GM606 60620 390 MT CL 0001 - 0
GM606 60620 390 MT CL 0001 - 0
GM606 60620 390 MT CL 0001 - 0
aggreko
dGAZPRDM SARQALA 1 CPF TO AGGREKO POWER
GENERATION PLANT
N E F T
'PetroWeld
DOCUMENT DETAILS
CONTRACTOR : Aggreko
Doc No : GM606-60620-390-MT-CL-0001
Table of Contents
1. INTRODUCTION ............................................................................................................................... 3
2. REFERENCES .................................................................................................................................... 3
3. SCOPE OF WORK ............................................................................................................................. 3
4. STRUCTURE DESCRIPTION............................................................................................................... 4
5. DESIGN PROTECTION CRITERIA ....................................................................................................... 4
6. SOIL RESISTIVITY TEST RESULTS ...................................................................................................... 4
7. GUIDELINES FOR DESIGN OF CP SYSTEM ........................................................................................ 5
8. CALCULATIONS FOR BURIED PIPELINES .......................................................................................... 6
8.1 DESIGN PARAMETERS .................................................................................................................. 6
8.2 ANODE SELECTION ....................................................................................................................... 6
8.3 CURRENT REQUIREMENT ............................................................................................................. 6
8.4 RESISTANCE OF SINGLE VERTICAL ANODE TO SOIL: .................................................................... 7
8.5 SINGLE ANODE CURRENT OUTPUT: ............................................................................................. 8
8.6 NUMBER OF ANODES BASED ON CURRENT OUTPUT .................................................................. 8
8.7 NUMBER OF ANODES REQUIRED BASED ON WEIGHT ................................................................. 9
9. CP SYSTEM DESCRIPTION ................................................................................................................ 9
9.1 TEST STATIONS AND MONITORING FACILITIES .......................................................................... 10
9.2 TEST STATION-POTENTIAL MONITORING .................................................................................. 10
9.3 TEST STATION ISOLATION JOINT .............................................................................................. 10
9.4 TEST STATION-POLARIZATION COUPON TEST POINT ................................................................ 11
9.5 TEST STATION-UNCASED ROAD & WATER CANAL CROSSING ................................................... 11
9.6 CABLE CONNECTION TO PIPELINES ............................................................................................ 11
10. BILL OF MATERIALS .................................................................................................................... 12
Page 2 of 12
CATHODIC PROTECTION SYSTEM
DESIGN AND CALCULATIONS
Doc No : GM606-60620-390-MT-CL-0001
1. INTRODUCTION
Corrosion Technology Services LLC (CTS) has been appointed by Petroweld Services Ltd. (Vide
PO No. PO-CTS-E&I EPR NO:004-2020) as vendor to design, supply materials, supervise the
installation, test and commission the Sacrificial Anode Cathodic Protection Systems for external
surface of buried Gas Pipelines associated with Aggreko Gas pipelines, Iraq.
This document outlines the detailed design and calculations of the proposed Sacrificial Anode
CP System for the external surface of buried pipelines associated with the above
project.
2. REFERENCES
G32300291-Rev-B - Specification for Gas supply pipelines for Kurdistan
Project
G32300166-Rev-A - Specification for piping corrosion protection
AGG-8GL-S1-PP-AS-01_16 -
Report No.111 - Report on Soil resistivity tests for Sarqala pipeline
Project
NACE SP0169 - Control of external corrosion on Underground or
submerged metallic piping systems
ISO15589-1:2015 - Petroleum, petrochemical and natural gas industries-
Cathodic protection of pipeline systems part1: on land
pipelines.
NACE SP0177 - Standard Practice for Mitigation of Alternating Current
and Lighting Effects on Metallic Structure and Corrosion
Control Systems.
NACE SP0286 - Electrical Isolation of Cathodically Protected Pipelines
3. SCOPE OF WORK
The scopes of works identified to be performed by CTS under this contract are as follows:
Page 3 of 12
CATHODIC PROTECTION SYSTEM
DESIGN AND CALCULATIONS
Doc No : GM606-60620-390-MT-CL-0001
4. STRUCTURE DESCRIPTION
Table 1 (Structure Details)
Pipe
Operating
SL No. Line ID Service Diameter Length (m) Coating
Temp. (°C)
(Inch)
1. GAS 16 4850 80 3LPP
Pipe
A minimum polarized potential of -850mV (Coupon OFF) with the cathodic protection current
applied to the structure with respect to a Cu/CuSO4 reference electrode (or -800mV with
respect to an Ag/AgCl reference electrode shall be considered as an alternate) is the protection
criteria for a sacrificial anode cathodic protection system using sacrificial anodes.
Or 100mV polarization shift criteria may also applicable in case above criteria is not able to
achieved.
the event of changes to the ground resistivity (i.e./. Due to various climatic conditions).
Table 3 below (ASTM Special Publication 741) can be used as guideline to evaluate the
corrosiveness of an environment with respect to the soil-resistivity values:
Page 4 of 12
CATHODIC PROTECTION SYSTEM
DESIGN AND CALCULATIONS
Doc No : GM606-60620-390-MT-CL-0001
10 to 25 High Corrosivity
25 to 50 Moderate Corrosivity
Based on past experience for similar terrain, we propose to use a soil resistivity of 10,000 Ohm-
cm for design calculation. If the installed number of anodes does not meet the protection
criteria then an additional anode shall be supplied and installed by the EPC contractor until the
protection criteria is met.
