The Project For The Planning of The Nadi River Flood Control Structures
The Project For The Planning of The Nadi River Flood Control Structures
The Project For The Planning of The Nadi River Flood Control Structures
JULY 2016
VOLUME I SUMMARY
Nadi Bay
Nadi River
Namosi River
Nawaka River
Malakua River
(ビチレブ島)
Nadi River
Nadi Bay
Denarau Area
Central of Nadi Town
River Mouth
Nadi River
Photo-3 Nadi River Basin(Panoramic view) Photo-4 Nadi River (River Mouth)
Photo-7 Nadi River (Upstream) Photo-8 Vaturu Dam (Nadi River Upstream)
Water Level Gauge
Nadi River
Nadi River
Photo-9 Nadi River(Nadi Town Bridge) Photo-10 Nadi River(Nadi Town Bridge)during Flood
Photo-11 Nadi River(Old Queens Road Bridge) Photo-12 Nadi River(Old QueensRoad Bridge)during Flood
Executive Summary of
Flood Control Master Plan and Priority Project
in Nadi River Basin
1. Master Plan
- In the Master Plan, based on the flood and river basin characteristics as well as properties in the
upstream, midstream and downstream of the Nadi River, taking into account measures in an entire
basin, comprehensive flood control plan consisting of dam, river improvement, retarding basins and
ring dikes are proposed.
- Taking into account a long term and the large budget to complete the structural measures, and also
taking into account the risk due to flood exceeding design scale, perfect protection measures for
flood inundation are not feasible. Therefore, structural measures and non-structural measures such
are proposed in the Master Plan..
- In the formulation of the Master Plan, it is an important to clarify priority protected areas from the
view point of clarification on the contents of flood control plan and addressing a road map for the
integration of short, middle and long term flood control plan. Therefore, Important Protected Area is
set and it is prioritized to be mitigated from damage by flood.
- The Master Plan is formulated considering Environmental and Social Considerations and Social
Acceptance for flood control
Target area of Master Plan is Nadi River Basin with catchment area of 516 km2.
Design flood scale for Master Plan is set as 1/50 with regard to previous maximum flood event occurred
in March 2012.
Structural Measures as shown in Figure1 and Table1 are proposed in order to mitigate flood damage by
targeted flood in Nadi River Basin.
Yachiyo Engineering Co., Ltd. July 2016
i
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
(5) :Dam
:River improvement in upstream
(6) :Retarding Basins in Tributaries incl. surrounding dike
:River Improvement in Tributaries incl. Rebuilding of 4(four) bridges
Component of
River, Location Quantities Remarks
the Master Plan
Structural 1. Nadi River Downstream (1) Retarding Basin and River A=725 ha
-
Measures Improvement in downstream V=9,715 千m3
(2) Ring Dike L=1.8 km -
Middlestream (3) River Widening2) L=13 km Including rebuilding of 2
(two) bridges
ii
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
Non-Structural Measures as shown in Table2 are proposed in order to corroborate and complement structural
measures and mitigate damage by targeted flood.
(2) Enhancing disaster preparedness for 2-1) Strengthening disaster management system
effective response
(3) Disaster risk management, risk 3-1) Technical assistant for land-use regulation
avoidance 3-2) Strengthening river basin management
(4) Economic disaster risk management 4-1) Strengthening economic disaster risk management by
regional BCP
Proposed entire implementation schedule of the Master Plan projects is shown in Table3. Target
implementation period of Master Plan is proposed as 30 years from the project commencement.
iii
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
20XX-20XX 20XX-20XX
Work Item
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Study on M/P
Detailed Design
I. Structural Measures
I-A. Priority Project (Short Term Measures)
1 River channel widening works in midstream section
1) River channel widening works in midstream section, L=13km
2 Retarding basin works in upstream section
1) Retarding basin (A) works in right bank side in Nadi River, A=35ha
2) Retarding basin (B) works in left bank side in Nadi River, A=178ha
3 Ring dike
1) Ring dike, L=1.8km
4 Shortcut in tributaries / Surrounding dike works in Nadi River
1) Shortcut in tributaries, A=0.5km
2) Surrounding dike, L=4.5km
5-1) Establishing a system of evaluation of Pre-disaster activity / existing measures and feedback
Note: *including loan agreement, EIA, land acquisition, procurement of consultant (D/D, C/S), detailed design, preparation of PQ and tender document and so on.
iv
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
2.Priority Project
- Taking into account a long term and the large budget to complete the structural measures, and also
taking into account the risk due to flood exceeding design scale, perfect protection measures for
flood inundation are not feasible. Therefore, Priority Project is selected in order to protect important
area and mitigate flood damage.
