Lecture - 01 - Introduction
Lecture - 01 - Introduction
Milkias B. 11/15/2023 1
EP-6071 _ Power System
Planning
Lecture One:
1. Introduction
Dr. Milkias B.
Dept. of Electrical Power and Control Engineering
Adama Science and Technologyy University
mil_ber2000@astu.edu.et
EP-6071 _ Power System Planning
Introduction on
Power System Planning
EP-6071_ Power System Planning
Learning Outcomes:
This course will introduce the fundamentals of Power System Planning and
power system Management. After this course the students should be able to:
▪Understand the general power system structure;
▪Understand load forecasting techniques;
▪Learn and understand basics design concepts and methods of
generating stations, switchyards, and transmission lines;
▪Understand and carry out cost analysis of generation systems;
▪Understand the planning of power systems;
▪Analysis of transmission losses for a power system;
▪Learn and understand the concepts and terminology used in
interchange evaluation;
▪Understand power pools issues;
▪Understand and carry out power system reliability analysis;
EP-6071_ Power System Planning
▪ 1. Introduction and FUNDAMENTALS
Introduction
Planning & economics
▪ 2. Load data and Forecasting
▪ 3. G, T&D Planning
▪ 4. DESIGN PRINCIPLES & PRACTICE OF
SUBSTATION
Substation sizing and spacing
Substation location
Effect of changing load density
Effect of changing primary voltage
Cost interaction of substation size and spacing vs primary voltage and
load density
▪ 5. Power quality and Reliability analysis
▪ 6. PROJECT MANAGEMENT and UNIT COMMITMENT
Project evaluation
Financing
Project phases
Key points
Unit commitment
Spinning reserve
Priority list method/Merit
Milkiasorder
B. scheduling 11/15/2023 5
Texts and References
Text Book
Sullivan, Power System Planning, McGraw-hill International
Book Company
References
1. Roy Billinton and Allan Ronald, “Power System
Reliability.”
Text books 2. Turan Gonen, Electric power distribution system
and Engineering McGraw Hill,1986
References 3. Hossein_Seifi, Mohammad_Sadegh_Electric Power
System Planning, Issues,Algorithms & Solutions
4. Arthur Mazer, Electric Power Planning for Regulated and
Deregulated Markets, WILEY-INTERSCIENCE, A John
Wiley & Sons, Inc., Publication, IEEE PRESS
5. Pansini, Anthony J. Power transmission and
distribution/Anthony J. Pansini 2nd ed.
EP-6071_ Power System Planning
Lecture 1
Course Introduction
Lecture Outline:
Generation Transmission
System System
15,20 kV 400,500 kV 400,500 kV 66,45 kV
Generator-1
Large
Consumers
Step-up Step-down
Transformer 132,230 kV Transformer
Distribution
System
Generator-2 400,500 kV
15,20 kV 132,230 kV
66,45 kV
Step-down
Transformer
Step-up
Transformer 33,15 kV
11,11.5 kV
400/220 V
33/15 kV
Medium
Generator-3 and small
Consumers
Milkias B. 11/15/2023 10
Brief description of the main Power System Components:
1.Generation System
Types of Energy Resources:
•Oil, Natural Gas, Coal, Atomic energy (Fossil fuel resources)
•Solar, Hydro, wind, hot water/spring, Biomass (Renewable energy
Resources)
Types of Energy Conversion Methods/Generation Systems:
•Diesel Generator, Gas Turbine, Steam Turbine, Combined Cycle Gas
Turbine (CCGT), Steam Injected Gas Turbine, Nuclear power (Conventional
systems)
•PV System, Solar Thermal, Hydropower, Wind Power, Geothermal,
Biomass (Renewable conversion systems)
2. Transmission Systems:
This component of the power system transmits bulk electrical energy from
generation stations where it is produced to the main load centres. The
transmission system is composed of:
• Step-up and Step-don substations
• Transmission lines
3.Distribution Systems
The distribution system gives out the energy from the medium voltage
substations to customers’ location. It is composed of:
• Medium Voltage (MV) lines (33kV, 15 kV)
• MV/LV transformer substations (33/15/ kV to 400/380/220 V)
• Distribution lines (33/15 kV, 380 V 3-phase and 220 v single phase)
Definition:
Power system Planning is optimization of facilities necessary to provide adequate
electrical energy in a power system network at a least cost, low environmental
and social impacts through which a sustainable energy supply to customers is
attained.
