Risk Assessment Piling Works
Risk Assessment Piling Works
Risk Assessment Piling Works
Asmalia Che AHMAD1, Izatul Farrita Mohd KAMAR2, Abdul Muhaimin Ab WAHID1,
Muhamad Fazreen Niza Shah ISMAIL1
ABSTRACT:
This study focuses on the piling works of Mass Rapid Transit (MRT) line 1 construction
project along Sungai Buloh Station to Kajang Station in Malaysia, considering that piling
work is one of the high risk construction activities. This study utilizes risk assessment tool
using Hazard Identification, Risk Assessment & Risk Control (HIRARC) to create safe
construction workplace. The hazard identification is a process of examination work area
and task inherent to piling activities. The risk assessment of piling works calculated using
likelihood and severity. Based on the hazard identification and risk assessment results,
control measures or risk control are taken into action. The risk assessment sheets as the
research instrument tool were filled by 30 construction professionals and safety
practitioners i.e. safety officers, safety supervisors, site engineers and site supervisors. The
results indicated that there were seven hazards that associated with piling works. One of the
hazards which caused structure collapse during test pile activity was assessed as the
extreme risk. Other six hazards were assessed as high risk. The total 27 risk control
measures were resolved in order to eliminate and reduce hazards as well as prevent accident
during piling work at the MRT construction project.
Key-words: Construction, Mass Rapid Transit (MRT), Piling Work, Risk Assessment.
1. INTRODUCTION
Mass Rapid Transit (MRT) is one of the prime transportation infrastructure projects in
Malaysia. MRT construction consists of three MRT urban rail lines. MRT line 1 connects
Sungai Buloh to Kajang which include of 31 stations with the rail span of 51 km. MRT line
2 connects Sungai Buluh to Putrajaya which consist of 40 stations that are spread along the
route. MRT line 3 is the Circle Line that loops around hotspot city area such as Kuala
Lumpur City Center (KLCC) covering 20 km radius of Bukit Bintang, Damansara and
Sentul. For MRT line 1 Sungai Buloh-Kajang, the first phase of construction from Sungai
Buloh to Semantan has been newly operational at the end of 2016. The second phase of
construction, from Semantan to Kajang is fully operational for public passengers by July
2017, allowing trains to run the entire alignment. Each train set serving the line have four
cars, allowing a total capacity of 1 200 passengers. The daily ridership is estimated to be
about 400 000 passengers. The fastest trains run at a frequency of 3.3 minutes (MyMRT,
2017).
1 Universiti Teknologi MARA, Faculty of Architecture Planning and Surveying, Seri Iskandar
Campus, Seri Iskandar, 32610, Perak, Malaysia. asmalia809@uitm.edu.my;
abdul982@uitm.edu.my; fazreen33@gmail.com;
2 Universiti Teknologi MARA, Centre of Postgraduate Studies, Seri Iskandar Campus, Seri Iskandar,
32610, Perak, Malaysia. izatu739@uitm.edu.my,
3 Universiti Teknologi MARA, Green Safe Cities (GreSafe) Research Group, Shah Alam Campus,
40450, Selangor, Malaysia.
Asmalia Che AHMAD, Izatul FarritaMohd KAMAR, Abdul Muhaimin Ab WAHID and … 233
MRT construction is one of the mega project with strict regulation regarding safety,
health and environmental. However, accidents could happen unpredictably and mostly end
with major injuries, fatal and costly massive losses (Albert et al., 2014; Kamar & Ahmad,
2016). Quite a number major accidents related to MRT construction have been reported
which caused fatality and injured cases. In large-scale construction projects, the accident
rate is higher than that of common construction projects due to the involvement of many
workers, many large and heavy plants, various materials, complex construction operation,
multi-interface, and complex management activities (Guo et al., 2013). Construction of
MRT project involved various construction activities that are hazardous such as piling in
obstructed urban area, tunnel excavation with extensive underground services, construction
works near uses public road and usage of high voltage electric for construction works
The prevention of construction accidents usually entails predicting future accident and
their nature under given circumstances (Al-Kilani, 2011). Therefore, it is important to
understand how these accidents and injuries are generated (Chi & Han, 2013). Accident
prediction is done through the risk management process which consists of identification of
the hazard, calculation of the risk assessment and determining safe control measures
(Health Safety Executive, 2006; Perry, 2003; Binnington, 2011). The aim of this study is to
measure and control the risk for one of the critical construction activities in MRT Project
which is piling works. The objectives of this study are to identify hazards during piling
works, to assess the risk level of those hazards and to determine the risk control measures.
