GM R134a - ATA 21-00-01
GM R134a - ATA 21-00-01
GM R134a - ATA 21-00-01
Seminole, OK 74868
Phone (405) 382-0731
Fax (405) 382-0737
http://www.enviro-ok.com
MAINTENANCE MANUAL
General Systems
REVISIONS
H Re- format document, combine Section 12.1 thru 12.10 into 04/27/0 BH
Table 2. 7
J Section 9.1was Isopropyl Alcohol is R-134a Refrigerant (flushing 6/5/07 BH
fluid)
K Correct Document Header to Current Revision, no subject 6/8/07 BH
matter changes
L Section 12 Inspection Schedule…Evaporators…removed all 10/3/08 BH
references to brush inspection and replacement.
M Section l2 Maintenance Schedule Table 2 update to approved 08/11/1 BH
time requirements. Section 8.29 and Figure 3 deleted. Was 1
brush wear calculations and example. Figures 3.3, 3.4, and 3.5
added. Section 8.7 refer to Section 12 Maintenance Schedule
for Brush replacement. Section 16 Figure 6 deleted, was Brush
Wear Example
N Section 8.1 add WARNING 08/25/1 BH
1
1 Updated entire manual using ATA Spec 2200 as guide. 10/05/1 BH
Changed number of manual to 21-00-01 was(GM R-134a). 1
Show revisions numerically Renum. Sections to Outline Format
TABLE OF CONTENTS
REVISIONS .......................................................................................................................................... 1
TABLE OF CONTENTS ....................................................................................................................... 2
LIST OF TABLES ................................................................................................................................. 3
LIST OF FIGURES ............................................................................................................................... 3
1 MANUAL INTRODUCTION ............................................................................................................. 4
1.1. General introduction (How to Use): ............................................................................................. 4
1.2. Acronyms, Abbreviations, and Symbols: ..................................................................................... 5
1.3. Standard Torque Values:............................................................................................................. 5
1.4. Documents Required:.................................................................................................................. 5
1.5. Consumable Products: ................................................................................................................ 6
2 SYSTEM DESCRIPTION R-134a.................................................................................................... 7
2.1. General: ....................................................................................................................................... 7
2.2. General System Description and Operation................................................................................ 8
2.3. System R-134a Component Location: ........................................................................................ 8
3 TESTING AND FAULT ISOLATION ................................................................................................ 9
3.1. General: ....................................................................................................................................... 9
3.2. Compressor Condenser Module Assembly Testing Procedures: ............................................... 9
3.3. Evaporator Module Assembly Testing Procedures ..................................................................... 9
3.4. System Leak Check Testing Procedure: ................................................................................... 10
4 EVACUATION AND CHARGING PROCEDURE: ......................................................................... 13
4.1. General ...................................................................................................................................... 13
4.2. Evacuation Procedure: .............................................................................................................. 14
4.3. Refrigerant Charging Procedure:............................................................................................... 14
5 EXPANSION VALVE ADJUSTMENT/BALANCING PROCEDURE .............................................. 17
5.1. General ...................................................................................................................................... 17
5.2. Expansion Valve Adjustment:.................................................................................................... 17
5.3. Valve Balancing Procedure: ...................................................................................................... 18
6 COMPRESSOR DRIVE BELT INSPECTION & MAINTENANCE ................................................. 19
6.1. General: ..................................................................................................................................... 19
6.2. Belt Removal Procedure:........................................................................................................... 19
6.3. Drive Belt Replacement Procedure: .......................................................................................... 19
6.4. Drive Belt Alignment Procedure: ............................................................................................... 20
6.5. Drive Belt Tensioning Procedure:.............................................................................................. 20
7 COMPRESSOR DRIVE MOTOR INSPECTION AND MAINTENANCE ....................................... 22
7.1. Drive Motor Inspection............................................................................................................... 22
7.2. Motor Brush Inspection Procedure: ........................................................................................... 22
7.3. Commutator Wear Inspection:................................................................................................... 24
7.4. Motor Insulation Resistance Check:.......................................................................................... 26
7.5. Internal Contamination Inspection: ............................................................................................ 26
7.6. Motor Bearing Inspection:.......................................................................................................... 27
7.7. Motor Brush Replacement......................................................................................................... 27
7.8. Motor Removal: ......................................................................................................................... 29
7.9. Motor Replacement: .................................................................................................................. 30
8 COMPRESSOR ASSY R-134a INSPECTIONS AND MAINTENANCE ........................................ 31
8.1. Special Tools And Equipment Required:................................................................................... 31
8.2. Compressor Inspection Procedure:........................................................................................... 31
8.3. Compressor Removal:............................................................................................................... 31
8.4. Compressor Replacement:........................................................................................................32
8.5. Compressor Oil Level Check:.................................................................................................... 33
9 EVAPORATOR MODULE INSPECTION AND MAINTENANCE .................................................. 34
LIST OF TABLES
LIST OF FIGURES
1. MANUAL INTRODUCTION
1.1. General introduction (How to Use):
1.1.1. This operating, servicing and component maintenance manual (CMM) covers the
requirements for field servicing the R-134a air conditioning system. This document includes
general component information for servicing, maintenance, inspection requirements. list.
1.1.2. This component maintenance manual has been prepared with guidance from the Air
Transport Association of America (ATA) Specification 2200. The user must not change the
repair methods in this manual without authorization from the aviation authorities and the
manufacturer.
1.1.3. This manual gives the procedures to perform the servicing and maintenance of the
component in a workshop environment as well as on the aircraft. Only approved personnel
with the necessary skills shall perform the maintenance procedures in this manual. Although
Enviro Systems tries to cover all conceivable issues that may arise, there may be issues that
are not covered in this manual. In these cases, please call Enviro Systems customer service.
1.1.4. You should use the instructions in this manual to do all the maintenance procedures related
to the component. Read all the related warnings, cautions and notes before you begin work
on the components. Warnings, cautions and notes shown in this manual provide the
following information:
1.1.4.1. WARNING: Discloses vital information in order to prevent injury or death while
performing the maintenance procedure.
1.1.4.3. NOTE: Discloses more information that will help perform a step of the
procedure or refers to a different procedure.