Thus, power system planning gives the necessary basis and jumpstart for a detail
The Purpose of Planning Is:
A proper planning can be performed necessarily through:
1. Load survey; - The present load requirement and the expected
load growth over a period of 5-10 years.
- power system design starts with load forecasting
For starting this work the following data should be collected:
1. A detailed map of the area
2. Nos.of houses, population and new construction.
3 Details of hospitals, transportations, railway station
4. The expected nos.of shops, post offices,….
5. Types and nos. of industries,…
6. The cultivated area and irrigation facilities,..
7. implemented and to be implemented projects
7. Development programs implemented.
1.3 Brief introduction of the Course
• Power system planning encompasses a broad collection of activities spanning
several time horizons and can be divided into categories of analysis such as
demand, generation, transmission and distribution.
• Thus, bulk power system planning includes Load Forecast, Generation
Planning, Transmission&Distribution planning at reasonable expansion cost.
• Power system planning is usually done on a long-term planning horizon up to
20 to 25 years.
A. Load Forecasting:
• It determines the future trend of electricity consumption of each demand sectors starting
from the base year for the whole projection period.
• It determines the total annual consumption as well as its discissions in to local and
interconnection power pool loads.
• It depends mainly on the historical and current data of the base year, national GDP
growth, population growmodelingmers’ income growth, government plan on rural
electrification, government policies and view on climate issues etc.
• It includes the historical data analysis and modelling annual forecast of energy demand
and peak capacity demand of a power system network within the projection period.
B. Generation Planning:
▪ Power System operation is the act of managing the power system network in
a low cost, efficient, stable, reliable, low-cost sustainable manner.
▪ The time frame for power system operation varies from a few seconds to a
few weeks.
▪ To assist with the operation of the system, modern power systems are
equipped with Energy Management Systems which coordinate various
control functions in system operation.
▪ The prime goal of Energy Management systems is the secure and economic
operation of power systems to ensure an uninterrupted, safe flow of power to
customers at minimum cost.
FUNDAMENTALS
11/15/2023 Milkias B. 19
1.2.
FUNDAMENTALS
2.1. INTRODUCTION
11/15/2023 Milkias B. 20
1. 2. FUNDAMENTALS
1. 2.1 INTRODUCTION
Retail sale of electric energy involves the delivery of power in ready to use form
equipment scattered over a wide geographical area and interconnected so that all
11/15/2023 Milkias B. 21
Methods of Power System Planning
The steps taken in the method of power system planning studies are
1. Forecast of annual energy and power demand
2. Load modelling
3. Generation and choice of mixing the various types of generating stations
4. Optimization of power plant characteristics
5. New substations; their capacity and location
6. New power plants and their subdivision in the main areas
7. Network expansion
8. Optimization of equipment characteristics
11/15/2023 Milkias B. 22
• The complex interaction of a T&D system is governed by a number of
physical laws relating to the natural phenomena that have been harnessed to
produce and move electric power.
• These interactions have created a number of "truths" that dominate the design
of T&D systems:
▪ It is more economical to move power at high voltage, and It is costly to change voltage
level.
11/15/2023 Milkias B. 23
Definitions and nomenclature defining "transmission" and "distribution" vary
greatly among different countries, companies, and power systems.
Traditionally, three types of distinction between the two were made:
By voltage class: transmission is anything above 34.5 kV; distribution is anything below that.
By function: distribution includes all utilization voltage equipment, plus all lines that feed power to service
transformers.
By configuration: transmission includes a network; distribution is all the radial equipment in the system.
11/15/2023 Milkias B. 25
1. 2.2 PLANNING AND ECONOMICS
Power system planning is complex because each unit of equipment in every
hierarchical level, generating units, transmission lines, substation
equipment/protective equipment, voltage regulators, power transformers/,
distribution lines, distribution transformers etc, influences the electrical
behaviour of its neighbours, and must be designed to function well in
conjunction with the rest of the system under a variety of different conditions,
regardless of shifts in the normal pattern of loads or the status of equipment
nearby.
• A power system can be expensive to design, build, and operate. Equipment at every
level incurs two types of costs.
o Initial costs /one time cost-include the equipment and land, labour for site preparation,
construction, assembly and installation, and any other costs associated with building
and putting the equipment into operation.
o Operating costs /continuous cost- include labour and equipment for operation,
maintenance and service, taxes and fees, as well as the value of the power lost to
electrical losses.
