SITE HANDING OVER NOTE
Project : Construction of Multilevel 2- wheeler and Car parking cum
Commercial Complex - Thampanoor Contractor : Heather Construction Date of Agreement : 18-May-2020 LOA No. : SCTL-PRJ/208/2019/M(UP)/1355 dtd 15-Feb-2020. Contract value of Project : 16,87,21,144.54/- Expected contract value : 16 Cr Physical Progress (%) : 75% Financial Progress (%) : 53% Recommended Billed Amount: 8,88,29,956/- Number of Bills Submitted : 15 Registers maintained at the site 1. Slump Register – 01Nos 2. Work Diary – 03 Nos 3. Steel Register - 01Nos 4. Site Order Book – 02 Nos 5. Cube Register – 03Nos 6. Cement Register – 02Nos 7. RMC Register – 01Nos 8. Hindrance Register – 01Nos 9. Solid Block Register – 01 Nos 10. Drawing Register – 01 Nos 11. Drawing issue Register – 01 Nos 12. Obsolete Drawing Register – 01 nos 13. Daily Measurement Book from MB No.1 to MB no 13 14. Test Report File.
Present Status of Project:
1. RCC Works – 97% completed Pending works a. Rainwater harvesting tank- wall and cover slab pending b. External drain – in progress c. DG foundation work -– yet to start 2. Finishing works –45% Completed Pending works a. Plastering - 95% completed b. Painting work – 40% completed c. VD flooring – 65% completed d. Floor epoxy painting - yet to start e. Floor tile and wall cladding – 70% completed f. External architectural finishes – 60% completed Page 1 of 2 g. Joinery works – on progress h. Staircase SS Handrail – on progress i. Cast Iron and MS Grill works – on progress j. Water proofing works – i. Roof water proofing – on progress ii. Rain water tank - yet to start k. External pavement works – yet to start
3. Firefighting work - 30% completed
4. Plumbing work – work started, sewerage connection pending 5. Electrical work i. LT work – 60% completed ii. HT work - yet to start 6. Elevator Works – on progress Pending Approvals A. Civil 1. Urinal Division plate - MAR/Sample submission pending - Heather 2. Differently abled & toilet accessories - MAR/Sample submission pending - Heather 3. UPVC door and accessories - MAR/Sample submission pending - Heather 4. Fire door and accessories - MAR/Sample submission pending - Heather 5. Corner guard - MAR/Sample submission pending - Heather 6. Polycarbonate convex mirror - MAR/Sample submission pending - Heather 7. Rubber polymer speed breakers - MAR/Sample submission pending - Heather 8. Rubber wheel stopper - MAR/Sample submission pending - Heather B. Electrical 1. Bi directional Lights - MAR/Sample submission pending - Heather 2. Spike Lights - MAR/Sample submission pending - Heather 3. Transformer - Supply pending - Heather 4. DG - Supply pending - Heather 5. Centrifugal pump 7.5 HP - MAR submission pending - Heather 6. Electrical post shifting at exit ramp - request from Heather received - SCTL