Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Quality Checklist For Site Works: 15 Plastering Preparation Task

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

#UNKNOWN!

QUALITY CHECKLIST FOR SITE WORKS

15 PLASTERING PREPARATION TASK


1ST & 2ND FLOOR

ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY

EXTRIOR

Building Unit Designation Name: Project ID:


Name of the Contractor Group: Location:
Construction Drawing Ref. No.: Quantity:

CL : 15-A
Sl.N Description YES NO NA
o.
x Is format CL:13-A & CL:014-A for Surveying complied with?
1 Check for COMPLETION OF PRECEDING ACTIVITIES like fixing of service Conduits, Water Supply & sanitation lines, etc.

2 Was the Materials to be used in plastering Tested (or MTC Reviewed) and Approved?
3 Mortar Machine available with spares & connected to water supply
4 Gypsum material is within expiry date?
5 Whether chicken mesh (Is Chicken / Fibre Mesh is fixed on the junction of RCC & Masonary work) and Corner beads used as per
specifications?
6 Door, Window frames / Sub frames fixed properly (Checked for Plumb, Line, level Warping etc.)
7 Check for MORTAR MIX PROPORTION & Check for Surface of mortar mixing and addition of water profing compond if required.

8 Joints between Masonary & RCC Beam / Column filled properly with Non-Shrink grout & cured

9 Joint between Masonary & Door, window frame has been filled

10 All concrete surfaces were hacked properly before plastering. (50 no's / sq.ft.)
11 Is the whole surface is made free from Dirt, Dust, Oil, Grease, Masking tape, Patra Patti, Nails, Algae etc. and cleaned properly ?

12 Is Pre – Wetting of wall sub-lyer has been done ?


13 Is Level Pads are provided on walls / beam soffit & slab soffit at determined intervals and reqd. thk. ?
14 Ensure for wall to receive plaster thick > 20mm, Cementitious non shrink repair mortar applied as per manufacturer
recommendation.
15 Check for THICKNESS & NUMBER OF COATS of Plaster and required finish for further activities ?
16 Check that proper curing is provided for the repaired mortar ?
17 Ensure the Surfaces to receive plastering free from all loose particles ?
18 Ensure proper installation of plastering accessories, openings' sub-frames & level Guides as per approved material submittal,
method statement & shop drawings.
19 Ensure the sequence of plaster application with protection of other works, embedment, finishing and corners have been carried
out as per requirement.
20 Ensure if Rush coat is applied on substrate as per the manufacturer recommendation and method statement (When required)
21 Ensure that surfaces are wet prior to plaster.
22 Ensure the area near wood frames, skirting and around pipes or fittings as true and level.
23 Ensure the required number of coats of plaster have been applied with respect to the requirements.
24 Check that the finish coats are applied as per DESIGN requirement ?
25 Check that proper curing of plaster layers is provided per CODE ?
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
Comments:

Contractor's Rep.: Client Rep.: Lines & Visions Int. Rep.:

You might also like