TD04 145kV GIS Technical Guide
TD04 145kV GIS Technical Guide
TD04 145kV GIS Technical Guide
Technical Guide
Page 1/44
132kV GIS extension at Kalika steel
CONTENTS
CONTENTS ............................................................................................................................... 2
1. General Description of Gas Insulated Switchgear Type 8DN8 ................................................ 3
2. FAT Protocol ..................................................................................................................... 11
3. Installation Gas-Insulated switchgear type 8DN8............................................................... 13
4. Commissioning Gas-Insulated switchgear type 8DN8 ....................................................... 22
5. High Voltage Test at Site of Gas Insulated Switchgear Type 8DN8 ................................... 29
6. Guidelines for storage & handling of GIS & its components............................................... 33
7. Low Voltage Equipment..................................................................................................... 40
8. List of secondary makes .................................................................................................... 41
9. Training ............................................................................................................................. 43
Page 2/44
132kV GIS extension at Kalika steel
Standard Specifications
The switchgear conforms to the following IEC standards:
Switchgear, general:
IEC 62271-1 Common specifications for high voltage switchgear and
controlgear standards
IEC 62271-203 High-voltage switchgear and controlgear
Part 203: Gas-insulated metal-enclosed switchgear for rated
voltages above 52 kV
Circuit-breakers:
IEC 62271-100 High-voltage switchgear and controlgear
Part 100: High-voltage alternating-current circuit-breakers
IEC 62271-101 High-voltage switchgear and controlgear
Part 101: Synthetic switching
Instrument transformers:
IEC 60044-1 Instrument transformers -
Part 1: Current transformers
IEC 60044-2 Instrument transformers -
Part 2: Inductive voltage transformers
IEC 60044-6 Instrument transformers -
Part 6: Requirements for protective current transformers for
transient performance
Cable connections:
IEC 62271-209 High-voltage switchgear and controlgear
Part 209: Cable connections for gas-insulated metal-enclosed
switchgear for rated voltages above 52 kV – Fluid-filled and dry-
type cable-terminations
Outdoor bushings:
IEC 60137 Insulated bushings for alternating voltages above 1000 V
Page 3/44
132kV GIS extension at Kalika steel
Surge arresters:
IEC 60099-4 Surge arresters
Part 4: Metal-oxide surge arresters without gaps for a.c. systems
SF6-Gas:
IEC 60376 Specification of technical grade sulfur hexafluoride (SF6) for use in
electrical equipment
IEC 60480 Guidelines for the checking and treatment of sulfur hexafluoride (SF6)
taken from electrical equipment and specification for its re-use
IEC/TR 62271-303 High-voltage switchgear and controlgear
Part 303: Use and handling of sulphur hexafluoride (SF6)
EMC:
IEC 62271-1 Common specifications for high voltage switchgear and
controlgear standards
Enclosure
Page 4/44
132kV GIS extension at Kalika steel
Modular design
Housings and expansion joints together form the pressure-resistant enclosure of the switchgear.
The housings are made of cast or welded aluminium, the expansion joints of high-grade steel
and the covers of steel or aluminium. The switchgear modules are three-phase or single-phase
encapsulated.
Three-phase: Single-phase:
Busbar Transformer termination module
Circuit-breaker SF6/air connection module
Disconnector
Three-position-switch (disconnector with earthing switch)
Earthing switch
Current transformer
Voltage transformer
Cable termination module
Surge arrester
The manufacturing and testing of the housings are state-of-the-art technology. Each housing is
subject to a pressure and gas tightness test and complies with the requirements of the relevant
EN standard.
Surface Treatment
Steel (covers):
Indoor: hot galvanised or painted
Outdoor: hot galvanised and painted
High-Grade Steel (expansion joints):
Indoor
Pre-treatment: none
Paint work: none
Outdoor
Pre-treatment: degrease
Paint work: same as housings of cast aluminium
Cast-aluminium:
Pre-treatment (indoor and outdoor): sand-blast or degrease alkaline
Internal surfaces (cast-aluminium): Seevenax protective paint RAL 7035
Internal surfaces (aluminium wrought alloy): without surface treatment
External surfaces
Material description: high-resistant 2-component
polyurethane paint
Color code: RAL 1013
Gloss: silk gloss - silk-matt
Drying: air or stove dried
Top coat: Outdoor: Alexit top coat 5225, 5:1
Indoor: Celerol top coat 362-24
Reaction component: Alexit hardener 402
Thinner: Alexit thinner 62 or 68
The used lacquers are free of harmful materials like cadmium, lead and chromic acids.
Page 5/44
132kV GIS extension at Kalika steel
Circuit-breaker
• The circuit-breaker can be vertically or horizontal arranged. It forms the basis on which the
other modules of the bay are mounted.
