ESTIMATE FOR BALANCE WORK OF Ms J.S .

KUMARI RESIDENCE BUILDING AT


KANDUWEWA ,NOCHCHIYAGAMA

Ite
Description Unit Quantity Rate Amount
m

Reinforced cement concrete demolished in suspended


1 floors, reinforcement removed and debris cleared m³ 0.2 21,924.00 4,384.80
within the site

Excavation in trenches for walls, column pits and


foundation in sort/loose soil up to a depth 1.5m and
2 depositing excavated material to distance within the m³ 1.5 1,086.00 1,629.00
site as directed.(Earth work support and back filling to
be paid separately where necessary).

Filling under floors with gravel or other approved


quality material supplying, filling, spreading, leveling,
3 watering and compaction in 150mm layers as per m³ 4.5 4,538.00 20,421.00
Engineer's instruction, measured on compacted
volume(material not available at site)

150-225mm Random rubble masonry in cement and


4 m³ 3.2 26,221.00 83,907.20
sand mortar 1:5 in supper structure

100mm thick nominal hollow block work in cement and


5 sand mortar 1:5 with 400x100x200mm blocks (cavities m² 108 2,742.00 296,136.00
unfilled)

Mixing & Placing in Position Cement concrete grade


6 C20/25 in column shaft using mixer,vibrator and curing- m³ 2.25 42,044.00 94,599.00
up to first floor level

Mixing and Placing in Position Lintel, cement concrete


grade C16/20, 112x150mm with 2 nos. 12 mm dia. high
7 Lm. 21 3,042.00 63,882.00
yield strength bars including necessary form work-up to
first floor level

112x150mm stiffener columns in 1:2:4(20mm) cement


8 concrete including reinforced with 2 nos of 10mm dia. Lm. 8.5 1,884.00 16,014.00
high yield steel bars , including necessary form work

12mm laminated plywood shuttering for column shaft


9 m² 18 4,504.00 81,072.00
including dismantling-up to first floor level

High yield strength reinforcing in columns, beams, slabs


10 and lintels up to second floor level bent to shape laid in Kg 85 661.00 56,185.00
position and tied with G.I. Wire as directed
Plain round steel reinforcements shape into stirrups
11 and laid in position and tied with GI wires as directed- Kg 18 658.00 11,844.00
up to first floor level
Cement plaster with 1:5 mix, 15mm thick finished
12 smooth with skim coat in internal walls-up to first floor m² 3 1,622.00 4,866.00
level
Cement plastering with 1:5 mix , 15mm thick finished
13 semi rough in external reveals (not exceeding 100mm Lm. 155 291.00 45,105.00
wide ) walls
Rendering cement 12mm, in 1:5 cement and sand on
14 existing concrete, floating coat using Colour cement, m² 98 1,584.00 155,232.00
finished smooth

Skirting 25x100mm in 1:5, projected or flush with walls


15 Lm. 17 698.00 11,866.00
and including forming groove finished with red cement

Asbestos corrugated sheet fixed on existing roof with


16 m² 39 3,248.00 126,672.00
necessary bolt and nuts

Fabricating and fixing door, 95mm x 70mm (nominal)


frame in class 1 or above timber and 19 to 22 mm )think
class 1 or above battened with grooved and tongued
joints sash with 3 nos of 5" x 3" sized brass(MELWA)
17 butt hinges and necessary screws as per engineer's m² 5 37,697.00 188,485.00
instruction. Rate shall be included cleaning and
preparation of surface and application primer for under
coat and two coats of enamel paint (Door lock barrel
bolt paid separately )

Prepare surface and apply one coats of floor paint, red,


18 m² 19 841.00 15,979.00
gray or black

Total Amount 1,278,279.00

PREPARED BY …………………………………………..