2.1.1. The air conditioning system installed on the aircraft is not considered a primary flight
system. However, an air conditioning system does perform the important function of
providing passenger and flight crew comfort during aircraft movement on the ground and
while in flight. Aircraft air conditioning systems not only provide effective passenger
cooling, but must also maintain a high level of reliability to minimize aircraft downtime due
to unscheduled repairs.
2.1.2. In order to ensure component reliability and achieve a long service life for which the
system is designed, periodic inspection and preventive maintenance must be performed.
Failure to complete periodic inspections, service, or maintenance schedules may reduce
product life and potentially void manufacturer’s warranty.
2.1.3. Inspections, servicing, and/or maintenance schedules are presented in the following
sections. This will ensure component and/or system reliability and performance are
maintained when performed at the specified intervals.
WARNING: PROPER VENTILATION IS REQUIRED. KEEP REFRIGERANTS AND OILS AWAY FROM
OPEN FLAMES. REFRIGERANTS CAN PRODUCE POISONOUS GASSES IN THE PRESENCE OF A
FLAME. WORK IN A WELL VENTILATED AREA AND AVOID BREATHING REFRIGERANT
/LUBRICANT VAPOR MIST IF ACCIDENTAL DISCHARGE OCCURS.
2.1.4. Do not discharge R-134a refrigerant into the atmosphere. Although its ozone depletion
potential is zero, it can have an effect on global warming. In the United States recovery
and recycling are mandated by the Clean Air Act
2.1.5. Refrigerant recovery/recycling service equipment must be approved for use with R-134a
refrigerant. Recycling machines must be approved by Underwriters Laboratories (UL)
and meet SAE standard J2210 and SAE standard J2099 for refrigerant purity.
2.2.1. The type of cooling system installed in an aircraft operates on a closed vapor cycle
concept using refrigerant R-134a as the heat absorption media. The Airborne R-134a Air
Conditioning System cools the aircraft in the same manner as a cooling system in an
automobile or home. However, one major difference in two type systems is the Airborne
R-134a System contains components which are designed to be light weight, compact,
provide high performance and operate at extreme altitudes and ambient temperatures.
The Airborne R-134a Vapor Cycle cooling system provides the highest performance per
aircraft horsepower than any other present cooling concept.
2.2.2. The concept of air-conditioning a room, cabin or cockpit is actually very simple. A typical
system is shown in Figures 4, refrigerant and Figure 5, the electrical schematic. The
refrigerant is the media which absorbs and rejects the room or cabin heat. By continuous
recirculation of the cabin the warm cabin air is absorbed in the evaporator module (s) and
the heat is rejected to the outside through the system condenser. When the system is
turned on the electric motor drives an R-134a compressor at a constant speed and
capacity which compresses the R-134a refrigerant gas to a high pressure. The hot, high
pressure gas then passes through the condenser coil where it is cooled and condensed
into a warm liquid at constant pressure. The warm liquid is then routed into a receiver-
dryer container in which the liquid and any remaining gasses are separated and any
moisture in the liquid is absorbed. The warm, dry, high quality liquid is then directed to
the evaporator module expansion valve where the high pressure liquid is expanded to a
low pressure. The expansion process creates a super cool gas which passes through
the evaporator coil and absorbs heat from the warm cabin air passing over the coils. The
low pressure warm gas enters the R-134a compressor where the process starts again.
In addition to cooling the air in the cabin, a refrigerant type system also removes a large
percentage of the moisture, dust and pollen particles in the air. Thus, the system
conditions the air as well as cooling it.
2.3.1. An Airborne R-134a Air Conditioning System may consist of one or more compressor-
condenser and evaporator modules. Location of these components will depend on
system effectiveness, available space and aircraft center of gravity restrictions.
2.3.2. The Compressor Condenser Module Assembly is packaged to meet the aircraft
installation requirements and contains the following major components.
Compressor Drive Motor
Compressor Assembly
Condenser Coil
Receiver Dryer Assembly
Binary Pressure Switch
3.1.1. Testing and Fault Isolation of the R-134a Air Conditioning System may be necessary if the
system does not operate and/or perform in accordance with information contained herein.
Therefore it is necessary for the service personnel to diagnose the discrepancy by
troubleshooting the system and its components. To assist in this diagnoses, refer to table 3
(Trouble Shooting List)
3.2.1. Ensure that power is applied to the aircraft and that the air conditioning system is switched on
using the cockpit mounted selector switch. Gain access to the Compressor Condenser
Module (refer to the aircraft maintenance manual for removal of access panels and other
hardware that might need to be removed). Verify that these components are operating and
perform the following:
Verify that system is running smoothly and that there is no excessive noise and/or vibration
coming from the assembly.
Verify that the system is cooling properly.
3.2.2. If there is excessive noise and/or vibration coming from the Compressor Condenser Module
assembly or the system is not cooling, refer to the Disassembly procedures in section 5 and
Check (inspection) procedures in section 7. This will help in identifying whether one or more
components are dirty or damaged and are in need of repair or replacement.
3.3.1. Verify blower motor operation in both low and high speed positions using cockpit mounted
selector switch.
3.3.2. While blower motor is operating in both positions, listen carefully for the following:
Verify that there is a distinct and noticeable change in sound of blower motor when changing
from low to high speed positions. This indicates that the cockpit selector switch is functioning
properly and that the blower motor is responding accordingly.
Verify that there is a smooth transition when changing from low to high speed positions, and
that there is no excessive noise or vibration coming from the blower motor during the change.
Excessive noise could indicate that the blower wheel is rubbing against the blower scroll.
3.3.3. If there is excessive noise and/or vibration coming from blower motor/wheel assembly during
this test, please refer to the disassembly procedures in section 5 and inspection procedures
in section 7. This will help in identifying whether the blower motor wheel is dirty or damaged
and is need of repair or replacement, the blower scroll is dirty or damaged and is need of
repair or replacement, or the blower motor itself is in need of replacement.
3.3.4. Verify that the system is cooling properly. If not, the expansion valve(s) might need aligning.
Refer to Special Procedures, Section 5, for Expansion Valve Alignment procedures.
3.4.1. A leak check of the refrigerant plumbing system is important to ensure the system maintains
its charge to provide the designed performance and reduce damage to system components.
