Paloncha Range of Paloncha
Division, during 2022-23 under CAMPA - NPV scheme.

Steel Rate Increase / Operatinal


Steel Rate To be paid
Steel as per BOC Decrease Percentage
Date of Work done Used Steel as per % of Operatinal Amount for
Sl. No. Description of Item MB. No. Page No. Requirm during the Rate of over
Recording Qty in MT in MT Agreement Variation Percentage Variation of
ent in MT month per Steel per sanction
per MT Rates in Cement
MT MT amount

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 Poviding HYSD steel 30-Dec-99 124/C/TW 3 0.17333 1.00 0.1733 55000 58000 5.45 3000 15.45 8500.00 1473.00

2 Poviding HYSD steel 30-Dec-99 124/C/TW 9 0.495234 1.00 0.4952 55000 58000 5.45 3000 15.45 8500.00 4209.00

3 Poviding HYSD steel 30-Dec-99 124/C/TW 18 0.41885 1.00 0.4189 55000 60000 9.09 5000 19.09 10500.00 4398.00

4 Poviding HYSD steel 30-Dec-99 124/C/TW 23 0.841 1.00 0.8410 55000 60000 9.09 5000 19.09 10500.00 8831.00
Total: 18911.00

Asst. Exe. Engineer Deputy Executive Engineer Executive Engineer


T.W. Yellandu T.W.S.D. - Sudimalla T.W.Divn., Bhadrachalam
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of Paloncha
Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.

SUPPLYMENTARY DATA

BLDCST 1 Brick Masonry in superstructure with CM (1:8) prop with Flyash Cement solid blocks of size 290 x 225 x
N-5-17 140 mm, for manufacturing of flyash solid blocks using flyash of 80 kgs, cement of 15 kgs. Gypsum of 5
Page.35 kgs. and stone dust with a compresive strength not lessthan 50 kg/sqm including cost and conveyance of
all materials, labour charges, seiniorage charges, scaffolding and curing etc., for Superstructure Walls.

Unit : Cum
a.Material
No of blocks required for one cum of Nos 110.00 25000.00 1000 2750.00
Masonry
CM (1:8) Cum 0.10 2190.80 Cum 219.08
2969.08
b.Labour
Mason 1st Class Day 0.420 520.00 Day 218.40
Mason 2nd Class Day 0.920 490.00 Day 450.80
Mazdoor (Unskilled) Day 2.800 465.00 Day 1302.00
Add Agency Allowance 0% 1971.20 0.00
1971.20
Rate per Cum 4940.28
Rate for other floors GF
a Basic rate per Cum. 4940.28
b Hire charges of Access Scaffolding @ 44.13
9.93/Sqm /0.225
c Labour charges for Access Scaffolding 301.95
material (Labour charge / 0.225)
d Allowance on labour charges for Asscess 0% 0.00
Scaffolding
e Lift charges of Labour - Add 10% labour 0.00
charges on G.F Rate, 20% on GF, 30% on
GF Rate only
Sub-Total :: 5286.36
f Add 13.615% Overhead & Contractors 719.74
profit on sub - total
g Seigniorage charge 4.40
(i) Sand - 0.11 x 40 = 4.4
Rate per Cum 6010.50
Say 6010.50

BLDCST 2 Reinforced Cement Concrete M20 Grade Nominal Mix corresponding to IS 456 using 20mm size graded machine
N - 3-13 crushed hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials
Page - 23 like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including Seigniorage charges, sales &
other taxes on all materials including all operational, incidental and labour charges such as machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) including centering, shuttering, laying concrete, curing etc. complete for Slab of 150mm thick.

Unit = 1 cum
a.Material
Cement Kg 400.00 5600.00 MT 2240.00
20mm HBG graded metal Cum 0.90 2011.27 Cum 1810.14
Fine aggregate (Sand) Cum 0.45 847.91 Cum 381.56
Water (including curing) Kl 1.20 98.00 KL 117.60
4549.30
b.Labour
Mason 1st Class Day 0.067 520.00 Day 34.84
Mason 2nd Class Day 0.133 490.00 Day 65.17
Mazdoor(Unskilled) Day 2.500 465.00 Day 1162.50
1262.51
c. Hire Charges of Machinery + Fuel charges + crew charges of Machinery
Concrete Mixer (0.2/0.8 cum capacity) 600/400 Hr 0.267 279.30 Hr 74.57
(Diesel)
Needle Vibrator hire charges 40mm (petrol) Hr 0.267 36.80 Hr 9.83
Crew charges of Concrete Mixer Hr 0.267 271.40 Hr 72.46
Crew charges of Vibrator Hr 0.267 195.60 Hr 52.23
209.09
Basic Rate per Cum 6020.90

Description of Item GF
a Basic rate of VRCC M-20 per Cum. For 140mm 903.14
thick
b Hire charges for centering and scaffolding 158.00
material
c Labour charges for centering and scaffolding 167.00
material
d Allowance on labour charges for centering and 25% 41.75
scaffolding material
e Lift charges of Labour - Add 10% labour 0.00
charges on G.F Rate, 20% on GF Rate, 30%
on GF Rate only
f Lift Charges of Material i.e.for Lifting Concrete 0.00
@ 10%
Sub-Total :: 1269.89
g Add 13.615% Overhead & Contractors profit on 172.89
sub - total
h Seigniorage charges (i) Aggregate 0.90 x 75 = 10.13
67.50
i (ii) Sand 0.45 x 40 = 18.00 2.70
Rate per Sqm. 1455.60
Say 1455.60

BLDCST 3 Providing Skirting to internal walls to 15 cm height and risers of steps with soluble salt porcelain vitrified
N-9-20 tiles screen printed and polished of size 600 x 600 mm and thickness between 8-10 mm 1st quality
Page.60 conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish of make Jhonson &
Jhonson, Kajaria, Nitco, Marbonite, set over base coat of CM (1:5) 12 mm thick with cement slurry of
honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed
with pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and
water etc., complete including seigniorage charges, etc., complete for finished item of work,

Unit : 10Sqm
a.Materials
Vitrified tiles (TBSC-C.II-02) Sqm 10.50 421.00 10Sqm 4420.50
Cement for CM(1:5) Proportion Kg 34.56 5600.00 MT 193.54
Sand for CM(1:8) Proportion cum 0.12 1037.91 cum 124.55
Cement slurry Kg 33.00 5600.00 MT 184.80
White Cement for Jointing & pointing Kg 2.00 271.40 Kg 542.80
5466.19
b.Labour
Mason 1st Class Day 0.96 520.00 Day 499.20
Mason 2nd Class Day 2.24 490.00 Day 1097.60
Mazdoor (Unskilled) Day 3.30 465.00 Day 1534.50
Add Agency Allowance 0% 3131.30 0.00
3131.30
Rate per 10 Sqm 8597.49

Description of Item GF
c Basic rate per 10 Sqm 8597.49
d Lift charges - Add 10% on labour for 0.00
F.F,20% for SF, 30% for T.F
Sub-Total :: 8597.49
e Add 13.615% Overhead & Contractors 1170.55
profit on sub - total
f Seigniorage charge 4.80
(i) Sand - 0.12 x 40 = 4.80
Rate as per 10 Sqm 977.28
Say 977.30
BLDCST 4 Reinforced Cement Concrete M20 Grade Nominal Mix corresponding to IS 456 using 20mm size graded machine
N - 3-13 crushed hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials
Page - 23 like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including Seigniorage charges, sales &
other taxes on all materials including all operational, incidental and labour charges such as machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) including centering, shuttering, laying concrete, curing etc. complete for Side Walls of 100mm thick.

Unit = 1 cum
a.Material
Cement Kg 400.00 5600.00 MT 2240.00
20mm HBG graded metal Cum 0.90 2011.27 Cum 1810.14
Fine aggregate (Sand) Cum 0.45 847.91 Cum 381.56
Water (including curing) Kl 1.20 98.00 KL 117.60
4549.30
b.Labour
Mason 1st Class Day 0.067 520.00 Day 34.84
Mason 2nd Class Day 0.133 490.00 Day 65.17
Mazdoor(Unskilled) Day 2.500 465.00 Day 1162.50
Add Agency Allowance 0% 1262.51 0.00
1262.51
c. Hire Charges of Machinery + Fuel charges + crew charges of Machinery
Concrete Mixer (0.2/0.8 cum capacity) 600/400 Hr 0.267 279.30 Hr 74.57
(Diesel)
Needle Vibrator hire charges 40mm (petrol) Hr 0.267 36.80 Hr 9.83
Crew charges of Concrete Mixer Hr 0.267 271.40 Hr 72.46
Crew charges of Vibrator Hr 0.267 195.60 Hr 52.23
209.09
Basic Rate per Cum 6020.90

Description of Item GF
a Basic rate of VRCC M-20 per Cum. 602.09
b Hire charges for centering and scaffolding
1206.00
material
c Labour charges for centering and scaffolding
1574.00
material
f Lift Charges of Material i.e.for Lifting Concrete
0.00
@ 10%
Sub-Total :: 3382.09
g Add 13.615% Overhead & Contractors profit on
460.47
sub - total
h Seigniorage charges (i) Aggregate 0.90 x 75 =
10.13
67.50
i (ii) Sand 0.45 x 40 = 18.00 2.70
Rate per Sqm. 3855.39
Say 3855.40

5 Supply and fixing of Black Granite stone and set over a base coat of CM (1:5), 12mm thick and neat cement paste
at the rate of 3.3 Kg/Sqmt. and jointed with white cement paste mixed with pigment of matching shade including cost
and conveyance of all materials like cement, sand, water, tiles, etc. to site, seigniorage charges, sales and other
taxes on all materials, and all opertional, incidental and all labour charges such as mixing of cement mortar, laying in
position, curing, lift charges etc., complete for finished item of work in all floors

Black Granite stone


Basic Rate per 10 Sqm Sqm 31694.39 10 Sqm 31694.39
Add13.615% Overhead & Contractors profit 4315.19
Total :: 36009.58

Forest Range Officer, Forest Divisional Officer,


E.Bayyaram Manuguru,
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram
Section of Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV
scheme.
Data - MS Gate
1 Supply and fixing of M.S.ate of size 2 x 1.20m x 1.50m with outer angular frame of hollow
rectangular section equal angle of ISA 5050 of size 40mm x 30mm x 4mm welded with safety
bars of 10mm square rods at 150mm centre to centre horizontally and verticlally including red
oxide primer of grade-I quality, sales and other taxes, cost and conveyance of all materials to
site, all labour charges and fixing in position etc., complete for finished item of work.

MS Gate size 2 x 1.20 X 1.50


AREA OF MS Grill 3.60 Sqmts.
THEORITICAL REQUIREMENT
1 OUTER RECTANGULAR FRAME OF ROLLED STEEL - 40mm x 30mm
x 4mm
Verticals 2 2 1.50 6.00
Horizontals 2 2 1.20 4.80
10.80 RM
2 Middle sections
Verticals 2 4 1.20 9.60
Horizontals 2 6 0.75 9.00
Horizontals 2 5 1.15 11.50
30.10 RM
Equivalent Weight 3.70 Kgs/RM
Total Weight 40.90 3.70 151.33 Kgs.
3 10mm square rods safety bars
Horizontals 5 0.75 3.75 RM
3.75 RM
Equivalent Weight 0.78 Kgs/RM
Total Weight 3.75 0.78 2.93 Kgs.
4 DATA for Red Oxide Primer
Cost of Red Oxide GRADE-I
0.60 130.00 78.00
Quality
Painter 1st class 0.21 675.00 141.75
Painter 2nd class 0.49 525.00 257.25
TOTAL Rs. 477.00 /10 Sqm.
ABSTRACT QUANTITY RATE Unit AMOUNT
1 OUTER RECTANGULAR 151.33 Kgs
FRAME OF ROLLED STEEL -
40mm x 30mm x 4mm
2 10mm square rods safety bars 2.93 Kgs
TOTAL 154.26 Kgs 55.00 /Kg 8484.30
3 Cost of Fixtures
a) MS Butt Hinges 100mm 8.00 No.s 50.00 Each 400.00
b) Aldrop 2.00 No.s 150.00 Each 300.00
4 Red Oxide Primer 3.60 Sqmts. 477.00 /10 Sqmts 171.72
5 Fabrication Charges 154.26 Kgs 35.00 /Kg 5399.10
6 Labour Charges for Fixing 154.26 Kgs 10.00 /Kg 1542.60
16297.72

TOTAL :: 16297.72 EACH

Asst. Exe. Engineer Deputy Exe. Engineer Executive Engineer


T.W. Tekulapalli T.W.S.D. - Paloncha T.W.Divn., Bhadrachalam
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram
Section of Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV
scheme.
DISMANTLING D A T A ( SoR 2018-19)
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
1 Dismantling, clearing away and carefully stacking useful materials for re-use and disposal of unserviceable
materials with 100m lead as directed by Executive Engineer duly taking actual premeasurements before
dismantling including all labour charges , overheads & contractor profit etc., complete.

a) Brick masonry
(BLD-CSTN-14-9/299)
Mazdoor(unskilled) 0.409 Nos. 400.00 1 Each 163.60
Add for MA @ 25% 0.25 40.90 10.23
Rate per 1 cum 173.83
Overheads&Contractors Profit 13.615%
@13.615% 173.83 23.67
Rate per 1 cum 197.49
Say 197.49
b) Reinforced cement concrete
(BLD-CSTN-14-8/298)
Mazdoor(unskilled) 4.32 Nos. 400.00 1 Each 1728.00
Add for MA @ 25% 0.25 432.00 108.00
for cutting steel bars (BLD-CSTN-14-
10/300)
Blacksmith 2nd class 0.50 Nos. 470.00 1 Each 235.00
Mazdoor(Male) 0.50 Nos. 400.00 1 Each 200.00
Add for MA @ 25% 0.25 108.75 27.19
Rate per 1 cum 2298.19
Overheads&Contractors Profit 13.615% 2298.19 312.90
@13.615%
Rate per 1 cum 2611.09
say 2611.10

d) Stone masonry in cement mortar


Rate as per SSR - TBSC-U.I-01 1.00 cum 421.00 1 cum 421.00
Add for MA @ 25% 0.25 105.25 26.31
Rate per 1 cum 447.31
Overheads&Contractors Profit 13.615% 447.31
@13.615% 60.90
Rate per 1 cum 508.21
Say 508.25

Asst. Exe. Engineer Deputy Exe. Engineer Executive Engineer


T.W. Tekulapalli T.W.S.D. - Paloncha T.W.Divn., Bhadrachalam
Water supply & Sanitary datas
SCHEDULE OF RATES FOR THE YEAR 2017 - 2018
Sl Amount Unit
Description of work
No. (Rs.)
1 Supplying & Fixing Orissa Pan 580 mm x 440 mm white glazed W.C 1st quality ISI
marked conforming to IS:2556-Part-3-1981 with "P" or "S" trap Hindware/ Parryware/
Neycer - ISI mark 580 mm x 440mm as approved by the Engineer-in-charge fixed in
brick masonry with necessary ‘S’ trap of water closet, shall be encased in C.C. (1:2:4) 6"
alround well above the joint, to stop leakage at the joint, cost & conveyance of all
materials and labour charges etc., including sales and other taxes on all materials
complete for finished item of work for all floors.

Orissa Pan - Item code No TBSP-E.I-03 1306.00


Brick masonry seat - Item code No TBSP-E.I-06 271.00
1577.00
Add Overheads and Contractor profits @ 13.615% 214.71
1791.71
Say 1791.75 /Each
2 Supplying & Fixing of 15 mm brass body CP finish bib tap of not less than 300
grams weight screw type (full turn) with internal / external threaded connection
conforming to IS 8931 including cost and conveyance of all materials to site, all labour
charges, sales and other taxes on all materials etc., complete for finished item of work
for All Floors.

Initial cost (TBSP-F.I-01 ) 223.00


Add Overheads and Contractor profits @ 13.615% 30.36
253.36
Say 253.40
3 Providing & Placing on Terrace ( at all floor levels) polyethylene water storage
tank with Double layer approved brand & manufacture with cover and suitable locking
arrangement & making necessary holes for inlet & outlets and over flow pipes but
without fittings & base support for tanks
Initial cost (TBSP-H.II-01) 7.00
Add Overheads and Contractor profits @ 13.615% 0.95
7.95
Say 8.00 Litre
6 Supply and Fixing of Ashirvad/ Ajay/ Astral Flowguard or equivalent 28.60mm dia CPVC
Pipes and Fittings to meet the requirement of ASTM-D 2846 and are produced in CTS
(Copper Tube Sizes 1/2" ton 2" Ashirvad Flowgurard SDR 11 and SDR 13.5 pipes are
made from idential CPVC compounds having the same physical Properties for Hot and
Cold Water (IS 15778:2007).

28.06mm dia
Rate as per SSR 2017-18 TBSP-J.III-03 193.00
Add Overheads and Contractor profits @ 13.615% 26.28
219.30 /Rmt

Asst. Exe. Engineer Deputy Exe. Engineer Executive Engineer


T.W. Tekulapally T.W.S.D. - Sudimalla T.W.Divn., Bhadrachalam
GOVERNMENT OF TELANGANA
TRIBAL WELFARE ENGINEERING DEPARTMENT

WORKDONE ESTIMATE & COMPLETION REPORT

NAME OF THE WORK : CONSTRUCTION OF NEW PRIMARY


VETERINARY CENTER BUILDING AT TEKULAPALLY (V & M) IN
BHADRADRI KOTHAGUDEM (Dist.)

Name of the District : Khammam


Name of the Division : Bhadrachalam
Name of the Sub Division : Sudimalla
Name of the Mandal : Tekulapally
Estimate Cost : 20.00 Lakhs
Grant : SCA(LWE)
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of
Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.
SUB ESTIMATE - Drilling Bore well & Submersible Motor
Sl. Measurements
Description of Item No Qty Units Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
1) Flushing charges for DTH Borewell 41/2" dia including cost and
conveyance of all charges etc., complete.
Qty. V. P. No. 76 of M. B. No. : 196/C/TW
1 1 - - - 1.00
1.00 Job 10000.00 /Rmt 10000.00
2) Supply and fixing of 1.00 HP 10 stage submersible motor with pump set
CRI, Texmo make including cost and conveyance of all materials etc.,
complete.
Qty. V. P. No. 20 of M. B. No. : 196/C/TW
1 2 - - - 2.00
2.00 No. 20000.00 Each 40000.00
3) Suupply and delivery of 32 mm dia HDPE(Godavari Make) pipe of 10
kg/cm² including cost and conveynece of all material and labour charges
etc., complete for finished item of work.
Qty. V. P. No. 20 of M. B. No. : 196/C/TW
1 1 26.00 - - 26.00
26.00 Rmt 95.00 /Rmt 2470.00
4) Suupply and fixinf of MS Clamp set including cost and conveynece of all
material and labour charges etc., complete for finished item of work.

Qty. V. P. No. 20 of M. B. No. : 196/C/TW


1 1 - - - 1.00
1.00 No. 30.00 Each 30.00
5) Suupply of 3 core 2.5 Sqmm Flat copper cable as per IS 694:1990 for
Submersible motors including cost and conveynece of all material and
labour charges etc., complete for finished item of work.
Qty. V. P. No. 21 of M. B. No. : 196/C/TW
1 1 35.00 - - 35.00
35.00 Rmt 105.00 /Rmt 3675.00
6) Erection Charges of Sub Mersible Motor
Qty. V. P. No. 20 of M. B. No. : 196/C/TW
1 2 - - - 2.00
2.00 No. 3450.00 Each 6900.00

Total:- 63075.00
7) GST @ 12% 7569.00
Grand Total:- 70644.00

Asst. Exe. Engineer Deputy Exe. Engineer Executive Engineer


T.W. Tekulapalli T.W.S.D. - Paloncha T.W.Divn., Bhadrachalam
Standard Data - Electrical Items For Buildings with Agency Allowance-2018-2019
Sl. Amount
Description Unit Qty. Rate Rs.
No. Rs.
1 Supply and fixing of batten holder / slanting holder Anchor / Gold medal olive /
Million zoom make with ISI mark in lieu of ceiling rose of light point with 40W
bulb all connections including cost and conveyance of all materials to site, labour
charges and sales tax etc., complete for finished item of work.
Taking Output = each
a) Material
PVC batten holder Anchor / Gold medal
olive / Million zoom make with ISI mark each 1 18.00 18.00
40W-60W Lamp of make Crompton /Bajaj /
Surya / HPL/ Havells. each 1 11.00 11.00
Total 29.00
b) Labour charges :
Skilled Electrician day 0.05 540.00 27.00
Helpers day 0.05 420.00 21.00
Total 48.00
c) Agency allowance @ 25% 25% 48.00 12.00
Total (a+b+c) 89.00
d) Overheads & Contractors Profit 13.615
89.00 12.12
on (a+b+c) %
Rate per each 101.12
101.20
Supply and transportation of 20W, 2000 lumens, T8,1200mm length LED tube
light, input voltage AC 220 - 260Volts with PF≥0.9, Surge protection: 2KV, THD<
125%, with inbuilt driver and frosted cover CCT: 3000K - 5700K, minimum
CRI≥80,.etc., complete Manufacture has to submit LM79,LM80 & Photobiological
Safety Report. Luminaire Performance Complies to IS10322 (Part 5/Sec 3) & IEC
60598-1,IEC 60529 ISO certified company. LUMINAIRE MAKE: Phillips /
OSRAM / GE / Crompton / VIN / Bajaj / Havells / Halonix / HPL. LED MAKE :
PHILIPS LUMILEDS / CREE / NICHIA / OSRAM / SAMSUNG / LG LEDs

a) Material
20W, 2000 lumens, T8,1200mm length LED tube light 1 730.00 730.00
23/0060 3 core Flat Copper Wire M 1.00 9.80 9.80
screws with rawal plugs each 2.00 1.00 2.00
T.W round blocks each 2.00 8.00 16.00
Cement and sand etc., LS 17.10
Total 774.90
b) Labour charges
Skilled Electrician/carpenter day 0.10 540.00 54.00
Semi skilled Electrician / Helper day 0.10 0.00 0.00
Total 54.00
c) Agency allowance @ 25% 25% 54.00 13.50
Total (a+b+c) 842.40
d) Overheads & Contractors Profit on (a+b+c) 13.615% 842.40 114.69
Rate per each 957.09
957.10

Asst. Engineer Deputy Exe. Engineer Executive Engineer


T.W. Yellandu T.W.S.D. - Sudimalla T.W.Divn., Bhadrachalam
HANDING OVER CERTIFICATE

1) Name of the Work :- Construction of ACR to AGHS Yellandu (M)


Bhadradri Kothagudem (Dist.)

2) Estimate Cost :- Rs. 12.20 Lakhs


3) Grant :- CAMPA
4) Admin. Sanction Proc. No. :- Proc. No.C1/375/2021, Dt. 24/04/2021. of District
Collector, Bhadradri Kothagudem.

5) Techincal Sanction :- TS. No.111/2021-22, of SE, TW, Wgl,


Dt.28.05.2021.
6) Name of The Agency :- Sri V. Chandra Shekhar, Contractor, H. No. 2-22/1,
R/o Vajumallaygudem, Chemmalapadu GP,
Singareni (M), Khammam District.

7) Plinth Area of the Building :- 725 SFT


8) Roof
a) Main Buidings :- RCC Roof Structure with fly ash brick walls with
palstering 20mm two coats out side and Plastering
12mm single coat inside and Ceiling plastering
12mm thick with single coat, Painting to New
External Walls with two coats of Plastic Emulsion
paint, Painting to new internal walls with two (2)
coats of ready mixed oil bound washable distemper
etc., complete.

9) Flooring
a) Ground Floor :- Soluble salt porcelain vitrified tiles screen printed
and polished of size 600 x 600 mm
10) Doors & Windows
a) MS Door :- a) Size : 1.20 x 2.10 m - 1No.s
b) UPVC Windows :- a) Size : 1.20 x 1.35m - 3 No.s
11) Electrification
a) Tube Lights (LED) :- 6 No.s
b) Fans :- 4 No.s

Certified that the above said work is inspected by me and satisfied with the
provisions as refered above and taken over by me.

Handed Over by, Taken over by,

Asst. Engineer,
TW, Yellandu.
WORKED OUT MEASUREMENTS
Name of the work : Construction of Forest Guard (FBO) Quarter at Valasala (W) Beat, Section : Valasala, in
Kachanapally Range of Yellandu Division, during 2021-22 under CAMPA - NPV scheme.
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
3) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance
of steel bars, including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire, cover blocks and
all incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

For Footings Mat


10mm dia 6" c/c
F1 type
C6,C9,C10,C11,C12,C13,C14 2 x 8 x 7 1.50 0.62 104.16
F2 Type C1,C3,C4,C5,C7,C8 2 x 8 x 6 1.50 0.62 89.28
F3 Type C2 2 x 10 x 1 1.50 0.62 18.60
Footings Total Qty : 212.04 Kgs
Columns
12mm dia
C1 type
C1,C3,C4,C5,C6,C7,C8,C9, 2 x 3 x 11 7.80 0.89 458.17
C10,C11,C12
C2 Type C2 2 x 4 x 1 7.80 0.89 55.54
C3 Type C13, C14 1 x 6 x 2 7.80 0.89 83.30
8mm dia
Stirrups 1 x 12 x 52 0.95 0.39 231.19
Stirrups 1 x 2 x 52 0.60 0.39 24.34
Columns Total Qty : 852.54 Kg
Total Qty : 1064.58 Kg 82.942 1 Kg 88298.39
4) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Column Footings.
F1 type C1 to C14 1 x 14 1.35 1.35 0.30 7.65
(0.30/3) x ((1.35² )+(0.30²)+
Taper Portion 1 x 14 5.88
√(1.35²) X (0.30²))
Total in Cu.Mt :: 13.53 Cu.Mt 11263.33 1 Cu.Mt 152392.85
5) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Columns.

Columns upto plinth beam 1 x 7 0.38 0.23 4.80 2.93


1 x 7 0.38 0.23 3.60 2.20
5.13 Cu.Mt 14753.05 1 Cu.Mt 75683.15
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
6) Filling with useful available excavated earth (excluding rock) in trenches,
sides of foundations and basement with initial lead in layers not exceeding
15 cm thick, consolidating each deposited layer by watering and ramming
including cost and conveyance of water to work site and all operational,
incidental, labour charges, hire charges of T & P etc., complete for finished
item of work. APSS No.309 & 310.
total EW forColumns pits 58.50
Deduct Columns -13.53
Deduct Footing straight -5.13
PCC Under Col. Footings -4.73
Total in Cu.Mt :: 35.11 Cu.Mt 361.86 1 Cu.Mt 12704.90
7) Earth work excavation for foundations and depositing on bank for all lifts and
with an initial lead of 10m including all operational, incidental, labour charges
such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS -
20 B (APSS 308). for building foundation.
Right side walls 1 x 1 14.50 0.45 1.20 7.83
Front side walls 1 x 1 7.50 0.45 1.20 4.05
Back side walls 1 x 1 7.50 0.45 0.60 2.02
Left side walls 1 x 1 14.50 0.45 0.60 3.91
Deduct Columns -1 x 12 0.38 0.23 0.91 -0.95
16.86 Cu.Mt 405.29 1 Cu.Mt 6833.19
8) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site,
mixing concrete in concrete mixer including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labour charges
such as laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for finished item
of work.
Under CRS Walls
Right side walls 1 x 1 14.50 0.45 0.15 0.97
Front side walls 1 x 1 7.50 0.45 0.15 0.51
Back side walls 1 x 1 7.50 0.45 0.15 0.51
Left side walls 1 x 1 14.50 0.45 0.15 0.98
2.97 Cu.Mt 6003.14 1 Cu.Mt 17829.33
9) Coursed Rubble Stone Masonry in CM (1:3) Prop: including cost and
conveyance of all materials like cement, sand, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental charges and labour charges such as mixing mortar, finishing,
curing, etc., complete for finished item of work. (APSS 901,906)
Right side walls 1 x 1 14.50 0.45 3.60 23.49
Front side walls 1 x 1 7.50 0.45 2.10 7.08
Back side walls 1 x 1 7.50 0.45 3.60 12.15
Left side walls 1 x 1 14.50 0.45 2.10 13.70
Total in Cu.Mt :: 56.42 Cu.Mt 5649.09 1 Cu.Mt 318721.66
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
10) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance
of steel bars, including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire, cover blocks and
all incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).
Plinth Beams (Outer)
10mm dia
C1 to C11 Top PB1 1 x 2 x 1 11.50 0.62 14.26
C1 to C11 Bottom PB1 1 x 2 x 1 11.50 0.62 14.26
C1 to C11 Crank PB1 1 x 2 x 1 11.50 0.62 14.26
C1 to C3 Top PB1 1 x 2 x 1 7.60 0.62 9.42
C1 to C3 Bottom PB1 1 x 2 x 1 7.60 0.62 9.42
C1 to C3 Crank PB1 1 x 2 x 1 7.60 0.62 9.42
C11 to C12 Top PB1 1 x 2 x 1 4.00 0.62 4.96
C11 to C12 Bottom PB1 1 x 2 x 1 4.00 0.62 4.96
C11 to C12 Crank PB1 1 x 2 x 1 4.00 0.62 4.96
C13 to C14 Top PB1 1 x 2 x 1 3.80 0.62 4.71
C13 to C14 Bottom PB1 1 x 2 x 1 3.80 0.62 4.71
C13 to C14 Crank PB1 1 x 2 x 1 3.80 0.62 4.71
C3 to C6 Top PB1 1 x 2 x 1 4.30 0.62 5.33
C3 to C6 Bottom PB1 1 x 2 x 1 4.30 0.62 5.33
C3 to C6 Crank PB1 1 x 2 x 1 4.30 0.62 5.33
C6 to C9 Top PB2 1 x 2 x 1 7.20 0.62 8.93
C6 to C9 Bottom PB2 1 x 2 x 1 7.20 0.62 8.93
8mm dia
Stirrups 1 x 1 x 77 0.95 0.39 28.53
Stirrups 1 x 1 x 51 0.95 0.39 18.90
Stirrups 1 x 1 x 27 0.95 0.39 10.00
Stirrups 1 x 1 x 26 0.95 0.39 9.63
Stirrups 1 x 1 x 29 0.95 0.39 10.74
Stirrups 1 x 1 x 48 0.95 0.39 17.78
Plinth Beams (Internal)
10mm dia
C4 to C5, C7 to C8 Top PB1 2 x 2 x 1 4.20 0.62 10.42
C4 to C5, C7 to C8 Bottom PB1 2 x 2 x 1 4.20 0.62 10.42
C4 to C5, C7 to C8 Crank PB1 2 x 2 x 1 4.20 0.62 10.42
C5 to C6,# to C9 Top PB1 2 x 2 x 1 3.80 0.62 9.42
C5 to C6,# to C9 Bottom PB1 2 x 2 x 1 3.80 0.62 9.42
C5 to C6,# to C9 Crank PB1 2 x 2 x 1 3.80 0.62 9.42
C2 to C5, C to C8 Top PB1 1 x 2 x 1 6.90 0.62 8.56
C2 to C5, C to C8 Bottom PB1 1 x 2 x 1 6.90 0.62 8.56
C2 to C5, C to C8 Crank PB1 1 x 2 x 1 6.90 0.62 8.56
C8 to C11, C13 Top PB3 1 x 2 x 1 4.80 0.62 5.95
12mm Dia
C8 to C11, C13 Bottom PB3 1 x 2 x 1 4.80 0.89 8.54
C8 to C11, C13 Crank PB3 1 x 2 x 1 4.80 0.89 8.54
8mm dia
Stirrups 1 x 1 x 28 0.95 0.39 10.37
Stirrups 1 x 1 x 25.3 0.95 0.39 9.39
Stirrups 1 x 1 x 46 0.95 0.39 17.04
Stirrups 1 x 1 x 32 0.95 0.39 11.86
386.37 Kg 82.942 1 Kg 32046.30
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
11) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Plinth Beam.

C1 to C11 1 x 1 11.55 0.23 0.30 0.80


C1 to C3 1 x 1 7.60 0.23 0.30 0.52
C11 to C12 1 x 1 4.00 0.23 0.30 0.28
C 13 to C14 1 x 1 3.80 0.23 0.30 0.26
C 3 to C14 1 x 1 11.05 0.23 0.30 0.76
Col 2 to 13 1 x 1 11.05 0.23 0.30 0.76
C4 to C5 & C7 to C8 2 x 2 4.00 0.23 0.30 1.10
at C9 to C8&C11, C6 to 5 2 x 2 3.60 0.23 0.30 0.99
at toilet 1 x 1 3.30 0.23 0.30 0.22
Total in Cu.Mt :: 5.69 Cu.Mt 14847.88 1 Cu.Mt 84484.44
12) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Columns.
Columns 12 x 1 0.30 0.23 3.00 2.48
Circuler Columns 2 x 0.785 0.23 0.23 3.00 0.24
2.72 Cu.Mt 14753.05 1 Cu.Mt 40128.30
13) Filling with Gravel in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15cm thick, consolidating each deposited layer
by watering and ramming including all operational, incidental, labour
charges, seignorage charges, hire charges of T & P etc., complete for
finished item of work. (APSS NO. 309 & 310).
Varandah 1 x 1 3.15 3.20 3.60 36.29
Living/Din 1 x 1 3.15 5.35 3.60 60.67
Store 1 x 1 1.80 1.20 3.60 7.78
Kitchen 1 x 1 3.15 2.20 3.60 24.95
Bed Room 1 1 x 1 3.53 3.75 3.60 47.66
Bath 1 1 x 1 2.10 1.20 3.60 9.07
Bath 2 1 x 1 1.20 1.05 3.60 4.54
Bed room 2 1 x 1 3.53 4.03 3.60 51.21
Wash area 1 x 1 8.20 2.40 3.60 70.85
Total in Cu.Mt :: 313.02 Cu.Mt 468.95 1 Cu.Mt 146790.73
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
14) Vibrated Plain Cement Concrete (1:4:8) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site,
mixing concrete in concrete mixer including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labour charges
such as laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for finished item
of work.