- Regarding structural measures of Priority Project, components which mitigate flood damage in
Important Protected Area is selected after setting Important Protected Area.
Structural Measures as shown in Figure 3 and Table 4 are proposed in order to mitigate flood damage in
Important Protected Area (Figure 2).
v
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
2. Tributaries Nawaka (6) River Improvement ⑤ Shortsut of Tributaries L=0.5 km Shortcut and Surrounding dike in
Maralua ③-2 Surrounding Dike of Nadi Town L=4.5 km tributaries are preceded to
Namosi Retarding Basins (13 sites) construction as part of the master
― -
River plan
Protection of human lives, understanding of disaster risks and evacuation are considered as a top priority,
under condition that the progress of structural measures project will be at initial phase. Therefore, activities
accompanied with development and disclosure of hazard maps and development of hydrological devices for
awareness of flood risks are proposed as Priority project. In addition, in order to evaluate the effect of
non-structural measures in the past or priority projects, and in order to connect to “Better disaster prevention”,
evaluation and feedback system on the past projects is also proposed as Priority Project.
vi
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
Category Measures
Non-structural Understanding disaster risk Strengthening of understanding flood risk with flood hazard
Measures and risk avoidance map
Strengthening flood forecasting technology, such as
expansion of rainfall gauge, water level gauge and
introduction of real-time monitoring camera
Integrated flood control facilities considering whole river basin have not been installed yet in spite of
effectiveness of structural measures and implementation of structural measures such as dam, retarding basin,
and river are required urgently. Therefore, structural measures of Priority Project are selected as
Implementation Project.
Objective of Implementation Project is to improve of vulnerability to flood in Nadi River Basin, mitigate
flood damage specially in Important Protected Area and contribute to improve living environment of
residents by developing flood control facilities such as river widening and retarding basin in Nadi River
Basin, which has been damaged by severe flood.
Components of Implementation Project is as shown in Figure 4 and Table 6, which are as same as structural
measures of Priority Project.
vii
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
2. Tributaries Nawaka (6) River Improvement ⑤ Shortsut of Tributaries L=0.5 km Shortcut and Surrounding dike in
Maralua ③-2 Surrounding Dike of Nadi Town L=4.5 km tributaries are preceded to
Namosi Retarding Basins (13 sites) construction as part of the master
River − plan
【Implementation Project 】
viii
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
Total cost of the priority project is JPY21.0 billion (F$385million) and the average annual benefit is JPY
1.88billion (F$34.5million). These figures lead to EIRR 12.0%, B/C=1.2 and NPV JPY1.8billion
(F$33million) respectively. This economic valuation is beyond the target investment rate of 10% in Fiji and
show the adequate economic effect.
Implementation Project proposed as one of the Priority Project is evaluate appropriate since it could mitigate
severe flood damage and it is feasible technically, economically, socially and environmentally. Therefore,
next steps such as securing budget and request for technical assistance as follows are recommended to be
conducted by Fiji Government as soon.
