Chapter 2 2009
Chapter 2 2009
Chapter 2 2009
Page 1
4. Implementation
At a later stage (in 1978) the author has added an additional stage called “Evaluation” which
usually closes the cycle as it gives rise to the identification of new projects. Thus making the
stages 5 in number.
These processes can usefully be considered as a comprehensive sequence in the sense that for
the project that is implemented, each stage naturally follows the proceeding one and leads on
to the next. Actually, the division into stages is artificial, but it helps us to understand that
project planning, though a continuous process over time, has distinct phases and stages.
Throughout the project cycle the primary preoccupation of the analyst is to consider
alternatives, evaluate them, and to make decisions as to which of them should be advanced to
the next stage. Thus, each of Baum’s main stages are discussed briefly below
2.2.1 Identification
The first stage in the cycle is to find potential projects. Some sources of projects are given
here.
Some may be “resource based” and stem from the opportunity to make profitable use
of available resources.
Some projects may be “market based” arising from an identified demand in home or
overseas markets.
Others may be “need-based” where the purpose is to try to make available to all
people in an area of minimal amounts of certain basic material requirements and
services.
Well – informed technical specialists and local leaders are also common sources of
projects. Technical specialists will have identified many areas where they feel new
investment might be profitable, while local leaders may have suggestion about where
investment might be carried out.
Ideas for new projects also come from proposals to extend existing programs.
In general, most projects start as an elementary idea. Eventually, some simple ideas are
elaborated into a form to which the title “project” can be formally applied.
2.2.2 Preparation (pre – feasibility or feasibility studies)
Once projects have been identified, there begins a process of progressively more detailed
preparation and analysis of project plans. At this stage the project is being seriously
considered as a definite investment action.
Project preparation (project formulation) covers the establishment of technical, economic and
financial feasibility. Decisions have to be made on the scope of the project, location and site,
soil and hydrological requirements, project size (farm or factory size) etc
Resource base investigations are undertaken and alternative forms of projects are explored.
Complete technical specifications of distinct proposals accompanied by full details of
Page 2
financial and economic costs and benefits are the out come of the project preparation stage.
The project now exists as a set of tangible proposals.
Project design and formulation is an area in which local and international consultants are very
active especially for big project that cover large areas and have big budgets.
2.2.3 Appraisal
After a project has been prepared, it is generally appropriate for a critical review or an
independent appraisal to be conducted. This provides an opportunity to re-examine every
aspect of the project plan to assess whether the proposal is appropriate and sound before large
sums are committed.
Generally, internal government staffs only are used for this work and not consultants and
projects are appraised both in the field and at the desk level. Appraisals should cover at least
seven aspects of a project, each of which must have been given special consideration during
the project preparation phase:
a) Technical – here the appraisals concentrate in verifying whether what is proposed
will work in the way suggested or not.
b) Financial – the appraisals try to see if the requirements for money needed by the
project have been calculated property, their sources are all identified, and reasonable
plans for their repayment are made where necessary.
c) Commercial – the way the necessary inputs for the project are conceived to be
supplied is examined and the arrangements for the disposal of the products are
verified.
d) Incentive – the appraisals see to it whether things are arranged in such a way that all
those whose participation is required will find it in their interest to take part in the
project, at least to the extent envisaged in the plan.
e) Economic – the appraisal here tries to see whether what is proposed is good from the
viewpoint of the national economic development interest when all project effects
(positive and negative) are taken into account and check if all are correctly valued.
f) Managerial – this aspect of the appraisal examines if the capacity exists for
operating the project and see if those responsible ones can operate it satisfactorily.
Moreover, it tries to see if the responsible are given sufficient power and scope to do
what is required.
g) Organizational – the appraisal examines the project if it is organized internally and
externally into units, contract policy institution, etc so as to allow the proposals to be
carried out properly and to allow for change as the project develops.
2.2.4 Implementation
The objective of any effort in project planning and analysis clearly is to have a project that
can be implemented to the benefit of the society. Thus, implementation is perhaps the most
important part of the project cycle.
Page 3
In this stage, funds are actually disbursed to get the project started and keep running. A major
priority during this stage is to ensure that the project is carried out in the way and within the
period that was planned. Problems frequently occur when the economic and financial
environment at implementation differs from the situation expected during appraisal.
Frequently original proposals are modified, though usually only with difficulty, because of
the need to get agreement between the parties involved.
It is during implementation that many of the real problems of projects are first identified.
Because of this, the feedback effect on the discovery and design of new projects and the
deficiencies in the capabilities of the project actor can be revealed.