Varandah 1 x 1 3.15 3.20 0.23 2.31


Living/Din 1 x 1 3.15 5.35 0.23 3.87
Store 1 x 1 1.80 1.20 0.23 0.49
Kitchen 1 x 1 3.15 2.20 0.23 1.59
Bed Room 1 1 x 1 3.53 3.75 0.23 3.04
Bath 1 1 x 1 2.10 1.20 0.23 0.57
Bath 2 1 x 1 1.20 1.05 0.23 0.28
Bed room 2 1 x 1 3.53 4.03 0.23 3.27
Wash area 1 x 1 8.20 2.40 0.23 4.52
Total in Cu.Mt :: 19.94 Cu.Mt 5634.11 1 Cu.Mt 112344.15

Total:- 1140361.71
II nd Part Bill
Name of the work : Construction of Forest Guard (FBO) Quarter at Valasala (W) Beat, Section : Valasala, in
Kachanapally Range of Yellandu Division, during 2021-22 under CAMPA - NPV scheme.
M. B. No. :
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per
IS 1786-1979) of different diameters for RCC works, including labour charges for
straightening, cutting, bending to required sizes and shapes, placing in position
with cover blocks of approved materials and size and tying and lapsplicing with
binding wire of 18 SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars including cost and
conveyance of binding wire, cover blocks and all incidental, operational, laour
charges such as cutting, bending placing in position, tying including sales and
other taxes on all materials etc., complete for finished item of work in all floors.
(APSS No.126).

Plinth Beam for Stair case


Plinth Beam top 12mm dia C/w 2 x 3 x 1 2.50 0.89 13.35
Plinth Beam Bottom 12mm dia C/w 2 x 3 x 1 2.50 0.89 13.35
Stirrups 8mm dia 2 x 1 x 17 0.90 0.39 11.93
Plinth Beam top 12mm dia L/w 1 x 3 x 1 3.60 0.89 9.61
Plinth Beam Bottom 12mm dia L/w 1 x 3 x 1 3.60 0.89 9.61
Stirrups 8mm dia 1 x 1 x 24 0.90 0.39 8.42
66.27 Kg 82.942 1 Kg 5496.57
2) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Plinth Beam.

Below stair case C/w 2 x 1 x 1 2.40


0.23 0.30 0.33
L/w 2 x 1 x 1 2.10
0.23 0.30 0.29
Total in Cu.Mt :: 0.62 Cu.Mt 14847.88 1 Cu.Mt 9205.69
3) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per
IS 1786-1979) of different diameters for RCC works, including labour charges for
straightening, cutting, bending to required sizes and shapes, placing in position
with cover blocks of approved materials and size and tying and lapsplicing with
binding wire of 18 SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars including cost and
conveyance of binding wire, cover blocks and all incidental, operational, laour
charges such as cutting, bending placing in position, tying including sales and
other taxes on all materials etc., complete for finished item of work in all floors.
(APSS No.126).

For Stair case I st Flight


Stair case I st flight 10mm dia top Bar
Cross 1 x 1 x 27 1.25 0.62 20.93
Stair case I st flight 10mm dia Bottom
Bar Cross 1 x 1 x 27 1.25 0.62 20.93
Stair case I st flight 10mm dia Bottom
Bar Long 1 x 1 x 6 4.00 0.62 14.88
Stair case I st flight 10mm dia Bottom
Bar Long 1 x 1 x 6 4.00 0.62 14.88
Landing 10 mm dia Top 1 x 1 x 6 1.20 0.62 4.46
Landing 10 mm dia Bottom 1 x 1 x 6 1.20 0.39 2.81
78.89 Kg 82.942 1 Kg 6543.29
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
4) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Stair case I st Flight.

Stair case I st flight


1 x 1 x 1 4.00
1.20 - 4.80
Total in Sq.Mt :: 4.80 Sq.Mt 1890.00 1 Sq.Mt 9072.00
5) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per
IS 1786-1979) of different diameters for RCC works, including labour charges for
straightening, cutting, bending to required sizes and shapes, placing in position
with cover blocks of approved materials and size and tying and lapsplicing with
binding wire of 18 SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars including cost and
conveyance of binding wire, cover blocks and all incidental, operational, laour
charges such as cutting, bending placing in position, tying including sales and
other taxes on all materials etc., complete for finished item of work in all floors.
(APSS No.126).

For Roof Beams


B1 type Beam
C13 to C14 12mm dia top 1 x 2 x 1 3.90 0.89 6.94
C13 to C14 12mm dia Bottom 1 x 2 x 1 3.90 0.89 6.94
C13 to C14 12mm dia Bottom Extra 1 x 1 x 1 3.90 0.89 3.47
Stirrups 8mm dia 1 x 1 x 26 1.25 0.39 12.68
C10 to C14 12mm dia top 1 x 2 x 1 2.50 0.89 4.45
C10 to C14 12mm dia Extra 1 x 1 x 1 1.20 0.89 1.07
C10 to C14 12mm dia Bottom 1 x 2 x 1 2.50 0.89 4.45
C10 to C14 12mm dia Extra 1 x 1 x 1 1.20 0.89 1.07
Stirrups 8mm dia 1 x 1 x 17 1.25 0.39 8.29
C9 to C10 12mm dia top 1 x 2 x 1 2.90 0.89 5.16
C9 to C10 12mm dia Extra 1 x 1 x 1 1.20 0.89 1.07
C9 to C10 12mm dia Bottom 1 x 2 x 1 2.90 0.89 5.16
C9 to C10 12mm dia Extra 1 x 1 x 1 1.20 0.89 1.07
Stirrups 8mm dia 1 x 1 x 19 1.25 0.39 9.26
C6 to C9 12mm dia top 1 x 2 x 1 2.80 0.89 4.98
C6 to C9 12mm dia Extra 1 x 1 x 1 1.20 0.89 1.07
C6 to C9 12mm dia Bottom 1 x 2 x 1 2.80 0.89 4.98
C6 to C9 12mm dia Extra 1 x 1 x 1 1.20 0.89 1.07
Stirrups 8mm dia 1 x 1 x 19 1.25 0.39 9.26
C4 to C7 12mm dia top 1 x 2 x 1 2.80 0.89 4.98
C4 to C7 12mm dia Extra 1 x 1 x 1 1.20 0.89 1.07
C4 to C7 12mm dia Bottom 1 x 2 x 1 2.80 0.89 4.98
C4 to C7 12mm dia Extra 1 x 1 x 1 1.20 0.89 1.07
Stirrups 8mm dia 1 x 1 x 19 1.25 0.39 9.26
B2 type Beam
C10 to C8-12, C5 to C6, C2 to C3
12mm dia top
3 x 2 x 1 4.20 0.89 22.43
" " 12mm dia Extras 3 x 2 x 1 1.20 0.89 6.41
C10 to C8-12, C5 to C6, C2 to C3
12mm dia Bottom
3 x 2 x 1 4.20 0.89 22.43
" " 12mm dia Extras 3 x 2 x 1 1.20 0.89 6.41
Stirrups 8mm dia 3 x 1 x 28 1.25 0.39 40.95
C3 to C6, C1 to C4 12mm dia top 2 x 2 x 1 4.50 0.89 16.02
" " 12mm dia Extras 2 x 2 x 1 1.20 0.89 4.27

C3 to C6, C1 to C4 12mm dia Bottom


2 x 2 x 1 4.50 0.89 16.02
" " 12mm dia Extras 2 x 2 x 1 1.20 0.89 4.27
Stirrups 8mm dia 2 x 1 x 30 1.25 0.39 29.25
C11 to C12, C7 to C8,C4 to C5,C1 to
C2 12mm dia top
4 x 2 x 1 4.50 0.89 32.04
" " 12mm dia Extras 4 x 2 x 1 1.20 0.89 8.54
C11 to C12, C7 to C8,C4 to C5,C1 to
C2 12mm dia Bottom
4 x 2 x 1 4.50 0.89 32.04
" " 12mm dia Extras 4 x 2 x 1 1.20 0.89 8.54
Stirrups 8mm dia 4 x 1 x 30 1.25 0.39 58.50
C5 to C8 12mm dia top 1 x 2 x 1 2.80 0.89 4.98
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
" " 12mm dia Extras 1 x 2 x 1 1.20 0.89 2.14
C5 to C8 12mm dia Bottom 1 x 2 x 1 2.80 0.89 4.98
" " 12mm dia Extras 1 x 2 x 1 1.20 0.89 2.14
Stirrups 8mm dia 1 x 1 x 20 1.25 0.39 9.75
C7 to C11 12mm dia top 1 x 2 x 1 4.50 0.89 8.01
" " 12mm dia Extras 1 x 2 x 1 1.20 0.89 2.14
C7 to C11 12mm dia Bottom 1 x 2 x 1 4.50 0.89 8.01
" " 12mm dia Extras 1 x 2 x 1 1.20 0.89 2.14
Stirrups 8mm dia 1 x 1 x 30 1.25 0.39 14.63
C12 to C13 12mm dia top 1 x 2 x 1 1.50 0.89 2.67
" " 12mm dia Extras 1 x 2 x 1 1.20 0.89 2.14
C12 to C13 12mm dia Bottom 1 x 2 x 1 1.50 0.89 2.67
" " 12mm dia Extras 1 x 2 x 1 1.20 0.89 2.14
Stirrups 8mm dia 1 x 1 x 10 1.25 0.39 4.88
B3 type Beam
C5 to C2 12mm dia top 1 x 2 x 1 4.80 0.89 8.54
" " 12mm dia Extras 1 x 2 x 1 1.20 0.89 2.14
C5 to C2 12mm dia Bottom 1 x 2 x 1 4.80 0.89 8.54
" " 16mm dia Extras 1 x 2 x 1 1.20 1.59 3.82
Stirrups 8mm dia 1 x 1 x 32 1.25 0.39 15.60
B4 type Beam
C8 to C12 12mm dia top 2 x 2 x 1 4.50 0.89 16.02
" " 16mm dia Extras 2 x 3 x 1 1.20 1.59 11.45
C8 to C12 16mm dia Bottom 2 x 2 x 1 5.60 1.59 35.62
" " 12mm dia Extras 2 x 2 x 1 1.20 1.59 7.63
Stirrups 8mm dia 2 x 1 x 30 1.25 0.39 29.25
Roof Beams Total Qty : 633.95 Kgs
Roof Slab Reinforcement
Long span bars 8mm dia 1 x 1 x 70 12.80 0.39 349.44
Short Span bars 8mm dia 1 x 1 x 90 9.40 0.39 329.94
Support Bars 1 x 4 x 10 3.50 0.39 54.60
Roof Slab Total Qty : 733.98 Kgs
Mid Landing Beam
12mm dia top 1 x 3 x 1 2.40 0.89 6.41
12mm dia Bottom 1 x 3 x 1 2.40 0.89 6.41
Stirrups 8mm dia 1 x 1 x 16 1.25 0.39 7.80
For Stair case II nd Flight
Stair case I st flight 10mm dia top Bar
Cross 1 x 1 x 12 1.20 0.89 12.82
Stair case I st flight 10mm dia Bottom
Bar Cross 1 x 1 x 12 1.20 0.89 12.82
Stair case I st flight 10mm dia Bottom
Bar Long 1 x 1 x 6 1.60 0.89 8.54
Stair case I st flight 10mm dia Bottom
Bar Long 1 x 1 x 6 1.60 0.89 8.54
Stair case Total Qty : 63.34 Kgs
Steel Total Qty : 1431.27 Kgs 82.942 1 Kg 118712.40
6) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Roof Beams.

B1 Type Beams C13 to C14 1 x 1 x 1 3.34 0.23 0.30 0.23


C10 to C14 1 x 1 x 1 2.10 0.23 0.30 0.14
C9 to C10 1 x 1 x 1 2.63 0.23 0.30 0.18
C6 to C9 1 x 1 x 1 2.58 0.23 0.30 0.18
C4 to C7 1 x 1 x 1 2.58 0.23 0.30 0.18
B2 Type Beams C8-12 to C10, C5 to C6,
C2 to C3 1 x 3 x 1 3.34 0.23 0.30 0.69
C3 to C6, C1 to C4 1 x 2 x 1 4.02 0.23 0.30 0.55
" " C1 to C2, C4 to C5, C7 to
C8, C11 to C12 1 x 4 x 1 3.64 0.23 0.30 1.00
C5 to C8 1 x 1 x 1 2.58 0.23 0.30 0.18
C7 to C11 1 x 1 x 1 3.82 0.23 0.30 0.26
C12 to C13 1 x 1 x 1 0.90 0.23 0.30 0.06
B3 Type Beams C2 to C5 1 x 1 x 1 4.02 0.23 0.30 0.28
B4 Type Beams C8 to C12 1 x 1 x 1 3.82 0.23 0.30 0.26
Total in Cu.Mt :: 4.19 Cu.Mt 15096.86 1 Cu.Mt 63255.84
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
7) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Roof Slab 125mm thick.

Main Slab 1 x 1 x 1 12.38 9.00 111.42


Total in Sq.Mt :: 111.42 Sq.Mt 1724.54 1 Sq.Mt 192148.25
8) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Stair case II nd Flight.

Stair case II nd flight


1 x 1 x 1 1.60 1.10 - 1.76
Total in Sq.Mt :: 1.76 Sq.Mt 1890.00 1 Sq.Mt 3326.40
9) Impervious coat 20mm thick over RCC roof slab surface with CM(1:3), promixed
with 1kg of water proof compound per bag of cement laid over roof when it is
green including cost of all materials, seigniorage charges, excluding conveyance
charges of materials and including all operational, incidental and labour charges
for mixing mortar, laying, rendering smooth and thread lining, curing, rounding
off junctions of wall and slab etc,, complete for finished item of work.

Main Slab 1 x 1 x 1 13.40 10.30 138.02


Varandah Projection 1 x 1 x 1 4.50 0.30 1.35
Total in Sq.Mt :: 139.37 Sq.Mt 555.93 1 Sq.Mt 77479.96
10) Plain Cement Concrete M15 grade nominal mix (1:2.5:5) proportion (cement: fine
aggregate: Coarse aggregate) using 40mm, 20mm, 10mm size Hard Broken
Granite (IS383, 1970) Machine Crushed metal from approved quarry including
cost and conveyance of all materials like cement, sand, coarse aggregate, water
etc. to site, including seigniorage charges, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing concrete in Concrete
Mixer, laying, curing concrete, etc., complete for finished item of work (APSS No.
402) Steps.
Stair case steps 1 x 1 x 18 1.10 0.20 (0+0.20)/2 0.40
Total in Cu.Mt :: 0.40 Cu.Mt 6503.81 1 Cu.Mt 2575.51
Total : 487815.91
11) Sanitory Charges 11% on total Cost 53659.75
12) Electrification Charges 9% on total Cost 43903.43
Total:- 585379.09
Name of the work : Construction of Forest Guard (FBO) Quarter at Valasala (W) Beat, Section :
Valasala, in Kachanapally Range of Yellandu Division, during 2021-22 under CAMPA - NPV scheme.

M. B. No. :
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1) Earth work excavation for foundations and depositing on bank for all lifts
and with an initial lead of 10m including all operational, incidental,
labour charges such as shoring ,sheeting, planking, strutting, etc.
complete for finished item of work including seigniorage excluding
dewatering charges etc as per SS - 20 B (APSS 308). for building
foundation.
Qty. V. P. No. of M. B. No. :
Columns C3, C6, C9, C10,C14 1 x 5 1.50 1.50 2.30 25.87
Columns C2,C5,C8,C12,C13 1 x 5 1.50 1.50 2.00 22.50
Columns C1, C4, C7, C11 1 x 4 1.50 1.50 1.20 10.80
59.17 Cu.Mt 336.53 1 Cu.Mt 19912.48
Qty. V. P. No. 8 of M. B. No. :
West side walls 1 x 1 14.17 0.45 0.91 5.80
South side walls 1 x 2 8.30 0.45 0.91 6.80
East side walls 1 x 1 15.46 0.45 0.91 6.33
North side walls 1 x 1 4.26 0.45 0.91 1.74
1 x 1 1.21 0.45 0.91 0.49
1 x 1 3.81 0.45 0.91 1.56
Qty. V. P. No. 9 of M. B. No. :
Deduct Columns -1 x 11 0.38 0.23 0.91 -0.87
21.85 Cu.Mt.
Qty. V. P. No. of M. B. No. :
Front side steps 1 x 1 4.00 1.20 0.20 0.96
Right side steps 1 x 1 2.60 1.20 0.20 0.62
1.58 Cu.Mt.
Total in Cu.Mt :: 82.60 Cu.Mt 336.53 1 Cu.Mt 27797.38
2) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine
aggregate: Coarse aggregate) using 40mm size Hard Broken Granite
(IS383, 1970) machine crushed metal from approved quarry including
cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, mixing concrete in concrete mixer
including seigniorage charges, sales & other taxes on all materials, all
operational, incidental, and labour charges such as laying and ramming
concrete in layers in position not exceeding 15cm, finishing top surface,
curing concrete, etc., complete for finished item of work.

Qty. V. P. No. 02 of M. B. No. :


PCC Under Col. Footings 1 x 14 1.50 1.50 0.15 4.73
4.73 Cu.Mt
Qty. V. P. No. 10 of M. B. No. :
Under CRS Walls
West side walls 1 x 1 14.30 0.45 0.15 0.96
South side walls 1 x 2 8.60 0.45 0.15 1.16
East side walls 1 x 1 14.20 0.45 0.15 0.96
3.08 Cu.Mt
Qty. V. P. No. of M. B. No. :
Septic tank bottom levelling 1 x 1 π/4 (1.30)² 0.15 0.19
0.19 Cu.Mt
Qty. V. P. No. of M. B. No. :
Front side steps 1 x 1 4.00 1.20 0.15 0.72
Right side steps 1 x 1 2.60 1.20 0.15 0.46
1.18 Cu.Mt.
Total in Cu.Mt :: 9.18 Cu.Mt 4976.25 1 Cu.Mt 45681.98
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
3) Vibrated Plain Cement Concrete (1:4:8) proportion (cement: fine
aggregate: Coarse aggregate) using 40mm size Hard Broken Granite
(IS383, 1970) machine crushed metal from approved quarry including
cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, mixing concrete in concrete mixer
including seigniorage charges, sales & other taxes on all materials, all
operational, incidental, and labour charges such as laying and ramming
concrete in layers in position not exceeding 15cm, finishing top surface,
curing concrete, etc., complete for finished item of work.

Qty. V. P. No. of M. B. No. :


Varandah 1 x 1 3.50 2.31 0.10 0.80
Living/Din 1 x 1 5.56 3.50 0.10 1.946
Pooja 1 x 1 1.82 1.30 0.10 0.236
Kitchen 1 x 1 3.38 2.74 0.10 0.926
Bed Room 1 1 x 1 4.03 4.02 0.10 1.62
Bath 1 1 x 1 2.13 1.21 0.10 0.257
Bath 2 1 x 1 2.05 1.20 0.10 0.24
Bed room 2 1 x 1 4.03 4.02 0.10 1.62
Wash area part 1 1 x 1 3.58 2.28 0.10 0.81
Wash area part 2 1 x 1 4.00 2.28 0.10 0.912
Total in Cu.Mt :: 9.367 Cu.Mt 4607.01 1 Cu.Mt 43153.86
4) Coursed Rubble Stone Masonry in CM (1:3) Prop: including cost and
conveyance of all materials like cement, sand, water etc., to site,
including seigniorage charges, sales & other taxes on all materials, all
operational, incidental charges and labour charges such as mixing
mortar, finishing, curing, etc., complete for finished item of work. (APSS
901,906)
Qty. V. P. No. of M. B. No. :
West side wall 1 x 1 14.30 0.45 2.70 17.37
South side wall 1 x 2 8.60 0.45 2.70 20.89
East side wall 1 x 1 14.20 0.45 2.70 17.25
55.51 Cu.Mt.

Total in Cu.Mt :: 55.51 Cu.Mt 4498.24 1 Cu.Mt 249697.30


5) Filling with useful available excavated earth (excluding rock) in trenches,
sides of foundations and basement with initial lead in layers not
exceeding 15 cm thick, consolidating each deposited layer by watering
and ramming including cost and conveyance of water to work site and
all operational, incidental, labour charges, hire charges of T & P etc.,
complete for finished item of work. APSS No.309 & 310.

Qty. V. P. No. 7 of M. B. No. :


total EW forColumns pits 59.17
Deduct Columns -7.611
Deduct Footing straight -3.110
PCC Under Col. Footings -4.730
43.719 Cu.Mt.
Qty. V. P. No. 14 of M. B. No. :
West side wall 1 x 1 14.17 0.45 0.91 5.80
South side wall 1 x 2 8.30 0.45 0.91 6.80
East side wall 1 x 1 15.46 0.45 0.91 6.33
18.93 Cu.Mt.
Qty. V. P. No. 15 of M. B. No. :
North side wall 1 x 1 4.26 0.45 0.91 1.74
1 x 1 1.21 0.45 0.91 0.49
1 x 1 3.81 0.45 0.91 1.56
3.79 Cu.Mt.
Total in Cu.Mt :: 66.44 Cu.Mt 274.72 1 Cu.Mt 18252.12
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
6) Filling with Gravel in trenches, sides of foundations and basement with
initial lead in layers not exceeding 15cm thick, consolidating each
deposited layer by watering and ramming including all operational,
incidental, labour charges, seignorage charges, hire charges of T & P
etc., complete for finished item of work. (APSS NO. 309 & 310).
Qty. V. P. No. 35 of M. B. No. :
Plinth Beam 1 x 1 14.17 8.30 1.52 178.77
1 x 1 3.81 1.21 1.52 7.01
185.78 Cu.Mt.
Deduct Total Qty. of Excavation
Columns pits -52.65
CRS walls -22.75
-75.40 Cu.Mt.
Total in Cu.Mt :: 110.38 Cu.Mt 368.00 1 Cu.Mt 40619.84
7) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Column Footings.

Qty. V. P. No. 05 of M. B. No. :


Straight 1 x 13 1.50 1.50 0.15 4.388
Taper (average) 1 x 13 0.95 0.87 0.30 3.223
Total in Cu.Mt :: 7.611 Cu.Mt 9302.11 1 Cu.Mt 70798.36
8) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Columns.

Qty. V. P. No. 06 of M. B. No. :


Columns upto plinth beam 1 x 13 2.74 0.38 0.23 3.11
3.11 Cu.Mt
Qty. V. P. No. 24 of M. B. No. :
Columns 1 x 11 0.30 0.23 3.00 2.277
Circuler Columns 1 x 2 3.01
5.29 Cu.Mt
Total in Cu.Mt :: 8.40 Cu.Mt 11963.17 1 Cu.Mt 100502.59
9) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Plinth Beam.

Qty. V. P. No. 19 of M. B. No. :


North side Plinth Beam 1 x 1 8.80 0.23 0.30 0.607
West side Plinth Beam 1 x 1 14.17 0.23 0.30 0.98
South side Plinth Beam 1 x 2 7.84 0.23 0.30 1.08
East side Plinth Beam 1 x 1 15.40 0.23 0.30 1.06
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
3.727 Cu.Mt.
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Qty. V. P. No. 20 of M. B. No. :
Internal Plinth Beam
Col 8 to 5 1 x 1 13.48 0.23 0.30 0.93
Col 2 to 7 1 x 2 4.14 0.23 0.30 0.57
1 x 2 3.45 0.23 0.30 0.47
1.97 Cu.Mt.
Total in Cu.Mt :: 5.697 Cu.Mt 11663.03 1 Cu.Mt 66444.28
10) Reinforced Cement Concrete M20 Grade Nominal Mix using 6 to 20mm
(SS-5) graded machine crushed hard granite metal (coarse aggregate)
from approved quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., to site and
including Seigniorage charges, sales & other taxes on all materials
including all operational, incidental and labour charges such as weigh
batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of
work (APSS No. 402) with minimum cement content @ 380Kgs/Cu.F.
from standard suppliers approved by the department including
centering, shuttering, laying concrete, vibrating, curing etc., complete.
For Lintels.

Qty. V. P. No. 43 of M. B. No. :


Main door 1 x 2 1.10 0.75 0.33 0.544
Kitchen entrance of Bed Room 1 x 4 1.10 0.12 0.10 0.052
Bed Room Bath rooms 1 x 2 0.95
0.12 0.10 0.022
Kitchen Door 1 x 1 1.10
0.23 0.33 0.083
Pooja 1 x 1 0.90
0.12 0.10 0.010
Total in Cu.Mt :: 0.711 Cu.Mt 12087.01 1 Cu.Mt 8593.86
11) Reinforced Cement Concrete M20 Grade Nominal Mix corresponding to
IS 456 using 20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and conveyance
of all materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges, sales & other taxes
on all materials including all operational, incidental and labour charges
such as machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of
work (APSS No. 402) including centering, shuttering, laying concrete,
curing etc. complete for Sunshades / Chajjas for 75mm thick at Fixed
end and 50mm thick at Free end and for a width of 0.60 Mts. etc
complete for finished item of work.

Qty. V. P. No. 37 of M. B. No. :


Windows for Kitchen, Hall, Bed
Rooms 1 x 4 1.65 0.70 - 4.62
Windows in Bed ROom1 pooja 1 x 3 1.10 0.70 - 2.31
Windows in Kitchen 1 x 1 1.35
0.70 - 0.945
Total in Sq.Mt :: 7.875 Sq.Mt 1090.21 1 Sq.Mt 8585.40
12) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Roof Beams.

Qty. V. P. No. 32 to 33 of M. B. No. :


West side Roof Beam 1 x 4 10.00 0.23 0.30 2.76
North to south roof Beams 1 x 3 13.41 0.23 0.30 2.77
Beam under stair case mid
landing 1 x 1 2.40 0.23 0.30 0.166
5.696 Cu.Mt.
Qty. V. P. No. 33 of M. B. No. :
Deduct Over lapping beam -1 x 13 0.30 0.20 0.30 -0.234
-0.23 Cu.Mt.
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Total in Cu.Mt :: 5.462 Cu.Mt 11581.80 1 Cu.Mt 63259.79
13) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Roof Slab
125mm thick.

Qty. V. P. No. 33 of M. B. No. :


Roof Slab 1 x 1 10.00
13.41 - 134.10
Total in Sq.Mt :: 134.10 Sq.Mt 1322.94 1 Sq.Mt 177406.25
14) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar,
constructing masonry, scaffolding charges, lift charges, curing, etc.,
complete for finished item of work.
9" Brick wall
Qty. V. P. No. 38 to 40 of M. B. No. :
East wall 1 x 1 10.49 0.23 2.90 6.997
West wall 1 x 1 14.23 0.23 2.90 9.491
North Wall 1 x 1 7.85 0.23 2.90 5.236
South Wall 1 x 1 7.85 0.23 2.90 5.236
1 x 1 1.94 0.23 2.15 0.959
1 x 1 1.17 0.23 2.15 0.579
Deductions in East wall :-
Columns -1 x 3 0.30 0.23 2.90 -0.600
Windows -1 x 2 1.52 0.23 1.42 -0.993
-1 x 1 0.96 0.23 1.42 -0.314
-1 x 1 1.52 0.23 1.10 -0.385
Deductions in west wall :-
Columns -1 x 4 0.30 0.23 2.90 -0.800
-1 x 1 1.54 0.23 1.38 -0.489
-1 x 1 0.93 0.23 1.36 -0.291
Ventilators -1 x 2 0.90 0.23 0.60 -0.248
Deductions in north wall :-
Main door -1 x 1 0.92 0.23 2.17 -0.459
Windows -1 x 2 1.50 0.23 1.42 -0.980
Columns -1 x 1 0.23 0.23 2.90 -0.153
Deductions in south wall :-
Window -1 x 1 1.24 0.23 1.12 -0.319
Kitchen Door -1 x 1 0.87 0.23 2.17 -0.434
Window -1 x 1 0.91 0.23 1.35 -0.283
Columns -1 x 1 0.30 0.23 2.90 -0.200
21.55 Cu.Mt
Qty. V. P. No. of M. B. No. :
Front side steps Step 1 1 x 1 3.95 0.30 0.20 0.24
Step 2 1 x 1 3.95 0.60 0.20 0.47
Step 3 1 x 1 3.95 0.90 0.20 0.71
Step 4 1 x 1 3.95 1.20 0.55 2.61
Right side steps Step 1 1 x 1 2.55 0.30 0.20 0.15
Step 2 1 x 1 2.55 0.60 0.20 0.31
Step 3 1 x 1 2.55 0.90 0.20 0.46
Step 4 1 x 1 2.55 1.20 0.55 1.68
6.63 Cu.Mt
Total in Cu.Mt :: 28.18 Cu.Mt 6222.35 1 Cu.Mt 175345.82
4.5" Brick wall
Qty. V. P. No. 41 to 43 of M. B. No. :
Master Bed Room 1 x 1 4.10 0.12 2.90 1.427
1 x 1 4.13 0.12 2.90 1.437
Children Bed Room 1 x 1 4.13 0.12 2.90 1.437
1 x 1 4.10 0.12 2.90 1.427
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Toilets 1 x 2 2.10 0.12 2.90 1.462
1 x 2 1.15 0.12 2.90 0.800
Wall Between Bed Rooms 1 x 1 2.48 0.12 2.90 0.863
Kitchen 1 x 1 3.44 0.12 2.90 1.197
Puja Room 1 x 1 1.80 0.12 2.90 0.626
1 x 1 1.33 0.12 2.90 0.463
Toilet Under Stair case 1 x 1 1.94 0.12 2.15 0.501
Parapet wall for stair case 1 x 2 4.05 0.12 0.75 0.729
1 x 2 1.80 0.12 0.75 0.324
1 x 1 0.75 0.12 0.75 0.068
Parapet wall over roof slab 1 x 1 46.70 0.10 0.85 3.970
Brick pillars for Parapet wall 1 x 13 0.25 0.16 0.85 0.442
Base for over head tank 1 x 1 1.30 4.30 0.10 0.186
Parapet wall at wash area 1 x 1 4.16 0.12 0.96 0.479
1 x 1 2.50 0.12 0.96 0.288
Deduction for Door in MB -1 x 1 1.00 0.12 2.14 -0.257
Deduction for Door in MB -1 x 1 0.78 0.12 2.18 -0.204
Deduction for Door in CB -1 x 1 1.00 0.12 2.10 -0.252
-1 x 1 0.96 0.12 2.15 -0.248
-1 x 1 0.78 0.12 2.18 -0.204
Deduction for wall b/w BR -1 x 1 0.98 0.12 2.15 -0.253
Deduction for Door of
-1 x 1 0.93 0.12 2.20 -0.246
Kitchen
Deduction for Door of Pooja
-1 x 1 0.80 0.12 2.18 -0.209
Room
Deduction for Door under
-1 x 1 0.84 0.12 2.10 -0.212
Stair case
Total in Sq.Mt :: 16.04 Sq.Mt 6222.35 1 Sq.Mt 99812.72
15) Impervious coat 20mm thick over RCC roof slab surface with CM(1:3),
promixed with 1kg of water proof compound per bag of cement laid over
roof when it is green including cost of all materials, seigniorage charges,
excluding conveyance charges of materials and including all operational,
incidental and labour charges for mixing mortar, laying, rendering
smooth and thread lining, curing, rounding off junctions of wall and slab
etc,, complete for finished item of work.

Qty. V. P. No. 34 of M. B. No. :


Terrace Flooring 1 x 1 10.00
13.41 - 134.10
Total in Sq.Mt :: 134.10 Sq.Mt 429.14 1 Sq.Mt 57547.67
16) Plastering 20mm thick in two coats with base coat of 16mm thick in CM
(1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish
including cost and conveyance of all materials like cement, screened
sand, water etc., to site, seigniorage charges, sales & other taxes on all
materials, all operational, incidental and labour charges such as mixing
mortar,scaffolding charges, lift charges, finishing,including cutting of
Grooves wherever necessary as directed by Engineer - in - charge,
curing, etc., for Uneven Surfaces of Brick Wall complete for finished
item of work. (APSS 901,903 & 904)

Qty. V. P. No. 68 of M. B. No. :


West side wall 1 x 1 14.17 - 1.50 21.25
South side 1 x 1 8.30 - 1.50 12.45
East side 1 x 1 15.46 - 1.50 23.19
North side 1 x 1 3.81 - 1.50 5.71
62.60 Sq.Mt
Qty. V. P. No. of M. B. No. :
Front side steps face 1 x 4 3.95 0.30 - 4.74
Front side steps 1 x 4 3.95 - 0.18 2.84
Front side steps face 1 x 4 2.50 0.30 - 3.00
Front side steps 1 x 4 2.50 - 0.18 1.80
12.38 Sq.Mt
Total in Sq.Mt :: 74.98 Sq.Mt 387.62 1 Sq.Mt 29063.75
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
17) Plastering 12mm thick in two coats with base coat of 9mm thick in CM
(1:6) and top coat of 3mm thick in CM (1:4) dubara sponge finish
including cost and conveyance of all materials like cement, screened
sand, water etc., to site, seigniorage charges, sales & other taxes on all
materials, all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, finishing, including cutting of
Grooves wherever necessary as directed by Engineer - in - charge,
curing, etc., for Uneven Surfaces of Brick Wall complete for finished
item of work. (APSS 901,903 & 904).