(7) Preparation and consolidation of organization responsible for flood control and capacity building
ix
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
Implementation Schedule
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Month
8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7
0
1
Pledge 1
1
Signing of Loan Agreement 1
1 1 1 1 1 1 1 1 1 1 1 1
Selection of Consultant (12 months) 12
1 1 1 1 1 1 1 1 1 1 1 1
Tender Assistance (12 months) 12
1 1 1
Preparation of Bid Document & JICA Concurrence (3 months) 3
1 1
Tender Period (2 months) 2
1 1
Evaluation of Bids (2months) 2
1
JICA Concurrence of Bid Evaluation (1 month) 1
1 1
Contract Negotiation (2 months) 2
1
JICA Approval of Contract (1 month) 1
1
Opening of L/C and Ussurance of L/Com (1 month) 1
0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Consulting Services (84 months) 84
1 1 1 1 1 1 1 1 1 1 1 1
Detailed Design (12 months) 12
1 1 1 1 1 1 1 1 1 1 1 1
Tender Assistance (12 months) 12
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Construction Supervision (50 months) 50
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Project Management Unit Supporting (84 months) 84
0
0 4 12 12 7 0 0 0 0 0
Land Acquisition 35
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 0 0 0 6 12 12 12 8 0 50
Package 1 River Widening 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Defect Liability Period
0 0 0 0 6 12 8 0 0 0 26
Package 2 Retarding Basin 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Defect Liability Period
0 0 0 0 0 6 12 8 0 0 26
Package 3 Ring Dike 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Defect Liability Period
0 0 0 0 0 6 12 12 8 0 38
Package 4 Surrounding Dike 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Defect Liability Period
*Year in above table shows the fiscal year of Fiji (August 1st to July 31th of following year)
x
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
xi
略 語
FINAL REPORT
VOLUME II MAIN REPORT
Chapter 24 Phasing of the Priority Project (Study for Reference) .................................................. 24-1
24.1 Basic Concept of Phasing ....................................................................................................... 24-1
24.2 Phasing ................................................................................................................................... 24-1
24.2.1 Phasing Case ...................................................................................................................... 24-1
24.2.2 Effectiveness of Phasing(Flood Analysis Result) ......................................................... 24-2
24.2.3 Project Cost of Phasing Project ........................................................................................ 24-12
24.2.4 Benefit of Phasing Project ................................................................................................ 24-12
24.2.5 Economic Evaluation after Phasing.................................................................................. 24-13
24.3 Summary .............................................................................................................................. 24-13
List of Table
Table 19-1 Ratio of foreign currency (FC) and local currency (LC) of unit prices .............................................................19-3
Table 19-2 Unit Prices for river work project cost estimation ............................................................................................19-4
Table 19-3 Unit Prices for bridge work project cost estimation (1) ....................................................................................19-5
Table 19-4 Unit Prices for Bridge work project cost estimation (2)....................................................................................19-6
Table 19-5 Cost for Consulting Service ..............................................................................................................................19-7
Table 19-6 Quantity of Each Work Item of River Improvement.........................................................................................19-7
Table 19-7 Quantity of Each Work Item of Bridge work ....................................................................................................19-8
Table 19-8 Quantity of Each Work Item of Site acquisition ...............................................................................................19-9
Table 19-9 Number of houses to be affected and relocated by the project ..........................................................................19-9
Table 19-10 Project Cost...................................................................................................................................................19-10
Table 19-11 Base Cost of Each Package ...........................................................................................................................19-11
Table 19-12 Construction Cost (Package-1: River Widening) ..........................................................................................19-11
Table 19-13 Construction Cost (Package-1: Rebuilding of Bridges) ................................................................................19-12
Table 19-14 Construction Cost (Package-2: Retarding Basin A,B) ..................................................................................19-13
Table 19-15 Construction Cost (Package-3: Ring Dike) ...................................................................................................19-13
Table 19-16 Construction Cost (Package-4: Surrounding Dike) .......................................................................................19-13
Table 19-17 Construction Cost (Package-4: Shortcut of Tributaries) ...............................................................................19-14
Table 19-18 Land Acquisition Cost ..................................................................................................................................19-14
Table 19-19 House Compensation Cost ............................................................................................................................19-14
Table 21 1 Total appraised value and number of houses in Viti Levu Island in Fiji ...........................................................21-3
Table 21 2 Average house price in expected inundation area in Viti Levu Island ..............................................................21-3
Table 21 3 Appraised value of household goods(including passenger car) ...................................................................21-4