A periodic check of the system charge is required to determine if any loss of refrigerant has
occurred.
3.4.2. A system leak check is required any time one or more of the following conditions occur:
New system plumbing installation
Component replacement in the plumbing system
Line or hose rupture
3.4.3. Special Tools and/or Equipment Required:
Gaseous dry nitrogen, regulated source (0-500 psig)
R-134a refrigerant charging manifold with gauges and hoses
Leak check fluid (soap solution)
Assorted hand tools
Hand and eye protection
Hose adapter (1/2 in. male acme to ¼ in. female flare)
3.4.4. Procedure
WARNING
DURING THIS PROCEDURE PROTECTIVE EYEWEAR AND GLOVES SHOULD BE WORN TO
PREVENT OPERATOR INJURY.
3.4.4.1. Remove, if required, all panels, doors, shrouds, etc, to gain access to
system/component being leak checked (refer to aircraft maintenance manual).
3.4.4.2. Remove, if required, any enclosures or access doors to expose all tubing,
hoses, fittings, etc. to the system components.
3.4.4.4. Verify that power is removed from aircraft. If it is not practical to remove
aircraft power, technician must pull and collar applicable circuit breakers.
CAUTION: HIGH PRESSURE HOSE (RED) IS CONNECTED TO PORT MARKED “D” AND THE LOW
PRESSURE HOSE (BLUE) IS CONNECTED TO THE SERVICE PORT MARKED “S”. INCORRECT
CONNECTION COULD RESULT IN MANIFOLD DAMAGE AND/OR INCORRECT PRESSURE READINGS.
3.4.4.5. Remove service port caps from the A/C system. The high pressure service
port is located on the receiver-dryer and low pressure service port is located
on the compressor suction header.
3.4.4.6. Close all manifold gauge valves and verify hose connections are tight.
NOTE: An adapter is required to connect yellow charging hose to the nitrogen source.
CAUTION: DO NOT EXCEED 150 PSIG NITROGEN PRESSURE DURING PROCEDURE OR DAMAGE TO
EXPANSION VALVE WILL RESULT.
3.4.4.10. Slowly open high pressure (red) manifold valve and allow system pressure to
increase gradually until a pressure of 150psig is achieved. Allow time for
system pressure to equalize across expansion valve and note final system
pressure.
CAUTION: DO NOT USE ANY LEAK DYE IN R-134A SYSTEM OR DAMAGE TO SYSTEM MAY RESULT.
3.4.4.11. Apply soapy leak check fluid to each fitting connection. If leaks are detected,
attempt to tighten fitting without over tightening. If leak cannot be corrected
with tightening, system must be evacuated (refer to Servicing, Section 4) and
then fitting must be disconnected and new thread sealant applied.
3.4.4.12. Using a wire brush and cleaning solvent, completely remove old thread
sealant. Apply a thin layer of thread sealant primer to fitting threads.
CAUTION: WHEN APPLYING THREAD SEALANT, TAKE EXTREME CARE TO KEEP SEALANT OFF
FIRST 2 OR 3 THREADS.
3.4.4.13. Apply Loctite thread sealant on all male fitting threads sparingly.
CAUTION: WHEN APPLYING REFRIGERANT OIL TO FLARE AND O-RING, TAKE EXTREME CARE TO
KEEP OIL AWAY FROM FITTING THREADS
3.4.4.14. Apply a light coating of refrigerant oil to flare and/or o-ring to prevent metal
galling or o-ring damage.
3.4.4.15. Tighten joints as required to stop leaks (refer to Table 1, Section 1 for torque
values).
CAUTION: VENT SYSTEM PRESSURE VERY SLOWLY TO ASSURE COMPRESSOR OIL IS NOT
VENTED WITH THE NITROGEN. DO NOT LET AIR ENTER THE SYSTEM.
3.4.4.16. After leak check is finished and system integrity is sound, turn off nitrogen
source, disconnect yellow charging hose from nitrogen source and slowly
release nitrogen pressure to zero
EFFECTIVITY: ALL 21-00-01
Page 11
OCTOBER 05, 2011
General Servicing and
Maintenance
R-134a
3.4.4.18. System is now ready for charging (refer to, Section 4.3).
4.1.1. Charging the refrigerant R-134a system is required on new system installations, after an
accidental line break, component failure, and excessive leaks. Due to the chemical
nature of the refrigerant, every precaution must be taken to protect the service person
from accidental exposure to the refrigerant. See service precautions in section 14.0.
Only R-134a refrigerant must be used or damage to the system will result. Overcharging
the system with refrigerant and/or oil will also result in system damage or reduction in
performance and service life.
Note: Prior to charging the system with refrigerant the system must be evacuated for a minimum of 45
minutes to remove all air and moisture which can cause the system to perform incorrectly.
4.2.3. Connect charging manifold to service ports (ref. section 4.2.1 through 4.2.3).
4.2.4. Connect manifold (yellow) hose to the vacuum pump and turn pump on. An adapter may
be required to allow vacuum pump hookup.
4.2.5. Open both valves on charging hose quick connect fittings to depress core if so equipped.
NOTE: Low pressure gauge "blue" will indicate vacuum value on lower range of gauge.
4.2.7. Evacuate system for 30 minutes. System vacuum should obtain 25-27 in. hg in 10 to 15
minutes.
4.2.8. Allow pump to hold a hard vacuum (29 to 30 in. hg.) for 15 minutes.
4.2.9. Close manifold valves and shutoff vacuum pump. Vacuum in system must not change
after 5 minutes.
4.2.10. Disconnect manifold service (yellow) hose. System is ready for refrigerant charging.
CAUTION: EXCESSIVE WATER OR AIR IN THE SYSTEM WILL CAUSE PRESSURE TO RISE, AND
THE EXPANSION VALVE TO FREEZE-UP.
4.3.3. Connect yellow manifold charging hose to R-134a cylinder shutoff valve and open.
EFFECTIVITY: ALL 21-00-01
Page 14
OCTOBER 05, 2011
General Servicing and
Maintenance
R-134a
4.3.4. Crack hose fitting at manifold and purge hose. If system refrigerant charge is to be
recorded place refrigerant container on a 0-50 lb. scale and note the initial weight.