A) Internal 9" brick walls :


Qty. V. P. No. 48 to 55 of M. B. No. :
North side 1 x 1 4.22 - 3.15 13.293
Deduct windows -1 x 1 1.52 - 1.30 -1.976
West side 1 x 1 4.20 - 3.15 13.230
Deduct window -1 x 1 1.52 - 1.30 -1.976
South side 1 x 1 4.22 - 3.15 13.293
Deduct Doors -1 x 1 0.96 - 2.05 -1.968
-1 x 1 0.80 - 1.90 -1.520
East side 1 x 1 4.20 - 3.15 13.230
Deduct door -1 x 1 0.96 - 2.05 -1.968
North side 1 x 1 1.87 - 3.15 5.890
Deduct door -1 x 1 0.96 - 2.05 -1.968
West side 1 x 1 2.50 - 3.15 7.875
South side 1 x 1 2.00 - 3.15 6.300
Deduct door -1 x 1 0.96 - 2.05 -1.968
East side 1 x 1 2.45 - 3.15 7.717
Deduct entrance -1 x 1 0.96 - 2.05 -1.968
South side wall 1 x 1 4.21 - 3.15 13.261
Deduct window -1 x 1 0.90 - 1.32 -1.188
West side wall 1 x 1 4.25 - 3.15 13.387
Deduct window -1 x 1 0.90 - 1.32 -1.188
North side wall 1 x 1 4.13 - 3.15 13.009
Deduct door -1 x 1 0.80 - 1.90 -1.520
-1 x 1 0.96 - 2.05 -1.968
East side wall 1 x 1 4.10 - 3.15 12.915
South side wall 1 x 1 2.05 - 3.15 6.457
North side wall 1 x 1 2.05 - 3.15 6.457
Deduct Bath room door -1 x 1 0.80 - 1.90 -1.520
East side wall 1 x 1 1.20 - 3.15 3.780
West side wall 1 x 1 1.15 - 3.15 3.622
Deduct Ventilator 1 x 1 0.89 - 0.59 0.525
South side wall 1 x 1 2.05 - 3.15 6.457
Deduct Bath room door -1 x 1 0.80 - 1.90 -1.520
North side wall 1 x 1 2.05 - 3.15 6.457
East side wall 1 x 1 1.20 - 3.15 3.780
West side wall 1 x 1 1.15 - 3.15 3.622
Deduct Ventilator -1 x 1 0.89 - 0.59 -0.525
Hall Plastering
North side wall 1 x 1 3.43 - 3.15 10.804
Deduct main door -1 x 1 0.90 - 2.05 -1.845
Window -1 x 1 1.46 - 1.37 -2.000
West side wall 1 x 1 7.10 - 3.15 22.365
Deduct entrance -1 x 1 0.96 - 2.05 -1.968
East side wall 1 x 1 5.50 - 3.15 17.325
Deduct Doors -1 x 1 1.52 - 1.37 -2.082
South side wall 1 x 1 1.80 - 3.15 5.670
1 x 1 1.50 - 3.15 4.725
Deduct Kitchen door -1 x 1 0.96 - 2.05 -1.968
Pooja Room
Pooja room Out side 1 x 1 1.33 - 3.15 4.189
Deduct door -1 x 1 0.76 - 2.03 -1.542
Nort side wall 1 x 1 1.75 - 3.15 5.512
East side wall 1 x 1 1.19 - 3.15 3.748
Deduct window -1 x 1 0.92 - 1.36 -1.251
South side wall 1 x 1 1.75 - 3.15 5.512
West side wall 1 x 1 1.19 - 3.15 3.748
Deduct Pooja Door -1 x 1 0.76 - 2.03 -1.542
Kitchen Room
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
North sidewall 1 x 1 3.42 - 3.15 10.773
Deduct Door -1 x 1 0.96 - 2.02 -1.939
West side wall 1 x 1 2.70 - 3.15 8.505
South side wall 1 x 1 3.44 - 3.15 10.836
Deduct Door -1 x 1 0.96 - 2.02 -1.939
Window -1 x 1 1.20 - 1.50 -1.800
East side wall 1 x 1 2.69 - 3.15 8.473
Deduct Window -1 x 1 1.50 - 1.04 -1.560
Total in Sq.Mt :: 250.56 Sq.Mt 375.17 1 Sq.Mt 94004.47
B) External 9" brick wall :-
Qty. V. P. No. 44 to 47 of M. B. No. :
North side wall 1 x 1 3.70 - 3.15 11.655
Deduction : Door -1 x 1 0.90 - 2.05 -1.845
windows -1 x 1 1.46 - 1.37 -2.000
O/s wall 1 x 1 1.28 - 3.15 4.032
Deduction : Door -1 x 1 0.90 - 2.05 -1.845
O/s wall 1 x 1 4.63 - 3.15 14.584
Deduction window -1 x 1 1.52 - 1.30 -1.976
West side wall 1 x 1 14.25 - 3.15 44.887
Deduction windows -1 x 1 1.52 - 1.30 -1.976
Ventilators -1 x 2 0.90 - 0.60 -1.080
Windows -1 x 1 0.90 - 1.32 -1.188
South side wall 1 x 1 8.10 - 3.15 25.515
Deductions Windows -1 x 1 0.90 - 1.32 -1.188
Kitchen Door -1 x 1 0.87 - 2.07 -1.800
Windows -1 x 1 1.20 - 1.05 -1.260
Wash are CW 1 x 1 2.50 1.40 - 3.500
Inner side 1 x 1 2.38 0.97 - 2.308
Top side 1 1 2.30 0.13 - 0.299
South side wall outer 1 x 1 8.10 1.40 - 11.340
inner 1 x 1 7.97 0.97 - 7.730
top side 1 x 1 7.97 0.13 - 1.036
West side wall inner 1 x 1 1.05 1.95 - 2.047
East side wall 1 x 1 10.45 - 3.15 32.917
Deduct windows -1 x 2 1.52 - 1.37 -4.164
window -1 x 1 0.93 - 1.37 -1.274
window -1 x 1 1.52 - 1.05 -1.596
Total in Sq.Mt :: 138.66 Sq.Mt 375.17 1 Sq.Mt 52020.32
18) RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire
mesh & nominal reinforcement as directed by Engineer-in-charge with
dubara sponge finishing, including cost & conveyance of all materials to
site, seigniorage charges, sales & other taxes on all materials,
operational & incidental, cost and conveyance of cement, wire mesh,
water to work site, centering, scaffolding and form work, lift charges
etc., complete for finished items of work but excluding cost of steel & its
fabrication charges, for finished item of work. (APSS No.403&903).

Qty. V. P. No. 56 to 57 of M. B. No. :


Portico 1 x 1 0.44 - 0.45 0.198
1 x 1 4.03 - 0.45 1.813
1 x 1 0.54 - 0.45 0.243
Drop wall North side 1 x 1 5.42 - 0.45 2.439
1 x 1 0.96 - 0.45 0.432
West side 1 x 1 13.60 - 0.45 6.120
South side 1 x 1 0.914 - 0.45 0.411
1 x 1 8.229 - 0.45 3.703
East Side 1 x 1 13.50 - 0.45 6.075
Total in Sq.Mt :: 21.43 Sq.Mt 1716.63 1 Sq.Mt 36794.25
19) Ceiling Plastering with CM(1:3) Prop: 12mm thick in single coat spong
finish including cost and conveyance of all materials like cement, sand,
water etc., to site, including seigniorage charges, sales & other taxes on
all materials, all operational, incidental charges and labour charges such
as mixing mortar, finishing, curing, etc., complete for finished item of
work. (APSS 901,906).
Qty. V. P. No. of M. B. No. :
1 x 1 13.60 10.00 136.00
Total in Sq.Mt :: 136.00 Sq.Mt 133.81 1 Sq.Mt 18198.16
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
20) Plain Cement Concrete M15 grade nominal mix (1:2.5:5) proportion
(cement: fine aggregate: Coarse aggregate) using 40mm, 20mm, 10mm
size Hard Broken Granite (IS383, 1970) Machine Crushed metal from
approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, including seigniorage
charges, sales & other taxes on all materials, all operational, incidental
and labour charges such as mixing concrete in Concrete Mixer, laying,
curing concrete, etc., complete for finished item of work (APSS No. 402)
Steps.

Qty. V. P. No. 37 of M. B. No. :


1 x 16 0.80 0.24 0.18 0.55
Total in Cu.Mt :: 0.55 Cu.Mt 5463.37 1 Cu.Mt 3004.85
21) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade
as per IS 1786-1979) of different diameters for RCC works, including
labour charges for straightening, cutting, bending to required sizes and
shapes, placing in position with cover blocks of approved materials and
size and tying and lapsplicing with binding wire of 18 SWG, forming grills
for reinforcement work as per approved designs and drawings, including
cost and conveyance of steel bars, including all wastages such as
overlaps, couplings, chairs, spacer bars including cost and conveyance of
binding wire, cover blocks and all incidental, operational, laour charges
such as cutting, bending placing in position, tying including sales and
other taxes on all materials etc., complete for finished item of work in all
floors. (APSS No.126).

For Footings Mat


10mm dia 6" c/c
F1 type
C1,C9,C10,C11,C12,C13,C14 9 x 7 1.50 0.62 58.59
F1 type
C1,C9,C10,C11,C12,C13,C14 9 x 7 1.50 0.62 58.59
F2 Type C1,C3,C4,C5,C7,C8 10 x 6 1.65 0.62 61.38
F2 Type C1,C3,C4,C5,C7,C8 10 x 6 1.65 0.62 61.38
F3 Type C2 10 x 1 1.65 0.62 10.23
Footings Total Qty : 250.17 Kgs
Columns
12mm dia
C1 Type
C1,C3,C4,C5,C6,C7,C8,C9,C10,C1 6 x 11 6.90 0.89 405.31
1,C12
C2 Type C2 8 x 1 6.90 0.89 49.13
C3 Type C13, C14 6 x 2 6.90 0.89 73.69
8mm dia
Stirrups 12 x 46 0.95 0.39 204.52
Stirrups 2 x 46 0.60 0.39 21.53
Columns Total Qty : 754.18 Kgs
Plinth Beams (Outer)
10mm dia
C1 to C11 6 x 1 10.95 0.62 40.73
C3 to C14 6 x 1 9.60 0.62 35.71
C14 to C11 6 x 1 7.90 0.62 29.39
C1 to C3 6 x 1 7.30 0.62 27.16
8mm dia
Stirrups 1 x 73 0.95 0.39 27.05
Stirrups 1 x 64 0.95 0.39 23.71
Stirrups 1 x 52 0.95 0.39 19.27
Stirrups 1 x 48 0.95 0.39 17.78
Plinth Beams (Internal)
10mm dia
C2 to C13 6 x 1 10.95 0.62 40.73
C6 to C4, C8 & C7 to C3 6 x 2 7.30 0.62 54.31
8mm dia
Stirrups 1 x 73 0.95 0.39 27.05
Stirrups 2 x 48 0.95 0.39 35.57
378.46 Kgs
1382.81 Kg 63.943 1 Kg 88421.02
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
22) Flooring with adanga Marbles of I st quality of size not exceeding 0.457
x 0.457m laid over CC Flooring bed set over 20mm thcik CM(1:8) drop
kase coat and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed
with white cement paste mixed with pigment of matching shade
including cost and conveyance of all materials like cement, sand, water,
tiles, etc. to site, seigniorage charges, sales and other taxes on all
materials, and all opertional, incidental and all labour charges such as
mixing of cement mortar, laying in position, curing, lift charges etc.,
complete for finished item of work in all floors.

Qty. V. P. No. 58-59 of M. B. No. :


1) Hall 1 x 1 5.50 3.45 - 18.98
1 x 1 1.60 1.60 - 2.56
2) Pooja Room 1 x 1 1.75 1.19 - 2.08
3) Kitchen Room 1 x 1 2.70 3.45 - 9.32
4) Master Bed Room 1 x 1 4.28 4.23 - 18.10
5) Children Bed Room 1 x 1 4.21 4.20 - 17.68
6) Bed Rooms area 1 x 1 2.52 1.90 - 4.79
7) Varandah 1 x 1 2.56 3.48 - 8.91
Total in Sq.Mt :: 82.42 Sq.Mt 988.47 1 Sq.Mt 81469.70
23) Timber shall be of the kind as specified, may be teak, shisham, sal,
deodar,etc., the timber shall be of best quality, well seasoned and free
from sap knots, warps, cracks and other defects, all wood work shall be
planed and neatly and truly finished to the exact dimensions. all joints
be neat and strong, truly and accurately fitted and glued before being
fitted together. Chunkhats : The Chunkhats shall be formed and joined
by motise and tenon joint with head wooden pins and the joints shall be
of coated with white lead before being fitted together.

Qty. V. P. No. 80 of M. B. No. :


1 x 6 0.96 - 2.05 6.00
Total in Sq.Mt :: 6.00 Each 15254.00 1 Each 91524.00
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
24) Providing and fixing 30mm thick Solid panel PVC door shutter consisting
of frame made out of M.S. tubes of 19 gauge thickness and size of
19mm x 19mm for stiles, & 15mm x 15mm for top & bottom rails. M.S.
frame shall have a coat of steel primers of approved make and
manufacture. M.S. frame shall be covered with 5mm thick heat molded
PVC ‘C’ channel of size 30 x 50mm forming stiles, and 5mm thick, 75mm
wide PVC sheets for top rail, lock rail & bottom rail on either side, and
10mm (5mm x 2) thick, 20mm wide cross PVC sheet as gap insert for
top rail & bottom rail. Paneling of 5mm thick PVC sheet to be fitted in
the M.S. frame welded / sealed to the stiles & rails with 30mm wide x
5mm thick PVC sheet beading on either side, and joined together with
solvent cement adhesive etc. An additional 5mm thick PVC strip of
20mm width is to be stuck on the interior side of the ‘C’ Channel using
PVC solvent adhesive. Complete as per direction of Engineer-in-charge,
manufacturer’s specification & drawing for finished item of work

Qty. V. P. No. 81 of M. B. No. :


Bath rooms door 1 x 2 0.80 - 1.90 3.04
Pooja Room Door 1 x 1 0.76 - 2.03 1.54
Toilet under stair case 1 x 1 0.84 - 2.10 1.76
Total in Sq.Mt :: 6.34 Sq.Mt 2493.00 1 Sq.Mt 15805.62
25) Supplying and fixing fully glazed anodized aluminium hinged type
window with fan light as per drawing using standard outer frame
38.5x33x21x2.5mm thick and central mullion of size
59(3mm)x33(4mm)x21(3mm) using 5mm thick, glass fitted with suitable
aluminium glazing clips and rubber beading including supplying and
fixing friction hinges (2np.s per shutter), handle with lock(1 no. per
shutter), incl cost and conveyance to site of aluminium sections, glass
rubber beading, fixtures etc., including labour charges for manufacturing
window, fixing in position using wooden blocks and sheet metalscrews
etc., complete for finished item of work.

Qty. V. P. No. 82 of M. B. No. :


Hall window 1 x 1 1.46 - 1.37 2.00
Bed Room 2 1 x 2 1.52 - 1.30 3.95
Bed Room 1 1 x 2 0.90 - 1.32 2.37
Hall 1 x 2 1.52 - 1.37 4.16
Kitchen window 1 x 1 1.20 - 1.50 1.80
1 x 1 1.04 - 1.50 1.56
Total in Sq.Mt :: 15.84 Sq.Mt 6417.00 1 Sq.Mt 101645.28
26) Glazed ventilator as per drawing using anodised aluminium sections of
38.5x33x21x2.50mm thick outer frame and central mullion of size
59(3mm) x 33 (2.5mm) and shutters with z section of 33(2.5mm) x 24.5
(3mm) x 21 (3mm) and 5mm thick plain glass fitted with suitable
aluminium glazing be made of single panel shutter of 25mm thick
providing with keyless lock, 100mm aluminium tower clips and rubber
beading including supply and fixing of no.s frictions hinges, 2no.s ISI
marked anodised aluminium tower bolts 75mm long including cost and
conveyance of all materials to site, fixtures in position using wooden
blocks & sheet metals screws etc.,

Qty. V. P. No. 83 of M. B. No. :


Ventilators 1 x 2 0.89 - 0.59 1.05
Pooja Room 1 x 1 0.90 - 1.36 1.22
Total in Sq.Mt :: 2.27 Sq.Mt 4246.00 1 Sq.Mt 9638.42
27) Painting to new walls with 2 coats of water proof cement paint of
apporved brand and shade as approved by the Engineer - in - Charge
over a base coat of approved cement primer grade II exterior making
three coats in all to give an even shade after thourughly brushing the
surface to remove all dirt and remains of loose powdered materials,
including cost and conveyance of all materials, cost of brushes, water to
site, etc., sales & other taxes, all operational, incidental, labour charges
etc. complete for finished item of work as per SS 912 for internal walls.
A) Internal walls :-
Qty. V. P. No. 72 to 79 of M. B. No. :
BED ROOM 2
North side 1 x 1 4.22 - 3.15 13.293
Deduct Window -1 x 1 1.52 - 1.30 -1.976
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
West side 1 x 1 4.20 - 3.15 13.230
Deduct window -1 x 1 1.52 - 1.30 -1.976
South side 1 x 1 4.22 - 3.15 13.293
Deduct Door -1 x 1 0.96 - 2.05 -1.968
Door (Bath) -1 x 1 0.80 - 1.90 -1.520
East side 1 x 1 4.20 - 3.15 13.230
Deduct Door -1 x 1 0.96 - 2.05 -1.968
Open area NS 1 x 1 1.87 - 3.15 5.890
Deduct Bed Room Door -1 x 1 0.96 - 2.05 -1.968
West side 1 x 1 2.50 - 3.15 7.875
South side 1 x 1 2.00 - 3.15 6.300
Deduct BR Door -1 x 1 0.96 - 2.05 -1.968
East side 1 x 1 2.45 - 3.15 7.717
Deduct : Entrance -1 x 1 0.96 - 2.05 -1.968
BR 1 South side wall 1 x 1 4.21 - 3.15 13.261
Deduct window -1 x 1 0.90 - 1.32 -1.188
West side wall 1 x 1 4.25 - 3.15 13.387
Deduct window -1 x 1 0.90 - 1.32 -1.188
North side wall 1 x 1 4.13 - 3.15 13.009
Deduct Bath room door -1 x 1 0.80 - 1.90 -1.520
Bed Room Door -1 x 1 0.96 - 2.05 -1.968
East side wall 1 x 1 4.10 - 3.15 12.915
Bed Room 2 S wall 1 x 1 2.05 - 1.10 2.255
North side wall 1 x 1 2.05 - 1.10 2.255
Deduct Door -1 x 1 0.80 - 1.90 -1.520
East side wall 1 x 1 1.20 - 1.10 1.320
West side wall 1 x 1 1.15 - 1.10 1.265
Deduct ventilator -1 x 1 0.89 - 0.59 -0.525
Bath room 1 S wall 1 x 1 2.05 - 1.10 2.255
Deduct Door -1 x 1 0.80 - 1.90 -1.520
North sidewall 1 x 1 2.05 - 1.10 2.255
East side wall 1 x 1 1.20 - 1.10 1.320
West side wall 1 x 1 1.15 - 1.10 1.265
Deduct ventilator -1 x 1 0.89 - 0.59 -0.525
Hall North side 1 x 1 3.43 - 3.15 10.804
Deduct main door -1 x 1 0.90 - 2.05 -1.845
Windows -1 x 1 1.46 - 1.37 -2.000
West side 1 x 1 7.10 - 3.15 22.365
Deduct BR Entrance -1 x 1 0.96 - 2.05 -1.968
East side 1 x 1 5.50 - 3.15 17.325
Deduct windows -1 x 1 1.52 - 1.37 -2.082
South side 1 x 1 1.80 - 3.15 5.670
1 x 1 1.50 - 3.15 4.725
Deduct Kitchen door -1 x 1 0.96 - 2.05 -1.968
Pooja room west wal 1 x 1 1.33 - 3.15 4.189
Deduct door 1 x 1 0.76 - 2.03 1.542
North side wall 1 x 1 1.75 - 3.15 5.512
East side wall 1 x 1 1.19 - 3.15 3.748
Deduct window -1 x 1 0.92 - 1.36 -1.251
South side wall 1 x 1 1.75 - 3.15 5.512
West side wall 1 x 1 1.19 - 3.15 3.748
Deduct Pooja Door -1 x 1 0.76 - 2.03 -1.542
Kitchen Room N S Walls 1 x 1 3.42 - 3.15 10.773
Deduct Kitchen Door -1 x 1 0.96 - 2.02 -1.939
West side wall 1 x 1 2.70 - 3.15 8.505
South side wall 1 x 1 3.44 - 1.85 6.364
Deduct Door -1 x 1 0.96 - 2.02 -1.939
East side wall 1 x 1 2.69 - 1.85 4.976
Total in Sq.Mt :: 221.55 Sq.Mt 193.32 1 Sq.Mt 42829.66
B) External walls :-
Qty. V. P. No. 69 to 71 of M. B. No. :
North side 1 x 1 3.70 - 3.15 11.655
Deduct Door -1 x 1 0.90 - 2.05 -1.845
Window -1 x 1 1.46 - 1.37 -2.000
Bed Room Outer wall 1 x 1 1.28 - 3.15 4.032
Deduct Door -1 x 1 0.90 - 2.05 -1.845
Bed Room outer wall 1 x 1 4.63 - 3.15 14.584
CRS+plinth Beam 1 x 1 4.63 - 1.50 6.945
Deduct Window -1 x 1 1.52 - 1.30 -1.976
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
West side wall 1 x 1 14.25 - (3.15+1.50) 66.26
Deduct Bed Room Window -1 x 1 1.52 - 1.30 -1.976
Ventilators -1 x 2 0.90 - 0.60 -1.080
Windows -1 x 1 0.90 - 1.32 -1.188
South side wall 1 x 1 8.10 - 3.15 25.515
CRS+plinth Beam 1 x 1 8.10 - (1.50+1.40) 23.49
Deduct window -1 x 1 0.90 - 1.32 -1.188
Door -1 x 1 0.87 - 2.07 -1.800
window -1 x 1 1.20 - 1.05 -1.260
Est side wall 1 x 1 2.50 - 2.90 7.250
9" wall+CRS 1 x 1 10.49 - (3.15+1.50) 48.78
Deduct Window 1 x 2 1.52 - 1.37 4.164
Window 1 x 1 0.93 - 1.37 1.274
Window 1 x 1 1.52 - 1.05 1.596
199.387 Sq.Mt
Qty. V. P. No. of M. B. No. :
West side wall 1 x 1 14.17 - 1.50 21.25
South side 1 x 1 8.30 - 1.50 12.45
East side 1 x 1 15.46 - 1.50 23.19
North side 1 x 1 3.81 - 1.50 5.71
62.60 Sq.Mt
Total in Sq.Mt :: 261.99 Sq.Mt 108.16 1 Sq.Mt 28336.51
28) Painting to new walls with 2 coats of water proof cement paint of
apporved brand and shade as approved by the Engineer - in - Charge
over a base coat of approved cement primer grade II exterior making
three coats in all to give an even shade after thourughly brushing the
surface to remove all dirt and remains of loose powdered materials,
including cost and conveyance of all materials, cost of brushes, water to
site, etc., sales & other taxes, all operational, incidental, labour charges
etc. complete for finished item of work as per SS 912 for internal walls.

Qty. V. P. No. 64 of M. B. No. :


Ceiling 1 x 1 13.60 10.00 - 136.00
Total in Sq.Mt :: 136.00 Sq.Mt 193.32 1 Sq.Mt 26291.52
29) Dadooing to walls with glazed red or white full body ceramic wall tiles of
size 200 x 300 mm / 245 mm x 325 mm and thickness 6 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any
colour and finish in all shades and designs, any brand as approved by
Engineer - in - charge and set over a base coat of CM (1:5), 12mm thick
and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with
white cement paste mixed with pigment of matching shade including
cost and conveyance of all materials like cement, sand, water, tiles, etc.
to site, seigniorage charges, sales and other taxes on all materials, and
all opertional, incidental and all labour charges such as mixing of cement
mortar, laying in position, curing, lift charges etc., complete for finished
item of work in all floors

Qty. V. P. No. 61 to 62 of M. B. No. :


Bath Rooms 1 x 2 2.05 2.05 - 8.41
1 x 2 1.20 2.05 - 4.92
Deduct Door -1 x 1 0.80 1.90 - -1.52
Ventilator -1 x 1 0.89 0.59 - -0.52
Bath Room 2 1 x 2 2.05 2.05 - 8.41
1 x 2 1.20 2.05 - 4.92
Deduction Door -1 x 1 0.80 1.90 - -1.52
Ventilators -1 x 1 0.89 0.59 - -0.52
Kitchen Room : East Side 1 x 1 2.69 1.30 - 3.49
Deduct Kitchen Window -1 x 1 1.50 1.04 - -1.56
South side 1 x 1 2.34 1.30 - 3.04
Deduct Kitchen Window -1 x 1 1.20 1.50 - -1.80
Total in Sq.Mt :: 25.75 Sq.Mt 777.37 1 Sq.Mt 20017.28
30) Providing and fixing non skid ceramic tiles for flooring over and inclusive
of 20mm thick base plaster in cement morter 1:5 (1 cement : 5 coarse
sand) including a floating cement slurry including grouting/ filling the
joints with white cement slurry mixed with matching, pigment, curing,
cleaning and leaving/making necessary holes for sanitory connection
complete but including cost of cement and tiles in all heights/level for
skirting complete for finished item of work.
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Qty. V. P. No. 60 of M. B. No. :
1) Bath Room- 1 1 x 1 2.05 1.2 - 2.46
2) Bath Room - 2 1 x 1 2.05 1.2 - 2.46
Total in Sq.Mt :: 4.92 Sq.Mt 775.71 1 Sq.Mt 3816.49
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
SUPPLYMENTARY ITEM
31) Brick Masonry in superstructure with CM (1:8) prop with Flyash Cement
solid blocks of size 290 x 225 x 140 mm, for manufacturing of flyash
solid blocks using flyash of 80 kgs, cement of 15 kgs. Gypsum of 5 kgs.
and stone dust with a compresive strength not lessthan 50 kg/sqm
including cost and conveyance of all materials, labour charges,
seiniorage charges, scaffolding and curing etc., for Superstructure
Walls.
Qty. V. P. No. 13 of M. B. No. :
West side wall 1 x 1 14.170.45 1.82 11.60
South side wall 1 x 2 8.300.45 1.82 13.59
East side wall 1 x 1 15.460.45 1.82 12.66
North side wall 1 x 1 9.280.45 1.82 7.60
Total in Cu.Mt :: 45.45 Cu.Mt 6010.50 1 Cu.Mt 273177.23
32) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Waist Slab
150mm thick.

Qty. V. P. No. 25 of M. B. No. :


Stair case Slab

From Ground Level to Landing 1 x 1 3.45 0.98 0.12 0.405


Only mid landing 1 x 1 1.27 0.95 0.12 0.144
From Landing to Roof Level 1 x 1 1.70 0.95 0.12 0.193
0.742 Cu.Mt
Total in Sq.Mt :: 4.95 Sq.Mt 1455.60 1 Sq.Mt 7205.22
33) Providing Skirting to internal walls to 15 cm height and risers of steps
with soluble salt porcelain vitrified tiles screen printed and polished of
size 600 x 600 mm and thickness between 8-10 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any
colour and finish of make Jhonson & Jhonson, Kajaria, Nitco, Marbonite,
set over base coat of CM (1:5) 12 mm thick with cement slurry of honey
like consistency spread at the rate of 3.30 kgs per sqm and jointed with
white cement paste mixed with pigment of matching shade to full depth,
including cost of all materials like tiles, cement, sand and water etc.,
complete including seigniorage charges, etc., complete for finished item
of work.

Qty. V. P. No. 65 to 67 of M. B. No. :


1) HALL North Side 1 x 1 3.73 - 0.1016 0.38
Deduct Door -1 x 1 0.90 - 0.1016 -0.09
West side 1 x 1 7.36 - 0.1016 0.74
Deduct Entrance -1 x 1 0.96 - 0.1016 -0.10
East side 1 x 1 5.50 - 0.1016 0.56
South Side 1 x 1 2.10 - 0.1016 0.21
2) Pooja Room N Side 1 x 1 1.75 - 0.10 0.175
South Side 1 x 1 1.75 - 0.10 0.175
East side 1 x 1 1.19 - 0.10 0.12
West side 1 x 1 1.19 - 0.10 0.12
Deduct Door -1 x 1 0.76 - 0.10 -0.076
3) Kitchen N Side 1 x 1 0.93 - 0.10 0.093
East 1 x 1 0.35 - 0.10 0.035
1 x 1 2.16 - 0.10 0.216
South 1 x 1 0.22 - 0.10 0.022
1 x 1 0.85 - 0.10 0.085
West side 1 x 1 2.50 - 0.10 0.250
4) Bed Room N Side 1 x 1 3.16 - 0.10 0.32
East side 1 x 1 (4.10+0.15) - 0.10 0.43
South side 1 x 1 4.21 - 0.10 0.42
West side 1 x 1 4.25 - 0.10 0.43
1 x 1 0.22 - 0.10 0.02
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
5) Bed Room North 1 x 1 4.22 - 0.10 0.422
South 1 x 1 3.10 - 0.10 0.310
East 1 x 1 3.10 - 0.10 0.310
West 1 x 1 4.20 - 0.10 0.420
6) Area bw Bed rooms 1 x 1 (0.84+0.09) - 0.10 0.100
South 1 x 1 0.35+1.16) - 0.10 0.100
East 1 x 1 (0.22+0.85) - 0.10 0.100
West 1 x 1 2.50 - 0.10 0.250
Total in Sq.Mt :: 6.547 Sq.Mt 977.30 1 Sq.Mt 6398.38
34) Supply and fixing of Black Granite stone and set over a base coat of CM
(1:5), 12mm thick and neat cement paste at the rate of 3.3 Kg/Sqmt.
and jointed with white cement paste mixed with pigment of matching
shade including cost and conveyance of all materials like cement, sand,
water, tiles, etc. to site, seigniorage charges, sales and other taxes on all
materials, and all opertional, incidental and all labour charges such as
mixing of cement mortar, laying in position, curing, lift charges etc.,
complete for finished item of work in all floors

Qty. V. P. No. 63 of M. B. No. :


East 1 x 1 1.95 0.50 - 0.98
1 x 1 1.82 0.50 - 0.91
Total in Sq.Mt :: 1.89 Sq.Mt 36009.58 10 Sq.Mt 6805.81
35) Reinforced Cement Concrete M20 Grade Nominal Mix corresponding to
IS 456 using 20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and conveyance
of all materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges, sales & other taxes
on all materials including all operational, incidental and labour charges
such as machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of
work (APSS No. 402) including centering, shuttering, laying concrete,
curing etc. complete for Side Walls of 100mm thick.

Qty. V. P. No. of M. B. No. :


Septic tank side wall 1 x 1 π/4 (1.30²-1.20²) 2.70 0.53
Top cover 1 x 1 π/4 (1.30²) 0.10 0.13
Bottom portion 1 x 1 π/4 (1.30²) 0.15 0.20
Total in Sq.Mt :: 0.86 Sq.Mt 3855.40 1 Sq.Mt 3321.57
36) Supply and fixing of M.S.Grill of size with outer angular frame of rolled
steel equal angle of ISA 2525 of size 25mm x 25mm x 4mm welded with
safety bars of 10mm square rods at 150mm centre to centre horizontally
and verticlally including red oxide primer of grade-I quality, sales and
other taxes, cost and conveyance of all materials to site, all labour
charges and fixing in position etc., complete for finished item of work.

Qty. V. P. No. of M. B. No. :


Hall window 1 x 1 1.46 - 1.37 2.00
Bed Room 2 1 x 2 1.52 - 1.30 3.95
Bed Room 1 1 x 2 0.90 - 1.32 2.37
Hall 1 x 2 1.52 - 1.37 4.16
Kitchen window 1 x 1 1.20 - 1.50 1.80
1 x 1 1.04 - 1.50 1.56
Total in Kgs :: 15.84 Sq.Mt 1506.00 1 Kgs 23855.04

Total:- 2337056.25

Forest Range Officer, Forest Divisional Officer,


E.Bayyaram Manuguru,
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of
Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.