Therefore, to allow the management to become aware of the difficulties that might arise,
recording, monitoring and progress reporting are important activities during the
implementation stage. There are some aspects of implementation that are of particular
relevance to project planning and analysis.
i. The first is that the better and more realistic a project plan is, the more likely it is
that the plan can be carried out and the expected benefit realized. This
emphasizes once again the need for careful attention to each aspect of project
planning and analysis.
ii. The second is that project implementation must be flexible. Circumstances will
change and project managers must be able to respond intelligently to these
changes.
The common ones are technical changes (soils, water logging, nitrogen application) price
changes economic changes, political changes and these will alter the ways in which it should
be implemented.
2.2.5 Evaluation
The final phase in the project cycle is evaluation. Once a project has been carried out, it is
often useful, (though not always done) to look back over what took place, to compare actual
progress with the plans, and to judge whether the decisions and actions taken were
responsible and useful.
The extent to which the objectives of a project are being realized provides the primary
criterion for an evaluation. The analyst looks systematically at the elements of success and
failure in the project experience to learn how better to plan for the future.
Evaluation is not limited only to completed projects. It is a most important managerial tool in
ongoing projects and rather formalized evaluation may take place at several times in the life
of a project.
Evaluation may be undertaken when the project is in trouble, as the first step in a re-planning
effort. Careful evaluation should precede any effort to plan follow – up projects. And,
finally, evaluation should be undertaken when a project is terminated or is well into routine
operation
2.3 UNIDO – Project Cycle
Page 4
UNIDO has established a project cycle comprising three distinct phases):
The pre investment phase,
Investment phase and
Operational phase phases.
The pre- investment phase comprises:
project identification,
project preparation and
Appraisal of project studies.
The investment phase constitutes negotiation and contracting, engineering design,
construction and preproduction marketing. And the operational phase includes
commissioning and starts up of production, replacement and rehabilitation, and expansion
and innovation.
Actually, this division is artificial but it helps to understand that project planning is a
continuous process over time. Throughout the project cycle the primary preoccupation of the
analyst is to consider alternatives, evaluate them, and to make decisions on which of them
should be advanced to the next stage.
With the clear understanding that project planning is an uninterrupted process, we shall
discuss the investigation work to be carried out at each stage of planning starting with project
identification. The stage of project implementation will not be covered thoroughly: we only
touch upon it in passing. This is not because project execution is of minor importance; on the
contrary, because of its significance in transforming project expectations into realities it
deserves a separate chapter. The same applies to the stage of operation and post-evaluation
which some authors include in the project cycle.
1. THE PRE INVESTMENT PHASE
The pre investment phase comprises several stages: identification of investment
opportunities (opportunity studies), project preparation (pre-feasibility and feasibility studies)
and project appraisal (preparation project investment decisions report).
i. Project Identification
Project identification amounts to finding projects which could contribute towards achieving
specified development objectives. In principle, especially in developing countries like
Ethiopia, project identification should be an integral part of the macro-planning exercise with
sectoral information and strategies as the main source of project ideas. In practice, however,
projects are not always derived from national and sectoral plans; they originate from multiple
sources such as investment promotion agencies, private consultants and private investors.
Irrespective of their origin project ideas should, in general, aim at: overcoming constraints to
the development effort, be they material, human or institutional constraints; or, meeting
unsatisfied needs and demand for goods and services. Constraints, needs and demand should
Page 5
be interpreted broadly to include, for example, foreign exchange constraints that might
necessitate projects for import substitution or export promotion.
a) Opportunity studies:
The identification of investment opportunities is the starting – point in a series of investment
– related activities, when potential investors (private or public) are interested in obtaining
information on newly identified viable investment opportunities.
Where does Projects Originate? The variety of projects makes it impossible to prepare an
exhaustive list of sources from where project ideas emanate; much depends on the
experience, and even imagination, of those entrusted with project creation. In general, we
can distinguish two levels where project ideas are born: the macro-level and the micro-level.
At the macro-level, project ideas emerge from:
i. national, sectoral,, or regional plans and strategies supplemented by special
studies, often called opportunity studies, conducted with the explicit aim of
translating national and sectoral programs into specific projects;
ii. constraints in the development process due to shortages of essential infrastructure
facilities, problems in the balance of payments, etc.;
iii. A government’s decision to correct social and regional inequalities or to satisfy
basic needs of the people through development projects;
iv. a possible external threat that necessitates projects aiming at achieving, for
example, self-sufficiency in basic materials, energy, transportation, etc.;
v. Unusual events such as droughts, floods, earth-quakes, hostilities, etc.; and
vi. A government’s decision to create locally project implementing capacity in such
areas as construction etc.