Table 21 4 Average appraised value of household goods(including passenger car) ......................................................21-4
Table 21 5 Depreciable property and stocks per each worker in expected inundation area ................................................21-4
Table 21 6 Planting acreage, yield and gate price of major crops in expected inundation area...........................................21-5
Table 21 7 Summary of assets and damage/loss calculation method ..................................................................................21-7
Table 21 8 Damage Rate by Inundation Depth ...................................................................................................................21-9
Table 21 9 Damage ratio in each inundation depth .............................................................................................................21-9
Table 21 10 Damage Rate by Inundation Depth ...............................................................................................................21-10
Table 21 11 Damage Rate by Inundation Depth ...............................................................................................................21-10
Table 21 12 Crops Damage Rate by Inundation Depth .....................................................................................................21-10
Table 21 13 Damage of livestock in the expected inundation area (1/50 probability) ......................................................21-11
Table 21 14 Damage of public utilities and infrastructures(1/50 probability) ................................................................21-11
Table 21 15 Loss for business in the expected inundation area (1 / 50 probability, except tourism) ................................21-12
Table 21 16 Loss for tourism in the expected inundation area (1 / 50 probability) ...........................................................21-13
Table 21 17 Loss for tourism in reduction of tourist arrivals (1 / 50 probability) .............................................................21-13
Table 21 18 Total loss for tourism ....................................................................................................................................21-13
Table 21 19 Loss for public utilities and infrastructures (1 / 50 probability) ....................................................................21-14
Table 21 20 Emergency Cost for household (1 / 50 probability) ......................................................................................21-14
Table 21 21 Emergency Cost for business entity in the expected inundated area (1 / 50 probability) ..............................21-15
List of Figure
Figure 18 73 Construction Access Road (Old Queens Road Bridge) .............................................................................. 18-113
Figure 18 74 General Drawing of New Bridge (Old Queens Road Bridge -Road Bridge-) ............................................ 18-114
Figure 18 75 General Drawing of New Bridge (Old Queens Road Bridge -Tramline Bridge-) ...................................... 18-115
Figure 18 76 Example of Pile Construction (Pile driving by Diesel Hammer) ............................................................... 18-116
Figure 18 77 Example of Girder Installation by Erection Beam ..................................................................................... 18-117
Figure 23 1 Drainage system of rainfall water in the central area of Nadi town .................................................................23-3
Figure 23 2 Nadi Town Drainage Plan (2000) ....................................................................................................................23-4
Figure 24 9 Flood Analysis Result (Case2: River Widening L=13km form 5.75 to 18.75km)(2/2) ...............................24-9
Figure 24 10 Flood Analysis Result (Case3: River Widening L=8.25km form 5.75 to 14.0km)(1/2) ............................24-10
Figure 24 11 Flood Analysis Result (Case3: River Widening L=8.25km form 5.75 to 14.0km)(2/2) ............................24-11
Figure 24 12 Flood Analysis Result by Full Components of the Priority Project .............................................................24-14
Figure 24 13 Flood Analysis Result by Case2: River Widening L=13km form 5.75 to 18.75km .....................................24-15
Figure 24 14 Flood Analysis Result by River Widening L=8.25km form 5.75 to 14.0km................................................24-15
Appendix
2. Tributaries Nawaka (6) River Improvement ⑤ Shortsut of Tributaries L=0.5 km Shortcut and Surrounding dike in
Maralua ③-2 Surrounding Dike of Nadi Town L=4.5 km tributaries are preceded to
Namosi Retarding Basins (13 sites) construction as part of the master
― -
River plan
Component
① River Widening
② Retarding Basin A, B
③ Surrounding Dike
④ Ring Dike
⑤ Shortcut of tributaries
⑥ Rebuilding of Bridge (Nadi town bridge)
Malakua River
⑦ Rebuilding of Bridge (Old Queens Road bridge)
V=7,200 thousand m3
V=7,200千m3
NaditownBridge BackroadBridge B NadiRiver Votualevu
-510
1 When the Master Plan will be completed, since the upstream dam is constructed, the discharge of 1,800m3/s can flow down in the river
channel section with free-board. In the Priority Project the discharge is permitted to flow down with the water level between the top of dike
and HWL considering that this stage is a step to the Master Plan.
2See [Draft Final Report: Main Report, Part I: Master Plan Study, Chapter 4, 4.1.1 ]
(2) Plan
Alignment of river widening is set considering current alignment of river channel and flood flow. Width
of river widening is set basically same width from center line between right bank side and left bank side
from the point of view of fairness.
10.25K
Alignment of river channel is sifted or loosed in order not to exceed design flood water revel when flood
water level exceeds design high water level due to effect by curvature at current alignment and there are
important areas to be protected behind the river. (Exception-1)
Alignment is loosed to the extent that does not deviate from the current river channel alignment extremely
for excessive bending portion such as a U-shaped or S-shaped curve (Exception-2) and alignment is newly
set for extreme crank shape curve in light of the continuity of the upstream and downstream alignment
(Exception-3).
Alignment of river channel is straighten and smoothen from 22.75k to 24.25k in order to intake flood water
smoothly to the retarding basin at overflow dike securing a required length and elevation (Exeption-4).