M. B. No. :
Sl. Measurements
No. Description of Item No.s
L B D
Qty Rate/Per Amount
1 2 3 4 5 6 7 8 9
3) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance
of steel bars, including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire, cover blocks and
all incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

For Footings Mat


10mm dia 6" c/c
F1 type C14 2 x 8 x 2 1.35 0.62 26.78
F2 Type C1,C2,C3,C4,C7,C10 2 x 9 x 6 1.50 0.62 100.44
F3 Type C5,C6,C9 2 x 10 x 3 1.70 0.62 63.24
F3 type C8 2 x 10 x 1 1.70 0.62 21.08
F4 Type CF1 C11-C13 1 x 10 x 1 1.60 0.62 9.92
F4 Type CF1 C11-C13 1 x 18 x 1 3.00 0.62 33.48
Footings Total Qty : 254.94 Kgs
Columns
12mm dia
C1 type C13, C14 1 x 2 x 6 7.20 0.89 76.90
C2 Type C1,C3,C4,C7,C10,C11 1 x 6 x 6 7.20 0.89 230.69
C3 Type C2,C5,C6,C9 1 x 4 6 7.20 0.89 153.79
C4 Type C8 1 x 1 x 8 7.20 0.89 51.26
8mm dia
Stirrups 1 x 11 x 48 0.95 0.39 195.62
Stirrups 1 x 2 x 48 0.60 0.39 22.46
Columns Total Qty : 730.72 Kgs
Total Qty : 985.66 Kg 79.803 1 Kg 78658.62
Sl. Measurements
No. Description of Item No.s
L B D
Qty Rate/Per Amount
1 2 3 4 5 6 7 8 9
4) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Column Footings.

F1 type C14 1 x 1 1.20 1.20 0.30 0.43


F2 Type C1,C2,C3,C4,C7,C10 1 x 6 1.50 1.50 0.30 4.05
F3 Type C5,C6,C9 1 x 3 1.70 1.70 0.30 2.60
F3 type C8 1 x 1 1.70 1.70 0.30 0.87
F4 Type CF1 C11-C13 1 x 1 3.00 1.50 0.30 1.35
(0.30/3) x ((1.20² )+(0.30²)+
Taper Portion 1 x 1 0.51
√(1.20²) X (0.30²))
(0.30/3) x ((1.50² )+(0.30²)+
Taper Portion 1 x 6 4.08
√(1.50²) X (0.30²))
(0.30/3) x ((1.70² )+(0.30²)+
Taper Portion 1 x 3 2.40
√(1.70²) X (0.30²))
(0.30/3) x ((1.70² )+(0.30²)+
Taper Portion 1 x 1 0.80
√(1.70²) X (0.30²))
(0.30/3) x ((3.00x1.50)+(0.30x0.60)+
Taper Portion 1 x 1 √(3.00x1.50) X (0.30x0.60))
1.36

Total in Cu.Mt :: 18.45 Cu.Mt 10420.38 1 Cu.Mt 192256.01


5) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Columns.

Columns upto plinth beam 1 x 13 0.38 0.23 2.70 3.06


3.06 Cu.Mt 13238.07 1 Cu.Mt 40508.49
6) Filling with useful available excavated earth (excluding rock) in trenches,
sides of foundations and basement with initial lead in layers not exceeding
15 cm thick, consolidating each deposited layer by watering and ramming
including cost and conveyance of water to work site and all operational,
incidental, labour charges, hire charges of T & P etc., complete for finished
item of work. APSS No.309 & 310.
total EW forColumns pits 62.55
Deduct Columns -18.45
Deduct Footing straight -3.06
PCC Under Col. Footings -4.99
Total in Cu.Mt :: 36.05 Cu.Mt 289.49 1 Cu.Mt 10436.11
7) Earth work excavation for foundations and depositing on bank for all lifts and
with an initial lead of 10m including all operational, incidental, labour charges
such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS -
20 B (APSS 308). for building foundation.

West side walls 1 x 1 14.50 0.45 1.90 12.39


South side walls 1 x 2 9.20 0.45 1.60 13.25
East side walls 1 x 1 14.50 0.45 1.20 7.83
Deduct Columns -1 x 12 0.38 0.23 0.91 -0.95
32.52 Cu.Mt 354.63 1 Cu.Mt 11532.57
Sl. Measurements
No. Description of Item No.s
L B D
Qty Rate/Per Amount
1 2 3 4 5 6 7 8 9
8) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site,
mixing concrete in concrete mixer including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labour charges
such as laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for finished item
of work.

Under CRS Walls


West side walls 1 x 1 14.50 0.45 0.15 0.97
South side walls 1 x 2 9.20 0.45 0.15 1.24
East side walls 1 x 1 14.50 0.45 0.15 0.98
3.19 Cu.Mt 5774.08 1 Cu.Mt 18419.32
9) Coursed Rubble Stone Masonry in CM (1:3) Prop: including cost and
conveyance of all materials like cement, sand, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental charges and labour charges such as mixing mortar, finishing,
curing, etc., complete for finished item of work. (APSS 901,906)

West side wall 1 x 1 14.50 0.45 2.65 17.29


South side wall 1 x 2 9.20 0.45 2.70 22.35
East side wall 1 x 1 14.50 0.45 2.55 16.64
Total in Cu.Mt :: 56.28 Cu.Mt 5137.19 1 Cu.Mt 289121.05
10) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance
of steel bars, including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire, cover blocks and
all incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

Plinth Beams (Outer)


10mm dia
C1 to C10 Top PB1 1 x 2 x 1 12.50 0.62 15.50
C1 to C10 Bottom PB1 1 x 2 x 1 12.50 0.62 15.50
C1 to C10 Crank PB1 1 x 2 x 1 12.50 0.62 15.50
C1 to C3 Top PB1 1 x 2 x 1 8.50 0.62 10.54
C1 to C3 Bottom PB1 1 x 2 x 1 8.50 0.62 10.54
C1 to C3 Crank PB1 1 x 2 x 1 8.50 0.62 10.54
C10 to C11 Top PB1 1 x 2 x 1 4.60 0.62 5.70
C10 to C11 Bottom PB1 1 x 2 x 1 4.60 0.62 5.70
C10 to C11 Crank PB1 1 x 2 x 1 4.60 0.62 5.70
C13 to C14 Top PB1 1 x 2 x 1 3.90 0.62 4.84
C13 to C14 Bottom PB1 1 x 2 x 1 3.90 0.62 4.84
C13 to C14 Crank PB1 1 x 2 x 1 3.90 0.62 4.84
C9 to C14 Top PB1 1 x 2 x 1 2.60 0.62 3.22
C9 to C14 Bottom PB1 1 x 2 x 1 2.60 0.62 3.22
C9 to C14 Crank PB1 1 x 2 x 1 2.60 0.62 3.22
C3 to C6 Top PB1 1 x 2 x 1 4.60 0.62 5.70
C3 to C6 Bottom PB1 1 x 2 x 1 4.60 0.62 5.70
C3 to C6 Crank PB1 1 x 2 x 1 4.60 0.62 5.70
C6 to C9 Crank PB3 1 x 2 x 1 6.00 0.62 7.44
12mm dia
C6 to C9 Top PB3 1 x 2 x 1 6.00 0.89 10.68
C6 to C9 Bottom PB3 1 x 2 x 1 6.00 0.89 10.68

8mm dia
Stirrups 1 x 1 x 84 0.95 0.39 31.12
Stirrups 1 x 1 x 57 0.95 0.39 21.12
Stirrups 1 x 1 x 31 0.95 0.39 11.49
Stirrups 1 x 1 x 26 0.95 0.39 9.63
Stirrups 1 x 1 x 18 0.95 0.39 6.67
Stirrups 1 x 1 x 31 0.95 0.39 11.49
Stirrups 1 x 1 x 40 0.95 0.39 14.82
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Plinth Beams (Internal)
10mm dia
C4 to C5, C7 to C8 Top PB1 2 x 2 x 1 4.50 0.62 11.16
C4 to C5, C7 to C8 Bottom PB1 2 x 2 x 1 4.50 0.62 11.16
C4 to C5, C7 to C8 Crank PB1 2 x 2 x 1 4.50 0.62 11.16
C5 to C6,# to C9 Top PB1 2 x 2 x 1 3.80 0.62 9.42
C5 to C6,# to C9 Bottom PB1 2 x 2 x 1 3.80 0.62 9.42
C5 to C6,# to C9 Crank PB1 2 x 2 x 1 3.80 0.62 9.42
C2 to C5, C to C8 Top PB1 1 x 2 x 1 7.20 0.62 8.93
C2 to C5, C to C8 Bottom PB1 1 x 2 x 1 7.20 0.62 8.93
C2 to C5, C to C8 Crank PB1 1 x 2 x 1 7.20 0.62 8.93
C8 to C11, C13 Top PB3 1 x 2 x 1 5.60 0.62 6.94
12mm Dia
C8 to C11, C13 Bottom PB3 1 x 2 x 1 5.60 0.89 9.97
C8 to C11, C13 Crank PB3 1 x 2 x 1 5.60 0.89 9.97
8mm dia
Stirrups 1 x 1 x 30 0.95 0.39 11.12
Stirrups 1 x 1 x 25.3 0.95 0.39 9.39
Stirrups 1 x 1 x 48 0.95 0.39 17.78
Stirrups 1 x 1 x 37.3 0.95 0.39 13.83
439.17 Kg 79.803 1 Kg 35047.08
11) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Plinth Beam.

C1 to C10 1 x 1 11.55
0.23 0.30 0.80
C1 to C3 1 x 1 8.20
0.23 0.30 0.57
C10 to C11 1 x 1 4.35
0.23 0.30 0.30
C 13 to C14 1 x 1 3.75
0.23 0.30 0.26
C 3 to C14 1 x 1 12.75
0.23 0.30 0.88
Col 2 to 13 1 x 1 12.75
0.23 0.30 0.88
C4 to C5 & C7 to C8 2 x 2 4.30
0.23 0.30 1.19
at C9 to C8&C11, C6 to 5 2 x 2 3.62
0.23 0.30 0.99
at toilet 1 x 1 3.30
0.23 0.30 0.22
Total in Cu.Mt :: 6.09 Cu.Mt 13707.49 1 Cu.Mt 83478.61
12) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Columns.

Columns 1 x 11 0.30 0.23 3.00 2.27


Circuler Columns 2 x 0.785 0.23 0.23 3.00 0.24
2.51 Cu.Mt 13238.07 1 Cu.Mt 33227.56
Sl. Measurements
No. Description of Item No.s
L B D
Qty Rate/Per Amount
1 2 3 4 5 6 7 8 9
13) Filling with Gravel in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15cm thick, consolidating each deposited layer
by watering and ramming including all operational, incidental, labour
charges, seignorage charges, hire charges of T & P etc., complete for
finished item of work. (APSS NO. 309 & 310).
Varandah 1 x 1 3.50 2.35 2.55 20.97
Living/Din 1 x 1 5.56 3.50 2.55 49.62
Pooja 1 x 1 1.80 1.30 2.55 5.97
Kitchen 1 x 1 3.50 2.70 2.55 24.10
Bed Room 1 1 x 1 4.20 4.28 2.55 45.84
Bath 1 1 x 1 2.10 1.20 2.55 6.43
Bath 2 1 x 1 1.20 1.05 2.55 3.21
Bed room 2 1 x 1 4.20 4.03 2.55 43.16
Wash area 1 x 1 8.20 2.40 2.55 50.18
Total in Cu.Mt :: 249.48 Cu.Mt 425.81 1 Cu.Mt 106231.08
14) Vibrated Plain Cement Concrete (1:4:8) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site,
mixing concrete in concrete mixer including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labour charges
such as laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for finished item
of work.

Varandah 1 x 1 3.50 2.35 0.23 1.89


Living/Din 1 x 1 5.56 3.50 0.23 4.47
Pooja 1 x 1 1.80 1.30 0.23 0.53
Kitchen 1 x 1 3.50 2.70 0.23 2.17
Bed Room 1 1 x 1 4.20 4.28 0.23 4.13
Bath 1 1 x 1 2.10 1.20 0.23 0.57
Bath 2 1 x 1 1.20 1.05 0.23 0.28
Bed room 2 1 x 1 4.20 4.03 0.23 3.89
Wash area 1 x 1 8.20 2.40 0.23 4.52
Total in Cu.Mt :: 22.450 Cu.Mt 5405.06 1 Cu.Mt 121343.60
15) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including seigniorage
charges, sales & other taxes on all materials, all operational, incidental and
labour charges such as mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc., complete for finished item of
work.

9" Brick wall


C1 to C10 1 x 1 11.55 0.23 0.12 0.32
C1 to C3 1 x 1 8.20 0.23 0.12 0.23
C10 to C11 1 x 1 4.35 0.23 0.12 0.12
C 13 to C14 1 x 1 3.75 0.23 0.12 0.10
C 3 to C14 1 x 1 12.75 0.23 0.12 0.35
Col 2 to 13 1 x 1 12.75 0.23 0.12 0.35
C4 to C5 & C7 to C8 2 x 2 4.30 0.23 0.12 0.47
at C9 to C8&C11, C6 to 5 2 x 2 3.62 0.23 0.12 0.40
Total in Cu.Mt :: 2.34 Cu.Mt 6779.83 1 Cu.Mt 15864.80
Total : 1087119.67
16) Sanitory Charges 11% on total Cost 119583.16
17) Electrification Charges 9% on total Cost 97840.77
Total:- 1304543.60
II nd Part Bill
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of Paloncha
Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.
M. B. No. :
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per IS
1786-1979) of different diameters for RCC works, including labour charges for
straightening, cutting, bending to required sizes and shapes, placing in position
with cover blocks of approved materials and size and tying and lapsplicing with
binding wire of 18 SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars including cost and
conveyance of binding wire, cover blocks and all incidental, operational, laour
charges such as cutting, bending placing in position, tying including sales and
other taxes on all materials etc., complete for finished item of work in all floors.
(APSS No.126).

Plinth Beam for Stair case


Plinth Beam top 12mm dia C/w 2 x 3 x 1 2.60 0.89 13.88
Plinth Beam Bottom 12mm dia C/w 2 x 3 x 1 2.60 0.89 13.88
Stirrups 8mm dia 2 x 1 x 18 0.90 0.39 12.64
Plinth Beam top 12mm dia L/w 1 x 3 x 1 2.20 0.89 5.87
Plinth Beam Bottom 12mm dia L/w 1 x 3 x 1 2.20 0.89 5.87
Stirrups 8mm dia 1 x 1 x 15 0.90 0.39 5.27
57.41 Kg 79.803 1 Kg 4581.49
2) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Plinth Beam.

Below stair case C/w 2 x 1 x 1 2.40


0.23 0.30 0.33
L/w 2 x 1 x 1 2.10
0.23 0.30 0.29
Total in Cu.Mt :: 0.62 Cu.Mt 13717.49 1 Cu.Mt 8504.84
3) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per IS
1786-1979) of different diameters for RCC works, including labour charges for
straightening, cutting, bending to required sizes and shapes, placing in position
with cover blocks of approved materials and size and tying and lapsplicing with
binding wire of 18 SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars including cost and
conveyance of binding wire, cover blocks and all incidental, operational, laour
charges such as cutting, bending placing in position, tying including sales and
other taxes on all materials etc., complete for finished item of work in all floors.
(APSS No.126).

For Stair case I st Flight


Stair case I st flight 10mm dia top Bar
Cross 1 x 1 x 27 1.20 0.62 20.09
Stair case I st flight 10mm dia Bottom
Bar Cross 1 x 1 x 27 1.20 0.62 20.09
Stair case I st flight 10mm dia Bottom
Bar Long 1 x 1 x 6 4.10 0.62 15.25
Stair case I st flight 10mm dia Bottom
Bar Long 1 x 1 x 6 4.10 0.62 15.25
Landing 10 mm dia Top 1 x 1 x 6 1.20 0.62 4.46
Landing 10 mm dia Bottom 1 x 1 x 6 1.20 0.39 2.81
77.95 Kg 79.803 1 Kg 6220.64
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
4) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Stair case I st Flight.

Stair case I st flight


1 x 1 x 1 4.10
1.10 - 4.51
Total in Sq.Mt :: 4.51 Sq.Mt 1750.00 1 Sq.Mt 7892.50
5) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per IS
1786-1979) of different diameters for RCC works, including labour charges for
straightening, cutting, bending to required sizes and shapes, placing in position
with cover blocks of approved materials and size and tying and lapsplicing with
binding wire of 18 SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars including cost and
conveyance of binding wire, cover blocks and all incidental, operational, laour
charges such as cutting, bending placing in position, tying including sales and
other taxes on all materials etc., complete for finished item of work in all floors.
(APSS No.126).

For Roof Beams


B1 type Beam
C1 to C9 12mm dia top 1 x 2 x 1 2.65 0.89 4.72
C1 to C9 12mm dia Bottom 1 x 2 x 1 2.65 0.89 4.72
Stirrups 8mm dia 1 x 1 x 18 1.25 0.39 8.78
C11 to C13 12mm dia top 1 x 2 x 1 1.24 0.89 2.21
C11 to C13 12mm dia Bottom 1 x 2 x 1 1.24 0.89 2.21
Stirrups 8mm dia 1 x 1 x 8 1.25 0.39 3.90
B2 type Beam
C13 to C14, C9 to C11-8, C2 to C3
12mm dia top
3 x 2 x 1 4.85 0.89 25.90
" " 16mm dia Extras 3 x 2 x 1 1.20 1.59 11.45
C13 to C14, C9 to C11-8, C2 to C3
12mm dia Bottom
3 x 2 x 1 4.85 0.89 25.90
" " 12mm dia Extras 3 x 2 x 1 1.20 0.89 6.41
Stirrups 8mm dia 3 x 1 x 32 1.25 0.39 46.80
B3 type Beam
C5 to C6 12mm dia top 1 x 2 x 1 4.00 0.89 7.12
" " 16mm dia Extras 1 x 2 x 1 1.20 1.59 3.82
C5 to C6 16mm dia Bottom 1 x 2 x 1 4.00 1.59 12.72
" " 16mm dia Extras 1 x 2 x 1 1.20 1.59 3.82
Stirrups 8mm dia 1 x 1 x 26 1.25 0.39 12.68
C10 to C11, C7 to C8, C4 to C5, C1 to
C2 12mm dia top 4 x 2 x 1 5.55 0.89 39.52
" " 16mm dia Extras 4 x 2 x 1 1.20 1.59 15.26
C10 to C11, C7 to C8, C4 to C5, C1 to
C2 16mm dia Bottom 4 x 2 x 1 5.55 1.59 70.60
" " 16mm dia Extras 4 x 2 x 1 1.20 1.59 15.26
Stirrups 8mm dia 4 x 1 x 37 1.25 0.39 72.15
C4 to C7, C5 to C8 12mm dia top
2 x 2 x 1 2.60 0.89 9.26
" " 16mm dia Extras 2 x 2 x 1 1.20 1.59 7.63
C4 to C7, C5 to C8 16mm dia Bottom 2 x 2 x 1 2.60 1.59 16.54
" " 16mm dia Extras 2 x 2 x 1 1.20 1.59 7.63
Stirrups 8mm dia 2 x 1 x 17 1.25 0.39 16.58
C2 to C5 12mm dia top 1 x 2 x 1 5.60 0.89 9.97
" " 16mm dia Extras 1 x 2 x 1 1.20 1.59 3.82
C2 to C5 16mm dia Bottom 1 x 2 x 1 5.60 1.59 17.81
" " 16mm dia Extras 1 x 2 x 1 1.20 1.59 3.82
Stirrups 8mm dia 1 x 1 x 38 1.25 0.39 18.53
B4 type Beam
C1 to C4, C3 to C6 12mm dia top 2 x 2 x 1 5.60 0.89 19.94
" " 16mm dia Extras 2 x 3 x 1 1.20 1.59 11.45
C1 to C4, C3 to C6 16mm dia Bottom 2 x 2 x 1 5.60 1.59 35.62
C1 to C4, C3 to C6 12mm dia Bottom 2 x 1 x 1 5.60 0.89 9.97
" " 16mm dia Extras 2 x 2 x 1 1.20 1.59 7.63
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Stirrups 8mm dia 2 x 1 x 32 1.25 0.39 31.20
C7 to C10 12mm dia top 1 x 2 x 1 4.65 0.89 8.28
" " 16mm dia Extras 1 x 3 x 1 1.20 1.59 5.72
C7 to C10 16mm dia Bottom 1 x 2 x 1 4.65 1.59 14.79
C7 to C10 12mm dia Bottom 1 x 1 x 1 4.65 0.89 4.14
" " 16mm dia Extras 1 x 2 x 1 1.20 1.59 3.82
Stirrups 8mm dia 1 x 1 x 32 1.25 0.39 15.60
B5 type Beam
C8 to C11 16mm dia top 1 x 2 x 1 4.65 1.59 14.79
" " 20mm dia Extras 1 x 3 x 1 1.20 2.48 8.93
C8 to C11 16mm dia Bottom 1 x 2 x 1 4.65 1.59 14.79
C8 to C11 20mm dia Bottom 1 x 1 x 1 4.65 2.48 11.53
" " 20mm dia Extras 1 x 2 x 1 1.20 2.48 5.95
Stirrups 8mm dia 1 x 1 x 32 1.25 0.39 15.60
C6 to C9 16mm dia top 1 x 2 x 1 6.00 1.59 19.08
" " 20mm dia Extras 1 x 3 x 1 1.20 2.48 8.93
C6 to C9 16mm dia Bottom 1 x 2 x 1 6.00 1.59 19.08
C6 to C9 20mm dia Bottom 1 x 1 x 1 6.00 2.48 14.88
" " 20mm dia Extras 1 x 2 x 1 1.20 2.48 5.95
Stirrups 8mm dia 1 x 1 x 32 1.25 0.39 15.60
Roof Beams Total Qty : 830.81 Kgs
Roof Slab Reinforcement
Long span bars 8mm dia 1 x 1 x 35 14.80 0.39 202.02
Long Span bars 8mm dia 1 x 1 x 42 14.20 0.39 232.60
Short span bars 8mm dia 1 x 1 x 99 11.20 0.39 432.43
Short span bars 8mm dia 1 x 1 x 2 4.90 0.39 3.82
Support Bars 1 x 1 x 10 3.50 0.39 13.65
Roof Slab Total Qty : 884.52 Kgs
Mid Landing Beam
12mm dia top 1 x 3 x 1 2.40 0.89 6.41
12mm dia Bottom 1 x 3 x 1 2.40 0.89 6.41
Stirrups 8mm dia 1 x 1 x 16 1.25 0.39 7.80
For Stair case II nd Flight
Stair case I st flight 10mm dia top Bar
Cross 1 x 1 x 11 1.20 0.62 8.18
Stair case I st flight 10mm dia Bottom
Bar Cross 1 x 1 x 11 1.20 0.62 8.18
Stair case I st flight 10mm dia Bottom
Bar Long 1 x 1 x 6 1.60 0.62 5.95
Stair case I st flight 10mm dia Bottom
Bar Long 1 x 1 x 6 1.60 0.62 5.95
Stair case Total Qty : 48.88 Kgs
Steel Total Qty : 1764.21 Kgs 79.803 1 Kg 140789.25
6) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Roof Beams.

B1 Type Beams C9 to C14 1 x 1 x 1 2.45 0.23 0.30 0.17


C11 to C13 1 x 1 x 1 1.25 0.23 0.30 0.09
B2 Type Beams C13 to C14 1 x 1 x 1 4.50 0.23 0.30 0.31
C# to C9, C2 to C3 1 x 2 x 1 4.50 0.23 0.30 0.62
B3 Type Beams C5 to C6 1 x 1 x 1 4.50 0.23 0.30 0.31
C4 to C7, C5 to C8 1 x 2 x 1 2.60 0.23 0.30 0.36
C2 to C5 1 x 1 x 1 5.30 0.23 0.30 0.37
" " C10 to C11, C7-8, C4
to C5, C1 to C2 1 x 4 x 1 5.22 0.23 0.30 1.44
B4 Type Beams C1 to C4, C3 to C6 1 x 2 x 1 5.30 0.23 0.30 0.73
C7 to C 10 1 x 1 x 1 4.35 0.23 0.30 0.30
B5 Type Beams C8 to C11 1 x 1 x 1 4.35 0.23 0.30 0.30
C6 to C9 1 x 1 x 1 5.74 0.23 0.30 0.40
Total in Cu.Mt :: 5.40 Cu.Mt 14126.61 1 Cu.Mt 76283.69
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
7) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Roof Slab 125mm thick.

Main Slab 1 x 1 x 1 13.40 10.30 138.02


Varandah Projection 1 x 1 x 1 4.50 0.30 1.35
Total in Sq.Mt :: 139.37 Sq.Mt 1614.22 1 Sq.Mt 224973.84
8) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Stair case II nd Flight.

Stair case II nd flight


1 x 1 x 1 1.60 1.10 - 1.76
Total in Sq.Mt :: 1.76 Sq.Mt 1750.00 1 Sq.Mt 3080.00
9) Impervious coat 20mm thick over RCC roof slab surface with CM(1:3), promixed
with 1kg of water proof compound per bag of cement laid over roof when it is
green including cost of all materials, seigniorage charges, excluding conveyance
charges of materials and including all operational, incidental and labour charges
for mixing mortar, laying, rendering smooth and thread lining, curing, rounding off
junctions of wall and slab etc,, complete for finished item of work.

Qty. V. P. No. of M. B. No. :


Main Slab 1 x 1 x 1 13.40 10.30 138.02
Varandah Projection 1 x 1 x 1 4.50 0.30 1.35
Total in Sq.Mt :: 139.37 Sq.Mt 474.08 1 Sq.Mt 66072.53
10) Brick Masonry in superstructure with CM (1:8) prop: using second class bricks of
size 23 x 11 x 7 Cms from approved source having minimum crushing strength of
40 Kg/Sqcm. including cost and conveyance of all materials like cement, sand,
bricks, water etc., to site, including seigniorage charges, sales & other taxes on all
materials, all operational, incidental and labour charges such as mixing cement
mortar, constructing masonry, scaffolding charges, lift charges, curing, etc.,
complete for finished item of work.

9" Brick wall


Hall L/w 1 x 1 x 1 5.45 0.23 2.10 2.63
C/w 1 x 1 x 1 3.45 0.23 2.10 1.67
Bed Room I L/w 1 x 1 x 1 4.00 0.23 2.10 1.93
C/w 1 x 1 x 1 4.00 0.23 2.10 1.93
Bed Room II L/w 1 x 1 x 1 4.05 0.23 2.10 1.96
C/w 1 x 1 x 1 4.00 0.23 2.10 1.93
Bath & Wc 1 x 1 x 1 2.40 0.23 2.10 1.16
Kitchen C/w 1 x 1 x 1 3.45 0.23 2.10 1.67
L/w 1 x 1 x 1 4.05 0.23 2.10 1.96
Stair case room L/w 1 x 1 x 1 1.80 0.23 2.10 0.87
C/w 1 x 1 x 1 3.90 0.23 (1.80+0)/2 0.81
Deductions :
Main Door D -1 x 1 x 1 1.20 0.23 2.10 -0.58
Door D2 -1 x 1 x 1 1.05 0.23 2.10 -0.51
Windows W1 -1 x 5 x 1 1.50 0.23 1.35 -2.33
W2 -1 x 2 x 1 0.90 0.23 1.35 -0.56
KW1 -1 x 1 x 1 1.50 0.23 1.05 -0.36
KW2 -1 x 1 x 1 1.20 0.23 1.05 -0.29
Total in Cu.Mt :: 13.89 Cu.Mt 6779.83 1 Cu.Mt 94171.84
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
11) Brick Masonry in superstructure with CM (1:8) prop: using second class bricks of
size 23 x 11 x 7 Cms from approved source having minimum crushing strength of
40 Kg/Sqcm. including cost and conveyance of all materials like cement, sand,
bricks, water etc., to site, including seigniorage charges, sales & other taxes on all
materials, all operational, incidental and labour charges such as mixing cement
mortar, constructing masonry, scaffolding charges, lift charges, curing, etc.,
complete for finished item of work.

4.5" Brick wall


Hall L/w 1 x 1 x 1 4.00 0.12 2.10 1.01
Bed Room I C/w 1 x 1 x 1 4.05 0.12 2.10 1.02
Bed Room II L/w 1 x 1 x 1 4.05 0.12 2.10 1.02
C/w 1 x 1 x 1 3.95 0.12 2.10 1.00
Bath & Wc 1 x 1 x 1 2.10 0.12 2.10 0.53
1 x 1 x 1 1.20 0.12 2.10 0.30
1 x 1 x 1 1.05 0.12 2.10 0.26
Kitchen C/w 1 x 1 x 1 3.42 0.12 2.10 0.86
Pooja Room 1 x 1 x 1 1.80 0.12 2.10 0.45
1 x 1 x 1 1.20 0.12 2.10 0.30
Parapet wall L/w 1 x 1 x 1 13.40 0.12 0.90 1.45
1 x 1 x 1 13.70 0.12 0.90 1.48
C/w 1 x 1 x 1 10.30 0.12 0.90 1.11
1 x 1 x 1 4.50 0.12 0.90 0.49
1 x 1 x 1 5.80 0.12 0.90 0.63
at Stair case I st Flight 1 x 2 x 1 4.60 0.12 0.90 0.99
II nd Flight 1 x 2 x 1 1.20 0.12 0.90 0.26
at Landing 1 x 2 x 1 1.00 0.12 0.90 0.22
Deductions :
Door D2 -1 x 5 x 1 1.05 0.23 2.10 -2.54
Wc Doors D3 -1 x 2 x 1 0.75 0.23 2.00 -0.69
Total in Cu.Mt :: 10.15 Cu.Mt 6779.83 1 Cu.Mt 68815.27
12) Plain Cement Concrete M15 grade nominal mix (1:2.5:5) proportion (cement: fine
aggregate: Coarse aggregate) using 40mm, 20mm, 10mm size Hard Broken
Granite (IS383, 1970) Machine Crushed metal from approved quarry including cost
and conveyance of all materials like cement, sand, coarse aggregate, water etc. to
site, including seigniorage charges, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing concrete in Concrete
Mixer, laying, curing concrete, etc., complete for finished item of work (APSS No.
402) Steps.
Stair case steps 1 x 1 x 18 1.10 0.20 (0+0.20)/2 0.40
Total in Cu.Mt :: 0.40 Cu.Mt 6278.81 1 Cu.Mt 2486.41
13) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per IS
1786-1979) of different diameters for RCC works, including labour charges for
straightening, cutting, bending to required sizes and shapes, placing in position
with cover blocks of approved materials and size and tying and lapsplicing with
binding wire of 18 SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars including cost and
conveyance of binding wire, cover blocks and all incidental, operational, laour
charges such as cutting, bending placing in position, tying including sales and
other taxes on all materials etc., complete for finished item of work in all floors.
(APSS No.126).

Lintels
Main door 10mm dia 1 x 4 x 1 1.50 0.62 3.72
Stirrups 8mm dia 1 x 1 x 12 0.45 0.39 2.11
d2 door 10mm dia 8 x 4 x 1 1.30 0.62 25.79
Stirrups 8mm dia 8 x 1 x 10 0.45 0.39 14.04
On Windows 10 mm 1 x 5 x 4 1.80 0.62 22.32
Stirrups 8mm dia 8 x 1 x 15 0.45 0.39 21.06
1 x 2 x 4 1.20 0.62 5.95
Stirrups 8mm dia 8 x 1 x 8 0.45 0.39 11.23
1 x 1 x 4 1.80 0.62 4.46
Stirrups 8mm dia 8 x 1 x 15 0.45 0.39 21.06
1 x 1 x 4 1.50 0.62 3.72
Stirrups 8mm dia 8 x 1 x 12 0.45 0.39 16.85
Sunshades
On Windows 8 mm Long 1 x 5 x 4 1.80 0.39 14.04
Short 1 x 5 x 4 0.60 0.39 4.68
On Windows 8 mm Long 1 x 2 x 4 1.20 0.39 3.74
Short 1 x 2 x 4 0.60 0.39 1.87
On Windows 8 mm Long 1 x 1 x 4 1.80 0.39 2.81
Short 1 x 1 x 4 0.60 0.39 0.94
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
On Windows 8 mm Long 1 x 1 x 4 1.50 0.39 2.34
Short 1 x 1 x 4 0.60 0.39 0.94
183.67 Kg 79.803 1 Kg 14657.42
14) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Lintels.

On Main Door 1 x 1 x 1 1.80 0.23 0.15 0.06


On Kitchen Door 1 x 1 x 1 1.50 0.23 0.15 0.05
On Windows 1 x 6 x 1 1.80 0.23 0.15 0.37
1 x 2 x 1 1.20 0.23 0.15 0.08
1 x 2 x 1 1.20 0.23 0.15 0.08
On Doors inside 1 x 7 x 1 1.35 0.12 0.15 0.17
Total in Cu.Mt :: 0.81 Cu.Mt 14003.84 1 Cu.Mt 11343.11
15) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard suppliers
approved by the department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Sunshades.

On Windows 1 x 6 x 1 1.80 0.60 - 6.48


1 x 2 x 1 1.20 0.60 - 1.44
1 x 2 x 1 1.20 0.60 - 1.44
Total in Sq.Mt :: 9.36 Sq.Mt 1345.238 1 Sq.Mt 12591.43
16) Brick Masonry in superstructure with CM (1:8) prop: using second class bricks of
size 23 x 11 x 7 Cms from approved source having minimum crushing strength of
40 Kg/Sqcm. including cost and conveyance of all materials like cement, sand,
bricks, water etc., to site, including seigniorage charges, sales & other taxes on all
materials, all operational, incidental and labour charges such as mixing cement
mortar, constructing masonry, scaffolding charges, lift charges, curing, etc.,
complete for finished item of work.