• Switching is actuated by means of a spring-charged operating mechanism for triple-pole
auto-reclosure
• The gas flow required for arc-quenching is generated in the interrupter units by means of the
puffer piston and cylinder (self-compression principle of SF6 gas in the arcing chamber)
• The control unit contains the drive mechanism and equipment for control and monitoring of
the circuit-breaker
• The module forms a separate gas compartment together with the CT module
• Position indicators which are directly connected to the switching rod show the triple-pole
switching state. Auxiliary switches allow electrical monitoring of the switching and
intermediate positions
Page 6/44
132kV GIS extension at Kalika steel
Current transformers
• The current transformers are of inductive single-conductor type (the primary conductor of the
switchgear is the primary winding with one turn). The secondary windings are fixed on
toroidal cores.
• Various cores for measuring, metering and protection purposes are possible
• The current transformers comply with IEC standards.
Page 7/44
132kV GIS extension at Kalika steel
Voltage transformers
Inductive voltage transformers consist of an iron core, the single-step primary winding with
the HV electrode, the secondary windings and the HV terminal; all windings are designed as
layer windings with plastic foil insulation
• Voltage transformers form a separate gas compartment
• Terminal box for connection of the secondary terminals
• The voltage transformers comply with IEC standards.
Surge arresters
• Surge arresters are designed to protect the switchgear against the effects of overvoltages.
• The normal type of surge arrester is suitable for power frequencies between 48 and 62 Hz
• The active part of the arrester are metal oxide resistors mounted in series within a cage of
FRP (Fibre Reinforced Plastic) rods.
• Pressurised SF6-gas filled into the aluminium cast tank forms the insulation. The pressure of
each arrester is indicated on the rating plate.
• The SF6 maintenance point and the density monitor are located on the cover on the earthed
side of the arrester housing.
• The gas compartment is monitored in the same way as the gas compartments of the
switchgear.
Interfaces to others
• The cable connection housings without cable sealing ends acc. to IEC 62271-209 and our
interface drawing 1)
• The terminal studs/plates of the SF6/air bushings acc. our interface drawing
• The transformer connection housings without SF6/oil bushing acc. to IEC 61639 and our
interface drawing.
1) Note: The design of the cable termination shall be fully in conformance with IEC 62271-209. According to this
standard, the insulation between the gas compartment of the gas-insulated cable connection enclosure and the
cable termination serves as a barrier to prevent the flow of insulating gas between the components. Cable
terminations which allow a flow of gas (e.g. SF6) between the components are not in conformity with the
standard and are not appropriate for installation into the calbe connection enclosure.
Page 8/44
132kV GIS extension at Kalika steel
EMC
A variety of EMC control measures are considered in the design of the 8DN8 switchgear
• Screening measures in the current and voltage transformers
• High-frequency-compatible shielded measuring and control cables
• Shielding and earthing of electronic modules
• High-frequency-compatible design of earthing for building and GIS (supplied by others)
Earthing material
All necessary material required for the connection of the switchgear to the embedded
grounding and potential grading grid, provided by the customer in the foundation plate, is
contained in the scope of our quotation. The switchgear bay is earthed via the circuit breaker,
the cable connection housings, the transformer connection modules and the SF6/air bushings.
Dispatch
The dispatch units are fixed at the factory with respect to the layout of the switchgear modules.
Delivery of one complete feeder with out the interface modules in one dispatch unit is possible
depending on the switchgear design. The other modules like voltage transformers, SF6/air
bushings, and connection modules will be packed separately.
Page 9/44
132kV GIS extension at Kalika steel
The current and voltage transformers, surge arrester as well as SF6/air-bushings are
manufactured in subsupplier’s factory.
The acceptance test of current and voltage transformers, surge arrester as well as SF6/air-
bushings is not envisaged. The routine test certificates of these parts will be handed over
together with the test certificates of the switchgear.
The mechanical tests will be done on one switching device of each type, the dielectric test on
one switchgear bay without voltage transformers, SF6/air-bushings and outgoing bus ducts.
Maintenance
Siemens metal-enclosed SF6 insulated switchgear requires extraordinarily little maintenance.