The result of this study could benefit the contractor in order to reduce risk of piling works
during MRT construction project. The methodology for this study has taken quantitative
approach using a risk assessment sheet as the instrument tool.
2. LITERATURE REVIEW
2.1. Risk Management
Construction industry is well known with hazardous workplace and accident potential.
There are five sequential dominos contributing to a construction accident i.e. (i) ancestry
and social environment, (ii) fault of a person, (iii) unsafe act and mechanical or physical
hazards, (iv) accident and (v) injury (Chi & Han, 2013; Ridley, 1990; Chong & Low,
2014). Accidents lead to injuries or worst death, and that these accidents occurred when
worker committed unsafe acts or there were direct mechanical or physical hazards related to
the work (Ridley, 1990; Chong & Low, 2014).
The prevention of construction accidents usually entails predicting future accidents and
their nature under given circumstances (Al-Kilani, 2011). Risk management is an approach
to - prevent accidents by early identification and suggesting appropriate control measures.
Risk management refers to the practice of identifying potential hazard in advance,
analyzing and evaluate the risk of those hazard and taking precautionary steps to reduce the
risk (Health Safety Executive, 2006).
2.2. HIRARC
Hazard Identification, Risk Assessment and Risk Control (HIRARC) have become an
essential tool in practice of planning, management and the operation of a basic of risk
management and assessment (Perry, 2003). HIRARC was applied to recognize substandard
act and working condition as list of hazards was developed and analyzed thus to take
necessary corrective action. In line with that, Department of Safety and Health (DOSH) has
highlighted HIRARC as important for identifying hazard, analyzing and assessing its
234
associated risk and then applying the suitable control measures subsequently. The process
of HIRARC is shown in Fig. 1.
Classify Work
Activities
Identify Hazards
Risk Assessment
Review
Risk Control
Implementation
Risk assessment is the overall process of risk analysis (identification and estimation)
and risk evaluation (measurement and tolerance) (Campbell, 2008). In other words, risk
assessment can be defined as the process of assessing the risks associated with each of the
construction hazards identified. The assessment could be done in structured discussion,
consultation or formal meetings (Work Safe Victoria, 2007).
Risk assessment contained information of identified hazards that could periodically
review or updated as construction work progresses (Hinze and Raboud, 1988).
Additionally, the risk assessment need to be done systematically in order the person in
charge of the construction site i.e. project manager and safety officer could resolve whether
they have taken adequate precautions or should do more control measures in order to
prevent harm (Health Safety Executive, 2006).
2.2.3. Risk Matrix
Risk matrix is used as basis to risk assessment. Risk matrix is the combination of
likelihood and consequence or severity range that gives an estimate of risk or risk level.
Construction of a Risk Matrix Level starts by establishing how the matrix is intended to be
used (Ahmad et al., 2016). Initial decision that has to be made is to define the risk
acceptability or tolerability criteria for the organization using the matrix.
Table 1 contains the value of Risk (R) on hazard that equals to multiplication of
Likelihood (L) and Severity (S) of the hazard. Table 2 shows the indication of Risk Matrix
Level that was categorized as Low, Medium, High and Extreme (Department of
Occupational Safety and Health, Ministry of Human Resources Malaysia, 2008).
Severity (S)
Likelihood (L)
Not Critical Low Moderate Very
Critical (4)
(1) Critical (2) (3) critical (5)
Never (1) 1 2 3 4 5
Rare (2) 2 4 6 8 10
Sometimes (3) 3 6 9 12 15
Frequently (4) 4 8 12 16 20
Almost Certain(5) 5 10 15 20 25
3. RESEARCH METHODOLOGY
The scope of study focuses on construction of MRT project. The case study
encompasses piling works on construction of MRT line 1 from Sungai Buloh station to
Kajang station. Fig. 2 shows the route map of MRT Line 1 Sungai Buloh to Kajang.