9" Brick wall


Hall L/w 1 x 1 x 1 5.45 0.23 0.90 1.13
C/w 1 x 1 x 1 3.45 0.23 0.90 0.71
Bed Room I L/w 1 x 1 x 1 4.00 0.23 0.90 0.83
C/w 1 x 1 x 1 4.00 0.23 0.90 0.83
Bed Room II L/w 1 x 1 x 1 4.05 0.23 0.90 0.84
C/w 1 x 1 x 1 4.00 0.23 0.90 0.83
Bath & Wc 1 x 1 x 1 2.40 0.23 0.90 0.50
Kitchen C/w 1 x 1 x 1 3.45 0.23 0.90 0.71
L/w 1 x 1 x 1 4.05 0.23 0.90 0.84
Deductions :
Ventilators -1 x 2 x 1 0.90 0.23 0.60 -0.25
Lintels On Main Door -1 x 1 x 1 1.80 0.23 0.15 0.06
" On Kitchen Door -1 x 1 x 1 1.50 0.23 0.15 0.05
" On Windows -1 x 6 x 1 1.80 0.23 0.15 0.37
" " -1 x 2 x 1 1.20 0.23 0.15 0.08
" " -1 x 2 x 1 1.20 0.23 0.15 0.08
Total in Cu.Mt :: 7.61 Cu.Mt 6779.83 1 Cu.Mt 51594.51
17) Brick Masonry in superstructure with CM (1:8) prop: using second class bricks of
size 23 x 11 x 7 Cms from approved source having minimum crushing strength of
40 Kg/Sqcm. including cost and conveyance of all materials like cement, sand,
bricks, water etc., to site, including seigniorage charges, sales & other taxes on all
materials, all operational, incidental and labour charges such as mixing cement
mortar, constructing masonry, scaffolding charges, lift charges, curing, etc.,
complete for finished item of work.

4.5" Brick wall


Hall L/w 1 x 1 x 1 4.00 0.12 0.90 0.43
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Bed Room I C/w 1 x 1 x 1 4.05 0.12 0.90 0.44
Bed Room II L/w 1 x 1 x 1 4.05 0.12 0.90 0.44
C/w 1 x 1 x 1 3.95 0.12 0.90 0.43
Bath & Wc 1 x 1 x 1 2.10 0.12 0.90 0.23
1 x 1 x 1 1.20 0.12 0.90 0.13
1 x 1 x 1 1.05 0.12 0.90 0.11
Kitchen C/w 1 x 1 x 1 3.42 0.12 0.90 0.37
Pooja Room 1 x 1 x 1 1.80 0.12 0.90 0.19
1 x 1 x 1 1.20 0.12 0.90 0.13
Deductions :
Lintels on Doors -1 x 7 x 1 1.20 0.12 0.15 -0.14
Total in Cu.Mt :: 2.76 Cu.Mt 6779.83 1 Cu.Mt 18712.33
Total : 812771.10
16) Sanitory Charges 11% on total Cost 89404.82
17) Electrification Charges 9% on total Cost 73149.40
Total:- 975325.32
III rd & Part
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of
Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.

M. B. No. :
Sl. Measurements
No. Description of Item No.s
L B D
Qty Rate/Per Amount
1 2 3 4 5 6 7 8 9
1) Earth work excavation for foundations and depositing on bank for all lifts and
with an initial lead of 10m including all operational, incidental, labour charges
such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS -
20 B (APSS 308). for building foundation.

Qty. V. P. No. of M. B. No. :


F/s Steps 1 x 1 2.40 1.50 0.15 0.54
Total in Cu.Mt :: 0.54 Cu.Mt 354.63 1 Cu.Mt 191.50
2) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site,
mixing concrete in concrete mixer including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labour charges
such as laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for finished item
of work.
Qty. V. P. No. of M. B. No. :
PCC Under Steps 1 x 1 2.40 1.50 0.15 0.54
Total in Cu.Mt :: 0.54 Cu.Mt 5774.08 1 Cu.Mt 3118.00
3) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including seigniorage
charges, sales & other taxes on all materials, all operational, incidental and
labour charges such as mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc., complete for finished item of
work.
9" Brick wall
Qty. V. P. No. of M. B. No. :
Front Steps Step I 1 x 1 x 1 2.40 1.50 0.20 0.72
Step II 1 x 1 x 1 2.40 1.20 0.20 0.58
Step III 1 x 1 x 1 2.40 0.90 0.20 0.48
Step IV 1 x 1 x 1 2.40 0.60 0.20 0.48
Step V 1 x 1 x 1 2.40 0.30 0.20 0.48
Total in Cu.Mt :: 2.74 Cu.Mt 6779.83 1 Cu.Mt 18576.73
4) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including seigniorage
charges, sales & other taxes on all materials, all operational, incidental and
labour charges such as mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc., complete for finished item of
work.
4.5" Brick wall
Qty. V. P. No. of M. B. No. :
Back side wall L/w 1 x 1 x 1 3.00 0.12 1.00 0.36
Back side wall C/w 1 x 1 x 1 2.40 0.12 1.00 0.29
Total in Cu.Mt :: 0.65 Cu.Mt 6779.83 1 Cu.Mt 4406.89
5) RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire mesh &
nominal reinforcement as directed by Engineer-in-charge with dubara sponge
finishing, including cost & conveyance of all materials to site, seigniorage
charges, sales & other taxes on all materials, operational & incidental, cost
and conveyance of cement, wire mesh, water to work site, centering,
scaffolding and form work, lift charges etc., complete for finished items of
work but excluding cost of steel & its fabrication charges, for finished item of
work. (APSS No.403&903).
Qty. V. P. No. of M. B. No. :
1 x 1 x 1 13.40 - 0.45 6.03
1 x 1 x 1 13.70 - 0.45 6.16
1 x 1 x 1 10.30 - 0.45 4.63
1 x 1 x 1 5.80 - 0.45 2.61
1 x 1 x 1 4.50 - 0.45 2.02
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1 x 1 x 2 0.30 - 0.45 0.27
Total in Sq.Mt :: 21.72 Sq.Mt 1846.39 1 Sq.Mt 40103.59
6) Ceiling Plastering with CM(1:3) Prop: 12mm thick in single coat spong finish
including cost and conveyance of all materials like cement, sand, water etc.,
to site, including seigniorage charges, sales & other taxes on all materials, all
operational, incidental charges and labour charges such as mixing mortar,
finishing, curing, etc., complete for finished item of work. (APSS 901,906).

Qty. V. P. No. of M. B. No. :


Hall Living area 1 x 1 x 1 3.313.307 - 10.94
Hall dining area 1 x 1 x 1 3.31 2.40 - 7.94
Bed Room I 1 x 1 x 1 4.20 4.21 - 17.68
Bed Room II 1 x 1 x 1 4.20 4.21 - 17.68
Kitchen 1 x 1 x 1 3.31 2.70 - 8.93
Bath 1 x 1 x 1 2.10 1.20 - 2.52
Wc 1 x 1 x 1 1.05 1.20 - 1.26
Pooja Room 1 x 1 x 1 1.80 1.20 - 2.16
" " Front 1 x 1 x 1 1.51 1.20 - 1.81
Wc Front 1 x 1 x 1 3.15 1.20 - 3.78
Bath Front side 1 x 1 x 1 2.10 1.20 - 2.52
Varandah 1 x 1 x 1 2.55 3.60 - 9.18
Slab Projection Sides 1 x 1 x 2 13.70 0.90 - 24.66
Back 1 x 1 x 1 10.30 0.90 - 9.27
Front 1 x 1 x 1 5.00 0.90 - 4.50
Beam sides 1 x 2 x 3 0.90 0.30 - 1.62
Total in Sq.Mt :: 126.45 Sq.Mt 158.37 1 Sq.Mt 20025.89
7) Plastering 20mm thick in two coats with base coat of 16mm thick in CM (1:6)
and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost
and conveyance of all materials like cement, screened sand, water etc., to
site, seigniorage charges, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing mortar,scaffolding
charges, lift charges, finishing,including cutting of Grooves wherever
necessary as directed by Engineer - in - charge, curing, etc., for Uneven
Surfaces of Brick Wall complete for finished item of work. (APSS 901,903 &
904).
Qty. V. P. No. of M. B. No. :
West side walls 1 x 1 x 1 11.55 - 1.20 13.86
South side wall 1 x 1 x 1 8.12 - 1.20 9.74
East side walls 1 x 1 x 1 15.15 - 1.20 18.18
North side walls 1 x 1 x 1 4.30 - 1.20 5.16
" " 1 x 1 x 1 3.85 - 1.20 4.62
For Steps Top 1 x 1 x 5 2.40 - 0.30 3.60
Side 1 x 1 x 5 2.40 0.20 - 2.40
Stair case steps 1 x 1 x 1 0.90 0.20 - 0.18
1 x 1 x 1 0.90 0.20 - 0.18
Total in Sq.Mt :: 57.92 Sq.Mt 432.66 1 Sq.Mt 25059.67
8) Plastering 12mm thick in two coats with base coat of 9mm thick in CM (1:6)
and top coat of 3mm thick in CM (1:4) dubara sponge finish including cost
and conveyance of all materials like cement, screened sand, water etc., to
site, seigniorage charges, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing mortar,
scaffolding charges, lift charges, finishing, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, curing, etc., for
Uneven Surfaces of Brick Wall complete for finished item of work. (APSS
901,903 & 904).

A) Internal 9" brick walls :


Qty. V. P. No. of M. B. No. :
Hall Short wals 1 x 1 x 1 3.31 - 3.30 10.92
Hall Long walls 1 x 1 x 1 5.78 - 3.30 19.07
Pooja room 1 x 1 x 1 1.20 - 3.30 3.96
Kitchen Room Short wall 1 x 1 x 1 3.31 - 3.30 10.92
Kitchen Room Long wall 1 x 1 x 1 2.70 - 3.30 8.91
Bed Room II Short walls 1 x 1 x 1 4.20 - 3.30 13.86
Bed Room II Long walls 1 x 1 x 1 4.27 - 3.30 14.09
Bed Room I Short walls 1 x 1 x 1 4.20 - 3.30 13.86
Bed Room I Long walls 1 x 1 x 1 4.12 - 3.30 13.59
Bath Short wall 1 x 1 x 1 1.20 - 3.30 3.96
Wc Short wall 1 x 1 x 1 1.20 - 3.30 3.96
at stair case bath room 1 x 1 x 1 2.10 - 2.40 5.04
at stair case bath room 1 x 1 x 1 1.50 - 2.40 3.60
Window offsets 1 x 1 x 6 1.35 - 1.35 10.93
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Window offsets 1 x 1 x 4 1.35 - 1.20 6.48
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
B) Internal 4.5" brick walls :
Hall Long wals 1 x 1 x 1 6.98 - 3.30 23.03
Pooja room 1 x 1 x 1 1.80 - 3.30 5.94
Pooja room 1 x 1 x 2 1.80 - 3.30 11.88
Pooja room 1 x 1 x 1 1.20 - 3.30 3.96
Kitchen Room Short wall 1 x 1 x 1 3.31 - 3.30 10.92
Kitchen Room Long wall 1 x 1 x 1 2.70 - 3.30 8.91
Bed Room II Short walls 1 x 1 x 1 4.20 - 3.30 13.86
Bed Room II Long walls 1 x 1 x 1 4.27 - 3.30 14.09
Bed Room I Short walls 1 x 1 x 1 4.20 - 3.30 13.86
Bed Room I Long walls 1 x 1 x 1 4.12 - 3.30 13.59
Bath Long walls 1 x 1 x 2 2.10 - 3.30 13.86
Wc Long walls 1 x 1 x 2 1.05 - 3.30 6.93
283.98 Sq.Mt 411.30 1 Sq.Mt 116800.97
C) External 9" brick walls :
Back side Wall 1 x 1 x 1 8.10 - 3.30 26.73
R/s wall 1 x 1 x 1 12.25 - 3.30 40.42
L/s wall 1 x 1 x 1 11.05 - 3.30 36.46
F/s wall 1 x 1 x 1 4.40 - 3.30 14.52
F/s wall 1 x 1 x 1 3.75 - 3.30 12.37
Back side wall 1 x 1 x 2 2.40 - 1.00 4.80
" " 1 x 1 x 2 2.70 - 1.00 5.40
Stair case walls 1 x 2 x 2 4.60 - 0.90 16.56
" " 1 x 2 x 2 1.20 - 0.90 4.32
'' '' 1 x 1 x 2 1.00 - 0.90 1.80
Parapet wall L/w 1 x 1 x 2 13.40 - 1.45 38.86
1 x 1 x 2 13.70 - 1.45 39.73
C/w 1 x 1 x 2 10.30 - 1.45 29.87
1 x 1 x 2 10.30 - 1.45 29.87
Window sunshades 1 x 6 x 2 1.80 - 0.60 12.96
1 x 4 x 2 1.20 - 0.60 5.76
320.43 Sq.Mt 411.30 1 Sq.Mt 131792.86

Total : 360076.10
16) Sanitory Charges 11% on total Cost Since first bill 237412.45
17) Electrification Charges 9% on total Cost Since first bill 194246.55
Total:- 791735.10

Forest Range Officer, Forest Divisional Officer,


Komararam Yellandu
I st & Part Bill
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of
Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.

Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1) Earth work excavation for foundations and depositing on bank for all lifts and
with an initial lead of 10m including all operational, incidental, labour charges
such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS -
20 B (APSS 308). for building foundation.

Columns C3, C6, C9, C14 1 x 4 1.65 1.65 1.65 17.96


Columns C2, C5, C8, C11, C13 1 x 5 1.65 1.65 1.65 22.46
Columns C1, C4, C7, C10 1 x 4 1.65 1.65 1.60 17.42
57.84 Cu.Mt 419.35 1 Cu.Mt 24255.20
2) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site,
mixing concrete in concrete mixer including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labour charges
such as laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for finished item
of work.

PCC Under Col. Footings 1 x 13 1.65 1.65 0.15 5.31


5.31 Cu.Mt 5187.81 1 Cu.Mt 27547.27
3) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance
of steel bars, including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire, cover blocks and
all incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

For Footings Mat


10mm dia 6" c/c
F1 type C14 2 x 10 x 2 1.70 0.62 42.16
F2 Type C1,C2,C3,C4,C7,C10 2 x 10 x 6 1.70 0.62 126.48
F3 Type C5,C6,C9 2 x 10 x 3 1.70 0.62 63.24
F3 type C8 2 x 10 x 1 1.70 0.62 21.08
F4 Type CF1 C11-C13 1 x 10 x 1 1.70 0.62 10.54
F4 Type CF1 C11-C13 1 x 20 x 1 3.30 0.62 40.92
Footings Total Qty : 304.42 Kgs
Columns
12mm dia
C1 type C13, C14 1 x 2 x 6 3.00 0.89 32.04
C2 Type C1,C3,C4,C7,C10,C11 1 x 6 x 6 3.00 0.89 96.12
16mm dia
C3 Type C2,C5,C6,C9 1 x 4 6 3.00 1.59 114.48
C4 Type C8 1 x 1 x 8 3.00 1.59 38.16
8mm dia
Stirrups 1 x 11 x 20 1.05 0.39 90.09
Stirrups 1 x 2 x 20 0.60 0.39 9.36
Columns Total Qty : 380.25 Kgs
Total Qty : 684.67 Kg 92.07 1 Kg 63037.57
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
4) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Column Footings.

F1 type C14 1 x 1 1.45 1.45 0.30 0.63


F2 Type C1,C2,C3,C4,C7,C10 1 x 6 1.50 1.50 0.30 4.05
F3 Type C5,C6,C9 1 x 3 1.60 1.60 0.30 2.30
F3 type C8 1 x 1 1.60 1.60 0.30 0.77
F4 Type CF1 C11-C13 1 x 1 3.00 1.60 0.30 1.44
(0.30/3) x ((1.45² )+(0.23x0.30)+
Taper Portion 1 x 1 0.59
√(1.45²) X (0.23x0.30))
(0.30/3) x ((1.50² )+(0.23x0.30)+
Taper Portion 1 x 6 3.72
√(1.50²) X (0.23x0.30))
(0.30/3) x ((1.60² )+(0.23x0.30)+
Taper Portion 1 x 3 2.04
√(1.60²) X (0.23x0.30))
(0.30/3) x ((1.60² )+(0.23x0.30)+
Taper Portion 1 x 1 0.68
√(1.60²) X (0.23x0.30))
(0.30/3) x ((3.00x1.60)+(0.23x0.30)+
Taper Portion 1 x 1 √(3.00x1.60) X (0.23x0.30))
1.06

Total in Cu.Mt :: 17.28 Cu.Mt 10302.30 1 Cu.Mt 178023.74


5) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Columns.

Columns upto plinth beam 1 x 13 0.30 0.23 2.10 1.88


1.88 Cu.Mt 13861.28 1 Cu.Mt 26059.21
7) Earth work excavation for foundations and depositing on bank for all lifts and
with an initial lead of 10m including all operational, incidental, labour charges
such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS -
20 B (APSS 308). for building foundation.

North Side 1 x 1 12.80 0.45 0.90 5.18


South side walls 1 x 1 11.55 0.45 0.90 4.68
At varandah 1 x 1 3.60 0.45 0.90 1.46
" " 1 x 1 1.25 0.45 0.90 0.51
East side walls 1 x 1 8.10 0.45 0.90 3.28
Deduct Columns -1 x 13 1.50 0.45 0.90 -7.89
7.22 Cu.Mt 419.35 1 Cu.Mt 3027.71
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
8) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site,
mixing concrete in concrete mixer including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labour charges
such as laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for finished item
of work.

Under CRS Walls


North Side 1 x 1 12.80 0.45 0.15 0.86
South side walls 1 x 1 11.55 0.45 0.15 0.77
At varandah 1 x 1 3.60 0.45 0.15 0.24
" " 1 x 1 1.25 0.45 0.15 0.08
East side walls 1 x 1 8.10 0.45 0.15 0.54
Deduct Columns -1 x 11 0.30 0.23 0.15 -0.11
-0.78 x 2 0.23 0.23 0.15 0.01
2.39 Cu.Mt 5187.81 1 Cu.Mt 12398.87
9) Coursed Rubble Stone Masonry in CM (1:3) Prop: including cost and
conveyance of all materials like cement, sand, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental charges and labour charges such as mixing mortar, finishing,
curing, etc., complete for finished item of work. (APSS 901,906).

North Side 1 x 1 12.75 0.45 1.80 10.32


South side walls 1 x 1 11.55 0.45 1.80 9.35
At varandah 1 x 1 3.61 0.45 1.80 2.92
" " 1 x 1 1.21 0.45 1.80 0.98
East side walls 1 x 1 4.20 0.45 1.80 3.40
West side walls 1 x 1 8.18 0.45 1.80 6.62
Back side of Building 2 x 1 2.40 0.45 1.80 3.88
Back side of Building Sides 1 x 1 7.70 0.45 1.80 6.23
Deduct Columns -1 x 11 0.30 0.23 1.80 -1.36
-0.78 x 2 0.23 0.23 1.80 -0.14
Total in Cu.Mt :: 42.20 Cu.Mt 4624.05 1 Cu.Mt 195134.91
10) Earth work excavation for foundations and depositing on bank for all lifts and
with an initial lead of 10m including all operational, incidental, labour charges
such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS -
20 B (APSS 308). for building foundation.
Stair case Column 1 x 1 1.20 1.20 1.00 1.44
1.44 Cu.Mt 419.35 1 Cu.Mt 603.86
11) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site,
mixing concrete in concrete mixer including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labour charges
such as laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for finished item
of work.
PCC Under Col. Footings 1 x 1 1.20 1.20 0.15 0.22
0.22 Cu.Mt 5187.81 1 Cu.Mt 1141.32
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
12) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance
of steel bars, including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire, cover blocks and
all incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

For Footings Mat


10mm dia 6" c/c
Stair case Column 2 x 10 x 2 1.70 0.62 42.16
Footings Total Qty : 42.16 Kgs
Columns
12mm dia
Stair case Column 1 x 2 x 6 3.75 0.89 40.05
8mm dia
Stirrups 1 x 1 x 25 1.05 0.39 10.24
Columns Total Qty : 50.29 Kgs
Total Qty : 92.45 Kg 92.07 1 Kg 8511.87
13) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Column Footings.

Stair case Col. Footing 1 x 1 1.45 1.45 0.30 0.63


(0.30/3) x ((1.45² )+(0.23x0.30)+
Taper Portion 1 x 1 0.59
√(1.45²) X (0.23x0.30))
Total in Cu.Mt :: 1.22 Cu.Mt 10302.33 1 Cu.Mt 12568.84
14) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Columns.

Columns upto plinth beam 1 x 1 0.30 0.23 0.90 0.06


0.06 Cu.Mt 13861.28 1 Cu.Mt 831.68
15) Filling with Gravel in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15cm thick, consolidating each deposited layer
by watering and ramming including all operational, incidental, labour
charges, seignorage charges, hire charges of T & P etc., complete for
finished item of work. (APSS NO. 309 & 310).
Inside Basement 1 x 1 11.49 7.61 1.20 104.92
Varandah Portion 1 x 1 3.46 1.04 1.20 4.32
109.24 Cu.Mt 463.33 1 Cu.Mt 50614.17
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
16) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site,
mixing concrete in concrete mixer including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labour charges
such as laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for finished item
of work.
Under Plinth Beam
Internal walls at Kitchen L/w 1 x 1 4.15 0.45 0.15 0.28
C/w 1 x 1 4.35 0.45 0.15 0.29
Pooja Room 1 x 1 2.10 0.45 0.15 0.14
Bed Room 1 1 x 1 3.60 0.45 0.15 0.24
" " 1 x 1 3.49 0.45 0.15 0.23
Tolet at Bed Room 1 1 x 1 2.10 0.45 0.15 0.14
1 x 1 1.20 0.45 0.15 0.08
Bed Room 2 1 x 1 4.20 0.45 0.15 0.28
1 x 1 4.26 0.45 0.15 0.28
Tolet at Bed Room 1 1 x 1 2.10 0.45 0.15 0.14
1 x 1 1.20 0.45 0.15 0.08
2.18 Cu.Mt 5187.81 1 Cu.Mt 11309.43
17) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance
of steel bars, including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire, cover blocks and
all incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

Plinth Beams
12mm Out side PB
C1 to C10 1 x 2 x 3 11.90 0.89 63.54
C3 to C14 1 x 2 x 3 13.00 0.89 69.42
C1 to C3 1 x 2 x 3 8.40 0.89 44.85
C10 to C11 1 x 2 x 3 4.80 0.89 25.63
C11 to C13 1 x 2 x 3 1.80 0.89 9.61
C13 to C14 1 x 2 x 3 4.05 0.89 21.62
C11 to C9-14 1 x 1 x 1 4.05 0.89 3.60
Stair case Beam 1 x 2 x 3 1.20 0.89 6.40
In side PB
Brd Room 1 C/w 1 x 2 x 3 4.20 0.89 22.42
In Between Bed Rooms 1 x 2 x 3 5.35 0.89 28.56
Brd Room 2 C/w 1 x 2 x 3 3.85 0.89 20.55
Toilets L/w 2 x 2 x 3 2.55 0.89 27.23
Toilets C/w 2 x 2 x 3 1.65 0.89 17.62
Kitchen & Pooja Room 1 x 2 x 3 4.55 0.89 24.29
In Between Kitchen & Pooja 1 x 2 x 3 3.35 0.89 17.88
8mm for Stirrups
C1 to C10 1 x 1 x 99 1.05 0.39 40.54
C3 to C14 1 x 1 x 108 1.05 0.39 44.22
C1 to C3 1 x 1 x 70 1.05 0.39 28.66
C10 to C11 1 x 1 x 40 1.05 0.39 16.38
C11 to C13 1 x 1 x 15 1.05 0.39 6.14
C13 to C14 1 x 1 x 34 1.05 0.39 13.92
C11 to C9-14 1 x 1 x 34 1.05 0.39 13.92
Stair case Beam 1 x 1 x 10 1.05 0.39 4.09
Brd Room 1 C/w 1 x 1 x 35 1.05 0.39 14.33
In Between Bed Rooms 1 x 1 x 45 1.05 0.39 18.42
Brd Room 2 C/w 1 x 1 x 32 1.05 0.39 13.10
Toilets L/w 2 x 1 x 21 1.05 0.39 17.19
Toilets C/w 2 x 1 x 14 1.05 0.39 11.46
Kitchen & Pooja Room 1 x 1 x 38 1.05 0.39 15.56
In Between Kitchen & Pooja 1 x 1 x 28 1.05 0.39 11.46
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Total in Kg:: 672.61 Kg 92.07 1 Kg 61927.20
18) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing
etc., complete. For Plinth Beam.
C1 to C10 1 x 1 11.60 0.23 0.30 0.80
C3 to C14 1 x 1 13.15 0.23 0.30 0.91
C1 to C3 1 x 1 7.75 0.23 0.30 0.53
C10 to C11 1 x 1 4.20 0.23 0.30 0.29
C11 to C13 1 x 1 1.00 0.23 0.30 0.07
C13 to C14 1 x 1 3.65 0.23 0.30 0.25
C11 to C9-14 1 x 1 3.65 0.23 0.30 0.25
Stair case Beam at GL 1 x 1 1.20 0.23 0.30 0.08
Brd Room 1 C/w 1 x 1 4.05 0.23 0.30 0.28
In Between Bed Rooms 1 x 1 4.80 0.23 0.30 0.33
Brd Room 2 C/w 1 x 1 3.40 0.23 0.30 0.23
Toilets L/w 2 x 1 2.10 0.23 0.30 0.29
Toilets C/w 2 x 1 1.20 0.23 0.30 0.17
Kitchen & Pooja Room 1 x 1 4.10 0.23 0.30 0.28
In Between Kitchen & Pooja 1 x 1 2.70 0.23 0.30 0.18
Total in Cu.Mt :: 4.94 Cu.Mt 14056.85 1 Cu.Mt 69440.84
Total : 746433.69
19) Sanitory Charges 6% on total Cost 44786.02
20) Electrification Charges 7% on total Cost 52250.36
Total:- 843470.07
II nd & Part Bill
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of
Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.

Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance
of steel bars, including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire, cover blocks and
all incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

Columns
12mm dia
C1 type C13, C14 1 x 2 x 6 4.20 0.89 44.86
C2 Type C1,C3,C4,C7,C10,C11 1 x 6 x 6 4.20 0.89 134.57
16mm dia
C3 Type C2,C5,C6,C9 1 x 4 6 4.20 1.59 160.27
C4 Type C8 1 x 1 x 8 4.20 1.59 53.42
8mm dia
Stirrups 1 x 11 x 28 1.05 0.39 126.13
Stirrups 1 x 2 x 28 0.60 0.39 13.10
Columns Total Qty : 532.35 Kgs
For Stair case I st Flight
Stair case I st flight 10mm dia
top Bar Cross 1 x 1 x 27 1.35 0.62 22.60
Stair case I st flight 10mm dia
Bottom Bar Cross 1 x 1 x 27 1.35 0.62 22.60
Stair case I st flight 10mm dia
Top Bar Long 1 x 1 x 7 4.10 0.62 17.79
Stair case I st flight 10mm dia
Bottom Bar Long 1 x 1 x 7 4.10 0.62 17.79
Landing 10 mm dia Top 1 x 1 x 12 2.10 0.62 15.62
Landing 10 mm dia Bottom 1 x 1 x 12 2.10 0.62 15.62
Landing 10 mm dia Top 1 x 1 x 20 1.20 0.62 14.88
Landing 10 mm dia Bottom 1 x 1 x 20 1.20 0.62 14.88
Landing Beam 1 x 2 x 3 2.30 0.89 12.28
Stair case Total Qty : 154.06 Kgs
Total Qty : 686.41 Kg 92.07 1 Kg 63197.77
2) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the department
including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Columns.
Columns 1 x 11 0.30 0.23 3.00 2.27
Circuler Columns 2 x 0.785 0.23 0.23 3.00 0.24
Stair case column 1 x 1 0.23 0.30 2.10 0.14
2.65 Cu.Mt 13861.28 1 Cu.Mt 36732.39
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
3) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the department
including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Mid Landing Beam.

Mid landing 1 x 1 x 1 2.30 0.23 0.30 0.16


Total in Cu.Mt :: 0.16 Cu.Mt 14339.59 1 Cu.Mt 2294.33
4) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the department
including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Stair case I st Flight.

Stair case I st flight 1 x 1 x 1 4.95 1.20 - 5.94


Mid landing 1 x 1 x 1 2.30 2.00 - 4.60
Total in Sq.Mt :: 10.54 Sq.Mt 1637.56 1 Sq.Mt 17259.88
5) Vibrated Plain Cement Concrete (1:4:8) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site,
mixing concrete in concrete mixer including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labour charges
such as laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for finished item
of work.

Varandah 1 x 1 3.40 2.20 0.23 1.72


Living/Din 1 x 1 4.80 3.40 0.23 3.75
Pooja 1 x 1 2.70 1.20 0.23 0.74
Kitchen 1 x 1 2.70 2.80 0.23 1.73
Bed Room 1 1 x 1 4.30 4.20 0.23 4.15
Bed room 2 1 x 1 3.60 3.40 0.23 2.81
Bath 1 & 2 1 x 2 2.10 1.20 0.23 1.15
Front side Toilets 1 x 1 1.20 1.90 0.23 0.52
1 x 1 1.20 1.30 0.23 0.35
Total in Cu.Mt :: 16.92 Cu.Mt 4818.78 1 Cu.Mt 81533.76
6) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance
of steel bars, including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire, cover blocks and
all incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

For Roof Beams


B1 type Beam
C14 to C9 12mm dia top 1 x 2 x 1 3.15 0.89 5.61
C14 to C9 12mm dia Bottom 1 x 2 x 1 3.15 0.89 5.61
Stirrups 8mm dia 1 x 1 x 21 1.25 0.39 10.24
C11 to C13 12mm dia top 1 x 2 x 1 2.00 0.89 3.56
C11 to C13 12mm dia Bottom 1 x 2 x 1 2.00 0.89 3.56
Stirrups 8mm dia 1 x 1 x 13 1.25 0.39 6.34
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
B2 type Beam
C13 to C14, C9 to C11-8, C2
to C3 12mm dia top 3 x 2 x 1 5.00 0.89 26.70
" " 16mm dia Extras 3 x 2 x 1 1.20 1.59 11.45
C13 to C14, C9 to C11-8, C2
to C3 12mm dia Bottom
3 x 2 x 1 5.00 0.89 26.70
" " 12mm dia Extras 3 x 2 x 1 1.20 0.89 6.41
Stirrups 8mm dia 3 x 1 x 33 1.25 0.39 48.26
B3 type Beam
C5 to C6 12mm dia top 1 x 2 x 1 5.00 0.89 8.90
" " 16mm dia Extras 1 x 2 x 1 1.20 1.59 3.82
C5 to C6 16mm dia Bottom 1 x 2 x 1 5.00 1.59 15.90
" " 16mm dia Extras 1 x 2 x 1 1.20 1.59 3.82
Stirrups 8mm dia 1 x 1 x 33 1.25 0.39 16.09
C10 to C11, C7 to C8, C4 to
C5, C1 to C2 12mm dia top 4 x 2 x 1 5.65 0.89 40.23
" " 16mm dia Extras 4 x 2 x 1 1.20 1.59 15.26
C10 to C11, C7 to C8, C4 to
C5, C1 to C2 16mm dia 4 x 2 x 1 5.65 1.59 71.87
Bottom
" " 16mm dia Extras 4 x 2 x 1 1.20 1.59 15.26
Stirrups 8mm dia 4 x 1 x 38 1.25 0.39 74.10
C4 to C7, C5 to C8 12mm dia
top
2 x 2 x 1 3.00 0.89 10.68
" " 16mm dia Extras 2 x 2 x 1 1.20 1.59 7.63
C4 to C7, C5 to C8 16mm dia
Bottom 2 x 2 x 1 3.00 1.59 19.08
" " 16mm dia Extras 2 x 2 x 1 1.20 1.59 7.63
Stirrups 8mm dia 2 x 1 x 20 1.25 0.39 19.50
C2 to C5 12mm dia top 1 x 2 x 1 5.70 0.89 10.15
" " 16mm dia Extras 1 x 2 x 1 1.20 1.59 3.82
C2 to C5 16mm dia Bottom 1 x 2 x 1 5.70 1.59 18.13
" " 16mm dia Extras 1 x 2 x 1 1.20 1.59 3.82
Stirrups 8mm dia 1 x 1 x 38 1.25 0.39 18.53
B4 type Beam
C1 to C4, C3 to C6 12mm dia
top 2 x 2 x 1 5.70 0.89 20.29
" " 16mm dia Extras 2 x 3 x 1 1.20 1.59 11.45
C1 to C4, C3 to C6 16mm dia
Bottom 2 x 2 x 1 5.70 1.59 36.25
C1 to C4, C3 to C6 12mm dia
Bottom 2 x 1 x 1 5.70 0.89 10.15
" " 16mm dia Extras 2 x 2 x 1 1.20 1.59 7.63
Stirrups 8mm dia 2 x 1 x 38 1.25 0.39 37.05
C7 to C10 12mm dia top 1 x 2 x 1 6.00 0.89 10.68
" " 16mm dia Extras 1 x 3 x 1 1.20 1.59 5.72
C7 to C10 16mm dia Bottom 1 x 2 x 1 6.00 1.59 19.08
C7 to C10 12mm dia Bottom 1 x 1 x 1 6.00 0.89 5.34
" " 16mm dia Extras 1 x 2 x 1 1.20 1.59 3.82
Stirrups 8mm dia 1 x 1 x 40 1.25 0.39 19.50
B5 type Beam
C8 to C11 16mm dia top 1 x 2 x 1 4.80 1.59 15.26
" " 20mm dia Extras 1 x 3 x 1 1.20 2.48 8.93
C8 to C11 16mm dia Bottom 1 x 2 x 1 4.80 1.59 15.26
C8 to C11 20mm dia Bottom 1 x 1 x 1 4.80 2.48 11.90
" " 20mm dia Extras 1 x 2 x 1 1.20 2.48 5.95
Stirrups 8mm dia 1 x 1 x 32 1.25 0.39 15.60
C6 to C9 16mm dia top 1 x 2 x 1 6.20 1.59 19.72
" " 20mm dia Extras 1 x 3 x 1 1.20 2.48 8.93
C6 to C9 16mm dia Bottom 1 x 2 x 1 6.20 1.59 19.72
C6 to C9 20mm dia Bottom 1 x 1 x 1 6.20 2.48 15.38
" " 20mm dia Extras 1 x 2 x 1 1.20 2.48 5.95
Stirrups 8mm dia 1 x 1 x 32 1.25 0.39 15.60
Roof Beams Total Qty : 883.82 Kgs
Roof Slab Reinforcement
Long span bars 8mm dia 1 x 1 x 47 15.50 0.39 284.12
Long Span bars 8mm dia 1 x 1 x 21 13.30 0.39 108.93
Short span bars 8mm dia 1 x 1 x 103 7.65 0.39 307.30
Short span bars 8mm dia 1 x 1 x 90 3.75 0.39 131.63
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
Support Bars 1 x 1 x 10 3.50 0.39 13.65
Roof Slab Total Qty : 845.63 Kgs
Mid Landing Beam
12mm dia top 1 x 3 x 1 2.40 0.89 6.41
12mm dia Bottom 1 x 3 x 1 2.40 0.89 6.41
Stirrups 8mm dia 1 x 1 x 16 1.00 0.39 6.24
For Stair case II nd Flight
Stair case II nd flight 10mm
dia top Bar Cross 1 x 1 x 11 1.20 0.62 8.18
Stair case II nd flight 10mm
dia Bottom Bar Cross 1 x 1 x 11 1.20 0.62 8.18
Stair case II nd flight 10mm
dia Bottom Bar Long 1 x 1 x 6 1.60 0.62 5.95
Stair case II nd flight 10mm
dia Bottom Bar Long 1 x 1 x 6 1.60 0.62 5.95
Stair case Total Qty : 47.32 Kgs
Steel Total Qty : 1776.77 Kgs 92.07 1 Kg 163587.21
7) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the department
including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Roof Beams.
B1 Type Beams C9 to C14 1 x 1 x 1 2.75 0.23 0.30 0.19
C11 to C13 1 x 1 x 1 1.55 0.23 0.30 0.11
B2 Type Beams C13 to C14 1 x 1 x 1 7.05 0.23 0.30 0.49
C# to C9, C2 to C3 1 x 2 x 1 4.50 0.23 0.30 0.62
B3 Type Beams C5 to C6 1 x 1 x 1 4.50 0.23 0.30 0.31
C4 to C7, C5 to C8 1 x 2 x 1 2.60 0.23 0.30 0.36
C2 to C5 1 x 1 x 1 5.30 0.23 0.30 0.37
" C10 to C11, C7-C8,
C4 to C5, C1 to C2 1 x 4 x 1 5.22 0.23 0.30 1.44
B4 Type Beams C1 to C4, C3 to
C6 1 x 2 x 1 5.30 0.23 0.30 0.73
C7 to C 10 1 x 1 x 10.235.55 0.30 0.38
B5 Type Beams C8 to C11 1 x 1 x 10.234.35 0.30 0.30
C6 to C9 1 x 1 x 10.235.75 0.30 0.40
Total in Cu.Mt :: 5.70 Cu.Mt 14339.59 1 Cu.Mt 81735.66
8) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the department
including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Roof Slab 125mm thick.