Alignment is sifted to the other side to the extent that there is no hindrance to a safe flow of flood water
from the viewpoint of reducing the number of house relocations if houses are present only one side of the
river channel (Exception-5)
Based on the above, plan of river widening is as shown in from Figure 18-3 to Figure 18.6.
In Figure 18-4~Figure 18.6 there are two kind of river alignment, blue and yellow lines, the blue line shows
the present river alignment and yellow line shows the alignment after river improvement.
18.75km
Denarau
Nadi river
Narewa village
:Embankment
5.75km
[Upper]: Discharge before Flood Control ※Flow volume after the priority project include natural
[上段]:基本高水
[Lower]: Design Discharge
下段:整備後流量(優先プロジェクト) after the Priority Project flood volume at outside section of Important Protected Area
V=7,200 thousand m3
V=7,200千m3
NaditownBridge BackroadBridge B NadiRiver Votualevu
-510
35.0
Segment2-1、coefficient
Segment3、coefficient roughness for Segment2-2、coefficient roughness for low-water channel n=-0.023 roughness for low-water channel
low-water channel n=-0.015 n=-0.027
Design Embankment Height
HWL
30.0 Nadi town Bridge Namosi River
Design Riverbed (after improvement)
Right
GroundBank
elevation at Right Bank Side
Overflow section of Retarding Basin B
Left Bank
Ground elevation at Left Bank Side Nawaka River Back road Bridge Design Flood Discharge
Average Riverbed Design Flood Discharge=1,400m3/s =1,600m3/s Design Flood Discharge=830m3/s
25.0
Lowest Riverbed
Discharge(Current River)
Reference Point
Gradient of HWL=1/1,600
After smoothing :Water Level Rising amount due to
curvature Considered (Planned River)
Gradient of HWL=1/2,150
10.0
5.0
0.0
Gradient of Design Riverbed=1/4,200 Gradient of Design Riverbed=1/2,600 Gradient of Design Riverbed=1/1,350 Gradient of Design Riverbed=1/1,000
-5.0
km
0.0 5.0 10.0 15.0 20.0 25.0
7.0
Flow Velocity at the time of Design Flood Discharge
6.0 (current channel:mean cross-section)
5.0 Flow Velocity at the time of Design Flood Discharge
4.0 (planned channel:average cross-section)
Velocity(m)
3.0
2.0
1.0
0.0
0.0 5.0 10.0 15.0 20.0 25.0 km
18.250 10.09 0.025 0.000205930 2.26 1.48 1.52 11.13 0.036 0.0001517 2.61 1.85 1.89
18.500 10.04 0.026 0.000441550 3.03 2.14 2.13 11.01 0.031 0.0003711 3.51 2.66 2.65
18.750 10.43 0.025 0.000526450 3.16 1.92 2.11 11.50 0.031 0.0001821 3.51 2.66 2.81
19.000 10.71 0.028 0.000704840 2.74 2.29 2.29 11.72 0.030 0.0004255 3.08 2.69 2.69
19.250 11.21 0.028 0.000678190 2.66 2.23 2.23 12.13 0.031 0.0003281 3.01 2.63 2.63
19.500 11.74 0.028 0.000585680 2.59 2.17 2.17 12.67 0.034 0.0005938 2.95 2.58 2.58
19.750 12.09 0.028 0.000496610 2.70 2.24 2.27 13.06 0.031 0.0006562 3.10 2.68 2.72
20.000 12.52 0.028 0.000468760 2.47 2.09 2.09 13.42 0.031 0.0004566 2.84 2.49 2.49
20.250 12.90 0.028 0.000378190 2.44 2.06 2.06 13.83 0.031 0.0002452 2.81 2.47 2.47
20.500 13.21 0.029 0.000442940 2.39 2.02 2.02 14.11 0.035 0.0003203 2.88 2.53 2.53
20.750 13.50 0.029 0.000438930 2.37 2.01 2.01 14.36 0.030 0.0002652 2.86 2.51 2.51
21.000 13.89 0.028 0.000312890 2.57 2.24 2.24 14.84 0.028 0.0001203 3.10 2.78 2.78 Retarding basin
21.250 13.99 0.030 0.000682360 2.51 2.19 2.19 14.80 0.029 0.0001786 3.02 2.72 2.72 Section
Adaptive management of
21.500 14.57 0.030 0.000455850 2.46 2.14 2.14 15.49 0.031 0.0002128 2.96 2.66 2.66
