Safe, Success To Deliver The Promise: Ruby Field Daily Production Report
Safe, Success To Deliver The Promise: Ruby Field Daily Production Report
Safe, Success To Deliver The Promise: Ruby Field Daily Production Report
DATE : 05-March-2018
NTR 0 NTR
3. ENVIRONMENTAL
Quantity
Effluent Stream Unit
Today Yesterday
Gas Flared 0.29 0.43 MMSCF
Produce Water overboard 5.24 0.00 BBLS
Oil In Water 5.46 5.54 PPM
4. POB IN FIELD
No. Location/Field/Vessel POB
1 PQP 27
2 TB Sejati 13
TOTAL 40
5. VESSELS
Fuel ROB Moored To
No. Name/Callsign Activity
Used(Ltr) (Ltr) Buoy (hrs)
6. PRODUCTION INFORMATION
A. GAS PRODUCTION
RUBY Metering Senipah Metering
Outlet Unit
Today Yesterday Today Yesterday
Ruby Net Production 92.04 5.36 MMSCF
Gas Energy Rate 93.58 4.41 87.90 14.60 BBTU
Gas Export Rate 90.74 4.27 84.07 13.97 MMSCF
Pipeline Pressure Avg 103.30 80.30 43.20 46.03 BARG
YTD Sales Gas Production 5,672.24 5,578.66 6,191.92 6,104.02 BBTU
YTD Sales Gas Production 6,378.66 6,287.92 6,388.29 6,304.22 MMSCF
CUM Sales Gas Production 117,399.94 117,306.36 122,551.74 122,463.83 BBTU
CUM Sales Gas Production 122,252.70 122,161.96 122,254.53 122,170.46 MMSCF
PRODUCTION ISSUES
- Nomination (115 MMscf) not achieved due to linepacking.
C. GAS COMPOSITION
Ruby-01/P 3 272 77.55 64.29 38.75 25.39 0.00 15.31 22 1.66 2/28/18
Ruby-03/P 11 272 75.87 75.67 52.13 26.09 0.00 15.17 22 1.72 2/27/18
Ruby-05/P 5 75 75.10 68.82 51.30 35.15 0.00 8.27 8 4.25 2/16/18
Ruby-06/P 2 144 73.65 72.10 52.00 42.80 0.00 15.21 4 2.81 2/12/18
- STOP card of the day: Found a contractor personnel not attending yet PTW training when he will-
propose permit to work. Stop him and inform to HSSE for giving the PTW training.
- Conducted PTW training for two personnel from contractor (PT. Jololu Utara) before their strating-
activity.
- Conducted table top ER drill with topic man over board with all Ruby ER team.
- Syslab reps. completed to collect air emission at GTG B and water for environment sample.
- Luas Birus reps. completed to collect produce water sample for SRB and DO analysis.
- Jololulu Utara reps. Checked and rectify AC cabin crane PQP (under monitoring)
- At 08.30 GTC 2 running after troubleshoot on Dry Seal Vent issue and export gas with flow rate-
115 mmscfd.
- Ran test potable water maker HP pump after alignment. Found pump still high vibration more than-
4 mm/s. Continue next day to re-alignment.
- Completed PM: Choke valve external visual inspection and lubrication at WHP(WO 98040).
- Completed PM: Inspection and functional test of flame detector at PQP Area (WO. 91048). Flame-
detectors at subcellar are functioning properly
- Completed to check OPGD 230GRX077 at PQP main deck. Found F12 fault code
- CM: Check & rectify condenser unit B of HVAC EER 242-UC-02-B1 due to low pressure indication.-
Preparation for brazing tool (disconnect control cable & junction box)
- Completed PM: Earthing bonding visual inspection for unit 216/221/226/229 (WO 90982/97983/84/87).-
Found unit in good condition
ISSUE CONCERN
1. Online GC at Senipah has been offline since 30-Nov-16. Gas composition data taken from Handil Lab
analysis. Repaired by Emerson Engineer was done in 7 November 2017, but still unsuccess. Waiting for
spare part to solve the problem.
2. Ruby Online GC is on manual keypad, due to waiting for spare part (membrane kit).