Main Slab 1 x 1 x 1 12.70


10.20 129.54
Varandah Projection 1 x 1 x 1 1.207.05 8.46
Total in Sq.Mt :: 138.00 Sq.Mt 1637.56 1 Sq.Mt 225983.28
9) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the department
including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Stair case II nd Flight.

Stair case II nd flight


Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1 x 1 x 1 2.30 1.22 - 2.81
Total in Sq.Mt :: 2.81 Sq.Mt 1637.56 1 Sq.Mt 4601.54
10) Impervious coat 20mm thick over RCC roof slab surface with CM(1:3),
promixed with 1kg of water proof compound per bag of cement laid over roof
when it is green including cost of all materials, seigniorage charges, excluding
conveyance charges of materials and including all operational, incidental and
labour charges for mixing mortar, laying, rendering smooth and thread lining,
curing, rounding off junctions of wall and slab etc,, complete for finished item
of work.
Main Slab 1 x 1 x 1 12.70 10.20 129.54
Varandah Projection 1 x 1 x 1 7.05 1.20 8.46
Total in Sq.Mt :: 138.00 Sq.Mt 554.83 1 Sq.Mt 76566.54
11) Plain Cement Concrete M15 grade nominal mix (1:2.5:5) proportion (cement:
fine aggregate: Coarse aggregate) using 40mm, 20mm, 10mm size Hard
Broken Granite (IS383, 1970) Machine Crushed metal from approved quarry
including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including seigniorage charges, sales & other
taxes on all materials, all operational, incidental and labour charges such as
mixing concrete in Concrete Mixer, laying, curing concrete, etc., complete for
finished item of work (APSS No. 402) Steps.
I st Flight 1 x 15 1.10 0.28 (0+0.15)/2 0.35
II nd Flight 1 x 7 1.10 0.28 (0+0.15)/2 0.16
Total in Cu.Mt :: 0.51 Cu.Mt 5641.32 1 Cu.Mt 2877.07
Total : 756369.43
12) Sanitory Charges 6% on total Cost 45382.17
13) Electrification Charges 7% on total Cost 52945.86
Total:- 854697.46
III rd Part Bill
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of
Paloncha Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete for
finished item of work.
9" Brick wall
Hall L/w 1 x 1 x 1 5.45 0.23 2.10 2.63
C/w 1 x 1 x 1 3.45 0.23 2.10 1.67
Bed Room I L/w 1 x 1 x 1 4.00 0.23 2.10 1.93
C/w 1 x 1 x 1 4.00 0.23 2.10 1.93
Bed Room II L/w 1 x 1 x 1 4.05 0.23 2.10 1.96
C/w 1 x 1 x 1 4.00 0.23 2.10 1.93
Bath & Wc 1 x 1 x 1 2.40 0.23 2.10 1.16
Kitchen C/w 1 x 1 x 1 3.45 0.23 2.10 1.67
L/w 1 x 1 x 1 4.05 0.23 2.10 1.96
Stair case room L/w 1 x 1 x 1 1.80 0.23 2.10 0.87
(1.80+0)/
C/w 1 x 1 x 1 3.90 0.23 2 0.81
Deductions :
Main Door D -1 x 1 x 1 1.20
0.23 2.10 -0.58
Door D2 -1 x 1 x 1 1.05
0.23 2.10 -0.51
Windows W1 -1 x 5 x 1 1.50
0.23 1.35 -2.33
W2 -1 x 2 x 1 0.90
0.23 1.35 -0.56
KW1 -1 x 1 x 1 1.50
0.23 1.05 -0.36
KW2 -1 x 1 x 1 1.20
0.23 1.05 -0.29
Total in Cu.Mt :: 13.89 Cu.Mt 8359.33 1 Cu.Mt 116111.09
2) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete for
finished item of work.
4.5" Brick wall
Hall L/w 1 x 1 x 1 4.00 0.12 2.10 1.01
Bed Room I C/w 1 x 1 x 1 4.05 0.12 2.10 1.02
Bed Room II L/w 1 x 1 x 1 4.05 0.12 2.10 1.02
C/w 1 x 1 x 1 3.95 0.12 2.10 1.00
Bath & Wc 1 x 1 x 1 2.10 0.12 2.10 0.53
1 x 1 x 1 1.20 0.12 2.10 0.30
1 x 1 x 1 1.05 0.12 2.10 0.26
Kitchen C/w 1 x 1 x 1 3.42 0.12 2.10 0.86
Pooja Room 1 x 1 x 1 1.80 0.12 2.10 0.45
1 x 1 x 1 1.20 0.12 2.10 0.30
Parapet wall L/w 1 x 1 x 1 13.40 0.12 0.90 1.45
1 x 1 x 1 13.70 0.12 0.90 1.48
C/w 1 x 1 x 1 10.30 0.12 0.90 1.11
1 x 1 x 1 4.50 0.12 0.90 0.49
1 x 1 x 1 5.80 0.12 0.90 0.63
at Stair case I st Flight 1 x 2 x 1 4.60 0.12 0.90 0.99
II nd Flight 1 x 2 x 1 1.20 0.12 0.90 0.26
at Landing 1 x 2 x 1 1.00 0.12 0.90 0.22
Deductions :
Door D2 -1 x 5 x 1 1.05 0.23 2.10 -2.54
Wc Doors D3 -1 x 2 x 1 0.75 0.23 2.00 -0.69
Total in Cu.Mt :: 10.15 Cu.Mt 8359.33 1 Cu.Mt 84847.20
3) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade
as per IS 1786-1979) of different diameters for RCC works, including
labour charges for straightening, cutting, bending to required sizes and
shapes, placing in position with cover blocks of approved materials and
size and tying and lapsplicing with binding wire of 18 SWG, forming grills
for reinforcement work as per approved designs and drawings, including
cost and conveyance of steel bars, including all wastages such as
overlaps, couplings, chairs, spacer bars including cost and conveyance of
binding wire, cover blocks and all incidental, operational, laour charges
such as cutting, bending placing in position, tying including sales and
other taxes on all materials etc., complete for finished item of work in all
floors. (APSS No.126).

Lintels
Main door 10mm dia 1 x 4 x 1 1.50 0.62 3.72
Stirrups 8mm dia 1 x 1 x 12 0.45 0.39 2.11
d2 door 10mm dia 8 x 4 x 1 1.30 0.62 25.79
Stirrups 8mm dia 8 x 1 x 10 0.45 0.39 14.04
On Windows 10 mm 1 x 5 x 4 1.80 0.62 22.32
Stirrups 8mm dia 8 x 1 x 15 0.45 0.39 21.06
1 x 2 x 4 1.20 0.62 5.95
Stirrups 8mm dia 8 x 1 x 8 0.45 0.39 11.23
1 x 1 x 4 1.80 0.62 4.46
Stirrups 8mm dia 8 x 1 x 15 0.45 0.39 21.06
1 x 1 x 4 1.50 0.62 3.72
Stirrups 8mm dia 8 x 1 x 12 0.45 0.39 16.85
Sunshades
On Windows 8 mm Long 1 x 5 x 4 1.80 0.39 14.04
Short 1 x 5 x 4 0.60 0.39 4.68
On Windows 8 mm Long 1 x 2 x 4 1.20 0.39 3.74
Short 1 x 2 x 4 0.60 0.39 1.87
On Windows 8 mm Long 1 x 1 x 4 1.80 0.39 2.81
Short 1 x 1 x 4 0.60 0.39 0.94
On Windows 8 mm Long 1 x 1 x 4 1.50 0.39 2.34
Short 1 x 1 x 4 0.60 0.39 0.94
183.67 Kg 92.070 1 Kg 16910.50
4) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Lintels.

On Main Door 1 x 1 x 1 1.80


0.23 0.15 0.06
On Kitchen Door 1 x 1 x 1 1.50
0.23 0.15 0.05
On Windows 1 x 6 x 1 1.80
0.23 0.15 0.37
1 x 2 x 1 1.20
0.23 0.15 0.08
1 x 2 x 1 1.20
0.23 0.15 0.08
On Doors inside 1 x 7 x 1 1.35
0.12 0.15 0.17
Total in Cu.Mt :: 0.81 Cu.Mt 14505.02 1 Cu.Mt 11749.07
5) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished item of work (APSS No.
402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering,
laying concrete, vibrating, curing etc., complete. For Sunshades.

On Windows 1 x 6 x 1 1.80 0.60 - 6.48


1 x 2 x 1 1.20 0.60 - 1.44
1 x 2 x 1 1.20 0.60 - 1.44
Total in Sq.Mt :: 9.36 Sq.Mt 1408.742 1 Sq.Mt 13185.83
6) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete for
finished item of work.
9" Brick wall
Hall L/w 1 x 1 x 1 5.45 0.23 0.90 1.13
C/w 1 x 1 x 1 3.45 0.23 0.90 0.71
Bed Room I L/w 1 x 1 x 1 4.00 0.23 0.90 0.83
C/w 1 x 1 x 1 4.00 0.23 0.90 0.83
Bed Room II L/w 1 x 1 x 1 4.05 0.23 0.90 0.84
C/w 1 x 1 x 1 4.00 0.23 0.90 0.83
Bath & Wc 1 x 1 x 1 2.40 0.23 0.90 0.50
Kitchen C/w 1 x 1 x 1 3.45 0.23 0.90 0.71
L/w 1 x 1 x 1 4.05 0.23 0.90 0.84
Deductions :
Ventilators -1 x 2 x 1 0.90
0.23 0.60 -0.25
Lintels On Main Door -1 x 1 x 1 1.80
0.23 0.15 0.06
" On Kitchen Door -1 x 1 x 1 1.50
0.23 0.15 0.05
" On Windows -1 x 6 x 1 1.80
0.23 0.15 0.37
" " -1 x 2 x 1 1.20
0.23 0.15 0.08
" " -1 x 2 x 1 1.20
0.23 0.15 0.08
Total in Cu.Mt :: 7.61 Cu.Mt 8359.33 1 Cu.Mt 63614.50
7) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete for
finished item of work.
4.5" Brick wall
Hall L/w 1 x 1 x 1 4.00 0.12 0.90 0.43
Bed Room I C/w 1 x 1 x 1 4.05 0.12 0.90 0.44
Bed Room II L/w 1 x 1 x 1 4.05 0.12 0.90 0.44
C/w 1 x 1 x 1 3.95 0.12 0.90 0.43
Bath & Wc 1 x 1 x 1 2.10 0.12 0.90 0.23
1 x 1 x 1 1.20 0.12 0.90 0.13
1 x 1 x 1 1.05 0.12 0.90 0.11
Kitchen C/w 1 x 1 x 1 3.42 0.12 0.90 0.37
Pooja Room 1 x 1 x 1 1.80 0.12 0.90 0.19
1 x 1 x 1 1.20 0.12 0.90 0.13
Deductions :
Lintels on Doors -1 x 7 x 1 1.20 0.12 0.15 -0.14
Total in Cu.Mt :: 2.76 Cu.Mt 8359.33 1 Cu.Mt 23071.75
8) Earth work excavation for foundations and depositing on bank for all lifts
and with an initial lead of 10m including all operational, incidental, labour
charges such as shoring ,sheeting, planking, strutting, etc. complete for
finished item of work including seigniorage excluding dewatering charges
etc as per SS - 20 B (APSS 308). for building foundation.

F/s Steps 1 x 1 2.40


1.50 0.15 0.54
Total in Cu.Mt :: 0.54 Cu.Mt 354.63 1 Cu.Mt 191.50
9) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine
aggregate: Coarse aggregate) using 40mm size Hard Broken Granite
(IS383, 1970) machine crushed metal from approved quarry including
cost and conveyance of all materials like cement, sand, coarse aggregate,
water etc. to site, mixing concrete in concrete mixer including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental, and labour charges such as laying and ramming concrete in
layers in position not exceeding 15cm, finishing top surface, curing
concrete, etc., complete for finished item of work.

PCC Under Steps 1 x 1 2.40 1.50 0.15 0.54


Total in Cu.Mt :: 0.54 Cu.Mt 5187.81 1 Cu.Mt 2801.42
10) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete for
finished item of work.

9" Brick wall


Front Steps Step I 1 x 1 x 1 2.40
1.50 0.20 0.72
Step II 1 x 1 x 1 2.40
1.20 0.20 0.58
Step III 1 x 1 x 1 2.40
0.90 0.20 0.48
Step IV 1 x 1 x 1 2.40
0.60 0.20 0.48
Step V 1 x 1 x 1 2.40
0.30 0.20 0.48
Total in Cu.Mt :: 2.74 Cu.Mt 8359.33 1 Cu.Mt 22904.56
11) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete for
finished item of work.
4.5" Brick wall
Back side wall L/w 1 x 1 x 1 3.000.12 1.00 0.36
Back side wall C/w 1 x 1 x 1 2.400.12 1.00 0.29
Total in Cu.Mt :: 0.65 Cu.Mt 8359.33 1 Cu.Mt 5433.56
12) RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire mesh
& nominal reinforcement as directed by Engineer-in-charge with dubara
sponge finishing, including cost & conveyance of all materials to site,
seigniorage charges, sales & other taxes on all materials, operational &
incidental, cost and conveyance of cement, wire mesh, water to work site,
centering, scaffolding and form work, lift charges etc., complete for
finished items of work but excluding cost of steel & its fabrication
charges, for finished item of work. (APSS No.403&903).
1 x 1 x 1
13.40 - 0.45 6.03
1 x 1 x 1
13.70 - 0.45 6.16
1 x 1 x 1
10.30 - 0.45 4.63
1 x 1 x 15.80 - 0.45 2.61
1 x 1 x 14.50 - 0.45 2.02
1 x 1 x 20.30 - 0.45 0.27
Total in Sq.Mt :: 21.72 Sq.Mt 2237.82 1 Sq.Mt 48605.45
13) Ceiling Plastering with CM(1:3) Prop: 12mm thick in single coat spong
finish including cost and conveyance of all materials like cement, sand,
water etc., to site, including seigniorage charges, sales & other taxes on
all materials, all operational, incidental charges and labour charges such
as mixing mortar, finishing, curing, etc., complete for finished item of
work. (APSS 901,906).
Hall Living area 1 x 1 x 1 3.31 3.307 - 10.94
Hall dining area 1 x 1 x 1 3.31 2.40 - 7.94
Bed Room I 1 x 1 x 1 4.20 4.21 - 17.68
Bed Room II 1 x 1 x 1 4.20 4.21 - 17.68
Kitchen 1 x 1 x 1 3.31 2.70 - 8.93
Bath 1 x 1 x 1 2.10 1.20 - 2.52
Wc 1 x 1 x 1 1.05 1.20 - 1.26
Pooja Room 1 x 1 x 1 1.80 1.20 - 2.16
" " Front 1 x 1 x 1 1.51 1.20 - 1.81
Wc Front 1 x 1 x 1 3.15 1.20 - 3.78
Bath Front side 1 x 1 x 1 2.10 1.20 - 2.52
Varandah 1 x 1 x 1 2.55 3.60 - 9.18
Slab Projection Sides 1 x 1 x 2 13.70 0.90 - 24.66
Back 1 x 1 x 1 10.30 0.90 - 9.27
Front 1 x 1 x 1 5.00 0.90 - 4.50
Beam sides 1 x 2 x 3 0.90 0.30 - 1.62
Total in Sq.Mt :: 126.45 Sq.Mt 168.83 1 Sq.Mt 21348.55
14) Plastering 20mm thick in two coats with base coat of 16mm thick in CM
(1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish
including cost and conveyance of all materials like cement, screened sand,
water etc., to site, seigniorage charges, sales & other taxes on all
materials, all operational, incidental and labour charges such as mixing
mortar,scaffolding charges, lift charges, finishing,including cutting of
Grooves wherever necessary as directed by Engineer - in - charge,
curing, etc., for Uneven Surfaces of Brick Wall complete for finished
item of work. (APSS 901,903 & 904).
West side walls 1 x 1 x 1
11.55 - 1.20 13.86
South side wall 1 x 1 x 18.12 - 1.20 9.74
East side walls 1 x 1 x 1
15.15 - 1.20 18.18
North side walls 1 x 1 x 14.30 - 1.20 5.16
" " 1 x 1 x 13.85 - 1.20 4.62
For Steps Top 1 x 1 x 52.40 - 0.30 3.60
Side 1 x 1 x 52.40 0.20 - 2.40
Stair case steps 1 x 1 x 10.90 0.20 - 0.18
1 x 1 x 10.90 0.20 - 0.18
Total in Sq.Mt :: 57.92 Sq.Mt 506.25 1 Sq.Mt 29322.00
15) Plastering 12mm thick in two coats with base coat of 9mm thick in CM
(1:6) and top coat of 3mm thick in CM (1:4) dubara sponge finish
including cost and conveyance of all materials like cement, screened sand,
water etc., to site, seigniorage charges, sales & other taxes on all
materials, all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, finishing, including cutting of
Grooves wherever necessary as directed by Engineer - in - charge,
curing, etc., for Uneven Surfaces of Brick Wall complete for finished
item of work. (APSS 901,903 & 904).

A) Internal 9" brick walls :


Hall Short wals 1 x 1 x 1 3.31 - 3.30 10.92
Hall Long walls 1 x 1 x 1 5.78 - 3.30 19.07
Pooja room 1 x 1 x 1 1.20 - 3.30 3.96
Kitchen Room Short wall 1 x 1 x 1 3.31 - 3.30 10.92
Kitchen Room Long wall 1 x 1 x 1 2.70 - 3.30 8.91
Bed Room II Short walls 1 x 1 x 1 4.20 - 3.30 13.86
Bed Room II Long walls 1 x 1 x 1 4.27 - 3.30 14.09
Bed Room I Short walls 1 x 1 x 1 4.20 - 3.30 13.86
Bed Room I Long walls 1 x 1 x 1 4.12 - 3.30 13.59
Bath Short wall 1 x 1 x 1 1.20 - 3.30 3.96
Wc Short wall 1 x 1 x 1 1.20 - 3.30 3.96
at stair case bath room 1 x 1 x 1 2.10 - 2.40 5.04
at stair case bath room 1 x 1 x 1 1.50 - 2.40 3.60
Window offsets 1 x 1 x 6 1.35 - 1.35 10.93
Window offsets 1 x 1 x 4 1.35 - 1.20 6.48
B) Internal 4.5" brick walls :
Hall Long wals 1 x 1 x 1 6.98 - 3.30 23.03
Pooja room 1 x 1 x 1 1.80 - 3.30 5.94
Pooja room 1 x 1 x 2 1.80 - 3.30 11.88
Pooja room 1 x 1 x 1 1.20 - 3.30 3.96
Kitchen Room Short wall 1 x 1 x 1 3.31 - 3.30 10.92
Kitchen Room Long wall 1 x 1 x 1 2.70 - 3.30 8.91
Bed Room II Short walls 1 x 1 x 1 4.20 - 3.30 13.86
Bed Room II Long walls 1 x 1 x 1 4.27 - 3.30 14.09
Bed Room I Short walls 1 x 1 x 1 4.20 - 3.30 13.86
Bed Room I Long walls 1 x 1 x 1 4.12 - 3.30 13.59
Bath Long walls 1 x 1 x 2 2.10 - 3.30 13.86
Wc Long walls 1 x 1 x 2 1.05 - 3.30 6.93
283.98 Sq.Mt 491.51 1 Sq.Mt 139579.01
C) External 9" brick walls :
Back side Wall 1 x 1 x 1 8.10 - 3.30 26.73
R/s wall 1 x 1 x 1 12.25 - 3.30 40.42
L/s wall 1 x 1 x 1 11.05 - 3.30 36.46
F/s wall 1 x 1 x 1 4.40 - 3.30 14.52
F/s wall 1 x 1 x 1 3.75 - 3.30 12.37
Back side wall 1 x 1 x 2 2.40 - 1.00 4.80
" " 1 x 1 x 2 2.70 - 1.00 5.40
Stair case walls 1 x 2 x 2 4.60 - 0.90 16.56
" " 1 x 2 x 2 1.20 - 0.90 4.32
'' '' 1 x 1 x 2 1.00 - 0.90 1.80
Parapet wall L/w 1 x 1 x 2 13.40 - 1.45 38.86
1 x 1 x 2 13.70 - 1.45 39.73
C/w 1 x 1 x 2 10.30 - 1.45 29.87
1 x 1 x 2 10.30 - 1.45 29.87
Window sunshades 1 x 6 x 2 1.80 - 0.60 12.96
1 x 4 x 2 1.20 - 0.60 5.76
320.43 Sq.Mt 491.51 1 Sq.Mt 157494.55

Total 757170.54
IV th & Part Bill
Name of the work : Construction of FSO/ Dy.R.O. Quarter at Suraram Beat of Suraram Section of Paloncha
Range of Paloncha Division, during 2022-23 under CAMPA - NPV scheme.

Sl. Description of Item Measurements


No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
1) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete for
finished item of work.
9" Brick wall
R/s Steps Step I 1 x 1 x 1 1.20 1.20 0.20 0.29
Step II 1 x 1 x 1 1.20 0.90 0.20 0.22
Step III 1 x 1 x 1 1.20 0.60 0.20 0.14
Step VI 1 x 1 x 1 1.20 0.30 0.20 0.07
At Kitchen 1 x 4 x 1 0.30 0.12 1.20 0.17
At Pooja Room 1 x 2 x 1 0.30 0.12 0.30 0.02
In Hall 1 x 1 x 1 0.30 0.12 1.80 0.06
Total in Cu.Mt :: 0.97 Cu.Mt 8359.33 1 Cu.Mt 8108.55
2) Plastering 20mm thick in two coats with base coat of 16mm thick in CM
(1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including
cost and conveyance of all materials like cement, screened sand, water
etc., to site, seigniorage charges, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing
mortar,scaffolding charges, lift charges, finishing,including cutting of
Grooves wherever necessary as directed by Engineer - in - charge, curing,
etc., for Uneven Surfaces of Brick Wall complete for finished item of
work. (APSS 901,903 & 904).
For Steps Top 1 x 4 x 1 1.20 - 0.20 0.96
1 x 4 x 1 1.20 0.30 - 1.44
" " 1 x 1 x 1 3.85 - 1.20 4.62
At Kitchen 1 x 4 x 1 0.30 - 1.20 1.44
At Pooja Room 1 x 2 x 1 0.30 - 0.30 0.18
In Hall 1 x 1 x 1 0.30 - 1.80 0.54
Total in Sq.Mt :: 9.18 Sq.Mt 506.25 1 Sq.Mt 4647.38
3) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating,
curing etc., complete. Shelves 50mm thick.

In Kitchen 1 x 1 x 1 1.80 0.30 - 0.54


1 x 1 x 1 1.60 0.30 - 0.48
Pooja Room 1 x 1 x 1 1.20 0.30 - 0.36
Hall 1 x 3 x 1 1.80 0.30 - 1.62
Bed Room 1 & 2 L/w 1 x 3 x 1 1.80 0.30 - 1.62
C/w 1 x 3 x 1 2.10 0.30 - 1.89
Total in Sq.Mt :: 6.51 Sq.Mt 432.66 1 Sq.Mt 2816.62
4) Flooring with adanga Marbles of I st quality of size not exceeding 0.457 x
0.457m laid over CC Flooring bed set over 20mm thcik CM(1:8) drop kase
coat and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with
white cement paste mixed with pigment of matching shade including cost
and conveyance of all materials like cement, sand, water, tiles, etc. to site,
seigniorage charges, sales and other taxes on all materials, and all
opertional, incidental and all labour charges such as mixing of cement
mortar, laying in position, curing, lift charges etc., complete for finished
item of work in all floors.

Hall Living area 1 x 1 x 1 3.31 3.307 - 10.94


Hall dining area 1 x 1 x 1 3.31 2.40 - 7.94
Bed Room I 1 x 1 x 1 4.20 4.21 - 17.68
Bed Room II 1 x 1 x 1 4.20 4.21 - 17.68
Kitchen 1 x 1 x 1 3.31 2.70 - 8.93
Pooja Room 1 x 1 x 1 1.80 1.20 - 2.16
" " Front 1 x 1 x 1 1.51 1.20 - 1.81
Wc Front 1 x 1 x 1 3.15 1.20 - 3.78
Bath Front side 1 x 1 x 1 2.10 1.20 - 2.52
Varandah 1 x 1 x 1 2.55 3.60 - 9.18
Total in Sq.Mt :: 82.62 Sq.Mt 1167.51 1 Sq.Mt 96459.68
Skirting
Hall Living area 1 x 1 x 2 (3.31+3.307) 0.10 1.32
Hall dining area 1 x 1 x 2 (3.31+2.40) 0.10 1.14
Bed Room I 1 x 1 x 1 (4.20+4.21) 0.10 0.84
Bed Room II 1 x 1 x 1 (4.20+4.21) 0.10 0.84
Kitchen 1 x 1 x 1 (3.31+2.70) 0.10 0.60
Pooja Room 1 x 1 x 1 (1.80+1.20) 0.10 0.30
" " Front 1 x 1 x 1 (1.51+1.20) 0.10 0.27
Wc Front 1 x 1 x 1 (3.15+1.20) 0.10 0.43
Bath Front side 1 x 1 x 1 (2.10+1.20) 0.10 0.33
Varandah 1 x 1 x 1 (2.55+3.60) 0.10 0.61
Total in Sq.Mt :: 6.68 Sq.Mt 673.09 1 Sq.Mt 4496.24
5) Providing and fixing non skid ceramic tiles for flooring over and inclusive of
20mm thick base plaster in cement morter 1:5 (1 cement : 5 coarse sand)
including a floating cement slurry including grouting/ filling the joints with
white cement slurry mixed with matching, pigment, curing, cleaning and
leaving/making necessary holes for sanitory connection complete but
including cost of cement and tiles in all heights/level for skirting complete
for finished item of work.
1 x 1 x 1 2.10 1.20 - 2.52
1 x 1 x 1 1.05 1.20 - 1.26
Total in Sq.Mt :: 3.78 Sq.Mt 911.42 1 Sq.Mt 3445.17
6) Dadooing to walls with glazed red or white full body ceramic wall tiles of
size 200 x 300 mm / 245 mm x 325 mm and thickness 6 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour
and finish in all shades and designs, any brand as approved by Engineer -
in - charge and set over a base coat of CM (1:5), 12mm thick and neat
cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white cement
paste mixed with pigment of matching shade including cost and
conveyance of all materials like cement, sand, water, tiles, etc. to site,
seigniorage charges, sales and other taxes on all materials, and all
opertional, incidental and all labour charges such as mixing of cement
mortar, laying in position, curing, lift charges etc., complete for finished
item of work in all floors

1 x 1 x 1 (2.10+1.20) 2.10 6.93


1 x 1 x 1 (1.05+1.20) 2.10 6.93
Total in Sq.Mt :: 13.86 Sq.Mt 922.40 1 Sq.Mt 12784.46
7) Painting to new walls with 2 coats of water proof cement paint of apporved
brand and shade as approved by the Engineer - in - Charge over a base
coat of approved cement primer grade II exterior making three coats in all
to give an even shade after thourughly brushing the surface to remove all
dirt and remains of loose powdered materials, including cost and
conveyance of all materials, cost of brushes, water to site, etc., sales &
other taxes, all operational, incidental, labour charges etc. complete for
finished item of work as per SS 912 for internal walls.

Hall Living area 1 x 1 x 1 3.31 3.307 - 10.94


Hall dining area 1 x 1 x 1 3.31 2.40 - 7.94
Bed Room I 1 x 1 x 1 4.20 4.21 - 17.68
Bed Room II 1 x 1 x 1 4.20 4.21 - 17.68
Kitchen 1 x 1 x 1 3.31 2.70 - 8.93
Bath 1 x 1 x 1 2.10 1.20 - 2.52
Wc 1 x 1 x 1 1.05 1.20 - 1.26
Pooja Room 1 x 1 x 1 1.80 1.20 - 2.16
" " Front 1 x 1 x 1 1.51 1.20 - 1.81
Wc Front 1 x 1 x 1 3.15 1.20 - 3.78
Bath Front side 1 x 1 x 1 2.10 1.20 - 2.52
Varandah 1 x 1 x 1 2.55 3.60 - 9.18
Slab Projection Sides 1 x 1 x 2 13.70 0.90 - 24.66
Back 1 x 1 x 1 10.30 0.90 - 9.27
Front 1 x 1 x 1 5.00 0.90 - 4.50
Beam sides 1 x 2 x 3 0.90 0.30 - 1.62
Total in Sq.Mt :: 126.45 Sq.Mt 252.13 1 Sq.Mt 31881.84
8) Painting to new walls with 2 coats of water proof cement paint of apporved
brand and shade as approved by the Engineer - in - Charge over a base
coat of approved cement primer grade II exterior making three coats in all
to give an even shade after thourughly brushing the surface to remove all
dirt and remains of loose powdered materials, including cost and
conveyance of all materials, cost of brushes, water to site, etc., sales &
other taxes, all operational, incidental, labour charges etc. complete for
finished item of work as per SS 912 for internal walls.

