Bill Of Quantities (BOQ)
Building Educational Infrastructures In Meghalaya
Grace Foundation U.P. School
Sl. No. Particulars Quantity Unit Rate (Rs) Amount (Rs)
Cement concrete flooring 1:2:4 (1 cement: 2 coarse sand: 4
1 graded stone aggregate) finished with a floating coat of neat
cement, including cement slurry, complete.
(a) 25 mm thick 168.6 sqm 370 62382
2 White washing with lime to give an even shade:
15 Library furniture - Wooden storage.(Rate not as per PWD SOR) 2 nos. 9,000 18000
Providing ancl laying Ceramic glazed floor tiles of size
300x300 mm (thickness to be specified by the
manufacturer), of let quality conforming to ls:15622, of
approved make, in all colours and shades laid on 20 mm
16 14 sqm 1,465 20510
thick bed of cement mortar 1:4 (1 Cement: 4 Coarse
sand), jointing with grey cement slurry @ 3.3 kg/sqm
including pointing the joints with white cement and
matching pigments etc., complete.
(a) 1.00 mm thick with zinc coating not less than 275
12.32 sqm 1,275 15708
gm/sqm
(a) 1.00 mm thick with zinc coating not less than 275 gm/sqm 18.96 sqm 1,275 24174
(a) 1.00 mm thick with zinc coating not less than 275 gm/sqm 16 sqm 1,275 20400
(a) 1.00 mm thick with zinc coating not less than 275 gm/sqm 19 sqm 1,251 23769
(a) 1.00 mm thick with zinc coating not less than 275 gm/sqm 19 sqm 1,275 24225
Providing wood work in frames of false ceiling, partitions, etc.
7 sawn and fixed in position with necessary stainless steel
screws ctc.
.(c) With 1st class Local wood
0.16 cum 76,500 12240
(i) Pooma/ Hollock/ Gamari and the like
Total Amount in words: Thirty nine lakh ninety four Thousand nine Hundred eleven Rupees