The maintenance effort recommended is limited to those parts which are subject to wear or
ageing. The time and extent of the work to be carried out depends on
• The number of short-circuit operations
• The switching frequency and
• The operating time
Page 10/44
132kV GIS extension at Kalika steel
2. FAT Protocol
1) Circuit-breaker
a) Operation
5 x CLOSE and OPEN at 110% Un
5 x CLOSE and OPEN at 100% Un
5 x CLOSE at 85% Un and 5 x OPEN at 70% Un
5 x OPEN-CLOSE-OPEN at 100% Un
Page 11/44
132kV GIS extension at Kalika steel
a) Operation
5 x CLOSE and OPEN at 100% Un
5 x CLOSE and OPEN at 85% Un
b) Current measurement of motor drive during CLOSE and OPEN operation at 100 % Un
c) Measurement of motor operating time during CLOSE and OPEN operation at 100 %Un
Page 12/44
132kV GIS extension at Kalika steel
3. Installation
Gas-Insulated switchgear type 8DN8
Switchgear room
The following preconditions must prevail in the switchgear building prior to the start of
installation work:
Civil works complete
Roofing work complete
Windows, doors and gates closable and windproof
Penetrations / openings fully sealed
Floors prepared according to loading specifications
Floors level and treated with primer coating
Switchgear room wall painted
Foundation plates and anchor rails (e.g. C-sections) complete
Cable ducts in the switchgear area complete
Earthing system and connection points for switchgear earthing complete
Crane system installed and ready for use
Lighting system complete
Ventilation system complete
Construction power supply available
Water supply available
Site arrangements
The following site arrangements are a precondition for the start of installation work:
Office space available
Sanitary facilities available
Additional room available as workshop
Storage room available
Hoisting gear, means of transportation available
Transport routes prepared
Accident prevention regulations available
First-aid facilities available
Warning and mandatory signs in position
Installation personnel
The involvement of outside/customer personnel in place of Siemens specialists shall be on
condition that the general minimum qualifications for the individual categories ranging from
unskilled helper to trade foreman are met and on condition that electricians, pipe fitters, steel
erectors, welders, etc. are adequately qualified according to the respective trade-specific
minimum requirements.
Page 13/44
132kV GIS extension at Kalika steel
Drawing documentation
GIS OM/TD-04 For offer only Rev 0
Rev 3: 20.10.2020 Date:17.10.2023
Page 14/44
132kV GIS extension at Kalika steel
Single-line diagram
Single-line representation of the switchgear with technical data, equipment identification
Assembly drawings
Earthing system, steel structures, switchgear components, building;
Plan and sectional view, representation of details, dimensions, item numbers
Detail drawing
Specific installation instructions (e.g. cable fastening, conductor connection, tie rods, switchgear operating
mechanism, bracing / supporting systems etc.)
Installation of modules
Conductor connection
Before connection of the modules, the coupling contacts of the inner conductors are cleaned,
greased and fitted.
The correct insertion depth of the sliding contact is verified by measurement and readjusted if
necessary.
Enclosure connection
Page 15/44
132kV GIS extension at Kalika steel
All bare metal surfaces on the inside and outside of the flange connection are cleaned and
treated with the respective prescribed anti-corrosive grease.
The relevant O-ring is then lightly greased and inserted in the flange groove which has been
treated with suitable oil.
The two flanges are pushed together, matched and connected by means of bolts and by
uniform tightening across the entire flange surface.
All bolt connections are greased beforehand and then tightened applying the prescribed torque.
Expansion joints
If an expansion joint is fitted, the flange and inner conductor connections are established as
described.
The setting of the tie rods is checked with reference to the bay width specified in the assembly
diagrams.
Covers
When the modules have been installed, the enclosures are sealed gas-tight by means of the
prescribed covers; the sealing surfaces are treated in the same way as applies to flange joints.
If filter holders are provided on the inside of the cover, the filter material is not inserted until
immediately prior to fitting of the covers.
If the covers are provided with rupture diaphragms, the outlet direction of the diverter nozzle is
set according to the drawings.
Supporting structure
After transportation to the place of installation, the preassembled steel components are bolted
together according to the drawings.
Next, the assembled supporting structure is set up at the prescribed place of installation,
aligned and fastened to the ground, using wall plugs, anchor bolts or anchor plates (depending
on the version).
By using hollow-slotted rails and spacer bolts, the half-shells or connection plates for fixing the
switchgear are then fitted to the support top or beam.
Sliding supports are set up with a sliding surface (made of high-grade steel plate on plastic
plate) and fixed-point supports without such a sliding surface.
Finally, the supporting structure and the switchgear section concerned are matched, aligned
and bolted together as specified in the drawings.
External connections
Page 16/44
132kV GIS extension at Kalika steel
Note: For external connections (cable, overhead line or transformer termination), the standardized end of the scope
of supply / interface is the conductor contact and the gas filling in the connection module.
The respective supplier is responsible for matching of the external device.
From case to case, special construction for the high-voltage test is taken into account when making external
connections.
With a cable termination, the insulator of the cable sealing end is fitted gastight to the enclosure
opening of the connection module.
The conductor connection is generally established with coupling contacts and necessary
spacers or adapter elements and screening parts.
With an overhead-line termination, an extension module is built onto the respective outgoing
feeder bay, led outside through the wall penetration and supported.
A porcelain bushing is attached to the extension module via angle housing.
Outer phases have from case to case to be inclined outwards in order to attain the required
striking distances (clearances).
If modules are installed in outdoor areas, they are attached by means of suitable belts or ropes
and lifted by crane.
Depending on the switchgear design, the conductor connections are bolted or established with
coupling contacts.
For the termination of the overhead-line cable, the connecting surface on the insulator top is
brushed, cleaned and greased and the cable clamp bolted on.