4.3.5. Open both manifold valves and allow refrigerant gas to enter system. Continue adding
refrigerant until system internal pressure has stabilized.
4.3.6. Close manifold valves and verify system internal pressure is 50 PSIG or greater.
NOTE: If internal pressure is not 50 psig or above the low pressure cutout switch will not close and the
drive motor power contactor will not operate. To assure an internal pressure of 50 psig the R-134a
charging can or container must be heated to obtain a minimum charge pressure of 70-80 psig.
WARNING: DO NOT HEAT R-134a CAN OR CONTAINER WITH OPEN FLAME OR CONTAINER
DAMAGE MAY RESULT WITH POSSIBLE INJURY TO OPERATOR. HEAT THE CONTAINER WITH
WARM WATER OR ROOM TEMPERATURE.
4.3.7. Verify system electrical power is off and connect an external, 28 VDC, 200 amp power
source to the aircraft.
CAUTION: DO NOT OPERATE SYSTEM WITH THE HIGH PRESSURE VALVE OPEN ON THE
CHARGING MANIFOLD GAUGE SET.
4.3.8. Turn aircraft power on, set evaporator blower speed to high position and turn the mode
switch to air-conditioning position.
4.3.9. With system operating, observe the system discharge and suction pressure values and
refrigerant condition in the receiver-dryer sight glass.
NOTE :A flashlight and inspection mirror is required during the system charging procedure. Excessive
bubbles in the sight-glass indicate a low refrigerant level.
4.3.10. With the R-134a cylinder connected to the charging hose, charging container shutoff
valve open and with hose purged, slowly open the suction (blue) manifold valve. The
suction pressure will increase to 60-70 psig while the R-134a refrigerant enters the
compressor.
NOTE: As refrigerant enters the compressor a slight increase in discharge pressure will be noted (2-5
psig). Also, compressor speed will reduce slightly.
4.3.11. Continue to add refrigerant per the above procedure until the sight-glass is clear of
excessive bubbles when charged on a hot day (95-105F)
NOTE: A desired sight-glass liquid condition is when only occasional bubbles are observed when
charging on a hot day (95-105°F.).
4.3.12. Close suction manifold valve (blue) and let system operate for 5-10 minutes and then
check sight-glass. If sight-glass is not totally clear, open suction manifold valve and add
a small quantity of refrigerant until 98% of bubbles disappear. Close manifold valve and
let system stabilize.
NOTE: Letting the system stabilize is required since the expansion valve is trying to stabilize to the
preset suction pressure value.
EFFECTIVITY: ALL 21-00-01
Page 15
OCTOBER 05, 2011
General Servicing and
Maintenance
R-134a
4.3.13. With the system fully charged and operating, observe the suction and discharge
pressures. Typical values at various ambient temperatures, with hot cabins, are shown
below:
OUTSIDE AMBIENT SUCTION DISCHARGE
TEMPERATURE (°F) PRESSURE (PSIG) PRESSURE (PSIG)
60-70 28±1 145-150
80 30±1 195±10
95 34±2 215±10
103 37±2 230±10
Figure 1 Suction and Discharge Pressure
NOTE: Whenever possible charge the system on a hot day (90-100 °F). If not "topping off" may be
required for hot ambient temperatures.
NOTE: After shutdown both suction and discharge pressures will immediately start equalizing.
Pressures should be equal in 60 to 90 seconds for those systems containing expansion valves with
bleeds.
WARNING: HAND AND EYE PROTECTION MUST BE WORN DURING THIS OPERATION TO
PREVENT SUBCOOLED REFRIGERANT FROM BURNING THE EYES OR HANDS.
4.3.15. Close refrigerant container shutoff valve (turn cw). Record the refrigerant container final
weight and calculate system refrigerant charge as follows: Charge (lb.) + W initial (lb.)- W
final (lb.)
4.3.16. Turn knob on suction and discharge charging hose quick coupler to closed position and
disconnect hoses from service ports.
4.3.17. Remove yellow charging hose from refrigerant container and store manifold gauge set.
5.1.1. Even though the automatic expansion valve is set at the factory there may be times when
it must be adjusted to assure proper refrigerant flow at the desired evaporating
temperature, due to excessive pressure drop for long suction line runs. Any adjustment
must not affect desired suction and discharge pressures as outlined in Section 4.3.13.
5.2.1. The expansion valve adjustment shall be performed in accordance with, but not limited
to, the following:
5.2.1.1. Verify that system leak check and refrigerant charging has been
performed and system is operating at typical values as outlined in
paragraph 5.3.13.
5.2.1.2. Remove all shrouds, covers or closures which prevent access to the
evaporator expansion valve adjust knob.
5.2.1.4. Verify that inlet to evaporator coil and blower ducting are free of any
contamination or restrictions which could alter air flow.
5.2.1.7. Close cabin and cargo doors and allow system to operate for 5 minutes.
5.2.1.8. Record compressor suction and discharge pressures and evaporator air
inlet and outlet temperatures.
5.2.1.10. If suction pressure is lower than values outlined Section 4.3.13 the
expansion valve must be turned CW in accordance with same procedure
as discussed in paragraph 5.2.1.9.
5.2.1.11. Allow system to operate for 5-10 minutes after expansion valve adjustment
to verify setting.
5.2.1.13. Shut system off and replace all shrouds, enclosures, ducting as required
and remove charging manifold gauges and hose assy.
WARNING: EYE AND HAND PROTECTION SHOULD BE WORN DURING THIS OPERATION.
5.3.2. Adjust the expansion valve on the evaporator with the highest outlet air temperature 1/4
revolution in a CW direction. This will increase the refrigerant flow and reduce the outlet
air temperature.
5.3.3. Adjust the remaining evaporator(s) with a lower outlet air temperature 1/4 revolution
CCW.
5.3.4. Allow system to stabilize, recheck the evaporator outlet temperatures and repeat
adjustment procedure if required. Evaporator outlet temperatures should be within 1-3F
of each other
NOTE: Proper evaporator balancing should not result in a change of the compressor suction pressure.
Verify system pressures are within values shown in Section 4.3.13.
5.3.5. If evaporator outlet temperatures are equal and suction pressure meets Section 4.3.13
servicing is complete. If not, repeat sections 5.2 and 5.3.
