26 42 14.00 10.pdf CP MIL Spec
26 42 14.00 10.pdf CP MIL Spec
26 42 14.00 10.pdf CP MIL Spec
DIVISION 26 - ELECTRICAL
SECTION 26 42 14.00 10
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 QUALITY ASSURANCE
1.3.1 Services of "Corrosion Expert"
1.3.2 Isolators
1.3.3 Anode and Bond Wires
1.3.4 Surge Protection
1.3.5 Nonmetallic Pipe System
1.3.5.1 Coatings
1.3.5.2 Tracer Wire
1.3.6 Drawings
1.4 DELIVERY, STORAGE, AND HANDLING
1.5 EXTRA MATERIALS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 26 42 14.00 10
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
Drawings; G
Contractor's Modifications; G
Equipment; G
Spare Parts
SD-07 Certificates
1.3.2 Isolators
Isolators are required to insulate the indicated pipes from any other
structure. Isolators shall be provided with lightning protection and a
test station as shown.
addition to anodes for the pipe under concrete slab and casing
requirements. For each cathodic system, the metallic components and
structures to be protected shall be made electrically continuous. This
shall be accomplished by installing bond wires between the various
structures. Bonding of existing buried structures may also be required to
preclude detrimental stray current effects and safety hazards. Provisions
shall be included to return stray current to its source without damaging
structures intercepting the stray current. The electrical isolation of
underground facilities in accordance with acceptable industry practice
shall be included under this section. All tests shall be witnessed by the
Contracting Officer.
In the event pipe other than metallic pipe is approved and used in lieu of
metallic pipe, all metallic components of this pipe system shall be
protected with cathodic protection. Detailed drawings of cathodic
protection for each component shall be submitted to the Contracting
Officer for approval within 45 days after date of receipt of notice to
proceed, and before commencement of any work.
1.3.5.1 Coatings
1.3.6 Drawings
After approval of shop drawings, and not later than three (3) months prior
to the date of beneficial occupancy, furnish spare parts data for each
different item of material and equipment specified, after approval of
detail drawings and not later than six (6) months prior to the date of
beneficial occupancy. The data shall include a complete list of parts,
special tools, and supplies, with current unit prices and source of
supply. One (1) spare anode of each type shall be furnished. In
addition, supply information for material and equipment replacement for
all other components of the complete system, including anodes, cables,
splice kits and connectors, corrosion test stations, and any other
components not listed above. [Furnish a reference cell on a reel with 120
m of conductor, along with other accessories, and a digital voltmeter that
can be used in the maintenance of this cathodic protection system. Use of
this equipment shall be demonstrated in actual tests during the training
course, which shall include a description of the the equipment and
measurement of the pipe-to-soil potential, rainfall, and gas company
voltages.]
PART 2 PRODUCTS
d. Submit proof that the materials and equipment furnished under this
section conform to the specified requirements contained in the
referenced standards or publications. The label or listing by the
specified agency will be acceptable evidence of such compliance.
The scope of services shall include, but shall not be limited to, the
following:
c. System testing.
e. Interference testing.
f. Training.
b. PIV.
c. Shutoff valves.
g. Backflow preventer.
h. Culvert.
Fire hydrant pipe components shall have a minimum of two (2) anodes.
These magnesium anodes shall have an unpackaged weight of 7.7 kg.
2.1.6.4 Valves
Gypsum 75
Bentonite 20
Sodium Sulphate 5
Total 100
Wire shall be No. 10 AWG solid copper wire, not less than 3 m long,
unspliced, complying with NFPA 70, Type RHW-USE insulation. Connecting
wires for magnesium anodes shall be factory installed with the place or
emergence from the anode in a cavity sealed flush with a dielectric
sealing compound. Connecting wires for zinc anodes shall be factory
installed with the place of connection to the protruding steel core
completely sealed with a dielectric material.
Cable for anode header and distribution shall be No. 8 AWG stranded copper
wire with type CP high molecular weight polyethylene, 2.8 mm thick
insulation, 600-volt rating.
Wire shall be No. 10 AWG stranded copper wire with NFPA 70, Type [TW]
Polyethylene insulation. Polyethylene insulation shall comply with the
requirements of ASTM D1248 and shall be of the following types, classes,
and grades:
Test wires shall be AWG No. 12 stranded copper wire with NFPA 70, Type TW
or RHW-USE with outer covering or polyethylene insulation.