The cable end is then brushed and greased, placed flush with the clamp and bolted tight.
With the transformer termination, the modular enclosure is slipped over the transformer bushing
and bolted gas-tight to its flange.
Depending on the version, the conductor connection is established with coupling contacts or
flexible connectors and necessary adapter elements, spacers and screening parts.
Depending on the local installation of the transformer, the connection with the outgoing feeder
bay is established with appropriately matched extension and angle modules.
Expansion joints and supporting elements are additionally provided to absorb constructional
tolerances and movements (thermal expansion).
Switchgear earthing
As specified in the relevant drawings, an earth bus made of galvanized steel or copper strip is
laid on the floor below the switchgear or along the wall in the switchgear room or basement and
connected to the tabs of the earthing network of the plant (prepared during civil work).
The run of the earth bus is marked beforehand and the earthing bars bolted in place by means
of suitable fixing clamps.
The switchgear housing, all steel structures for switchgear bracing’s, the local control cabinets,
cable trays and risers are connected at the prescribed points to the earth bus by means of
stranded or strip-type copper earthing conductors.
The earthing conductors are laid according to the drawings, cut to length, fastened and
connected to the marked earthing points by means of press-on cable lugs.
All connection surfaces are cleaned and greased beforehand.
Gas piping
Page 17/44
132kV GIS extension at Kalika steel
In case of centralized gas monitoring the gas pipes are installed as specified in the gas
monitoring diagram.
Each switchgear gas compartment is connected to the relevant gas monitoring cabinet
(equipped with built-in density monitor and pressure gauge).
Note: Depending on the switchgear type, certain gas lines are completed at the works and various gas lines requiring
further installation work on site are prepared ex-works and provided with transport seals.
For installation on site, the copper tube is straightened and then cut to length and bent in
accordance with the respective route.
Necessary pipe connections are soldered using sleeves or solder fittings and one connection
flange is soldered to each end of the pipe.
The prepared pipes are attached to the switchgear flanges using fastening lugs and clips.
Depending on the switchgear version and module type, either a screw joint with a union nut or a
flat connection with a connecting plate is made for the connection of the pipes to the stub of the
gas compartment and monitoring cabinet concerned.
Secondary equipment
Local control cabinets
Note: Depending on the switchgear version, local control cabinets are integrated ex-works in the bay construction
(IOS) or set up separately on site (GOS).
In the case of the integrated version, no cabinet installation is necessary on site.
For switchgear with separately standing local control cabinets, the cabinets or cabinet units are
lifted out of their cases by crane, checked for completeness and brought to their place of
installation by lifting truck or high-strength rollers.
In line with the specified floor penetrations, the first cabinet is placed on the finished floor or on
the foundation frame / rails provided.
It is then aligned and the cabinet baseframe is either bolted to the floor using suitable plugs or
welded with the foundation frame / rails.
In sequence, all cabinets or units are pushed up to the already installed cabinets, aligned and
fastened to the floor.
The cabinets are bolted together at the rows of holes provided in the cabinet side walls.
After installation, the cabinets or rows thereof are earthed as specified in the drawings.
Finally, separately supplied withdrawable units or cabinet modular assemblies are fitted and the
locking mechanism of the cabinet doors and the paint finish checked
Cable trays
Supports, brackets
GIS OM/TD-04 For offer only Rev 0
Rev 3: 20.10.2020 Date:17.10.2023
Page 18/44
132kV GIS extension at Kalika steel
The trays are delivered and unloaded as near as possible to the cable ducts or the scheduled
place of installation and sorted according to the width.
The installation axes for the tray routing are marked as specified in the drawings and the
installation points / holes for the standing or suspended tray supports (depending on the
version) marked and drilled.
The supports are aligned and bolted in place using suitable plugs.
The brackets are then sorted and prepared in accordance with the various cable tray widths and
the installation heights measured and marked according to the number of tray layers.
Next, the tray brackets are attached to the supports at the height marked, aligned and bolted
using the relevant screw-type material.
If installation rails are concreted in, the brackets are attached to these rails and there is no need
to fit supports.
Cabling
Cable route
The cable drums are transported by suitable vehicle into the switchgear room, unloaded at
selected installation points and set up with an unwinder or pay-out device.
With reference to cable lists and assembly drawings, all cables are initially prepared according
to cable route (from - to), cable designation, cable type and estimated cable length.
Next, the cable route and tray loading are determined for the various cable runs.
Cable laying
At a suitable point, the cable drum is set up and the cable pulled off the drum to its destination,
placed in the trays concerned and cut to the necessary length.
In certain cases (identical cable runs) the cable lengths are measured and cut before laying.
The cable length is selected so that each connection point at both ends of the cable run
(cabinet, switching device) can be reached.
The cable designation taken from the cable list is provisionally marked at the start of the cable
using suitable legend labels.