At the macro-level, project ideas can also originate from multilateral or bilateral
development agencies and as a result of regional or international agreements in which a
country participates.
At the micro-level, the variety of sources is equally broad. Project ideas emanate from:
i. The identification of unsatisfied demand or needs;
ii. The existence of unused or underutilized natural or human resources and the
perception of opportunities for their efficient use;
iii. The need to remove shortages in essential materials, services or facilities that
constrain the development effort;
iv. The initiative of private or public enterprises in response to incentives provided by
the government;
v. The necessity to complement or expand investments previously undertaken; and
vi. The desire of local groups or organizations to enhance their economic
independence and improve their welfare.
Page 6
Project proposals could also originate from foreign firms either in response to government
investment incentives or, because they consider local production a better way to secure a
substantial share of the domestic market for their products.
Opportunity studies are rather sketchy in nature and rely more on aggregate estimates rather
than on detailed analysis. Cost data are usually taken from comparable existing projects and
not from quotations of sources such as suppliers. Depending on the prevailing situation,
either a general opportunity study (sector approach) or a specific opportunity study
(enterprise approach) or both will have to be undertaken.
General opportunity studies*
General opportunity study may be divided into three categories:
Area studies to identify opportunities in a given area
Industry studies to identify opportunities in a delimited industrial branch
Resource-based studies to reveal opportunities based on the utilization of natural
resources
Specific project opportunity studies*
A specific project opportunity study may be defined as the transformation of a project idea
into a broad investment proposition. This study usually springs from general opportunity
studies, in the form of products with the potential for domestic manufacture. The purpose of
Specific project opportunity studies is to arrive at a quick and inexpensive determination of
the salient facts of an investment possibility. It therefore should not involve any substantial
cost in it preparation (Project identification will be discussed in detail in chapter 3).
b) Preliminary Screening: Once some project ideas have been put forward, the first
step is to select one or more of them as potentially viable. This calls for a quick
preliminary screening by experienced professionals who could also modify some of
the proposals. At this stage the screening criteria are vague and rough, becoming
specific and refined as project planning advances. During preliminary selection the
analyst should eliminate project proposals that are technically unsound and risky;
have no market for the output; have inadequate supply of inputs; are very costly in
relation to benefits; assume overambitious sales and profitability; etc.
Obviously, since the criteria are imprecise much depends on the experience and impartiality
of the professionals applying them. It is, however, necessary to conduct this screening, even
with indistinct criteria, in order to reduce to a manageable number the project alternatives to
which more work and time will be devoted. After all, project planning is a process of
elimination, i.e. elimination of inferior alternatives.
c) Pre-feasibility Studies: Following the preliminary screening, promising project
options should be investigated in a systematic manner. This requires the preparation
of brief reports that indicate in sufficient, but not painstaking, detail the project
versions that are still promising and suggest which ones should be eliminated.
Sophisticated analysis, of the technical, financial, economic social and institutional
Page 7
aspects of the project are postponed to a later stage before assigning larger funds for
such a study, since feasibility studies are costly and time-consuming.
However, the reports should indicate which of these aspects deserve particular attention
during the subsequent step. Reports of this type are often called pre-feasibility or pre-
investment.
The objectives of the pre- feasibility study are to determine whether:
All possible project alternatives have been examined
The project idea justifies a detailed analysis by a feasibility study
Any aspects of the project are critical to the project that may require in depth
investigation through functional studies
Environmental situation at the planned site and the potential impact of the projected,
production process are in line with national standards.
A pre – feasibility study should be viewed as an intermediate stage between a project
opportunity study and a detailed feasibility study, the difference being in the degree of detail
of the information obtained and the intensity with which project alternative are discussed.
The structure of a pre – feasibility study should be the same as that of a detailed feasibility
study.
Content of the Pre-feasibility Study: To enable the relevant authorities to decide on the
merits of various project options, the pre-feasibility study should, although briefly, discuss:
i. The structure and objectives of the project;
ii. The nature and size of the demand for the output or the needs that it would satisfy,
together with the foreseen beneficiary groups;
iii. The availability of the most important materials and human inputs;
iv. Basic alternative technologies available and their merits and weaknesses;
v. Approximate investment and operation costs as well as expected revenues and
other benefits;
vi. Rough estimates of financial and economic returns;
vii. Any major factor that is likely to have an important effect on the project; and
viii. What further information on the technical, financial, economic or institutional
aspects of the project should be acquired through special studies and surveys?
By the end of the identification stage we should know:
a) Whether further detailed work is justified;
b) What major issues have been identified, what project alternatives have been
considered and which of them have been rejected; and
c) A rough estimate of costs.