The types of collected data are primary and secondary data. Primary data entailed risk
assessment involving construction professionals and safety practitioners of MRT project.
Secondary data encompassed progress and safety reports of MRT project. Primary data
were obtained from risk assessment sheets. The risk assessment sheet consist list of hazard
identification, risk assessment and control measure as according to HIRARC process which
tailored for the piling works at MRT construction site. Secondary data were extracted
accordingly to develop the risk assessment sheet which present as the research instrument
tool.
Asmalia Che AHMAD, Izatul FarritaMohd KAMAR, Abdul Muhaimin Ab WAHID and … 237
Table 4. The summary of Hazard Identification, Risk Assessment and Risk Control (HIRARC)
for piling works in MRT construction project with Control Measures Indicator: Excellent.
Activitie Hazard Identification Risk Assessment
s
Piling Hazard Hazard Risk Risk Risk Control Control
Works Identificatio Classific Matri Matrix Ran Measures Measure
n ation x Level k s Mean
Mean
1 Test Pile Structure Safety 12.76 Extreme 1 i Close 3.63
collapse supervision
by assigned
personnel
i Ensure 3.16
i suitable
foundation
for
temporary
works
i Inspection 3.53
i of physical
i load test
material
i Do not 3.23
v seating
under the
load test
border
2 Lifting Unsecure Safety 9.67 High 3 i Assign 3.53
reinforce load/mecha competent
ment and nical failure person
casting i Using ‘tag 3.16
i line’ during
lifting
work3.16
i Carry out 3.00
i physical
i inspection
for lifting
i Sling—do 3.26
v not stand
under
suspension
load
v Appoint 3.10
banksman
3 Machine Machinery Safety 9.06 High 4 i Machinery 3.30
ry work movemen/m inspection
echanical i Supervision 3.46
failure i during
movement
i Competent 3.53
i person
Asmalia Che AHMAD, Izatul FarritaMohd KAMAR, Abdul Muhaimin Ab WAHID and … 239
i
i Appoint 3.40
v banksman
4 Concrete Mixer truck Safety 8.40 High 5 i Provide 3.50
work movement proper
access
i Appoint 3.80
i banksman
i Apply speed 3.36
i limit
i
5 Welding Heat/burn/h Safety & 7.63 High 6 i Obtain hot 3.36
& oxy armful fume Health work permit
cutting i Attend 3.4
i toolbox
briefing
i Brief on 3.36
i HIRARC &
i method
statement
i Provide 3.60
v PPE
v Provide fire 3.46
extinguisher
6 Concrete Chemical Health 6.40 High 7 i Use proper 2.90
work hazard PPE to
avoid
irritation
and
splashing
i Brief on 3.60
i HIRARC &
Control Measures Indicator: Good method
statement
7 Excavati Landslide/s Safety 9.86 High 2 i Machinery 3.3
on of heet pile inspection
pile cap topple i Supervision 3.36
i during
movement
i Competent 3.30
i operator
i
i Appoint 3.46
v banksman
5. CONCLUSIONS
This risk assessment study has found that there were seven identified hazards during
piling works of MRT project. One hazard had been assessed as extreme risk and other six
hazards were high risks providing evidence that piling work for MRT construction was
hazardous, risky and dangerous. For improving this hazardous situation, 27 risk control
actions were conducted. All the control measures were rated as excellent actions with only
240
one control act rated as good. These findings conclude that the MRT has taken an excellent
risk control actions to counteract the perilous MRT construction site. Furthermore, this
study also highlights HIRARC as a vital risk assessment tool that assist hazards
identification, assessing the risk level and risk control measures with the purpose of
eliminating or reducing the hazards of piling works at MRT construction project.
ACKNOWLEDGEMENTS
This study was supported by Ministry of Higher Education, Malaysia through Fundamental Research
Grant Scheme (Ref: FRGS/1/2016/SSI11/UITM/03/1). The authors also would like to thank
Universiti Teknologi MARA, Perak Branch and MRT staff for the assistance and opportunity to share
these research findings in international conferences and publications.
REFERENCES
Ahmad, C. A, Zin, I. N. M., Wahid, A. M. A. & Kamar, I. F. M. (2016), Hazard and risk of highway
maintenance: case study of PLUS Expressways, In The 4th International Building Control
Conference 2016, MATEC Web of Conferences, 66 (106), 1-7.