The marking at the cable end is applied after cutting to the necessary length.
Note: The provisional cable markings are removed after connection of the cables and the cables then designated
using the actual legend plates provided.
Page 19/44
132kV GIS extension at Kalika steel
At certain points, the laid cables are bundled and fastened by means of clips or plastic tapes
(ties).
Note: For connection of the transformer cables, terminal blocks are provided in the main transformer connection
boxes and local control cabinets.
The transformer cables are bent out, stripped and inserted into the cabinet or connection box on
both sides.
Depending on the design and use of the cable, the cable screen or armoring is appropriately
treated and earthed.
If cable glands are provided, the lower section of the gland is pushed over the cable, the
clamping ring fitted and the cable inserted and screw-connected.
After cable entering and gland-bolting, the inner insulation of the cable is stripped off and the
individual cores are led to the respective terminal strip.
The cores are then connected with reference to the connection lists, assembly drawings and
terminal diagrams.
Gas compartments
Filters
Shortly before gas-tight sealing of the gas compartment, the filter material for keeping the SF6
gas dry is placed in the holders provided.
Such holders are frequently on the inside of the manway cover.
Note: Depending on the switchgear type, certain gas compartments are supplied prefilled with gas and with filters in
place.With such gas compartments; there is no need to fit filter material on site.
In the case of connection modules, the filters are fitted only when the external connection has been assembled and
before the gas compartment concerned is finally sealed.
Evacuating
After gas-tight sealing, evacuation of the gas compartment is commenced.
Page 20/44
132kV GIS extension at Kalika steel
A suitable gas service unit is connected to the maintenance flange on the relevant gas
compartment and a vacuum meter is connected to a suitable point for measuring purposes.
With the vacuum pump of the service unit, the gas compartment is evacuated down to an
absolute pressure of <20 mbar.
Page 21/44
132kV GIS extension at Kalika steel
4. Commissioning
Gas-Insulated switchgear type 8DN8
Preparation
Prior to the pre-commissioning tests, the installation of the main switchgear is checked for
completeness and correctness.
The inspection is related to:
- arrangement and mounting position of high-voltage switching devices and instrument
transformers
- rated data of high-voltage equipment
- spacing between switchgear bays and adjustment of chamber expansion joints
- phase relation of main conducting paths
- installation of SF6 gas pipework
- assignment/mounting position of gastight and perforated bushings
- co-ordination of gas pressure values for the individual gas compartments
- earthing, earth connection
- cabling, cable connection
- labeling, nameplates
- cleanliness
- damage
End position
For disconnectors and earthing switches it is checked, by way of electrical ON and OFF
operation, that the actual end positions of the main contacts - indicated by a lever - match with
the markings showing the end positions determined and applied at the manufacturer`s works.
Page 22/44
132kV GIS extension at Kalika steel
A test current is injected or a test voltage applied to each phase of the transformer primary
winding and correct phase assignment is proved by measuring the secondary current or voltage
arising at the appropriate secondary terminals.
SF6 percentage
For the measurement, an SF6 percentage measuring device is connected by means of a hose
coupling to the gas compartment.
Subsequently a small quantity of gas is released and the gas flows through the built-in detector
of the testing device.
Measured values for SF6 percentage can be read off directly and must not be lower than 95%.
Gas tightness
For verifying the gas tightness, all flanged joints, pipe connections and soldered junctions
concerned with the gas compartments are sniffed off using a suitable gas leakage detector.
Any leaks are indicated acoustically.
Page 23/44
132kV GIS extension at Kalika steel
After completion of erection on site, the main conducting paths of the switchgear must undergo
high-voltage testing in order to verify the integrity of the insulation and the dielectric condition.
The appropriate test voltage values and test sequence/procedure are selected separately for
each actual switchgear version.
The test sections of the GIS are chosen as small as possible, in order to limit the capacitive
loading of the testing device and to avoid damage to the equipment due to high voltage
reflections or discharge energies in case of disruptive discharges (flashover, insulation
breakdown) during the test.
Owing to their high charging currents, high-voltage cables, overhead lines, power transformers
and in certain cases voltage transformers are disconnected from the GIS prior to the testing.
Arresters are disconnected as well because of their voltage-limiting effects.
The high-voltage is applied to one single phase with the two other phases and the enclosure
earthed.
The GIS has passed the test if all tested switchgear sections have withstood the specified test
voltage without disruptive discharge.
Also the following must be tested (For further details see operating instructions):
auto-reclosure lockout
closing lockout
general lockout
Page 24/44
132kV GIS extension at Kalika steel
Functional testing of the gas monitoring is carried out by raising and lowering the gas pressure
by using the gas filling device.
According to the given pick-up values, correct sequence of initiated signals of the density
monitors and proper functioning of the associated control circuits are tested.
ON-OFF operation
Electrical closing and opening control of all circuit-breakers is checked by giving the respective
commands from the local control panel, whereby all closing and opening coils of the switching
circuits are activated.