riverbank protection
21.750 14.89 0.030 0.000484000 2.41 2.11 2.11 15.79 0.028 0.0002408 2.90 2.62 2.62
22.000 15.28 0.028 0.000269290 2.37 2.08 2.08 16.19 0.031 0.0002098 3.00 2.71 2.71
22.250 15.61 0.027 0.000105960 2.34 2.05 2.05 16.68 0.026 0.0000832 2.95 2.66 2.66
22.500 15.42 0.031 0.000767510 2.31 2.03 2.03 16.18 0.034 0.0003624 2.90 2.62 2.62
22.750 16.11 0.031 0.000323530 2.63 2.31 2.31 17.27 0.031 0.0002048 2.86 2.59 2.59
23.000 16.24 0.030 0.000425690 2.57 2.26 2.26 17.32 0.030 0.0002858 2.82 2.55 2.55
23.250 16.61 0.033 0.000368010 2.52 2.22 2.22 17.67 0.032 0.0002463 2.79 2.53 2.53
23.500 16.84 0.043 0.000743410 2.47 2.18 2.18 17.83 0.039 0.0004763 2.76 2.50 2.50
23.750 17.21 0.035 0.000339860 2.44 2.15 2.15 18.06 0.034 0.0003705 3.43 3.11 3.11
24.000 17.15 0.031 0.000754130 2.39 2.10 2.10 17.67 0.030 0.0009251 3.31 3.00 3.00
24.250 17.93 0.031 0.000259490 2.13 1.81 1.82 19.16 0.031 0.0002862 2.81 2.53 2.46
24.500 18.05 0.035 0.000567050 2.75 2.50 2.46 19.17 0.033 0.0006263 3.71 3.46 3.41
24.750 18.46 0.028 0.000160740 1.98 1.68 1.56 19.79 0.028 0.0001944 2.65 2.33 2.22
25.000 18.48 0.028 0.000254140 2.58 2.07 2.15 19.72 0.028 0.0003298 3.52 2.94 3.07
25.250 18.789 0.029 0.000141620 1.90 1.25 1.20 20.22 0.029 0.0001745 2.55 2.24 2.21
25.500 18.953 0.035 0.000190190 1.56 1.44 1.30 20.39 0.037 0.0004362 2.73 2.55 2.34
25.750 19.08 0.038 0.000159340 1.41 1.29 1.26 20.73 0.039 0.0003746 2.50 2.32 2.24
26.000 19.176 0.034 0.000154170 1.37 1.10 1.23 21.02 0.036 0.0002938 2.21 1.88 1.99 Current River
26.250 19.254 0.037 0.000199370 1.55 1.42 1.37 21.16 0.038 0.0004327 2.63 2.39 2.40 Channel
26.500 19.392 0.036 0.000100130 1.15 0.96 1.02 21.53 0.037 0.0001997 1.88 1.63 1.71 section
26.750 19.429 0.039 0.000233720 1.53 1.40 1.38 21.59 0.041 0.0004495 2.48 2.32 2.26
27.000 19.529 0.035 0.000188490 1.61 1.42 1.38 21.79 0.036 0.0003845 2.66 2.40 2.33
27.060 19.565 0.039 0.000209760 1.55 1.43 1.36 21.87 0.039 0.0004413 2.60 2.43 2.32
27.250 19.685 0.049 0.000242170 1.22 1.12 1.21 22.20 0.050 0.0004446 1.86 1.81 1.82
27.500 19.776 0.040 0.000107270 0.99 0.83 0.93 22.40 0.041 0.0001772 1.49 1.28 1.46
27.750 19.82 0.040 0.000311820 1.48 1.37 1.33 22.51 0.043 0.0004541 1.91 1.86 1.70
28.000 19.987 0.036 0.000104720 1.06 0.87 0.95 22.76 0.038 0.0001604 1.57 1.37 1.41
28.250 19.997 0.040 0.000341880 1.76 1.62 1.61 22.73 0.040 0.0006072 2.64 2.53 2.41
28.500 20.154 0.029 0.000165340 1.64 1.06 1.34 23.10 0.031 0.0002372 2.21 1.72 1.66
28.750 20.298 0.030 0.000085830 1.20 0.95 0.87 23.35 0.031 0.0001313 1.71 1.26 1.36
1)At hatching section in above table, the flow rate exceeds 2.0 m/s
2) Riverbank protection is considered adaptively, if necessary in the future, river bank protection shall be installed
V=7,200 thousand m3
V=7,200千m3
NaditownBridge BackroadBridge B NadiRiver Votualevu
-510
Although these basins are filled with flood water when large scale flood (more than 1/10 design return
period) occurs, flood water is drained to the river after flood and after clearing, basins become like normal
condition and it also becomes possible to cultivate. In addition, the river dike (surrounding dike of retarding
basins) is constructed together with the retarding basins so that the inundation damages by small scale flood
are reduced.