5.3.6. Shut system off and replace all shrouds, enclosures, ducting as required and remove
charging manifold gauges and hose assembly.
6.1.1. Inspection of the compressor drive train components according to the Inspection
Schedule (Section 12 Table 4) is recommended. A visual inspection should verify proper
belt alignment and detect premature component wear. Examine the belt and pulleys for
excessive and/or uneven wear.
6.1.2. When the compressor drive belt requires removal and replacement, tensioning or
alignment the following procedures will apply:
6.2.2. Remove all access panels and exhaust ducts to gain access to compressor module.
6.2.4. With socket and box end type wrenches slightly loosen the two 3/8 bolts that support the
R-134a compressor.
6.2.5. Loosen (ccw turn) tension nut on compressor side of rod end bearing and swing
compressor down to loosen belt.
6.2.6. Loosen socket head set screws in motor pulley and slide pulley off motor shaft while at
the same time sliding the drive belt off the compressor pulley.
NOTE: This procedure assures that the motor pulley flange and belt are not damaged during removal.
CAUTION: DO NOT BEND OR TWIST EXCESSIVELY THE DRIVE BELT DURING REMOVAL OR
DAMAGE MAY RESULT.
6.2.7. Inspect belt for cracks or missing teeth and clean any oil or other contamination from
both pulleys and belt.
6.3.1. Verify belt size and part number before installing or damage may result.
6.3.3. Place belt on motor pulley and slide pulley on end of motor shaft and at the same time
slide belt over compressor pulley. Slightly tap motor pulley on shaft until belt completely
covers compressor pulley.
NOTE: Verify the belt teeth are in the grooves of each pulley and during installation slightly rotate both
pulleys to assure proper engagement.
CAUTION: DURING THIS PROCEDURE DO NOT SHARPLY BEND OR TWIST THE BELT AND DO
NOT ALLOW BELT TO ROTATE ON MOTOR PULLEY FLANGE. DAMAGE TO BOTH MAY RESULT.
6.3.4. After belt is installed, rotate the compressor pulley clockwise to align belt on pulley. Belt
must ride directly over the compressor pulley.
NOTE: If the belt is too far forward or aft on the compressor pulley the motor pulley must be adjusted
fore or aft to allow belt to ride directly over compressor pulley.
6.3.5. If belt alignment is good, slightly tighten the two (2) 3/8 compressor support bolts and
turn rod end bearing adjust nut until snug.
6.4.1. Loosen motor pulley set screws, if required, with pulley on shaft and rotate compressor
pulley clockwise (cw). At the same time slide the motor pulley forward or aft until the belt
rides directly over the compressor pulley.
6.4.2. Slightly tighten motor pulley set screws and rotate the compressor pulley (cw) for
approximately ten (10) revolutions to assure belt is tracking as required. If so, tighten set
screws.
CAUTION: ALL BOLTS AND NUTS MUST BE SLIGHTLY TIGHT BEFORE ALIGNMENT IS
PERFORMED OR GROSS BELT AND/OR COMPRESSOR ALIGNMENT MAY RESULT.
6.5.1. Verify all the compressor mounting hardware is slightly tight and belt is properly aligned.
6.5.2. Apply hand pressure to the compressor to increase belt tension and tighten upper
compressor mounting bolt.
NOTE: A Wagoner FDK-10 spring loaded force gage is required for this procedure.
CAUTION: DO NOT OVER TENSION BELT. BELT OR MOTOR BEARING DAMAGE MAY RESULT.
6.5.3. Place Enviro belt tension tool on drive belt and orient as shown in Figure 2.
6.5.4. Position the spring scale into the pilot hole on the tensioning fixture corresponding to the
belt mid-span between pulleys.
6.5.5. Depress the spring scale until the plunger housing contacts the tension tool surface.
NOTE: This is equivalent to a belt deflection of 0.10 inch with a mid-span force of 1.50 to 1.75 pounds.
6.5.8. When proper belt tension is obtained tighten compressor mounting bolts Torque the nuts
to 175-200 in-lbs.
6.5.9. Recheck belt alignment as described in Section 6.4 and adjust as required.
7.1.2. Inspection of the drive motor will consist of, but not limited to, the following:
Brush wear inspection
Commutator wear inspection
Internal contamination inspection
Bearing noise inspection
7.2. Motor Brush Inspection Procedure:
WARNING: MAKE INSPECTION EVERY 300 HOURS LOGGED ON AIRFRAME HOUR METER.
CHECK HOUR METER ON COMPRESSOR CONDENSER MODULE FOR MANDATORY BRUSH
REPLACEMENT SCHEDULE
7.2.2. Remove all access panels and exhaust ducts to gain access to the drive motor.
7.2.3. Disconnect power leads from motor terminals (1/4 - 28). Tag positive lead
7.2.4. Remove condenser support bracket to provide access to brush cover fasteners and
remove motor cuff shroud.
7.2.5. Loosen and unsnap brush cover assy. Remove from motor.
7.2.6. With wire, hook or scribe lift brush spring and remove brush.
7.2.7. Inspect brush for cracks, chipped edges, frayed leads, loose rivets or shunt connections.
Replace defective brush(s).
7.2.8. Continue inspection until all brushes have been observed. In addition, inspect brush
holders and springs for looseness, as well as damage from arcing, heat distortion or
cracks.
7.2.9. With brushes removed and using shop air at 40 psig (max) and nozzle. Blow out as
much carbon and/or copper dust as possible out of the commutator, armature and field
windings. Purge from the commutator end of the motor.
WARNING: EYE AND MOUTH PROTECTION MUST BE USED DURING THIS OPERATION OR
EXCESSIVE LUNG AND EYE IRRITATION WILL RESULT. DO NOT DIRECT AIR JET ON BEARINGS
OR INTERNAL CONTAMINATION WILL RESULT.
CAUTION: DURING BRUSH REPLACEMENT DO NOT ALLOW BRUSH SPRING TO SNAP INTO
PLACE QUICKLY OR DAMAGE TO BRUSH MAY RESULT. ALSO, DO NOT CHIP OR SCRATCH
BRUSH CONTACT SURFACE DURING INSTALLATION.
7.2.10. Replace existing brushes in brush holder with brush chamfer leading edge pointing in the
direction of rotation of the commutator.