In doing so, correct co-ordination between control and display elements on the local control
panel and the respective circuit-breakers and correct checkback indication of the breaker
switching position on the local control panel are checked additionally.
Switching lockouts
After testing the closing and opening function, all lockout functions of the spring drive and gas
system of the circuit-breaker are initiated one after another and their effectiveness checked for
all closing and opening circuits by way of giving electrical switching commands.
The function is tested with the circuit-breaker in ON position and by tripping of the single
breaker poles one after another.
At the same time, the two other poles must also trip in each case.
With the breaker in the OFF position, the single breaker poles are closed one after another and
it is checked that the breaker opens again in each case.
Anti-pumping feature
Note: The anti-pumping feature prevents the circuit-breaker from switching repeatedly as a result of simultaneous ON
and OFF commands.
For the test, closing and opening commands are given simultaneously and it is checked that the
circuit-breaker in the ON position only performs one OFF operation and that the circuit-breaker
in the OFF position only performs one ON-OFF operation.
Page 25/44
132kV GIS extension at Kalika steel
ON-OFF operation
Electrical closing and opening control of all disconnectors and earthing switches is checked by
giving the respective commands from the local control panel.
In doing so, correct co-ordination between control and display elements on the local control
panel and the respective HV switching devices as well as correct checkback indication of
switching positions on the local control panel are checked.
Electrical interlocking
According to the given interlocking scheme, the appropriate release and blocking functions for
ON and OFF operation are checked by way of giving of electrical commands at - therefore
prepared - specific switching states of the HV devices concerned.
The aforesaid test covers
- all internal interlocking conditions between the individual HV switching devices of one
switchgear bay/feeder,
- superimposed interlocking conditions for bus couplers, busbar earthing switches etc. and
- all external interlocking conditions (e.g. between generator outgoing feeder and substation
incoming feeder).
Internal interlocking conditions are generally provided between
- circuit-breaker and intermediate position of associated disconnectors,
- disconnector and associated circuit-breaker,
- disconnector and associated earthing switch,
- earthing switch and associated disconnector.
Signalling
All alarm and indication signals of HV switching devices and of pressure, density and voltage
monitors as well as of fuses and mcbs are initiated at the respective device and checked upto
the local control panel (alarm board) for proper assignment and indication.
Additionally, all aux. functions (reset, lamp test etc.) and correct designation of the signals are
tested.
Anti-condensation heaters
When testing the heaters for preventing condensate, the current consumption per phase of all
heating circuits is measured and the heating effect checked.
Voltage transformers
GIS OM/TD-04 For offer only Rev 0
Rev 3: 20.10.2020 Date:17.10.2023
Page 26/44
132kV GIS extension at Kalika steel
Design
Visual checks in order to verify correct design of the voltage transformers are carried out with
regard to
- ratings (ratio, class, power)
- application of secondary windings (metering or protection purposes)
- earthing of secondary windings and cable shielding
Secondary circuitry
When testing the secondary circuits, electrical continuity up to the last point of connection in the
local control panel and connection in correct phase sequence of all interconnected metering
units is verified.
In doing so, a test voltage (preferably with different value for the three phases) is applied to the
transformer secondary terminal of each phase with the secondary winding disconnected.
Next, the applied voltage is measured at specific points in the secondary circuitry and the
function of all interconnected metering units is checked.
Current transformers
Design
Visual checks in order to verify correct design of the current transformers are carried out with
regard to
- ratings (ratio, class, power)
- application of secondary windings (metering or protection purposes)
- earthing of secondary windings and cable shielding
Polarity
A polarity check is carried out in order to verify correct winding direction and assignment and
identification of secondary terminals.
In doing so, a suitable voltage source is used to apply a DC voltage impulse to the primary
winding of the current transformer and correct direction of the voltage impulse at all secondary
windings - resulting thereupon - is checked by using a bi-directional voltmeter.
Note: In various cases, the polarity check is carried out in the course of checking the main conducting paths by way
of voltage drop measurement.
Secondary circuitry
When testing the secondary circuits, electrical continuity up to the last point of connection in the
local control panel and connection in correct phase sequence of all interconnected metering
units is verified.
Page 27/44
132kV GIS extension at Kalika steel
In doing so, a test current is injected at the transformer secondary terminal of each phase and
the respective current flow is measured at suitable points in the secondary circuitry.
At the same time, the function of all interconnected metering units is checked.
Page 28/44
132kV GIS extension at Kalika steel
Conditioning / Forming
Before high-voltage testing, the switchgear must be conditioned. It is carried out by means of a
specified, stepwise increase of the AC test voltage. This conditioning is a single-phase process,
using a test transformer.
Instrument transformers
During high-voltage tests, the secondary windings of current transformers must be short-
circuited and earthed.
Inductive-type voltage transformers need not be disconnected during testing with AC-voltage.