A) Internal 9" brick walls :


Hall Short wals 1 x 1 x 1 3.31 - 3.30 10.92
Hall Long walls 1 x 1 x 1 5.78 - 3.30 19.07
Pooja room 1 x 1 x 1 1.20 - 3.30 3.96
Kitchen Room Short wall 1 x 1 x 1 3.31 - 3.30 10.92
Kitchen Room Long wall 1 x 1 x 1 2.70 - 3.30 8.91
Bed Room II Short walls 1 x 1 x 1 4.20 - 3.30 13.86
Bed Room II Long walls 1 x 1 x 1 4.27 - 3.30 14.09
Bed Room I Short walls 1 x 1 x 1 4.20 - 3.30 13.86
Bed Room I Long walls 1 x 1 x 1 4.12 - 3.30 13.59
Bath Short wall 1 x 1 x 1 1.20 - 3.30 3.96
Wc Short wall 1 x 1 x 1 1.20 - 3.30 3.96
at stair case bath room 1 x 1 x 1 2.10 - 2.40 5.04
at stair case bath room 1 x 1 x 1 1.50 - 2.40 3.60
Window offsets 1 x 1 x 6 1.35 - 1.35 10.93
Window offsets 1 x 1 x 4 1.35 - 1.20 6.48
B) Internal 4.5" brick walls :
Hall Long wals 1 x 1 x 1 6.98 - 3.30 23.03
Pooja room 1 x 1 x 1 1.80 - 3.30 5.94
Pooja room 1 x 1 x 2 1.80 - 3.30 11.88
Pooja room 1 x 1 x 1 1.20 - 3.30 3.96
Kitchen Room Short wall 1 x 1 x 1 3.31 - 3.30 10.92
Kitchen Room Long wall 1 x 1 x 1 2.70 - 3.30 8.91
Bed Room II Short walls 1 x 1 x 1 4.20 - 3.30 13.86
Bed Room II Long walls 1 x 1 x 1 4.27 - 3.30 14.09
Bed Room I Short walls 1 x 1 x 1 4.20 - 3.30 13.86
Bed Room I Long walls 1 x 1 x 1 4.12 - 3.30 13.59
Bath Long walls 1 x 1 x 2 2.10 - 3.30 13.86
Wc Long walls 1 x 1 x 2 1.05 - 3.30 6.93
283.98 Sq.Mt 141.85 1 Sq.Mt 40282.56
C) External 9" brick walls :
Basement
West side walls 1 x 1 x 1 11.55 - 1.20 13.86
South side wall 1 x 1 x 1 8.12 - 1.20 9.74
East side walls 1 x 1 x 1 15.15 - 1.20 18.18
North side walls 1 x 1 x 1 4.30 - 1.20 5.16
" " 1 x 1 x 1 3.85 - 1.20 4.62
Back side Wall 1 x 1 x 1 8.10 - 3.30 26.73
R/s wall 1 x 1 x 1 12.25 - 3.30 40.42
L/s wall 1 x 1 x 1 11.05 - 3.30 36.46
F/s wall 1 x 1 x 1 4.40 - 3.30 14.52
F/s wall 1 x 1 x 1 3.75 - 3.30 12.37
Back side wall 1 x 1 x 2 2.40 - 1.00 4.80
" " 1 x 1 x 2 2.70 - 1.00 5.40
Stair case walls 1 x 2 x 2 4.60 - 0.90 16.56
" " 1 x 2 x 2 1.20 - 0.90 4.32
'' '' 1 x 1 x 2 1.00 - 0.90 1.80
Parapet wall L/w 1 x 1 x 2 13.40 - 1.45 38.86
1 x 1 x 2 13.70 - 1.45 39.73
C/w 1 x 1 x 2 10.30 - 1.45 29.87
1 x 1 x 2 10.30 - 1.45 29.87
Window sunshades 1 x 6 x 2 1.80 - 0.60 12.96
1 x 4 x 2 1.20 - 0.60 5.76
371.99 Sq.Mt 141.85 1 Sq.Mt 52766.78
9) Timber shall be of the kind as specified, may be teak, shisham, sal,
deodar,etc., the timber shall be of best quality, well seasoned and free
from sap knots, warps, cracks and other defects, all wood work shall be
planed and neatly and truly finished to the exact dimensions. all joints be
neat and strong, truly and accurately fitted and glued before being fitted
together. Chunkhats : The Chunkhats shall be formed and joined by motise
and tenon joint with head wooden pins and the joints shall be of coated
with white lead before being fitted together.

1 x 1 1.20 - 2.10 1.00


1 x 5 0.96 - 2.05 5.00
Total in Sq.Mt :: 6.00 Each 3970.00 1 Each 23820.00
10) Providing and fixing 30mm thick Solid panel PVC door shutter consisting of
frame made out of M.S. tubes of 19 gauge thickness and size of 19mm x
19mm for stiles, & 15mm x 15mm for top & bottom rails. M.S. frame shall
have a coat of steel primers of approved make and manufacture. M.S.
frame shall be covered with 5mm thick heat molded PVC ‘C’ channel of size
30 x 50mm forming stiles, and 5mm thick, 75mm wide PVC sheets for top
rail, lock rail & bottom rail on either side, and 10mm (5mm x 2) thick,
20mm wide cross PVC sheet as gap insert for top rail & bottom rail.
Paneling of 5mm thick PVC sheet to be fitted in the M.S. frame welded /
sealed to the stiles & rails with 30mm wide x 5mm thick PVC sheet beading
on either side, and joined together with solvent cement adhesive etc. An
additional 5mm thick PVC strip of 20mm width is to be stuck on the interior
side of the ‘C’ Channel using PVC solvent adhesive. Complete as per
direction of Engineer-in-charge, manufacturer’s specification & drawing for
finished item of work

Bath rooms door 1 x 2 0.80 - 1.90 3.04


Pooja Room Door 1 x 1 0.80 - 2.03 1.62
Toilet under stair case 1 x 1 0.95 - 2.10 2.00
Total in Sq.Mt :: 6.66 Sq.Mt 2618.00 1 Sq.Mt 17435.88
11) Supplying and fixing fully glazed anodized aluminium hinged type window
with fan light as per drawing using standard outer frame
38.5x33x21x2.5mm thick and central mullion of size
59(3mm)x33(4mm)x21(3mm) using 5mm thick, glass fitted with suitable
aluminium glazing clips and rubber beading including supplying and fixing
friction hinges (2np.s per shutter), handle with lock(1 no. per shutter), incl
cost and conveyance to site of aluminium sections, glass rubber beading,
fixtures etc., including labour charges for manufacturing window, fixing in
position using wooden blocks and sheet metalscrews etc., complete for
finished item of work.

Hall window 1 x 1 1.46 - 1.37 2.00


Bed Room 2 1 x 2 1.52 - 1.30 3.95
Bed Room 1 1 x 2 0.90 - 1.32 2.37
Hall 1 x 2 1.52 - 1.37 4.16
Kitchen window 1 x 1 1.20 - 1.50 1.80
1 x 1 1.04 - 1.50 1.56
Total in Sq.Mt :: 15.84 Sq.Mt 7485.00 1 Sq.Mt 118562.40
12) Painting to New wood work with two coats of ready mixed Synthetic
Enamel paints in all shades Grade - I having VOC (Volatile Organic
Compound) content less than 50 grams/ liter first quality all shades to
give an even shade over base coatof wood Primer finishing with putty for
wood work after thouroughly brushing the surface to remove all remains
including cost and conveyance of all materials to site, sales & other taxes,
all operational, incidental and labour charges etc., complete for finished
item of work.(3 coats) (APSS No. 1201 & 1212).in All Floors

1 x 1 1.20 - 2.10 2.52


1 x 5 0.96 - 2.05 9.84
Total in Sq.Mt :: 12.36 Sq.Mt 2227.29 1 Sq.Mt 27529.30
13) Supply and fixing of M.S.Grill of size with outer angular frame of rolled
steel of ISA 2525 of size 25mm x 25mm x 4mm welded with safety bars
of 45 x 25mm Square pipes at 150mm centre to centre horizontally and
verticlally including red oxide primer of grade-I quality, sales and other
taxes, cost and conveyance of all materials to site, all labour charges and
fixing in position etc., complete for finished item of work.
Hall window 1 x 1 1.46 - 1.37 2.00
Bed Room 2 1 x 2 1.52 - 1.30 3.95
Bed Room 1 1 x 2 0.90 - 1.32 2.37
Hall 1 x 2 1.52 - 1.37 4.16
Kitchen window 1 x 1 1.20 - 1.50 1.80
1 x 1 1.04 - 1.50 1.56
Total in Sq.Mt :: 15.84 Sq.Mt 2500.00 1 Sq.Mt 39600.00

Total : 484636.86
14) Sanitory Charges 11% on total Cost Since first bill 53310.05
15) Electrification Charges 9% on total Cost Since first bill 43617.32
Total:- 581564.23
I st & Part Bill
Name of the work : Construction of Ground Floor with R.C.C. at Yeducharlapalli Venkatapuram

Sl. Description of Item Measurements


No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
1) Earth work excavation for foundations and depositing on bank for
all lifts and with an initial lead of 10m including all operational,
incidental, labour charges such as shoring ,sheeting, planking,
strutting, etc. complete for finished item of work including
seigniorage excluding dewatering charges etc as per SS - 20 B
(APSS 308). for building foundation.
Columns C1 type 1 x 10 1.65 1.65 1.50 40.83
Columns C2 type 1 x 6 1.35 1.35 1.50 16.40
57.23 Cu.Mt 419.35 1 Cu.Mt 23999.40
2) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine
aggregate: Coarse aggregate) using 40mm size Hard Broken
Granite (IS383, 1970) machine crushed metal from approved quarry
including cost and conveyance of all materials like cement, sand,
coarse aggregate, water etc. to site, mixing concrete in concrete
mixer including seigniorage charges, sales & other taxes on all
materials, all operational, incidental, and labour charges such as
laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for
finished item of work.

PCC Under Col. Footings 1 x 10 1.65 1.65 0.15 4.08


1 x 6 1.35 1.35 0.15 1.64
5.72 Cu.Mt 5187.81 1 Cu.Mt 29674.27
3) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500
grade as per IS 1786-1979) of different diameters for RCC works,
including labour charges for straightening, cutting, bending to
required sizes and shapes, placing in position with cover blocks of
approved materials and size and tying and lapsplicing with binding
wire of 18 SWG, forming grills for reinforcement work as per
approved designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps, couplings,
chairs, spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, laour charges such as
cutting, bending placing in position, tying including sales and other
taxes on all materials etc., complete for finished item of work in all
floors. (APSS No.126).

For Footings Mat


10mm dia 6" c/c
F1 type 10 x 10 x 2 1.70 0.62 210.80
F2 type 6 x 10 x 2 1.55 0.62 115.32
Footings Total Qty : 326.12 Kgs
Columns
20mm dia
C1 type 10 x 1 x 6 4.32 2.48 642.82
16mm dia
C1 Type 10 x 1 x 6 4.32 1.59 412.13
C2 Type 6 x 1 x 6 4.32 1.59 247.28
8mm dia
Stirrups 10 x 29 x 1 1.60 0.39 179.71
Stirrups 6 x 29 x 1 1.30 0.39 87.61
Columns Total Qty : 1569.55 Kgs
Total Qty : 1895.67 Kg 92.07 1 Kg 174534.34
Sl. Description of Item Measurements
No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
4) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from
approved quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., to site
and including Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing
etc.,complete but excluding cost of steel and its fabrication charges
for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Column Footings.

F1 type 10 x 1 1.55 1.55 0.45 10.81


F2 Type 6 x 1 1.35 1.35 0.45 4.92
Total in Cu.Mt :: 15.73 Cu.Mt 10302.30 1 Cu.Mt 162055.18
5) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from
approved quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., to site
and including Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing
etc.,complete but excluding cost of steel and its fabrication charges
for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Columns.

Columns upto plinth


beam
1 x 10 0.30 0.45 1.80 2.43
Columns upto plinth
beam
1 x 6 0.23 0.30 1.80 0.74
3.17 Cu.Mt 13861.28 1 Cu.Mt 43940.26
Sl. Description of Item Measurements
No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
8) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine
aggregate: Coarse aggregate) using 40mm size Hard Broken
Granite (IS383, 1970) machine crushed metal from approved quarry
including cost and conveyance of all materials like cement, sand,
coarse aggregate, water etc. to site, mixing concrete in concrete
mixer including seigniorage charges, sales & other taxes on all
materials, all operational, incidental, and labour charges such as
laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for
finished item of work.

Under CRS Walls


1 x 2 22.40 0.45 0.15 3.02
1 x 2 9.00 0.45 0.15 1.21
Deduct Columns -1 x 10 0.30 0.45 0.15 -0.20
" " -1 x 6 0.23 0.30 0.15 -0.06
3.97 Cu.Mt 5187.81 1 Cu.Mt 20595.61
9) Coursed Rubble Stone Masonry in CM (1:3) Prop: including cost and
conveyance of all materials like cement, sand, water etc., to site,
including seigniorage charges, sales & other taxes on all materials,
all operational, incidental charges and labour charges such as
mixing mortar, finishing, curing, etc., complete for finished item of
work. (APSS 901, 906).

1 x 2 22.40 0.45 0.60 12.09


1 x 2 9.00 0.45 0.60 4.86
Deduct Columns -1 x 10 0.30 0.45 0.15 -0.20
" " -1 x 6 0.23 0.30 0.15 -0.06
Total in Cu.Mt :: 16.69 Cu.Mt 4624.05 1 Cu.Mt 77175.39
17) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500
grade as per IS 1786-1979) of different diameters for RCC works,
including labour charges for straightening, cutting, bending to
required sizes and shapes, placing in position with cover blocks of
approved materials and size and tying and lapsplicing with binding
wire of 18 SWG, forming grills for reinforcement work as per
approved designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps, couplings,
chairs, spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, laour charges such as
cutting, bending placing in position, tying including sales and other
taxes on all materials etc., complete for finished item of work in all
floors. (APSS No.126).

Plinth Beams (Outer)


16mm dia
Main Beam L/w 2 x 2 x 3 22.40 1.59 427.39
C/w 2 x 2 x 3 9.00 1.59 171.72
Internal Beams
12mm dia
L/w 1 x 2 x 3 9.00 0.89 48.06
C/w 2 x 2 x 3 2.40 0.89 25.63

8mm dia
Stirrups 1 x 1 x 150 1.25 0.39 73.13
Stirrups 1 x 1 x 60 1.25 0.39 29.25
Stirrups 1 x 1 x 60 1.25 0.39 29.25
Stirrups 1 x 1 x 16 1.25 0.39 7.80
812.23 Kg 92.070 1 Kg 74782.02
Sl. Description of Item Measurements
No.s Qty Rate/Per Amount
No. L B D
1 2 3 4 5 6 7 8 9
18) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded
machine crushed hard granite metal (coarse aggregate) from
approved quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., to site
and including Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing
etc.,complete but excluding cost of steel and its fabrication charges
for finished item of work (APSS No. 402) with minimum cement
content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete,
vibrating, curing etc., complete. For Plinth Beam.

Main Beams L/w 2 x 1 22.40 0.23 0.30 3.09


2 x 1 9.00 0.23 0.30 1.24
1 x 1 9.00 0.23 0.23 0.48
2 x 1 2.40 0.23 0.23 0.25
Total in Cu.Mt :: 5.06 Cu.Mt 14056.85 1 Cu.Mt 71127.66
II nd & Part Bill
Name of the work : Construction of Ground Floor with R.C.C. at Yeducharlapalli Venkatapuram

Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Columns.

Columns C1 type 10 x 1 0.30 0.45 3.00 4.05


Columns C2 type 6 x 1 0.23 0.30 3.00 1.24
5.29 Cu.Mt 13861.28 1 Cu.Mt 73326.17
2) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Mid Landing Beam.

Mid landing 1 x 1 x 1 2.60 0.23 0.30 0.18


Total in Cu.Mt :: 0.18 Cu.Mt 14339.59 1 Cu.Mt 2581.13
4) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Stair case I st Flight.

Stair case I st flight 1 x 1 x 1 5.10 1.25 - 6.38


Mid landing 1 x 1 x 1 2.60 2.02 - 5.25
Total in Sq.Mt :: 11.63 Sq.Mt 1637.56 1 Sq.Mt 19044.82
5) Vibrated Plain Cement Concrete (1:4:8) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site, mixing
concrete in concrete mixer including seigniorage charges, sales & other taxes
on all materials, all operational, incidental, and labour charges such as laying
and ramming concrete in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete for finished item of work.

Hall 1 x 1 20.00 9.00 0.15 27.00


Total in Cu.Mt :: 27.00 Cu.Mt 4818.78 1 Cu.Mt 130107.06
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
6) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying
and lapsplicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps, couplings, chairs, spacer
bars including cost and conveyance of binding wire, cover blocks and all
incidental, operational, laour charges such as cutting, bending placing in
position, tying including sales and other taxes on all materials etc., complete
for finished item of work in all floors. (APSS No.126).

For Roof Beams


16mm dia
Main Beam L/w 2 x 2 x 3 22.40 1.59 427.39
C/w 2 x 2 x 3 9.00 1.59 171.72
Internal Beams
12mm dia
L/w 1 x 2 x 3 9.00 0.89 48.06
C/w 2 x 2 x 3 2.40 0.89 25.63

8mm dia
Stirrups 1 x 1 x 150 1.65 0.39 96.53
Stirrups 1 x 1 x 60 1.65 0.39 38.61
Stirrups 1 x 1 x 60 1.65 0.39 38.61
Stirrups 1 x 1 x 16 1.65 0.39 10.30
Roof Beams Total Qty : 856.85 Kgs
Roof Slab Reinforcement
Long span bars 10mm dia 1 x 1 x 68 22.80 0.62 961.25
Short span bars 8mm dia 1 x 1 x 152 10.20 0.39 604.66
Support Bars 1 x 3 x 5 3.50 0.39 20.48
Roof Slab Total Qty : 1586.39 Kgs
Mid Landing Beam
12mm dia top 1 x 3 x 1 2.75 0.89 7.34
12mm dia Bottom 1 x 3 x 1 2.75 0.89 7.34
Stirrups 8mm dia 1 x 1 x 16 1.00 0.39 6.24
For Stair case II nd Flight
Stair case II nd flight 10mm dia
top Bar Cross 1 x 1 x 15 1.20 0.62 11.16
Stair case II nd flight 10mm dia
Bottom Bar Cross 1 x 1 x 15 1.20 0.62 11.16
Stair case II nd flight 10mm dia
Bottom Bar Long 1 x 1 x 8 2.30 0.62 11.41
Stair case II nd flight 10mm dia
Bottom Bar Long 1 x 1 x 8 2.30 0.62 11.41
Stair case Total Qty : 66.06 Kgs
Steel Total Qty : 2509.30 Kgs 92.070 1 Kg 231031.25
7) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Roof Beams.

Main Beam L/w 1 x 2 x 1 22.80 0.23 0.30 3.15


C/w 1 x 2 x 1 10.20 0.23 0.30 1.41
Internal Beams L/s 1 x 1 x 1 10.20 0.23 0.30 0.70
C/s 1 x 2 x 1 2.40 0.23 0.30 0.33
Total in Cu.Mt :: 5.59 Cu.Mt 14339.59 1 Cu.Mt 80158.31
Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
8) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Roof Slab 125mm thick.

Main Slab 1 x 1 x 1 22.80 10.20 232.56


Total in Sq.Mt :: 232.56 Sq.Mt 1637.56 1 Sq.Mt 380830.95
9) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. For Stair case II nd Flight.

Stair case II nd flight


1 x 1 x 1 2.30 1.20 - 2.76
Total in Sq.Mt :: 2.76 Sq.Mt 1637.56 1 Sq.Mt 4519.67
10) Impervious coat 20mm thick over RCC roof slab surface with CM(1:3),
promixed with 1kg of water proof compound per bag of cement laid over roof
when it is green including cost of all materials, seigniorage charges, excluding
conveyance charges of materials and including all operational, incidental and
labour charges for mixing mortar, laying, rendering smooth and thread lining,
curing, rounding off junctions of wall and slab etc,, complete for finished item
of work.
Main Slab 1 x 1 x 1 22.80 10.20 232.56
Total in Sq.Mt :: 232.56 Sq.Mt 554.83 1 Sq.Mt 129031.26
11) Plain Cement Concrete M15 grade nominal mix (1:2.5:5) proportion (cement:
fine aggregate: Coarse aggregate) using 40mm, 20mm, 10mm size Hard
Broken Granite (IS383, 1970) Machine Crushed metal from approved quarry
including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including seigniorage charges, sales & other
taxes on all materials, all operational, incidental and labour charges such as
mixing concrete in Concrete Mixer, laying, curing concrete, etc., complete for
finished item of work (APSS No. 402) Steps.
I st Flight 1 x 15 1.20 0.28 (0+0.15)/2 0.38
II nd Flight 1 x 7 1.20 0.28 (0+0.15)/2 0.18
Total in Cu.Mt :: 0.56 Cu.Mt 5641.32 1 Cu.Mt 3159.14

Total : 1053789.76
III rd Part Bill
Name of the work : Construction of Ground Floor with R.C.C. at Yeducharlapalli Venkatapuram

Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including seigniorage
charges, sales & other taxes on all materials, all operational, incidental and
labour charges such as mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc., complete for finished item of
work.

Main Hall L/w 1 x 2 x 1 20.00 0.23 3.00 27.60


Main Hall C/w 1 x 2 x 1 9.00 0.23 3.00 12.42
Deductions :
Main Door D1 -1 x 1 x 1 1.50 0.23 2.10 -0.72
Windows W1 -1 x 8 x 1 1.50 0.23 1.35 -3.73
Total in Cu.Mt :: 35.57 Cu.Mt 8359.33 1 Cu.Mt 297341.37
11) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including seigniorage
charges, sales & other taxes on all materials, all operational, incidental and
labour charges such as mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc., complete for finished item of
work.
4.5" Brick wall
Internal Walls L/w 1 x 1 x 1 9.00 0.23 3.00 6.21
C/w 1 x 1 x 1 2.40 0.23 3.00 1.66
Deductions :
D2 -1 x 1 x 4 0.800.23 2.10 -1.55
W2 -1 x 2 x 1 0.900.23 1.20 -0.50
Total in Cu.Mt :: 5.82 Cu.Mt 8359.33 1 Cu.Mt 48651.30
13) Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as
per IS 1786-1979) of different diameters for RCC works, including labour
charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and
tying and lapsplicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings, including cost
and conveyance of steel bars, including all wastages such as overlaps,
couplings, chairs, spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, laour charges such as cutting,
bending placing in position, tying including sales and other taxes on all
materials etc., complete for finished item of work in all floors. (APSS
No.126).

Lintels
Main door D1 10mm dia 5 x 4 x 1 1.60 0.62 19.84
Stirrups 8mm dia 1 x 1 x 11 0.65 0.39 2.79
D2 door 10mm dia 2 x 4 x 1 1.50 0.62 7.44
Stirrups 8mm dia 2 x 1 x 10 0.65 0.39 5.07
On Windows W1 10 mm 3 x 4 x 1 2.90 0.62 21.58
Stirrups 8mm dia 3 x 1 x 19 0.65 0.39 14.45
On Windows W2 10 mm 3 x 4 x 1 2.20 0.62 16.37
Stirrups 8mm dia 3 x 1 x 15 0.62 0.39 10.88
On Windows W3 10 mm 2 x 4 x 1 1.90 0.62 9.42
Stirrups 8mm dia 2 x 1 x 13 0.65 0.39 6.59
On Windows KW1 10 mm 1 x 4 x 1 2.20 0.62 5.46
Stirrups 8mm dia 1 x 1 x 15 0.65 0.39 3.80
On Windows KW2 10 mm 1 x 4 x 1 1.90 0.62 4.71
Stirrups 8mm dia 1 x 1 x 13 0.65 0.39 3.30
Sunshades
On Windows W1 8 mm Long 3 x 4 x 1 2.70 0.39 12.64
Short 3 x 18 x 1 0.60 0.39 12.64
On Windows W2 8 mm Long 3 x 4 x 1 1.90 0.39 8.89
Short 3 x 13 x 1 0.60 0.39 9.13
On Windows W3 8 mm Long 2 x 4 x 1 1.70 0.39 5.30
Short 2 x 11 x 1 0.60 0.39 5.15
On Windows Kw1 8 mm Long 1 x 4 x 1 1.90 0.39 2.96
Short 1 x 13 x 1 0.60 0.39 3.04
On Windows Kw2 8 mm Long 1 x 4 x 1 1.70 0.39 2.65
Short 1 x 11 x 1 0.60 0.39 2.57
196.67 Kg 92.070 1 Kg 18107.41
14) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating,
curing etc., complete. For Lintels.

On D1 1 x 5 x 1 1.50 0.23 0.15 0.26


On D2 1 x 2 x 1 1.40 0.23 0.15 0.10
On D3 1 x 3 x 1 1.30 0.23 0.15 0.13
Windows W1 1 x 3 x 1 2.700.23 0.15 0.28
Windows W2 1 x 4 x 1 2.100.23 0.15 0.29
Windows W3 1 x 3 x 1 2.000.12 0.15 0.11
Total in Cu.Mt :: 1.17 Cu.Mt 14505.02 1 Cu.Mt 16970.87
15) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating,
curing etc., complete. For Sunshades.

On Windows W1 1 x 3 x 1 2.70 0.60 - 4.86


1 x 4 x 1 2.10 0.60 - 5.04
1 x 3 x 1 2.00 0.60 - 3.60
Total in Sq.Mt :: 13.50 Sq.Mt 1408.742 1 Sq.Mt 19018.02
16) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including seigniorage
charges, sales & other taxes on all materials, all operational, incidental and
labour charges such as mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc., complete for finished item of
work.
9" Brick wall
C1 to C2 1 x 1 x 1 3.65 0.23 0.90 0.76
C2 to C3 1 x 1 x 1 4.40 0.23 0.90 0.91
C3 to C8 1 x 1 x 1 4.75 0.23 0.90 0.98
C8 to C5 1 x 1 x 1 3.35 0.23 0.90 0.69
C5 to C7 1 x 1 x 1 3.40 0.23 0.90 0.70
C7 to C12/11 1 x 1 x 1 4.60 0.23 0.90 0.95
C11 to C10 1 x 1 x 1 3.65 0.23 0.90 0.76
C4 to C10 1 x 1 x 1 3.36 0.23 0.90 0.70
C6 to C4 1 x 1 x 1 5.00 0.23 0.90 1.04
C1 to C6 1 x 1 x 1 4.75 0.23 0.90 0.98
Deductions :
Ventilators -1 x 2 x 1 0.90 0.23 0.60 -0.25
Lintels On D1 -1 x 5 x 1 1.50 0.23 0.15 -0.26
" On D2 -1 x 2 x 1 1.40 0.23 0.15 -0.10
" On D3 -1 x 3 x 1 1.30 0.23 0.15 -0.13
" W1 -1 x 3 x 1 2.70 0.23 0.15 -0.28
" W2 -1 x 4 x 1 2.10 0.23 0.15 -0.29
" W3 -1 x 3 x 1 2.00 0.23 0.15 -0.21
Total in Cu.Mt :: 6.95 Cu.Mt 8359.33 1 Cu.Mt 58097.34
17) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including seigniorage
charges, sales & other taxes on all materials, all operational, incidental and
labour charges such as mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc., complete for finished item of
work.
4.5" Brick wall
Hall L/w 1 x 1 x 1 6.70 0.12 0.90 0.72
Extra Bed Room L/w 1 x 1 x 1 3.82 0.12 0.90 0.41
C/w 1 x 1 x 1 3.60 0.12 0.90 0.39
Bed Room I L/w 1 x 1 x 1 3.82 0.12 0.90 0.41
C/w 1 x 1 x 1 3.70 0.12 0.90 0.40
Bed Room II L/w 1 x 1 x 1 3.82 0.12 0.90 0.41
C/w 1 x 1 x 1 4.80 0.12 0.90 0.52
Pooja Room L/w 1 x 1 x 1 1.50 0.12 0.90 0.16
C/w 1 x 1 x 1 1.20 0.12 0.90 0.13
Kitchen L/w 1 x 1 x 1 3.50 0.12 0.90 0.38
C/w 1 x 1 x 1 2.85 0.12 0.90 0.31
Toilet 1 C/w 1 x 1 x 1 1.35 0.12 0.90 0.15
Toilet 2 C/w 1 x 1 x 1 1.50 0.12 0.90 0.16
Stair case Toilet C/w 1 x 1 x 1 2.50 0.12 2.20 0.66
Parapet wall L/w 1 x 2 x 1 16.30 0.12 0.80 3.13
C/w 1 x 2 x 1 10.80 0.12 0.80 2.07
at Stair case I st Flight 1 x 2 x 1 5.10 0.12 0.80 0.98
II nd Flight 1 x 2 x 1 2.60 0.12 0.80 0.50
at Landing 1 x 1 x 1 2.35 0.12 0.80 0.23
Deductions :
Lintels on Doors D1 -1 x 4 x 1 1.50 0.12 0.15 -0.10
D2 -1 x 3 x 1 1.40 0.12 0.15 -0.08
Total in Cu.Mt :: 11.94 Cu.Mt 8359.33 1 Cu.Mt 99810.40
18) Earth work excavation for foundations and depositing on bank for all lifts
and with an initial lead of 10m including all operational, incidental, labour
charges such as shoring ,sheeting, planking, strutting, etc. complete for
finished item of work including seigniorage excluding dewatering charges etc
as per SS - 20 B (APSS 308). for building foundation.

F/s Steps 1 x 1 5.80 0.90 0.30 1.56


1 x 1 2.80 0.90 0.30 0.75
Total in Cu.Mt :: 2.31 Cu.Mt 419.35 1 Cu.Mt 968.70
19) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate:
Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970)
machine crushed metal from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc. to site,
mixing concrete in concrete mixer including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labour charges
such as laying and ramming concrete in layers in position not exceeding
15cm, finishing top surface, curing concrete, etc., complete for finished item
of work.

PCC Under Steps 1 x 1 5.80 0.90 0.15 0.78


1 x 1 2.80 0.90 0.15 0.37
Total in Cu.Mt :: 1.15 Cu.Mt 5187.81 1 Cu.Mt 5965.98
20) Brick Masonry in superstructure with CM (1:8) prop: using second class
bricks of size 23 x 11 x 7 Cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, including seigniorage
charges, sales & other taxes on all materials, all operational, incidental and
labour charges such as mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc., complete for finished item of
work.

9" Brick wall


Front Steps Step I 1 x 1 x 1 5.80 0.90 0.20 1.04
Step II 1 x 1 x 1 5.80 0.60 0.20 0.70
Step III 1 x 1 x 1 5.80 0.30 0.20 1.16
Step I 1 x 1 x 1 2.80 0.60 0.20 0.56
Step II 1 x 1 x 1 2.80 0.30 0.20 0.56
Total in Cu.Mt :: 4.02 Cu.Mt 8359.33 1 Cu.Mt 33604.51
21) RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire mesh &
nominal reinforcement as directed by Engineer-in-charge with dubara
sponge finishing, including cost & conveyance of all materials to site,
seigniorage charges, sales & other taxes on all materials, operational &
incidental, cost and conveyance of cement, wire mesh, water to work site,
centering, scaffolding and form work, lift charges etc., complete for finished
items of work but excluding cost of steel & its fabrication charges, for
finished item of work. (APSS No.403&903).
1 x 2 x 1 16.30 - 0.45 14.67
1 x 2 x 1 10.80 - 0.45 9.72
Deduct Stair case Portion -1 x 1 x 1 3.30 - 0.45 -1.48
-1 x 1 x 1 1.20 - 0.45 -0.54
Total in Sq.Mt :: 22.37 Sq.Mt 2237.82 1 Sq.Mt 50060.03
22) Ceiling Plastering with CM(1:3) Prop: 12mm thick in single coat spong finish
including cost and conveyance of all materials like cement, sand, water etc.,
to site, including seigniorage charges, sales & other taxes on all materials, all
operational, incidental charges and labour charges such as mixing mortar,
finishing, curing, etc., complete for finished item of work. (APSS 901,906).

Slab Projection Sides 1 x 2 x 1


16.30 0.90 - 29.34
F/s & B/s 1 x 2 x 1
10.80 0.90 - 19.44
Stair case Bottom 1 x 1 x 1
5.30 1.20 - 6.36
" 1 x 1 x 1
2.60 1.20 - 3.12
Mid Landing 1 x 1 x 1
2.50 1.20 - 3.00
Window Sunshades W3 1 x 3 x 1
2.10 0.60 - 3.78
W2 1 x 3 x 1
1.50 0.60 - 2.70
W1 1 x 2 x 1
1.40 0.60 - 1.68
K W1 1 x 1 x 1
1.50 0.60 - 0.90
K W2 1 x 1 x 1
1.40 0.60 - 0.84
Varandah 1 x 1 x 1
5.80 2.35 - 13.63
Total in Sq.Mt :: 84.79 Sq.Mt 168.83 1 Sq.Mt 14315.10
23) Plastering 20mm thick in two coats with base coat of 16mm thick in CM
(1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including
cost and conveyance of all materials like cement, screened sand, water etc.,
to site, seigniorage charges, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing mortar,scaffolding
charges, lift charges, finishing,including cutting of Grooves wherever
necessary as directed by Engineer - in - charge, curing, etc., for Uneven
Surfaces of Brick Wall complete for finished item of work. (APSS 901,903 &
904).
West side wall 1 x 1 x 1
14.25 - 0.60 8.55
South side wall 1 x 1 x 1
9.75 - 0.60 5.85
East side walls 1 x 1 x 1
15.15 - 0.60 9.09
North side walls 1 x 1 x 1
4.15 - 0.60 2.49
" " 1 x 1 x 1
5.80 - 0.60 3.48
" " 1 x 1 x 1
1.80 - 3.30 5.94
For Steps Top 1 x 1 x 3
5.80 - 0.30 5.22
Side 1 x 1 x 3
5.80 0.20 - 3.48
Stair case steps 1 x 15 x 1
1.20 0.28 - 5.04
1 x 7 x 1
1.20 0.28 - 2.35
Total in Sq.Mt :: 51.49 Sq.Mt 506.25 1 Sq.Mt 26066.81
24) Plastering 12mm thick in two coats with base coat of 9mm thick in CM (1:6)
and top coat of 3mm thick in CM (1:4) dubara sponge finish including cost
and conveyance of all materials like cement, screened sand, water etc., to
site, seigniorage charges, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing mortar,
scaffolding charges, lift charges, finishing, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, curing, etc., for
Uneven Surfaces of Brick Wall complete for finished item of work. (APSS
901,903 & 904).