CAUTION: BRUSHES MUST SLIDE EASILY UP AND DOWN THE BRUSH RACK, IF THEY DO NOT
LIGHTLY SAND THE SIDES OF THE BRUSHES UNTIL THEY DO.
Excellent Condition
Commutator is still bright and shows little sign of wear.
Figure 3.3: Commutator Excellent Condition Example
Serviceable Condition
Shows some signs of wear and carbon build up
Figure 3.4: Commutator Serviceable Condition Example
7.4.2. With OHM meter positive lead connected to the motor positive terminal and the other
lead connected to motor case (ground) measure and record resistance. Resistance
value must be equal to or greater than 10,000 OHMS. If less resistance is measured the
motor should be replaced.
7.5.1. Verify that no foreign matter is lodged in the motor air intake or field winding areas.
7.5.3. Purge motor and air passages as required removing any dust, dirt or other
contamination.
CAUTION: INSPECT MOTOR BEARING TO ASSURE THAT PREMATURE SEIZURE DOES NOT
OCCUR.
7.6.3. Remove brush cover. On some systems removal of motor power leads is required prior
to brush cover removal, tag positive terminal.
7.6.4. Remove brushes from brush guides Section 7 and remove belt from motor pulley as
outlined in Section 6.
7.6.5. Rotate motor shaft by hand to ensure freedom of rotation. Visually inspect bearing for
sign of overheating or loss of lubrication with an inspection mirror.
7.6.6. If bearings are good install belt and brushes. Check belt alignment and tension per
procedure.
CAUTION
CAREFULLY LAY BRUSH SHUNT LEADS IN A POSITION WHICH WILL PREVENT ANY POSSIBLE
SHORTING PROBLEMS. LEADS MUST BE ABLE TO EASILY FOLLOW BRUSH AND SPRING
MOVEMENT AS WEAR OCCURS. IMPROPER LEAD PLACEMENT MAY RESULT IN MOTOR
DAMAGE.
7.6.7. Replace brush cover and tighten and safety wire (8-32 UNC) brush cover screws.
Replace motor cooling fan shroud.
7.6.8. Connect power leads to motor terminals and tighten (1/4 - 28) nuts.
Motor inspection did not show any defects which would require motor replacement.
Only approved vendor brushes are used.
Brushes are installed, seated and tested in accordance with the following procedures.
7.7.3. Perform brush inspection procedure as outlined paragraph 7.2 (as required).
7.7.4. Verify all power is off, all panels, shrouds, brackets and fairings are removed.
7.7.5. With a stiff wire hook or scribe lift brush spring from holder and remove each worn brush
set, until all four brush sets are removed.
7.7.6. Remove brush shunt wire terminal screw and discard worn brush set. Continue this step
until all four screws are removed.
CAUTION: DO NOT ALLOW BRUSH SPRING TO SNAP HARD INTO PLACE OR DAMAGE TO BRUSH
MAY RESULT.
7.7.7. Install each brush set by lifting brush springs, sliding brush into holder (with brush leading
edge in direction of rotation) and lightly releasing the brush spring on the brush. (See
figure 6).
CAUTION: BRUSHES MUST SLIDE EASILY UP AND DOWN THE BRUSH RACK, IF THEY DO NOT
LIGHTLY SAND THE SIDES OF THE BRUSHES UNTIL THEY DO.
7.7.8. Verify that brush seats flat on the commutator and that no binding in holder is present.
Align brush spring in center of brush groove.
7.7.9. Install terminal screw and lock washer on brush shunt lead and other leads and tighten.
Repeat this step for other brush sets.
7.7.10. Seat the new brushes according to the following procedure. All new brushes must be
seated to assure proper motor operation and performance. If motor is operated without
seating the motor warranty may be voided.
CAUTION: EXCESSIVE SEATING IS NOT ADVISED. BRUSH LIFE MAY BE REDUCED. REMOVE
GRIT PAPER AND BLOW OUT ALL CARBON DUST FROM COMMUTATOR AND BRUSH AREA.
WARNING: EYE, NOSE AND THROAT PROTECTION MUST BE WORN DURING THIS PROCEDURE.
7.7.10.1. Cut 4 inch long by 1.5 inch wide strip of 400-500 grit paper and place, with
rough side out, on motor commutator.
7.7.10.2. Secure one end of the paper to the commutator with masking tape in a
manner such that the taped end will lead in the direction of shaft rotation
(ccw looking at fan end). The other end will remain loose and overlap the
taped end.
7.7.10.3. Raise each brush momentarily while rotating the shaft until the taped end
has passed under each brush. After the grit paper is properly located tight
against the commutator and encompasses all brush surface area, carefully
rotate the armature, by hand, in the normal direction of rotation until a full
seat is obtained on each new brush. Three to four rotations is generally
adequate.
7.7.11. Carefully lay brush shunt leads in position such as to prevent any shorting problems.
Leads must be able to easily follow brush and spring movement as brush wear occurs.
7.7.14. Visually inspect motor to assure all brackets are installed, cooling fan does not interfere
with shroud, motor drive belt installed, aligned, tensioned and belt cover installed.
7.7.15. The motor should be tested or run in to verify proper operation. Connect ground power
source or verify aircraft power on and turn system on.
7.7.16. Run system for a minimum of 15 minutes to seat brushes and check motor operation.
7.7.17. Turn system and aircraft power off. System is ready for use.
7.8.2. Remove access doors, exhaust ducting and/or enclosure to gain access to motor
assembly.
7.8.3. Remove belt cover, drive belt and pulley, receiver dryer (if required) and condenser
support bracket. Refer to section 7.0 for belt and pulley removal. If unit is not installed in
aircraft motor removal will be simplified by removing condenser coil.
CAUTION: DURING THIS OPERATION DO NOT LET MOTOR FALL ON POWER CONTACTOR OR
DAMAGE MAY RESULT.
7.8.6. Remove all wires tie strapped to the motor, slightly lift motor up and turn 90 Deg. to
remove from mounting bracket.
7.8.8. Disconnect motor positive (red) and negative (black) leads from 3/8 relay stud and 1/4
unit grounding bolt, respectively.