2.3.2 Conduit
Bonds shall be provided across all joints in the metallic water and gas
lines, across any electrically discontinuous connections and all other
pipes and structures with other than welded or threaded joints that are
included in this cathodic protection system. Unless otherwise specified
in the specifications, bonds between structures and across joints in pipe
with other than welded or threaded joints shall be No. 8 AWG stranded
copper cable with polyethylene insulation. Bonds between structures shall
contain sufficient slack for any anticipated movement between structures.
Bonds across pipe joints shall contain a minimum of 102 mm of slack to
allow for pipe movement and soil stress. Bonds shall be attached by
This coating specification shall take precedence over any other project
specification and drawing notes, whether stated or implied, and shall also
apply to the pipeline or tank supplier. No variance in coating quality
shall be allowed by the Contractor or Base Construction Representative
without the written consent of the designer. All underground metallic
pipelines and tanks to be cathodically protected shall be afforded a good
quality factory-applied coating. This includes all carbon steel,
cast-iron and ductile-iron pipelines or vessels. Coatings shall be
selected, applied, and inspected as specified. If non-metallic pipelines
are installed, all metallic fittings on pipe sections shall be coated in
accordance with this specification section.
b. Pipe and joint coating for factory applied or field repair material
shall be applied as recommended by the manufacturer and shall be one
of the following:
All field joints shall be coated with materials compatible with the
pipeline coating compound. The joint coating material shall be applied to
an equal thickness as the pipeline coating. Unbonded coatings shall not
be used on these buried metallic components. This includes the
elimination of all unbonded polymer wraps or tubes. Once the pipeline or
vessel is set in the trench, an inspection of the coating shall be
conducted. This inspection shall include electrical holiday detection.
Any damaged areas of the coating shall be properly repaired. The
Contracting Officer shall be asked to witness inspection of the coating
and testing using a holiday detector.
Any damage to the protective covering during transit and handling shall be
repaired before installation. After field coating and wrapping has been
applied, the entire pipe shall be inspected by an electric holiday
detector with impressed current in accordance with NACE SP0188 using a
full-ring, spring-type coil electrode. The holiday detector shall be
equipped with a bell, buzzer, or other type of audible signal which sounds
when a holiday is detected. All holidays in the protective covering shall
be repaired immediately upon detection. Occasional checks of holiday
detector potential will be made by the Contracting Officer's
representative to determine suitability of the detector. All labor,
materials, and equipment necessary for conducting the inspection shall be
2.3.17 Casing
PART 3 EXECUTION
3.1.2 Aluminum
For copper piping, the following criteria shall apply: A minimum of 100
millivolts of cathodic polarization between the structure surface and a
3.3 INSTALLATION
Test stations shall be of the type and location shown and shall be curb box
or post mounted. Provide buried insulating joints with test wire
connections brought to a test station. Reference all test stations with
GPS coordinates. Unless otherwise shown, locate other test stations as
follows:
Submit test reports in booklet form tabulating all field tests and
measurements performed, upon completion and testing of the installed
system and including close interval potential survey, casing and
interference tests, final system test verifying protection, insulated
joint and bond tests, and holiday coating test. Submit a certified test
report showing that the connecting method has passed a 120-day laboratory
test without failure at the place of connection, wherein the anode is
subjected to maximum recommended current output while immersed in a three
percent sodium chloride solution.
Before the anode system is connected to the pipe, an isolation test shall
be made at each isolating joint or fitting. This test shall demonstrate
that no metallic contact, or short circuit exists between the two isolated
sections of the pipe. Any isolating fittings installed and found to be
defective shall be reported to the Contracting Officer.
resistance (sensitivity) of not less than 10 megohms per volt and a full
scale of 10 volts. The locations of these measurements shall be identical
to the locations used for baseline potentials. The values obtained and
the date, time, and locations of measurements shall be recorded. No less
than eight (8) measurements shall be made over any length of line or
component. Additional measurements shall be made at each distribution
service riser, with the reference electrode placed directly over the
service line.
Any damage to the protective covering during transit and handling shall be
repaired before installation. After field-coating and wrapping has been
applied, the entire pipe shall be inspected by an electric holiday
detector with impressed current in accordance with NACE SP0188 using a
full-ring, spring-type coil electrode. The holiday detector shall be
equipped with a bell, buzzer, or other type of audible signal which sounds
when a holiday is detected. Holidays in the protective covering shall be
repaired upon detection. Occasional checks of holiday detector potential
will be made by the Contracting Officer to determine suitability of the
detector. Labor, materials, and equipment necessary for conducting the
3.8 SEEDING
3.9 CLEANUP
-- End of Section --