11/15/2023 Milkias B. 27
• Initial cost of equipment can always be traded against long-term loss costs.
• Highly efficient transformers can be purchased to use considerably less power to
perform their function than standard designs.
• Larger conductors can be used in any transmission or distribution line, which will
lower impedance and thus losses for any level of power delivery.
• But both examples here cost more money initially - the efficient transformer may
cost three times what a standard design does; the larger conductor might entail a
need for not only large wire but heavier hardware to hold it in place and stronger
towers and poles to keep it in the air.
• In addition, these changes may produce other costs - for example, the use of a larger
conductor has a higher fault duty (short circuit current), which increases the required
rating and cost for circuit breakers.
• A second and related cost decision involves determining if a present expense is justified
because it will reduce future operating expenses by some amount.
• For planning purposes, the present worth factor should be regarded simply as a
value that sums up all the reasons why a company would prefer to spend money
tomorrow rather than today.
• It is a planning tool used to evaluate and rank alternatives based on when they call
for expenditures and leads to prioritization of options.
11/15/2023 Milkias B. 30
Q.1.Suppose it has been determined that
a new substation must be built in an area
of the service territory which is the site
of much new customer growth. Present
needs can be met by completing this
new substation with only one
transformer, at a total initial cost of
$1,000,000. Alternatively, it could be
built with two transformers - twice as
much capacity - at a cost of $1,800,000.
Although not needed immediately, this
second transformer will be required
within four years because of continuing
Q.2. Suppose a new feeder is to be built along with growth. If added at that time, it will cost
the new substation. If built with 336 MCM(Million $1,284,000 - a reflection of the
Cubic Meter) conductor at a cost of $437,000, the additional start-up cost for a new project
new feeder will be able to satisfy all loading, and of working at an already-energized
voltage drop, contingency, and other criteria. and in service substation rather than at a
However, if built with 600 MCM conductor, at a "cold" site. Which plan is best? Should
total cost of $597,000, it will lower annual losses planners recommend that the utility
costs every year in the future by an estimated spend $800,000 now to save $1,284,000
$27,000. Are the planners justified in four years from now? Present worth
recommending that $160,000 be spent on the factor = 0.83, 0.9
larger, based on the long term continuing savings?
Present worth factor = 0.83, 0.9
11/15/2023 Milkias B. 31
• Adding 1% - or whatever is appropriate based on analysis of the uncertainty
and the planning method being used - to the PWF biases all planning
decisions so that they reflect this imperfection of planning.
11/15/2023 Milkias B. 32
▪ Cost to deliver power varies depending on location within a power system. Variations
are both due to "natural" reasons - it is difficult to deliver power to some locations like
the tops of mountains, etc., and due to "system characteristic" reasons: no matter how
a delivery system is laid out, some consumers will be close to a substation and others
will be farther away from it.
▪ In some sense, those farthest from it are most expensive to serve, those closest to it
less expensive to serve.
▪ One must bear in mind that traditional and established regulatory opinion holds that
such variations do not automatically justify proportional pricing of electric service.
11/15/2023 Milkias B. 33
• All cost evaluation for power delivery planning should be based upon
economic evaluation that is consistent over the range of all alternatives.
• Usually, this means that present and future costs must be compared.
• Present worth analysis, lifetime levellized costing, or some similar method of
putting present and future value on a comparable basis will be used.
• One complication in determining the most economical equipment for a power
system is that its various levels — transmission, substation, and distribution –
are interconnected, with the distribution, in turn, connected to the customers.
• This means that the best size and equipment type at each level and location in
the system is a function not only of the local load but of the types of
equipment selected for the other levels of the system nearby, their locations,
and characteristics, as well as the loads they serve.
11/15/2023 Milkias B. 34
▪ Two Q method: A complication of modern, non-traditional distribution
planning is that reliability is often a key design element.
▪ Planners are challenged to reduce overall cost while achieving designs that
achieve targets for both capacity and reliability.
• This means they plan and design systems to numerical reliability targets in
addition to, as traditional methods do, planning and designing to numerical
demand targets.
11/15/2023 Milkias B. 36
Any Question??
?
Any Question ?
Any Question ?
?
Any Question ?
? ? ?
? ?
? ? ? ?
11/15/2023
?Any Question ? ?
Milkias B. 37 37
NEXT
Lecture 02