7.8.9. Remove fan blade from motor by unscrewing 3/8 locknut from motor shaft and loosening
fan hub set screw with 1/8 inch allen wrench. Access fan hub set screw through the
Ø.0187 hole in the blade root area.
7.9.1. Apply thread sealant to fan hub set screw. Place fan assembly on motor shaft and align
set screw with flat on shaft. Tighten set screw slightly. Secure condenser fan to motor
shaft using 3/8 inch washer and locknut, hold fan while tightening locknut. Tighten fan
hub set screw.
7.9.4. Position motor into mounting bracket with keyed shaft end toward compressor pulley
7.9.5. Replace motor support bolts and lock washers and torque to 10-15 in-lbs, except bolts
for belt guard bracket and upper compressor support.
7.9.6. Install upper compressor support bracket and verify alignment with compressor mounting
ear. Torque the compressor support mounting bolts to 10-15 in-lbs.
7.9.7. Secure motor and control wiring with cable ties and route to prevent chaffing.
7.9.8. Install condenser support bracket on motor support using 6-32unc fillister screws.
CAUTION: ADJUST FAN SHROUD TO ASSURE THAT FAN BLADE DOES NOT HIT. ROTATE FAN
TO VERIFY.
7.9.9. Attach condenser coil assembly, if required. Align condenser fan shroud to achieve
uniform blade tip clearance. Seal fan shroud with RTV sealant
7.9.10. Replace motor pulley and drive belt (ref. section 7.0)
7.9.13. Verify all hardware and brackets are secure and all fillister screws are properly safety
wired.
7.9.15. Operate system to verify motor and system are functioning correctly
8.2.2. Remove access doors, exhaust ducts and enclosure to gain access to compressor.
8.2.3. Remove belt cover and inspect for belt alignment and tension. (Ref. section 7.0)
8.2.4. Visually inspect compressor pulley for excessive wear, nicks, cracks or looseness.
8.2.5. Visually inspect compressor output shaft for excessive oil leaks.
NOTE If excessive oil is noted the compressor should be checked for leaks. Use fluid or leak detector as
required. If leak is noted the compressor should be replaced. If compressor has not been operated for
30-60 days or more the dynamic shaft seal may indicate a small leak due to no oil on dynamic seal
surface. Operation of system should eliminate this type leak. If not, replace R-134a compressor.
8.2.7. Visually check drive belt for cracks, wear and excessive oil. With clean shop rag clean
all oil and other contamination from belt cogs.
NOTE Checking compressor oil quantity is only required if an excessive amount of oil is observed leaking
or the system has been vented very quickly thereby causing a loss of oil. An oil check can only be made
with the system vented. (See oil check procedure.)
8.2.8. If visual check is good, replace belt cover and secure fasteners.
8.3.3. Connect refrigerant manifold gauge and hose assy. to compressor suction and discharge
service valves.
8.3.4. Recover system refrigerant charge as detailed in reclaim systems operating manual.
8.3.7. Remove drive belt and motor pulley as described in section 7.0.
8.3.8. Remove system suction and discharge hose connections and cap off immediately.
CAUTION: ALL SYSTEM CONNECTIONS MUST BE CAPPED TO PREVENT WATER, DUST OR ANY
OTHER CONTAMINATION FROM ENTERING THE SYSTEM.
8.3.9. Remove compressor mounting bolts and lift compressor free of mounting bracket.
8.4.1. Lift compressor into support bracket and install support bolts, washers and nuts. Place
rod end bearing into adjustment hole in motor support bracket and install washers and
nut.
8.4.2. Snug lower compressor mounting bolts and rotate compressor toward drive motor
centerline and install drive belt.
8.4.3. Replace, align and tension belt per paragraphs 7.3 thru 7.4. Replace belt guard.
NOTE: Lightly apply refrigerant oil on compressor fitting (s) flare and apply a small amount of thread
sealant to fitting threads (stay clear of first 2-3 threads).
8.4.4. Remove compressor suction and discharge fitting caps and connect system hoses.
8.4.5. Tighten o-ring fitting nuts to 150-200 in-lbs. Do not over torque.
8.4.6. Connect R-134a manifold gauge and hose assy. to suction and discharge service ports.
8.4.7. If failed compressor contaminated system and system was cleaned and purged an
additional charge of refrigerant oil is required.
8.4.7.1. If failed compressor did not contaminate the system no additional oil is
required since the new compressor contains the required charge.
8.5.2. Drain and measure oil from new compressor in a clean container for reuse.
CAUTION: ONLY AN ENVIRO APPROVED TYPE OF OIL MAY BE USED IN THIS TYPE
COMPRESSOR CONTACT ENVIRO FOR APPROVED OIL TYPE.
8.5.3. Measure an amount of new oil equal to the amount drained from the used compressor.
Pour it into the new compressor.
9.4.1.1. Verify all power to unit is off and all shrouds, enclosures, etc. are removed
from around the module/blower assy.
NOTE: The blower motor is a permanent magnet type and therefore may be wired to rotate either CW or
CCW. It is necessary that the motor wires and associated colors be observed before being
disconnected.
9.4.1.3. For motors which rotate CW (looking at output shaft) the motor red wire is
+ 28 VDC and the black wire is ground. For CCW rotation the red wire is
ground and the black wire is + 28 VDC.
NOTE: At this point it is very important to observe the wire colors and connections from the resistor
assembly and motor and record them.
9.4.1.4. Remove motor wire clamp and disconnect the wire splice from the resistor
wire.
The resistor red wire is the low speed control
The orange wire is the high speed.
9.4.1.5. Remove motor mounting screws and with a putty or pocket knife slide
between the motor and plastic scroll to cut the RTV sealant bonding. Avoid
damage to the scroll.
9.4.1.6. Lift blower motor out of scroll assy. and remove blower wheel.
9.4.2.1. Replace motor wheel on new motor shaft where the back of the wheel is
.25 inches from the motor mounting surface. The set screw on the wheel
hub must be located on the motor shaft flat section. Use a thread lock
sealant and tighten set screw.
9.4.2.2. Rotate blower wheel on motor shaft to check wheel wobble. Lightly apply
a force on the wheel O.D. to eliminate any wobble as required.
NOTE: Observe blower wheel blade and verify leading edge is in direction of rotation.