A) Internal 9" brick walls :


Hall Short wals 1 x 1 x 1 4.25 - 3.30 14.02
Hall Long walls 1 x 1 x 1 7.00 - 3.30 23.10
Pooja room L/w 1 x 2 x 1 1.20 - 3.30 7.92
C/w 1 x 2 x 1 1.80 - 3.30 11.88
Kitchen Room Short wall 1 x 1 x 1 2.65 - 3.30 8.74
Kitchen Room Long wall 1 x 1 x 1 3.25 - 3.30 10.72
Extra Bed Room Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Extra Bed Room Long walls 1 x 1 x 1 3.40 - 3.30 11.22
Bed Room II Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room II Long walls 1 x 1 x 1 3.50 - 3.30 11.55
Bed Room I Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room I Long walls 1 x 1 x 1 4.60 - 3.30 15.18
Toilet 1 Short walls 1 x 1 x 1 1.35 - 3.30 4.45
Toilet 2 Short walls 1 x 1 x 1 1.50 - 3.30 4.95
Out side Toilet 1 x 2 x 1 2.40 - 3.30 15.84
1 x 2 x 1 1.35 - 3.30 8.91
Window offsets 1 x 3 x 2 2.10 - 0.15 1.89
1 x 3 x 2 1.35 - 0.15 1.21
1 x 4 x 2 1.50 - 0.15 1.80
1 x 4 x 2 0.35 - 0.15 0.42
1 x 3 x 2 1.20 - 0.15 1.08
1 x 3 x 2 0.35 - 0.15 0.31
B) Internal 4.5" brick walls :
Hall Long wals 1 x 1 x 1 7.00 - 3.30 23.10
Deduction Toilet Open 1 x -1 x 1 1.35 - 3.30 -4.45
Pooja room 1 x 1 x 2 1.80 - 3.30 11.88
Pooja room 1 x 1 x 2 1.20 - 3.30 7.92
Kitchen Room Short wall 1 x 1 x 1 2.65 - 3.30 8.74
Kitchen Room Long wall 1 x 1 x 1 3.25 - 3.30 10.72
Extra Bed Room Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Extra Bed Room Long walls 1 x 1 x 1 3.40 - 3.30 11.22
Bed Room II Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room II Long walls 1 x 1 x 1 3.50 - 3.30 11.55
Bed Room I Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room I Long walls 1 x 1 x 1 4.60 - 3.30 15.18
Toilet 1 Long walls 1 x 2 x 1 2.40 - 3.30 15.84
Toilet 1 Short walls 1 x 1 x 1 1.35 - 3.30 4.45
Toilet 2 Long walls 1 x 1 x 1 2.70 - 3.30 8.91
Toilet 2 Short walls 1 x 1 x 1 1.50 - 3.30 4.95
Toilet 2 Front area 1 x 1 x 1 2.70 - 3.30 8.91
1 x 1 x 1 1.20 - 3.30 3.96
369.35 Sq.Mt 491.51 1 Sq.Mt 181539.22
C) External 9" brick walls :
West side wall 1 x 1 x 1 14.25 - 3.30 47.02
South side wall 1 x 1 x 1 9.75 - 3.30 32.17
East side walls 1 x 1 x 1 15.15 - 3.30 49.99
North side walls 1 x 1 x 1 4.15 - 3.30 13.69
" " 1 x 1 x 1 5.80 - 3.30 19.14
" " 1 x 1 x 1 1.80 - 3.30 5.94
Stair case walls 1 x 2 x 2 5.30 - 0.90 19.08
" " 1 x 2 x 2 2.30 - 0.90 8.28
'' '' 1 x 1 x 2 2.50 - 0.90 4.50
Parapet wall L/w 1 x 2 x 2 16.30 - 1.45 94.54
1 x 2 x 2 10.80 - 1.45 62.64
Deduct Stair case Portion -1 x 1 x 1 3.30 - 1.45 -4.78
-1 x 1 x 1 1.20 - 1.45 -1.74
350.47 Sq.Mt 491.51 1 Sq.Mt 172259.51
25) Supplying and fixing of false ceiling using Plaster of Paris Boards 12 mm
thick with standard GI ceiling angles, sections perimeter channels including
cost and conveyance of all materials and labour charges etc complete.

Hall Living area 1 x 1 x 1 4.06 7.24 - 29.39


Extra Bed Room 1 x 1 x 1 3.83 3.60 - 13.78
Toilet Front 1 x 1 x 1 1.35 1.45 - 1.95
Bed Room I 1 x 1 x 1 3.83 3.60 - 13.78
Bed Room II 1 x 1 x 1 3.30 4.80 - 15.84
Toilet Front 1 x 1 x 1 2.10 1.50 - 3.15
Pooja Room 1 x 1 x 1 1.50 1.35 - 2.02
Pooja Front 1 x 1 x 1 1.35 1.20 - 1.62
Kitchen 1 x 1 x 1 2.85 3.50 - 9.97
Total in Sq.Mt :: 91.50 Sq.Mt 454.46 1 Sq.Mt 41583.09

Total 1084359.66
26) Sanitory Charges 7% on total Cost Since first bill 75905.18
27) Electrification Charges 6% on total Cost Since first bill 65061.58
Total: 1225326.42
IV th & Part Bill
Name of the work : Construction of Ground Floor with R.C.C. at Yeducharlapalli Venkatapuram

Sl. Measurements
No. Description of Item No.s Qty Rate/Per Amount
L B D
1 2 3 4 5 6 7 8 9
1) VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine
crushed hard granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402) with minimum cement content @ 380Kgs/Cu.F. from standard
suppliers approved by the department including centering, shuttering, laying
concrete, vibrating, curing etc., complete. Shelves 50mm thick.

In Kitchen 1 x 1 x 1 1.80 0.30 - 0.54


1 x 1 x 1 1.60 0.30 - 0.48
Pooja Room 1 x 1 x 1 1.20 0.30 - 0.36
Hall 1 x 3 x 1 1.80 0.30 - 1.62
Bed Room 1 & 2 L/w 1 x 3 x 1 1.80 0.30 - 1.62
C/w 1 x 3 x 1 2.10 0.30 - 1.89
Total in Sq.Mt :: 6.51 Sq.Mt 432.66 1 Sq.Mt 2816.62
2) Flooring with adanga Marbles of I st quality of size not exceeding 0.457 x
0.457m laid over CC Flooring bed set over 20mm thcik CM(1:8) drop kase coat
and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white
cement paste mixed with pigment of matching shade including cost and
conveyance of all materials like cement, sand, water, tiles, etc. to site,
seigniorage charges, sales and other taxes on all materials, and all opertional,
incidental and all labour charges such as mixing of cement mortar, laying in
position, curing, lift charges etc., complete for finished item of work in all
floors.

Hall Living area 1 x 1 x 1 4.06 7.240 - 29.39


Extra Bed Room 1 x 1 x 1 3.83 3.60 - 13.78
Toilet Front 1 x 1 x 1 1.35 1.45 - 1.95
Bed Room I 1 x 1 x 1 3.83 3.60 - 13.78
Bed Room II 1 x 1 x 1 3.30 4.80 - 15.84
Toilet Front 1 x 1 x 1 2.10 1.50 - 3.15
Pooja Room 1 x 1 x 1 1.50 1.35 - 2.02
Pooja Front 1 x 1 x 1 1.35 1.20 - 1.62
Kitchen 1 x 1 x 1 2.85 3.50 - 9.97
Varandah 1 x 1 x 1 5.80 2.35 - 13.63
Total in Sq.Mt :: 105.13 Sq.Mt 1167.51 1 Sq.Mt 122740.33
Skirting
Hall Living area 1 x 1 x 2 (4.06+7.24) 0.10 2.26
Extra Bed Room 1 x 1 x 2 (3.83+3.60) 0.10 1.48
Toilet Front 1 x 1 x 2 (1.35+1.45) 0.10 0.56
Bed Room I 1 x 1 x 2 (3.83+3.60) 0.10 1.48
Bed Room II 1 x 1 x 2 (3.30+4.80) 0.10 1.62
Kitchen 1 x 1 x 2 (2.85+3.50) 0.10 1.27
Pooja Room 1 x 1 x 2 (1.50+1.35) 0.10 0.57
" " Front 1 x 1 x 2 (1.35+1.20) 0.10 0.51
Varandah 1 x 1 x 1 (5.80+2.40) 0.10 0.82
Total in Sq.Mt :: 10.57 Sq.Mt 673.09 1 Sq.Mt 7114.56
3) Providing and fixing non skid ceramic tiles for flooring over and inclusive of
20mm thick base plaster in cement morter 1:5 (1 cement : 5 coarse sand)
including a floating cement slurry including grouting/ filling the joints with
white cement slurry mixed with matching, pigment, curing, cleaning and
leaving/making necessary holes for sanitory connection complete but including
cost of cement and tiles in all heights/level for skirting complete for finished
item of work.

Toilet 1 1 x 1 x 1 2.40 1.35 - 3.24


Toilet 2 1 x 1 x 1 2.70 1.50 - 4.05
Stair case Toilet 1 x 1 x 1 2.20 1.35 - 2.97
Total in Sq.Mt :: 10.26 Sq.Mt 911.42 1 Sq.Mt 9351.17
4) Dadooing to walls with glazed red or white full body ceramic wall tiles of size
200 x 300 mm / 245 mm x 325 mm and thickness 6 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and
finish in all shades and designs, any brand as approved by Engineer - in -
charge and set over a base coat of CM (1:5), 12mm thick and neat cement
paste at the rate of 3.3 Kg/Sqmt. and jointed with white cement paste mixed
with pigment of matching shade including cost and conveyance of all materials
like cement, sand, water, tiles, etc. to site, seigniorage charges, sales and
other taxes on all materials, and all opertional, incidental and all labour
charges such as mixing of cement mortar, laying in position, curing, lift
charges etc., complete for finished item of work in all floors

Toilet 1 1 x 1 x 1 (2.40+1.35) 2.10 7.87


Toilet 2 1 x 1 x 1 (2.70+1.50) 2.10 8.82
Stair case Toilet 1 x 1 x 1 (2.20+1.35) 2.10 7.45
Total in Sq.Mt :: 24.14 Sq.Mt 922.40 1 Sq.Mt 22266.74
5) Painting to new walls with 2 coats of water proof cement paint of apporved
brand and shade as approved by the Engineer - in - Charge over a base coat of
approved cement primer grade II exterior making three coats in all to give an
even shade after thourughly brushing the surface to remove all dirt and
remains of loose powdered materials, including cost and conveyance of all
materials, cost of brushes, water to site, etc., sales & other taxes, all
operational, incidental, labour charges etc. complete for finished item of work
as per SS 912 for internal walls.

Ceiling :
Hall Living area 1 x 1 x 1 4.06 7.24 - 29.39
Extra Bed Room 1 x 1 x 1 3.83 3.60 - 13.78
Toilet Front 1 x 1 x 1 1.35 1.45 - 1.95
Bed Room I 1 x 1 x 1 3.83 3.60 - 13.78
Bed Room II 1 x 1 x 1 3.30 4.80 - 15.84
Toilet Front 1 x 1 x 1 2.10 1.50 - 3.15
Pooja Room 1 x 1 x 1 1.50 1.35 - 2.02
Pooja Front 1 x 1 x 1 1.35 1.20 - 1.62
Kitchen 1 x 1 x 1 2.85 3.50 - 9.97
Slab Projection Sides 1 x 2 x 1 16.30 0.90 - 29.34
F/s & B/s 1 x 2 x 1 10.80 0.90 - 19.44
Stair case Bottom 1 x 1 x 1 5.30 1.20 - 6.36
" 1 x 1 x 1 2.60 1.20 - 3.12
Mid Landing 1 x 1 x 1 2.50 1.20 - 3.00
Window Sunshades W3 1 x 3 x 1 2.10 0.60 - 3.78
W2 1 x 3 x 1 1.50 0.60 - 2.70
W1 1 x 2 x 1 1.40 0.60 - 1.68
K W1 1 x 1 x 1 1.50 0.60 - 0.90
K W2 1 x 1 x 1 1.40 0.60 - 0.84
Varandah 1 x 1 x 1 5.80 2.35 - 13.63
Total in Sq.Mt :: 176.29 Sq.Mt 252.13 1 Sq.Mt 44448.00
6) Painting to new walls with 2 coats of water proof cement paint of apporved
brand and shade as approved by the Engineer - in - Charge over a base coat of
approved cement primer grade II exterior making three coats in all to give an
even shade after thourughly brushing the surface to remove all dirt and
remains of loose powdered materials, including cost and conveyance of all
materials, cost of brushes, water to site, etc., sales & other taxes, all
operational, incidental, labour charges etc. complete for finished item of work
as per SS 912 for internal walls.

A) Internal 9" brick walls :


Hall Short wals 1 x 1 x 1 4.25 - 3.30 14.02
Hall Long walls 1 x 1 x 1 7.00 - 3.30 23.10
Pooja room L/w 1 x 2 x 1 1.20 - 3.30 7.92
C/w 1 x 2 x 1 1.80 - 3.30 11.88
Kitchen Room Short wall 1 x 1 x 1 2.65 - 3.30 8.74
Kitchen Room Long wall 1 x 1 x 1 3.25 - 3.30 10.72
Extra Bed Room Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Extra Bed Room Long walls 1 x 1 x 1 3.40 - 3.30 11.22
Bed Room II Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room II Long walls 1 x 1 x 1 3.50 - 3.30 11.55
Bed Room I Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room I Long walls 1 x 1 x 1 4.60 - 3.30 15.18
Toilet 1 Short walls 1 x 1 x 1 1.35 - 3.30 4.45
Toilet 2 Short walls 1 x 1 x 1 1.50 - 3.30 4.95
Out side Toilet 1 x 2 x 1 2.40 - 3.30 15.84
1 x 2 x 1 1.35 - 3.30 8.91
Window offsets 1 x 3 x 2 2.10 - 0.15 1.89
1 x 3 x 2 1.35 - 0.15 1.21
1 x 4 x 2 1.50 - 0.15 1.80
1 x 4 x 2 0.35 - 0.15 0.42
1 x 3 x 2 1.20 - 0.15 1.08
1 x 3 x 2 0.35 - 0.15 0.31
B) Internal 4.5" brick walls :
Hall Long wals 1 x 1 x 1 7.00 - 3.30 23.10
Deduction Toilet Open 1 x -1 x 1 1.35 - 3.30 -4.45
Pooja room 1 x 1 x 2 1.80 - 3.30 11.88
Pooja room 1 x 1 x 2 1.20 - 3.30 7.92
Kitchen Room Short wall 1 x 1 x 1 2.65 - 3.30 8.74
Kitchen Room Long wall 1 x 1 x 1 3.25 - 3.30 10.72
Extra Bed Room Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Extra Bed Room Long walls 1 x 1 x 1 3.40 - 3.30 11.22
Bed Room II Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room II Long walls 1 x 1 x 1 3.50 - 3.30 11.55
Bed Room I Short walls 1 x 1 x 1 3.60 - 3.30 11.88
Bed Room I Long walls 1 x 1 x 1 4.60 - 3.30 15.18
Toilet 1 Long walls 1 x 2 x 1 2.40 - 3.30 15.84
Toilet 1 Short walls 1 x 1 x 1 1.35 - 3.30 4.45
Toilet 2 Long walls 1 x 1 x 1 2.70 - 3.30 8.91
Toilet 2 Short walls 1 x 1 x 1 1.50 - 3.30 4.95
Toilet 2 Front area 1 x 1 x 1 2.70 - 3.30 8.91
1 x 1 x 1 1.20 - 3.30 3.96
369.35 Sq.Mt 141.85 1 Sq.Mt 52392.30
C) External 9" brick walls :
Basement
West side wall 1 x 1 x 1 14.25 - 0.60 8.55
South side wall 1 x 1 x 1 9.75 - 0.60 5.85
East side walls 1 x 1 x 1 15.15 - 0.60 9.09
North side walls 1 x 1 x 1 4.15 - 0.60 2.49
" " 1 x 1 x 1 5.80 - 0.60 3.48
" " 1 x 1 x 1 1.80 - 3.30 5.94
West side wall 1 x 1 x 1 14.25 - 3.30 47.02
South side wall 1 x 1 x 1 9.75 - 3.30 32.17
East side walls 1 x 1 x 1 15.15 - 3.30 49.99
North side walls 1 x 1 x 1 4.15 - 3.30 13.69
" " 1 x 1 x 1 5.80 - 3.30 19.14
" " 1 x 1 x 1 1.80 - 3.30 5.94
Stair case walls 1 x 2 x 2 5.30 - 0.90 19.08
" " 1 x 2 x 2 2.30 - 0.90 8.28
'' '' 1 x 1 x 2 2.50 - 0.90 4.50
Parapet wall L/w 1 x 2 x 2 16.30 - 1.45 94.54
1 x 2 x 2 10.80 - 1.45 62.64
Deduct Stair case Portion -1 x 1 x 1 3.30 - 1.45 -4.78
-1 x 1 x 1 1.20 - 1.45 -1.74
385.87 Sq.Mt 141.85 1 Sq.Mt 54735.66
7) Timber shall be of the kind as specified, may be teak, shisham, sal,
deodar,etc., the timber shall be of best quality, well seasoned and free from
sap knots, warps, cracks and other defects, all wood work shall be planed and
neatly and truly finished to the exact dimensions. all joints be neat and strong,
truly and accurately fitted and glued before being fitted together. Chunkhats :
The Chunkhats shall be formed and joined by motise and tenon joint with head
wooden pins and the joints shall be of coated with white lead before being
fitted together.

1 x 5 0.90 - 2.10 9.45


1 x 2 0.85 - 2.10 3.57
Total in Sq.Mt :: 13.02 Each 15254.00 1 Each 198607.08
8) Providing and fixing 30mm thick Solid panel PVC door shutter consisting of
frame made out of M.S. tubes of 19 gauge thickness and size of 19mm x
19mm for stiles, & 15mm x 15mm for top & bottom rails. M.S. frame shall have
a coat of steel primers of approved make and manufacture. M.S. frame shall
be covered with 5mm thick heat molded PVC ‘C’ channel of size 30 x 50mm
forming stiles, and 5mm thick, 75mm wide PVC sheets for top rail, lock rail &
bottom rail on either side, and 10mm (5mm x 2) thick, 20mm wide cross PVC
sheet as gap insert for top rail & bottom rail. Paneling of 5mm thick PVC sheet
to be fitted in the M.S. frame welded / sealed to the stiles & rails with 30mm
wide x 5mm thick PVC sheet beading on either side, and joined together with
solvent cement adhesive etc. An additional 5mm thick PVC strip of 20mm width
is to be stuck on the interior side of the ‘C’ Channel using PVC solvent
adhesive. Complete as per direction of Engineer-in-charge, manufacturer’s
specification & drawing for finished item of work.

Toilet doors 1 x 3 0.75 - 1.90 4.28


Total in Sq.Mt :: 4.28 Sq.Mt 2618.00 1 Sq.Mt 11205.04
9) Supplying and fixing fully glazed anodized aluminium hinged type window with
fan light as per drawing using standard outer frame 38.5x33x21x2.5mm thick
and central mullion of size 59(3mm)x33(4mm)x21(3mm) using 5mm thick,
glass fitted with suitable aluminium glazing clips and rubber beading including
supplying and fixing friction hinges (2np.s per shutter), handle with lock(1 no.
per shutter), incl cost and conveyance to site of aluminium sections, glass
rubber beading, fixtures etc., including labour charges for manufacturing
window, fixing in position using wooden blocks and sheet metalscrews etc.,
complete for finished item of work.

W1 1 x 3 2.10 - 1.35 8.50


W2 1 x 3 1.50 - 1.35 6.07
W3 1 x 2 1.40 - 1.35 3.78
Kw1 1 x 1 1.50 - 0.90 1.35
Kw2 1 x 1 1.20 - 0.90 1.08
V1 & V2 1 x 2 0.60 - 0.30 0.36
Total in Sq.Mt :: 21.14 Sq.Mt 7485.00 1 Sq.Mt 158232.90
10) Painting to New wood work with two coats of ready mixed Synthetic Enamel
paints in all shades Grade - I having VOC (Volatile Organic Compound) content
less than 50 grams/ liter first quality all shades to give an even shade over
base coatof wood Primer finishing with putty for wood work after thouroughly
brushing the surface to remove all remains including cost and conveyance of
all materials to site, sales & other taxes, all operational, incidental and labour
charges etc., complete for finished item of work.(3 coats) (APSS No. 1201 &
1212).in All Floors

1 x 5 0.90 - 2.10 9.45


1 x 2 0.85 - 2.10 3.57
Total in Sq.Mt :: 13.02 Sq.Mt 2227.29 1 Sq.Mt 28999.32
11) Supply and fixing of M.S.Grill of size with outer angular frame of rolled steel of
ISA 2525 of size 25mm x 25mm x 4mm welded with safety bars of 45 x 25mm
Square pipes at 150mm centre to centre horizontally and verticlally including
red oxide primer of grade-I quality, sales and other taxes, cost and conveyance
of all materials to site, all labour charges and fixing in position etc., complete
for finished item of work.
W1 1 x 3 2.10 - 1.35 8.50
W2 1 x 3 1.50 - 1.35 6.07
W3 1 x 2 1.40 - 1.35 3.78
Kw1 1 x 1 1.50 - 0.90 1.35
Kw2 1 x 1 1.20 - 0.90 1.08
Total in Sq.Mt :: 20.78 Sq.Mt 2500.00 1 Sq.Mt 51950.00

Total : 764859.72
12) Sanitory Charges 7% on total Cost Since first bill 53540.18
13) Electrification Charges 6% on total Cost Since first bill 45891.58
Total:- 864291.48
Quantity since
executed for previous Rema
Unit supplied upto Item of work, of supplies granted under "sub-head" and sub work of estimate Rate Upto date bill total rks
date as per for each
measurement subhead

1 2 3 4 5 6 7
1) Earth work excavation for foundations and depositing on bank for all lifts and with an
Cu.Mt 76.08 initial lead of 10m including all operational, incidental, labour charges such as 336.53 25603.20
### shoring
Err:509 ,sheeting, planking, strutting, etc. complete for finished item of work
### Err:509 including seigniorage excluding dewatering charges etc as per SS - 20 B (APSS 308). Err:509 Err:509
2) Vibrated Plain Cement Concrete (1:3:6) proportion (cement: fine aggregate: Coarse
Cu.Mt 9.34 aggregate) using 40mm size Hard Broken Granite (IS383, 1970) machine crushed 4976.25 46468.22
21) metal fromHigh
Providing approved quarry Deformed
Yield Strength including cost
(HYSD)andsteel
conveyance
bars (Fe of
500allgrade
materials
as perlike
IS
Kg 3521.05 cement, sand,ofcoarse
1786-1979) aggregate,
different waterfor
diameters etc.RCC
to site, mixing
works, concrete
including in concrete
labour chargesmixer
for 63.94 225146.76
straightening, cutting, bending to required sizes and shapes, placing
VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine crushedin position with
cover blocks of
hard granite approved
metal materials
(coarse and size
aggregate) fromand tying and
approved lapsplicing
quarry withcost
including binding
and
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water
etc., to site and including Seigniorage charges, sales & other taxes on all materials
including all operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and
Cu.Mt 7.61 its fabrication charges for finished item of work (APSS No. 402) with minimum 9302.11 70798.36
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Column Footings.

VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine crushed
hard granite metal (coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water
etc., to site and including Seigniorage charges, sales & other taxes on all materials
including all operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and
Cu.Mt 8.40 its fabrication charges for finished item of work (APSS No. 402) with minimum 11963.17 100502.59
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Columns.

Filling with useful available excavated earth (excluding rock) in trenches, sides of
foundations and basement with initial lead in layers not exceeding 15 cm thick,
consolidating each deposited layer by watering and ramming including cost and
Cu.Mt 60.26 conveyance of water to work site and all operational, incidental, labour charges, hire 274.72 16554.90
charges of T & P etc., complete for finished item of work. APSS No.309 & 310.

Coursed Rubble Stone Masonry in CM (1:3) Prop: including cost and conveyance of all
materials like cement, sand, water etc., to site, including seigniorage charges, sales &
other taxes on all materials, all operational, incidental charges and labour charges
Cu.Mt 20.32 such as mixing mortar, finishing, curing, etc., complete for finished item of work. 4498.24 91404.24
(APSS 901,906)

VRCC (1:1½:3) prop nominal mix using 6 to 20mm (SS-5) graded machine crushed
hard granite metal (coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water
etc., to site and including Seigniorage charges, sales & other taxes on all materials
including all operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and
Cu.Mt 5.70 its fabrication charges for finished item of work (APSS No. 402) with minimum 11663.03 66444.28
cement content @ 380Kgs/Cu.F. from standard suppliers approved by the
department including centering, shuttering, laying concrete, vibrating, curing etc.,
complete. For Plinth Beam.

Cu.Mt 110.38 Filling with Gravel in trenches, sides of foundations and basement with initial lead in 368.00 40619.84
layers
Vibrated notPlain
exceeding
Cement 15cm thick, consolidating
Concrete (1:4:8) proportion each deposited layeraggregate:
(cement: fine by watering and
Coarse
Cu.Mt 9.37 ramming including all operational, incidental, labour charges, seignorage charges, 4607.01 43153.86
aggregate)
VRCC usingprop
(1:1½:3) 40mm size Hard
nominal mix Broken
using 6 Granite
to 20mm (IS383,
(SS-5) 1970)
graded machine
machine crushed
crushed
Cu.Mt 5.46 hire charges
metal of T & P etc.,
from approved complete
quarry for finished
including itemconveyance
cost and of work. (APSS NO. 309 & 310).
ofincluding
all materials like 11581.80 63259.79
27) hard
cement,
granite
Painting to new
sand,
metal
walls(coarse
coarse aggregate,
aggregate)
with 2 coats of water
water etc.
from
proof
to
approved paint
site,cement
mixing
quarry
of apporved
concrete
cost and
brand
inaggregate,
concrete and
mixer
0.00 0.00 conveyance of all materials like cement, fine aggregate (sand) coarse
shade as approved by the Engineer - in - Charge over a base coat of approved cement water 0.00 0.00
etc., to site andII including Seigniorage charges, sales &toother taxes on all materials
13) primer grade
VRCC (1:1½:3) exterior
prop nominalmaking three
mix using 6coats
to 20mmin all(SS-5)give an even
graded shade
machine after
crushed
Sq.Mt 134.10 thourughly brushing the surface to remove all dirt and remains
hard granite metal (coarse aggregate) from approved quarry including cost and of loose powdered 1322.94 177406.25
15) conveyance
Impervious coat of all20mm
materials like
thick overcement,
RCC rooffineslab
aggregate
surface(sand) coarse aggregate,
with CM(1:3), promixedwater
with
Sq.Mt 134.10 etc., of
1kg to water
site and including
proof compoundSeigniorage
per bagcharges,
of cement saleslaid
& other taxeswhen
over roof on allitmaterials
is green 429.14 57547.67
including cost of all materials, seigniorage charges, excluding conveyance
14) Brick Masonry in superstructure with CM (1:8) prop: using second class bricks of size charges of
0.00 0.00 materials
23 x 11 x and 7 Cmsincluding all operational,
from approved source incidental
having minimumand labour charges
crushing for mixing
strength of 40 0.00 0.00
### Kg/Sqcm.
Err:509 including cost and conveyance of all materials like cement, sand, bricks,
### Err:509 water etc., to site, including seigniorage charges, sales & other taxes on all materials, Err:509 Err:509
10) Reinforced Cement Concrete M20 Grade Nominal Mix using 6 to 20mm (SS-5) graded
Cu.Mt 0.71 machine crushed hard granite metal (coarse aggregate) from approved quarry 12087.01 8593.86
including cost
11) Reinforced and Concrete
Cement conveyance M20ofGrade
all materials
NominallikeMix cement, fine aggregate
corresponding to IS 456(sand)
using
Sq.Mt 7.88 coarse aggregate,
20mm size gradedwater
machineetc., tocrushed
site andhard
including
graniteSeigniorage charges,
metal (coarse sales & other
aggregate) from 1090.21 8585.40
23) approved
Timber shallquarry
be ofincluding
the kind cost and conveyance
as specified, of allshisham,
may be teak, materials sal,like cement, fine
deodar,etc., the
Each 6.00 aggregate
timber shall(sand) coarse
be of best aggregate,
quality, water etc.,
well seasoned and to site
free fromandsapincluding
knots, warps,Seigniorage
cracks 15254.00 91524.00
24) and other defects,
Providing all 30mm
and fixing wood work thickshall
Solidbepanel
planed
PVC and neatly
door and truly
shutter finished
consisting of to the
frame
Sq.Mt 6.34 exact
made dimensions. all joints
out of M.S. tubes of 19begauge
neat thickness
and strong,andtruly
sizeand accurately
of 19mm x 19mm fittedfor
and glued
stiles, & 2493.00 15805.62
26) 15mm
Glazed x 15mm for top
ventilator as & per
bottom rails. M.S.
drawing frameanodised
using shall have aluminium
a coat of steel primers of
sections of
Sq.Mt 2.27 approved make and manufacture.
38.5x33x21x2.50mm thick outer frame M.S. frame shall bemullion
and central coveredofwithsize5mm59(3mm)thick xheat
33 4246.00 9638.42
17) (2.5mm)
Plasteringand
12mmshutters
thick with
in two z section
coats withof 33(2.5mm)
base coat ofx9mm 24.5 thick
(3mm) in CMx 21(1:6)
(3mm)and and
top
0.00 0.00 5mm thick plain glass fitted with suitable aluminium glazing be made
coat of 3mm thick in CM (1:4) dubara sponge finish including cost and conveyance of of single panel 0.00 0.00
18) all
RCM materials like
facia 5cm cement,
thick in CMscreened
(1:3) forsand,
dropwater
walls,etc.,
fins to site,
with seigniorage
rabbit wire mesh charges, sales
& nominal
Sq.Mt 21.43 & other taxes onasalldirected
reinforcement materials, byallEngineer-in-charge
operational, incidentalwithand labour
dubara chargesfinishing,
sponge such as 1716.63 36794.25
including cost & conveyance of all materials to site, seigniorage charges, sales & other
taxes on all materials, operational & incidental, cost and conveyance of cement, wire
Quantity since
executed for previous Rema
Unit supplied upto Item of work, of supplies granted under "sub-head" and sub work of estimate Rate Upto date bill total rks
date as per for each
measurement subhead

1 2 3 4 5 6 7
28) Painting to new walls with 2 coats of water proof cement paint of apporved brand and
Sq.Mt 136.00 shade as approved by the Engineer - in - Charge over a base coat of approved cement 193.32 26291.52
16) primer grade
Plastering 20mm II thick
exterior making
in two coats three
with basecoats in ofall16mm
coat to give anineven
thick shade
CM (1:6) andafter
top
Sq.Mt 74.98 thourughly
coat of 4mmbrushing
thick in CMthe (1:4)
surface to remove
dubara spongeall dirt including
finish and remains cost of
andloose powdered
conveyance of 387.62 29063.75
29) all materials
Dadooing like cement,
to walls screened
with glazed red sand,
or whitewater
fulletc.,
body to ceramic
site, seigniorage
wall tilescharges, salesx
of size 200
Sq.Mt 25.75 &
300other
mmtaxes
/ 245on mm allxmaterials,
325 mm and all thickness
operational, incidental
6 mm and conforming
1st quality labour charges such as
to IS:13711, 777.37 20017.28
IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades
30) Providing and fixing non skid ceramic tiles for flooring over and inclusive of 20mm and designs,
Sq.Mt 4.92 any brand
thick as approved
base plaster by Engineer
in cement morter 1:5- in (1
- charge
cementand set oversand)
: 5 coarse a base coat of CM
including (1:5),
a floating 775.71 3816.49
cement slurry including grouting/ filling the joints with white cement slurry mixed
Err:509
with matching, pigment, curing, cleaning and leaving/making necessary holes for Err:509
Err:509
### Err:509
### Err:509 Err:509 Err:509
### Err:509
### Err:509 Err:509 Err:509
### Err:509
### Err:509 Err:509 Err:509
### Err:509
### Err:509 Err:509 Err:509
### Err:509
### Err:509 Err:509 Err:509
### Err:509
### Err:509 Err:509 Err:509
### Err:509
### Err:509 Err:509 Err:509
### Err:509
### Err:509 Err:509 Err:509
### Err:509
### Err:509 Err:509 Err:509
### Err:509
### Err:509 Err:509 Err:509
### Err:509
### Err:509 Err:509 Err:509
### Err:509
### Err:509 Err:509 Err:509
Err:509 Err:509
TOTAL :- 2292471.29

You might also like