Line Components Solutions
Line Components Solutions
Overview
𝒔𝟐 𝒘𝟐
𝑀𝑎𝑘𝑖𝑛𝑔 𝑇 𝑡ℎ𝑒 𝑠𝑢𝑏𝑗𝑒𝑐𝑡 𝑜𝑓 𝑡ℎ𝑒 𝑓𝑜𝑟𝑚𝑢𝑙𝑎 𝑔𝑖𝑣𝑒𝑠; 𝑻𝜽 = √
𝒍
𝟐𝟒 [(𝒔) − 𝟏]
Question 1
a) Thermal heating on transmission lines is of great concern to engineers.
Discuss the effects resulting from thermal heating.
Elongation of the conductor when it heats up resulting into sagging for
overhead lines which may be a danger to people
Reduction in mechanical strength of a conductor at higher temperatures.
Increase in power losses as a result of increase in resistance.
b) A 33 𝑘𝑉 wood pole overhead line system with 110 𝑚 span length is designed
to operate at 600 𝐶 thermal rating with conductor tension of 9 𝑘𝑁.The
conductor has a 19 × 10−6 𝐾 −1 coefficient of linear expansion, 2.1 𝑘𝑔/𝑚
mass and a 0.0678 Ω/𝑘𝑚 resistance at 600 𝐶. Consider gravity acceleration
of 9.81 m/s. Assuming solar heat gain of 7.55 W/m, radiated loss of
3.24 𝑊/𝑚 and convection loss of 21.22 𝑊/𝑚, calculate:
Note; in this case as the temperature is changed from 60 to 5, the length of the
conductor will decrease because the change is a negative as shown above OR if
you want to maintain the temp. difference as a positive then exchange the lengths.
iii) The new maximum operating temperature of the line when a 20%
increase in the installation tension of the 33 kV overhead line system
is applied.
{Hint: The length of the conductor at the new operating temperature must
remain the same as it were at 60 ºC}
𝐿𝑒𝑡 𝑡ℎ𝑒 𝑛𝑒𝑤 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑡𝑒𝑚𝑝𝑒𝑟𝑎𝑡𝑢𝑟𝑒 𝑏𝑒 𝜃
𝑵𝒐𝒕𝒆; 𝑇ℎ𝑒 𝑖𝑛𝑠𝑡𝑎𝑙𝑙𝑎𝑡𝑖𝑜𝑛 𝑡𝑒𝑛𝑠𝑖𝑜𝑛 𝑎𝑡 5℃ 𝑤𝑎𝑠 𝑖𝑛𝑐𝑟𝑒𝑎𝑠𝑒𝑑 𝑏𝑦 20% 𝑚𝑒𝑎𝑛𝑖𝑛𝑔 𝑡ℎ𝑎𝑡 𝑡ℎ𝑒 𝑛𝑒𝑤 𝑡𝑒𝑛𝑠𝑖𝑜𝑛
𝑤𝑖𝑙𝑙 𝑐𝑜𝑟𝑟𝑒𝑠𝑝𝑜𝑛𝑑 𝑡𝑜 5 ℃ .
𝑁𝑒𝑤 𝑡𝑒𝑛𝑠𝑖𝑜𝑛 𝑎𝑡 5℃ , 𝑇5℃ = 11.564 + .2(11.564) = 13.877 𝑘𝑁
1102 (2.1 × 9.81)2
𝑁𝑒𝑤 𝑙𝑒𝑛𝑔𝑡ℎ 𝑎𝑡 5℃ 𝑙5℃ = 110 (1 + ) = 110.122 𝑚
24(13.877𝑘)2
𝐹𝑟𝑜𝑚; 𝑙𝜃1 = 𝑙𝜃0 (1 + 𝛼(𝜃1 − 𝜃0 )) 𝑖𝑛 𝑡ℎ𝑖𝑠 𝑐𝑎𝑠𝑒 𝑡ℎ𝑒 𝑜𝑙𝑑 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑡𝑒𝑚𝑝. , 𝜃0 = 5℃
High initial costs that involve manufacture and installation of concrete poles
which are much higher than those incurred for wooden poles.
Concrete poles are very heavy which makes transportation and installation
more challenging.
Read about steel lattice towers also.
Question 2
a) In the construction of long transmission lines, transposition of towers is
sometimes in inevitable. Explain with illustrations the meaning of
transposition of towers and its importance in transmission lines.
Make your own research on this!!!!!
b) Over time, medium voltage lines will no longer have the original sag at
which they are meant to operate. Advise a network operator on the possible
solution so as to maintain the line in operation.
To maintain the proper sag in medium voltage power lines over time, network
operators should:
𝑙70℃ = 𝑙5℃ (1 + 19 × 10−6 (70 − 5)) = 125.3965(1 + 19 × 10−6 (70 − 5)) = 125.584 𝑚
𝑤𝑠 2 (1.8 × 9.81)(125)2
𝐶𝑜𝑛𝑑𝑢𝑐𝑡𝑜𝑟 𝑠𝑎𝑔, 𝑆𝜃 = = = 5.232 𝑚
8𝑇 8 × 6.592𝑘
𝑇ℎ𝑒 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 𝑐𝑙𝑒𝑎𝑟𝑎𝑛𝑐𝑒 𝑜𝑓 𝑡ℎ𝑒 66 𝑘𝑉 𝑠𝑦𝑠𝑡𝑒𝑚 𝑖𝑠 6 𝑚 𝑤ℎ𝑒𝑛 𝑖𝑡 𝑖𝑠 𝑛𝑜𝑡 𝑐𝑟𝑜𝑠𝑠𝑖𝑛𝑔 𝑡ℎ𝑒 𝑟𝑜𝑎𝑑 𝑠𝑜:
𝐶𝑙𝑒𝑎𝑟𝑎𝑛𝑐𝑒 𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑 = 13.2 − 5.323 = 7.968 𝑚 > 6𝑚
𝑯𝒆𝒏𝒄𝒆 𝒕𝒉𝒆 𝒔𝒕𝒓𝒖𝒄𝒕𝒖𝒓𝒆 𝒑𝒓𝒐𝒗𝒊𝒅𝒆𝒔 𝒆𝒏𝒐𝒖𝒈𝒉 𝒈𝒓𝒐𝒖𝒏𝒅 𝒄𝒍𝒆𝒂𝒓𝒂𝒏𝒄𝒆.
iii) The maximum span length that can be used for the overhead line
without infringing the statutory clearance.
𝑀𝑎𝑥𝑖𝑚𝑢𝑚 𝑝𝑒𝑟𝑚𝑖𝑡𝑡𝑒𝑑 𝑠𝑎𝑔, 𝑆𝜃 (𝑚𝑎𝑥) = 13.2 − 6 = 7.2 𝑚
1 1
8𝑇70 𝑆𝜃 (𝑚𝑎𝑥) 2 8(6.592𝑘)(7.2) 2
𝑀𝑎𝑥𝑖𝑚𝑢𝑚 𝑝𝑒𝑟𝑚𝑖𝑡𝑡𝑒𝑑 𝑠𝑝𝑎𝑛 𝑙𝑒𝑛𝑔𝑡ℎ, 𝑠(𝑚𝑎𝑥) = [ ] =[ ]
𝑤 (1.8 × 9.81)
𝑠(𝑚𝑎𝑥) = 146.64 𝑚
COMPILED BY BALUKU