Albert, A., Hallowell, M. R & Kleiner, B. M. (2014) emerging strategies for construction safety &
health hazard recognition. Journal of Safety, Health & Environment Research, 10 (2), 152-161.
Al-Kilani, F. M. (2011), Improving safety performance in construction projects in libya (case study:
in Tripoli City): Master Thesis. Diponegoro University, Semarang, Indonesia.
Binnington, B. (2011) Managing risks in construction work draft code practice. Safe Work
Australia, Australia.
Campbell, J. M. (2008) Safety hazard and risk identification and management in infrastructure
management: doctoral dissertation. The University of Edinburgh, Scotland.
https://www.era.lib.ed.ac.uk/handle/1842/3170
Carter, G. & Smith, S. (2006) Safety hazard identification on construction projects. Journal of
Construction Engineering and management, 132(2):197-205.
Chi, S. & Han, S. (2013) Analyses of systems theory for construction accident prevention with
specific reference to Osha accident reports. International Journal of Project Management, 31
(7), 1027-104.
Chong, H. Y. & Low, T. S. (2014) Accidents in Malaysian construction industry: statistical data and
court cases. International Journal of Occupational Safety and Ergonomics, 20 (3), 503-513.
Department of Occupational Safety and Health, Ministry of Human Resources Malaysia, (2008)
Guidelines for Hazard Identification, Risk Assessment and Risk Control (HIRARC), Ministry of
Human Resources, Malaysia, 6-12.
Fang, D. P., Xie, F, Huang, W. Y. & Li, H. (2004) Factor Analysis-based Studies on Construction
Workplace Safety Management in China. International Journal of Project Management, 22, 43-
49.
Goetsch, D. L. (2009) Construction Safety & OSHA Standards. Prentice Hall, 89-90.
Guo, H. L., Li, H. & Li, V. (2013) VP-Based Safety Management in Large-Scale Construction
Projects: A Conceptual Framework, Automation in Construction, 34, 16–24.
Hamid, A. R. A., Yusuf, W. Z. W. & Singh, B. (2003) Hazards at Construction Site, In Proceedings
of the 5th Asia Pacific Structural Engineering and Construction Conference (ASPEC).
http://eprints.utm.my/445/
Health Safety Executive (2006), Risk Assessment: A Brief Guide to Controlling Risks in the
Workplace. Health Safety Executive, U.K. 1-5.
Hinze, J. & Raboud, P. (1988) Safety on large building construction projects. Journal of
Construction Engineering and Management,114 (2), 286-293.
Asmalia Che AHMAD, Izatul FarritaMohd KAMAR, Abdul Muhaimin Ab WAHID and … 241
Huges, P. & Ferrett, E. (2008) Introduction to Safety and Health in Construction. Elsevier Ltd. 68-
80.
Kamar, I. F. M. & Ahmad, C.A. (2016) A Conceptual Framework of Safety and Health in
Construction Management, In The 4th International Building Control Conference 2016,
MATEC Web of Conferences, 66 (107), 1-9.
Lam, P. T. I., Chan, E. H. W., Poon, C. S., Chau, C.K. & Chun, K. P. (2010) Factors affecting the
implementation of green specification in construction. Journal of Environmental Management,
93 (3), 654-661.
MyMRT (2017) The MRT Sungai Buloh-Kajang Line. Retrieved from
http://www.mymrt.com.my/en/sbk/travel-info
Perry, P. (2003) Construction Safety Question and Answer: A practical Approach. Thomas Telford
LTD, Victoria, 181-190.
Ridley, J. R. (1990) Safety at Work. Third Edition. Butterworth Heinemann Ltd. 153-158
Stefanescu, L., Botezan, C. & Craciun, L. (2018) Vulnerability Analysis for Two Accident Scenarios
at An Upper-Tier Seveso Establishment in Romania. Geographia Technica, 13 (1), 109-118.
Welfare Health & Safety Unit. (2015) Hazard Identification, Risk assessment and control procedure.
Western Sydney University, Australia.
Work Safe Victoria. (2007) A Handbook for Workplaces-Controlling OHS Hazards and Risk,
Victoria State Goverment.