In all cases, the manufacturer’s instructions are decisive and must be followed.
Disconnection of equipment
Owing to their high charging currents or voltage-limiting effects, certain items of high-voltage
equipment joined to the GIS via air-insulated or SF6-insulated connections must be
disconnected from the GIS during high-voltage testing.
These include:
- Overhead lines
- High-voltage cables
- Arresters
- Power transformers
The disconnection points (clearances) must be screened.
Page 29/44
132kV GIS extension at Kalika steel
Test sequence
The test frequency is depended of the capacitance of the test section.
The frequency will be in between 50 Hz – 300Hz as per IEC 62271-203.
The testing with AC power-frequency voltage will be carried out in the following sequence:
- Gradual voltage increase up to 1,2 x Ur/3
- Conditioning 5 min
- Gradual voltage increase up to 1,2 x Ur
- Conditioning 3 min
- Gradual voltage increase up to test voltage Uds acc. IEC 62271-203 tab 107
- High-voltage testing (main test) 1 min
- Voltage Reduction
To pass the test, the equipment must withstand the full test voltage for 1 min.
V
1 min.
Uds
3 min:
Ur
5 - 15 min:
Ur /3
C T
0 5 10 15 20 25 30
t
Page 30/44
132kV GIS extension at Kalika steel
Page 31/44
132kV GIS extension at Kalika steel
Test connection
Page 32/44
132kV GIS extension at Kalika steel
Objective
This work instruction describes all storage, handling and transport of GIS bays and module after
receipt of GIS bays, modules and material at site in order to be able to ensure the product
quality.
Taking into account the various influences on the goods (climate conditions, duration of
transport and storage, method of transport), several different types of packaging are used. The
type of packaging is noted on the packing slip and subsequently described. Drawings on the
packaging give information on the nature and arrangement of transport devices.
The accessory items are delivered on wooden pallets, in open crates or sturdy corrugated-
cardboard boxes.
The sealed packaging surrounds the contents on all sides with a barrier layer. The quantity of
drying agent contained in this barrier layer limits the relative humidity to a level of < 60%, a level
which can cause no damage to the contents of the packaging for the duration of their storage
life unless it is damaged & mishandled. The amount of desiccant depends on the crate surface
area, the type of barrier (vapors permeability), the climatic conditions and active life in months.
Scope
All types of GIS products, its components, modules
Page 33/44
132kV GIS extension at Kalika steel
Storage of goods
Storage must take place
In closed rooms (Indoor)
Outdoors after applying a folding box. Limited storage period for packaged goods in
basic packaging. Shipping units in the basic packaging may only be stored in the open if
it is certain that they are adequately protected from the elements, particularly from
moisture.
Requirements to be met when choosing and preparing storage areas
Protect stored goods against moisture (flooding, runoff from melting snow and ice), dirt,
destructive creatures such as rats, mice and termites, and unauthorized access.
Place crates on boles or squared timber to protect them against ground moisture and for
better ventilation.
Determine the loading capacity of the area.
Arrange the storage area based on packing slip information, symbols and details on the
packages.
Keep access routes free.
Stored goods should be inspected at regular intervals. After storms, heavy rain or snow,
appropriate additional measures should be taken. If erection of the installation does not
take place until after the intended life of the package seals, appropriate steps must be
taken in good time. This may include:
Proper reconditioning of the sealed packaging.
Unpacking of goods and storage in an appropriate storage room. Where required,
qualified personnel can be consulted through the appropriate Siemens office. Time-
limited storage in sealed packaging that is exclusively designed for transport.
1. Use proper equipments for unloading the GIS material from the trucks/trolleys
2. Use the guidelines (SOP) stick on the boxes to tie the slings for unloading to avoid damage to
the material
3. After proper unloading, if the erection is not to be started immediately follow the below
guidelines for storage of the GIS material
4. If the GIS is to be stored indoor
a) GIS equipment should be stored indoor always in a lock and key arrangement
b) The hall should have proper flooring and roof top with closed
window (if any), and shall be kept ,
c) Sealing all the open entries so as to avoid water, moisture, dust,
destructive creatures like rats/mice and termites
d) Do not put heavy goods on top of one other, do not overload any
goods by excessive stacking
e) The cases (boxes) should be arranged in such a way that the packing
list/ box details are not torn off
5. If the GIS is to be stored outdoor in absence of indoor space below guidelines to be followed
GIS OM/TD-04 For offer only Rev 0
Rev 3: 20.10.2020 Date:17.10.2023
Page 34/44
132kV GIS extension at Kalika steel
a) The GIS should be stored at elevated base (to avoid water ingress)
b) The base should have enough loading capacity to bear the load of GIS bays
c) There should be a proper roof (shed) over the elevated ground
d) Do not put heavy goods on top of one other, do not overload any goods by
excessive stacking
e) The cases (boxes) should be arranged in such a way that the packing list/ box
details are not torn off
f) Once all the boxes are kept in the prescribed area, cover all the boxes with proper
tarpaulin sealing all the open entries so as to avoid water, moisture, dust, destructive
creatures like rats/mice and termites
Store the goods carefully in accordance with the directives in the following section. Store spare
parts separately. Specially preserve small components if the storage room is unable to maintain
required storage conditions or if the storage time is expected to be particularly long.
