Berita Acara Volume Monthly Nov 2023 - LPPBJ
Berita Acara Volume Monthly Nov 2023 - LPPBJ
Berita Acara Volume Monthly Nov 2023 - LPPBJ
1 Volume Batubara :
Coal Getting On Pit Seam A 2867.178 BCM 3,727.33 MT
Coal Getting On Pit Seam B 1,480.113 BCM 1,924.15 MT
Density Batubara (Bituminus) 1.3
Total Volume Batubara 4,347.29 BCM 5,651.48 MT
2 Volume Overburden :
Total Volume Monthly LPPBJ 01 - 30 Nov 2023 39,203.84 BCM
6 Fuel Consumption
Solar Issued during the month for OB & Coal LPPBJ 47,615 Liter
Fuel Untuk Kegiatan
Fuel Ratio Liter/BCM Penambangan di PIT 2
1.09
Notes : 1. Fuel Ratio < 0.80 (PIT & ROAD HAUL)
2. Pekerjaan TNB dibagian expose a telah ter cut oleh LPPBJ pada tanggal 19/11/2023 shift 2 sehingga
perhitungan OB yang telah dikerjakan di adjust berdasarkan truckcount LPPBJ sehingga didapatkan volume
385.44 bcm
Truck Count Direkap Oleh : Diukur dan Diolah Oleh : Diverifikasi Oleh:
Admin Produksi Surveyor Mine Plan Engineer Dept head Engineering
PT Lahat Pulau Pinang Bara Jaya PT Lahat Pulau Pinang Bara Jaya PT Lahat Pulau Pinang Bara Jaya PT Lahat Pulau Pinang Bara Jaya
Diketahui Oleh:
Kepala Teknik Tambang
PT Lahat Pulau Pinang Bara Jaya
Joni Suherna
PT. LAHAT PULAU PINANG BARA JAYA
LAMPIRAN 1 Engineering Department
HASIL PERHITUNGAN VOLUME BY SURPAC Site Lubuk Betung, Merapi Selatan
01 s/d 30 Nov 2023
Mine Survey - Wahyu