18.2.1 Retarding Basin A
(1) Layout and Facilities Design
Layout and Facilities Design is conducted considering ensuring of flood control discharge at the Priority
Project and smooth intake of peak cut discharge 80m3/s to the basin. In order to secure flood control
discharge, location of overflow dike is set at 20.5km of Nadi River.
Specifications of the basin are set in order to secure peak cut discharge through hydrological analysis. Peak
cut discharge, flood control discharge and outflow rate is set as mentioned in Table 18-6. Specifications of
drainage sluice gate (the number of gates, outflow rate) are set as a scale that flood water in the basin can
be drained within 24 hours2.
2
The reason is that the second peak of rainfall occurred 24 hours later and the durable inundated hours of sugar cane is
approximately 72 hours.
In addition, ground elevation in the basin is high in some part (high terrace). Therefore, high-level terrace
in the basin is excavated 1.5m to the bottom such as stripping topsoil and leveling in order to secure flood
control discharge in the basin4Layout of Retarding Basin A is as shown in Figure 18-11.
Outlet
Retarding
Basin A
Votualevu
Outlet
25.0 p
Lowest Riverbed Elevation Calculation Water Level for Design Flood Discharge(Planned River)
Retarding Basin B
20.0
i Retarding Basin A Over Flow Dike B
19.75~24.10k
EL. 17.25m
Elevation(m)
Drainage Sluise A
15.0 19.13k
a EL.9.59m
Nadi River
l
10.0
Over Flow Dike A
20.455~20.50k
EL.13.53m
Drainage Sluise B
5.0 19.13k
EL.8.2m
0.0
C
Gradient of HWL=1/700 Gradient of HWL=1/1000
Gradient of HWL=1/1,600
s o
n
The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji
YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV
Figure 18-14 Typical Cross Section of Overflow Dike for Retarding Basin A
In addition, ground elevation in the basin is high in some part (high terrace). Therefore, high-level terrace
in the basin is excavated 1.0m to the bottom such as stripping topsoil and leveling in order to secure flood
control discharge in the basin.
Layout of Retarding Basin B is as shown in Figure 18-16.
Outlet
Retarding
Basin A
Votualevu
Outlet
p
Lowest Riverbed Elevation Calculation Water Level for Design Flood Discharge(Planned River)
25.0 Retarding Basin B
Elevation(m)
Drainage Sluise A
15.0 19.13k
a
EL.9.59m
l
10.0
Over Flow Dike A
20.455~20.50k
EL.13.53m
Drainage Sluise B
5.0 19.13k
EL.8.2m
0.0
C
Gradient of HWL=1/700 Gradient of HWL=1/1000
Gradient of HWL=1/1,600
o
SLUICEWAYS of Drainage
s
y
s
p
i ▼HWL 18.05m
S
c
e
a
c
l
Nadi River t
i Overflow- Dike
C
Over Flow Dike
o y
r
n p ▼Design Bank Height 19.05m
▼HWL 18.05m
o
i
s
c
s
a
l
S
Typical cross section
e
y C
c
p r
t
i o
i
▼EL. 19.05m ▼HWL 18.05m
c s
o
a s
n
l
S
C e
r c
Figure 18-17 General Plan of Retarding Basin B
o t
Figure 18-18 Typical Cross Section of Overflow Dike for Retarding Basin B
Surrounding Dike
Nadi Town
Hindu Temple
Surrounding
Dike
Nawaka Village
Nawaka River
Surrounding Dike
断側線位置図
Location of Cross Section
Slope
Cross
Section Ring Dike
Outlet of drainage