Page 8
For projects that still look promising, a specific work plan for the next stage should also be
included in the study.
ii. Project Preparation – Feasibility Studies
A feasibility study should provide all data necessary for an investment decision. The
commercial, technical, financial, economic and environment prerequisites for an investment
project should therefore be defined and critically examined on the basis of alternative
solutions already reviewed in the pre – feasibility study.
If the pre-feasibility study indicates that the project is, prima facie, promising and further
work is justified, the project enters the stage of preparation. The project, already defined in a
sketchy form, is now being advanced to a level at which it can be appraised thoroughly
before a decision is taken on whether to implement it. The analysis of the project’s
marketing, technical, financial, economic and institutional aspects should be comprehensive
enough to allow the policy makers to decide on the future of the project with confidence.
Project preparation takes the form of a feasibility study conducted by the agency sponsoring
the project or by consultants. At this point it would be helpful to address a question often
raised, i.e. What is the difference between a pre- feasibility and a feasibility study? The
answer is simple: they differ only with respect to the amount of work needed to decide if a
project is viable. The table of contents is the same in both; it is the details and the
sophistication that vary.
iii. Appraisal and Investment Decision
Up to the completion of preparation, the project has been nursed by the sponsoring agency;
now it changes hands. The project proposal in the form of a feasibility study is submitted to
the investment decision makers for a broad and impartial appraisal. Appraisal is the
comprehensive and systematic assessment of all aspects of the proposed project. After
appraising the project carefully, appraisers will decide whether it will be implemented or not,
with or without minor modifications.
Appraisal Perspectives: Considered always within the broad development framework, the
project, during appraisal, is viewed from different perspectives.
1) Technical: On the technical side, we must be sure that alternatives have been
diligently considered and that the selected one provides sound solutions.
2) Commercial: Appraisal of the commercial aspect amounts to verifying that the
markets for the output and the inputs of the project have been thoroughly investigated,
including the channels of distribution and supply.
3) Financial: From the financial viewpoint, appraisal aims at ensuring that the
necessary funds to implement and operate the project will be available timely and
whether the project is financially viable.
4) Economic: The economic appraisal of the project relates closely to its technical
aspect. Of course, during project preparation cost-benefit analysis should ensure that
Page 9
the technological solutions adopted are those that best fit the conditions prevailing in
the country and are not simply the most advanced ones. However, the appraisal stage
is where the final review and evaluation of these matters are made.
5) Managerial: From the managerial angle we should check whether the proposed top
management and key staff are adequate for the prompt implementation and smooth
operation of the project.
Page 10
programmed carefully and executed diligently if delays and problems are to be avoided, or at
least minimized.
In general, it is to be noted that in the pre – investment phase, the quality and dependability of
the project are more important than the time factor, while in the investment phase, the time
factor is more critical in order to keep the project within the forecast made in the feasibility
study.
The phase is divided into the following stages:
1) Establishing the legal, financial and organizational basis for the implementation of
the project.
2) Technology acquisition and transfer, including basic engineering.
3) Detailed engineering design and contracting, including tendering, evaluation of bids
and negotiations. Detailed engineering design will include site preparation final
selection of technology construction planning and time scheduling as well as flow
charts and scale drawings preparation. Negotiations are concerned with legal
obligations arising from the acquisition of technology, construction of buildings,
purchase and installation of machinery, and financing
4) Acquisition of land construction work and installation. This involves site preparation
construction of buildings and other civil works, together with erection and installation
of equipment
5) Pre-production marketing, including the securing of supplies and setting up of the
administration of the firm. This and secures critical supplies prepares the market for
the new product
6) Recruitment and training of personnel. This stage proceeds simultaneously with the
construction stage to ensure timely commissioning and the expected growth in
productivity and efficiency in plant operations.
7) Plant commissioning and start-up. It is usually a brief but technically critical span in
project implementation. It links the preceding construction phase with the operational
(production) phase. The success achieved in this stage demonstrates the effectiveness
of implementation planning and execution of the project and has a bearing on the
future performance of the project.
3) OPERATIONAL PHASE
This is the production phase that commences after commissioning and start-up. The resultant
challenges of this phase are viewed from the short-term perspective and long-term
perspective. In the shot-term challenges may arise with regard to application of production
techniques operation of equipment, inadequate labor productivity due to a lack of qualified
staff and labor etc. Most of these problems have their origin in the implementation phase.
The long-term view relate to the chosen strategies and the associated production and
marketing costs as well as sales revenues. These have a direct relationship on the projections
Page 11
made during the pre-investment phase. If such strategies and projection prove faulty any
remedial measure will not only prove difficult but may be too expensive.
Page 12