9.4.2.3. Apply a small bead of RTV sealant (or gasket seal if equipped) on the
scroll and install the blower wheel and motor with motor wires in a location
near the resistor wires and mounting screw.
9.4.2.5. With access thru the blower outlet rotate the blower wheel to assure that
no rubbing exists.
9.4.2.9. Connect power leads to blower assy. and test for proper operation.
9.4.2.10. Replace all ducting, shrouds and enclosures, etc. Unit is ready for
operation.
9.5.2. The automatic expansion valve normally does not require replacement. However, in the
unlikely event it malfunctions or it has a clogged inlet filter the following procedures will
apply:
9.5.2.1. The refrigerant system charge must be reclaimed and to the expansion
valves must be accessible.
WARNING: EYE AND HAND PROTECTION SHOULD BE WORN IN THE EVENT SYSTEM IS STILL
UNDER PRESSURE. PLACE CAP ON OPEN SYSTEM PORTS.
9.5.2.2. Remove valve inlet tubing and remove valve from coil tubing header.
9.5.2.3. Inspect valve inlet filter for contamination and clean. If no contamination is
noted, valve should be replaced if operation was erratic prior to removal.
CAUTION: DO NOT ADJUST INTERNAL SPRING SETTING OR VALVE WILL NOT OPERATE
CORRECTLY.
9.5.2.4. Inspect valve internal works to verify that no contamination exists in the
seat or orifice. Clean and purge as required.
9.5.3.1. Set new valve adjustment screw to same position of failed valve.
9.5.3.2. Apply thread sealant (sparingly) to male fitting inlet and outlet port threads
avoiding the first 2-3 threads. Apply a very slight amount of refrigerant oil
to both valve port flare surfaces Do not put oil on fitting threads.
CAUTION: USE BACKUP WRENCH DURING TIGHTENING AND DO NOT OVERTORQUE "B" NUT.
9.5.3.3. Install valve in coil header and position as required. Tighten connection to
190-195 in-lbs.
9.5.3.5. Leak check, evacuate and charge system per sections 4.0 and 5.0.
9.5.3.6. Operate system and verify valve is performing as required. Adjust valve,
according to section 4.0 and section 5.0
10.1.1. There may a time when the system does not operate and/or perform in accordance with
information contained herein. Therefore, it is necessary for the service personnel to
diagnose the discrepancy by trouble shooting the system and its components.
10.1.2. To assist in the diagnoses refer to Table 3 Diagnosis and Trouble Shooting. The list of
system and component failure and/or abnormal operation and possible solutions are only
a partial listing of what may occur. The more informed the service personnel are in the
operation of the system and its various components will reduce the time to diagnose
failures and may add other probable causes to the list.
12.1.1. If ambient temperature is below 50° F (10°C), the pressure switch is designed to keep
the system from operating and causing possible damage if operated for extended periods
of time. In this case, it is recommended that the aircraft be heated above this threshold
to enable the system to operate.
CAUTION: OPERATION OF THE SYSTEM AT LOW AMBIENT TEMPERATURES FOR MORE THAN
15 MINUTES CAN RESULT IN MAJOR DAMAGE OF THE R-134A COMPRESSOR.
12.2. Procedures
12.2.1. During cold winter months, the system should be operated for 10-15 minutes every two
weeks to maintain a thin oil film on the compressor output shaft dynamic seal to prevent
shaft leakage.
12.2.2. Prior to turning on the air conditioning system (energizing the compressor drive), run
blowers on high speed for a minimum of 5 minutes. This will aid in warming the
refrigerant and bringing it up to an acceptable temperature enabling operation of the
system.
13.1.1. If unit is stored for periods in excess of 12 months the following preventative
maintenance should be followed for the compressor.
NOTE: When installing unit with MFG date in excess of 12 months, prior to installation date, verify record
of preventative maintenance. If no maintenance record exist contact Enviro Systems Inc. prior to
installation.
13.1.2. Perform the following procedures at 12 months from MFG date on unit and every 6
months thereafter for a maximum of 36 months.
13.2.1. For internal pressure within a range of 5-15 PSIG rotate compressor by hand through a
minimum of 10 revolutions.
13.2.2. For internal pressure below 5 PSIG the system should be pressurized to 15 PSIG using
regulated dry nitrogen. After pressurizing the system, rotate the compressor by hand
through a minimum of 10 revolutions.
13.2.3. If the system does not have any detectable pressure, check the compressor oil for
contamination.
13.3.1. Remove compressor oil plug and insert a clean tie strap into oil fill hole. To inspect the
oil remove the strap. Oil should have a clear to amber color.
13.3.2. If oil shows specs of black or other contamination, the compressor must be flushed and
the receiver dryer must be replaced. The compressor should then be evacuated for a
minimum of 30 minutes and then pressurized to 15 PSIG according to Section 4.
14.1.1. Unit or component warranty may be denied should any of the following conditions occur:
Component damaged due to negligence
Component disassembled
Component altered in configuration
Component failure due to refrigerant system contamination or improper charge
Component not serviced or maintained correctly
Component out of warranty
Component not returned in proper shipping container (Use same container that the
component was shipped in)
Component repaired or overhauled with parts not FAA/PMA approved
Component ports not capped
Component warranty claim filed incorrectly
15.1.1. Always wear eye and hand protection when servicing an air conditioning system. Liquid
refrigerant can cause frostbite or blindness.
15.2.1. Do not discharge R-134a refrigerant into the atmosphere. Although the ozone depletion
potential is zero, it can have an effect on global warming. In the United States recovery
and recycling are mandated by the Clean air Act..Refrigerant recovery/recycling service
equipment must be approved for use with R-134a refrigerant.
15.2.2. Recycling machines must be approved by Underwriters Laboratories and meet SAE
standard J2210 and SAE standard j2099 for refrigerant purity.
15.3. Ventilation
15.3.1. Keep refrigerants and oils away from open flames. Refrigerants can produce poisonous
gasses in the presence of a flame. Work in a well ventilated area and avoid breathing
refrigerant /lubricant vapor mist if accidental discharge occurs.
15.4.1. Do not introduce compressed air or oxygen into an air conditioning system or refrigerant
container. R-134a in the presence of air or oxygen above atmospheric pressure may
form a combustible mixture.