Avoid damage to modular assemblies during storage – Damage can affect subsequent
operation.
Pay attention to the carrying capacity of the floor.
Do not place heavy goods on top of one other. Do not overload any goods by excessive
stacking.
The cases should be arranged so that the case number is clearly visible. Related parts
should be stored in line with the sequence in which they are to be erected.
Store machines with rolling-contact bearings (or assemblies containing machines) on
vibration-free floors (the bearings may otherwise be damaged).
For Highly flammable materials
Smoking is forbidden
Observe fire prevention regulations.
Fire engines must have unhindered access in the event of fire.
Ensure that extinguishers are available adequately protected from adverse weather
conditions.
The protection can be considered sufficient if
The requirements outlined in this section with regard to the selection of and conditions in
a site for the storage of seaworthy crates are met.
The case of tents and tarpaulins, it is ensured that they are secured properly and that
water cannot accumulate (such canopies must cover the goods far enough to prevent
the penetration of rain driven from the side, snow etc.),
There is adequate ventilation underneath the weather protection (covers must not lay
directly against the cases. Use a frame of slats or boards to ensure that there is an air
gap of approx. 30 cm.)
The supply voltage to the anti-condensation heating is connected and the heating is in
operation if the unpacked assembly is to be stored in the open for more than 2 weeks.
Page 35/44
132kV GIS extension at Kalika steel
Depending on the respective local conditions, the packages can be either unpacked directly at
the assembly point, in a special room, or with suitable weather conditions.
Essentially, it has proven beneficial to unpack the packages directly in the switchgear hall after
leveling the switchgear, if this is possible.
After this is finished the hall floor must be thoroughly cleaned before any further work can begin.
Page 36/44
132kV GIS extension at Kalika steel
Annexure
Page 37/44
132kV GIS extension at Kalika steel
Symbols on packages
The packing crates bear symbols which give instructions for safe transport and proper storage.
Page 38/44
132kV GIS extension at Kalika steel
In order to clearly organize the location of assembly for the switch gear, shipping assemblies
are specifically labeled. These labels have been placed on the protective covers on the joints of
the assembly.
Page 39/44
132kV GIS extension at Kalika steel
RELAYS
CIRCUIT BREAKER
PLUG
MCB
PROTECTIONS DISCONNECTORS &
TERMINALS
TERMINALS
FUSES
EARTHING SWITCHES
TERMINALS
Cables busway running in the underground floor under the GIS room or in the cable trenches
Page 40/44
132kV GIS extension at Kalika steel
Page 41/44
132kV GIS extension at Kalika steel
Lugs Lapp / 3D
Schneider / Local indication for CT
Digital ammeter
Rishabh current
Schneider / Local indication for VT
Digital voltmeter
Rishabh voltage
Cubicle heater with internal
Velico Anti condensation
thermostat (LCC)
Cubicle heater (drive cubicles) Variturn Anti condensation Crimp contact HAN E
Insert HAN 46 EE
Drive cubicle-LCC Coding system guide
connections pin
Harting / TE Coding system guide
M/F plug sockets (46 pin, 7 pin) density monitor-drive
connectivity
cubicle connections bush
Housing bulkhead
mounting HAN 24 B
Switch position indicator LED based position
Steam Airetric
( Semaphore ) indication
Switch position indicator Dav / Gossen Rotary type position
16 window / 16 relays
( Semaphore ) Muller indication
Fault annunciator with relay
Minilec Fault alarms
module
For no voltage / under Resettable / non-
3-phase under voltage relay EES
voltage signals resettable
Cycle / operation
Operations counter GIC
counting
Rollytray /
PVC channel Cable guiding inside LCC
Connectwell
LV device mounting
Din rail (35 mm) Connectwell
inside LCC
RR / Polycab /
Internal wires Inside LCC wiring
Relicab
Page 42/44
132kV GIS extension at Kalika steel
9. Training
This course informs on construction and function, maintenance and service of Siemens HV SF6-
insulated switchgear. The training is basically tailored to give a technical overview on the
switchgear. Individual adaptations on the individual group and their knowledge and aims are
possible. Training shall be conducted in English. Travel, hotel and food expenses shall be borne
by the participants.
Training Agenda:
Training introduction
Product Overview :
- general explaination of GIS
- layout and architecture of GIS
Your project:
- single Line Diagram
- substation Layout
- GIS Technology
Product Overview :
- Know your GIS
Page 43/44
132kV GIS extension at Kalika steel
Page 44/44