The cathodic protection for the project pipelines shall be achieved by utilizing pre-
packaged magnesium anodes
Magnesium anodes shall be installed horizontally at 1.5 to 2m depth approximately
at 2m away from the pipeline
The anode cable tail shall be terminated in a test facility located adjacent to pipeline
and provided with shunts and variable resistors
At all test facilities, two cables shall be connected to pipeline. The size and type of
cables shall be as per construction drawing
All pipeline-to-cable connection shall be done by Thermite weld technique
All pipeline-to-cable connections shall be encapsulated using Intergard 821 compound
or equivalent
All CP cables shall be XLPE/PVC cables
In order to achieve adequate cathodic protection on the existing buried pipeline,
effective electrical isolation is mandatory which shall prevent leakage of cathodic
protection current to other buried metallic structures and earthing. The pipeline shall
be isolated from the concrete foundation reinforcement steel, foreign pipe Tap-
Off/Tie-in, valves, vents, chambers, stacks, scraper traps, casings, earthing and all
other locations as deemed necessary by suitable means
Protective Current density of 0.01mA/m2 as per ISO 15589-1:2015(table-3) shall be
applied for the subject pipeline
Page 5 of 12
CATHODIC PROTECTION SYSTEM
DESIGN AND CALCULATIONS
Doc No : GM606-60620-390-MT-CL-0001
Where:
SA - Surface Area (m2)
d - Diameter (m)
L - Pipeline length (m)
Current Requirement = SA x Current Density
Page 6 of 12
CATHODIC PROTECTION SYSTEM
DESIGN AND CALCULATIONS
Doc No : GM606-60620-390-MT-CL-0001
Where:
SA - Surface Area (m2)
Current Density = 0.01mA/m2
The temperature corrected current density is given by:
Where:
CDT = Temperature Corrected Current Density (mA/m2)
CD = Current Density (0.01 mA/m2)
T = Operating Temperature (80°C)
Therefore, the temperature corrected current density is 0.0351 mA/m2.
The current requirement for the piping is given by:
Where:
I = Current Demand (A)
SA = Surface Area (m2)
CDT = Temperature Corrected Current Density (mA/m2)
Temp
Pipe Pipeline Pipeline Surface Corrected Current
S.No.
Start and End points Length Diameter Area Current Required
(m) (m) (m2) Density (Amp)
(mA/m2)
1 4850 0.406 6186.1 0.0351 0.188
Page 7 of 12
CATHODIC PROTECTION SYSTEM
DESIGN AND CALCULATIONS
Doc No : GM606-60620-390-MT-CL-0001
Where:
Where:
AOCP = Anode Open Circuit Potential (-1.70 V)
SPP = Structure Protected Potential (-0.85 V)
Therefore, the calculated current output of a single 7.7 Kg magnesium anode to achieve a
structure protected potential of -850mV is 0.010A (10mA).
Page 8 of 12
CATHODIC PROTECTION SYSTEM
DESIGN AND CALCULATIONS
Doc No : GM606-60620-390-MT-CL-0001
Where:
Design Life = 10 Years
Consumption Rate = 7.96 kg/Ay
I = Current Demand (A)
Utilization Factor = 0.8
The results of Equation are given below in Table 6.
9. CP SYSTEM DESCRIPTION
A sacrificial anode cathodic protection system using sacrificial magnesium alloy is designed to
provide corrosion control to the external surface of the buried pipelines. The pre-packaged
magnesium anodes are designed to provide protection for a period of 10 years. For effective
functioning of CP System, the pipelines under the scope must be electrically isolated at the start
and end locations, any branches and from other metallic structures including earthing and rebar
in concrete.
The pipe-to-cable connections for the project pipes are to be carried out using thermite weld
for new pipelines. The test coupons, and cable connections on to the buried pipeline for the
test stations such as potential monitoring test stations, road crossing test stations, and
insulating joint test stations which are part of the cathodic protection system are recommended
Page 9 of 12
CATHODIC PROTECTION SYSTEM
DESIGN AND CALCULATIONS
Doc No : GM606-60620-390-MT-CL-0001
to be installed during the pipe construction phase, before backfilling the pipe in order to avoid
re-excavation.
The following section describes the purpose of the test facilities for the permanent cathodic
protection that are to be installed (cable to pipe connection in particular) as part of the SACP
system materials are installed.
The project pipelines traverses through various crossings such as roads, and water canal
crossing at different locations between the S1 to power plant.
Page 10 of 12
CATHODIC PROTECTION SYSTEM
DESIGN AND CALCULATIONS
Doc No : GM606-60620-390-MT-CL-0001
Page 11 of 12
CATHODIC PROTECTION SYSTEM
DESIGN AND CALCULATIONS
Doc No : GM606-60620-390-MT-CL-0001
1 SACP Materials
SI.
Description Unit Quantity
No
Polarization Coupon Point Test Station with reed switch c/w
1 No. 2
uPVC conduit 2m long, 5 terminal board and lockable cap
Test Station for Magnesium Anode c/w Cott shunt & variable
2 No. 6
resistor, uPVC conduit 2m long, 5 terminal board, lockable cap
Isolation Flange Test Post c/w uPVC conduit 2m long, 5
3 No 2
terminal board, lockable cap
7.7kg Magnesium Anode c/w 10m of 10mm2 XLPE/PVC Red
4 No. 18
Cable
Polarization Coupon c/w 2 x 10mm2 XLPE/PVC Black/ Yellow
5 No. 2
Cable
Cu/CuSO4 Reference electrode c/w 10sqmm XLPE/PVC cable
D 6 No. 8
(Yellow/Blue)
7 Thermite Weld Charges (15g) with Mould (1 No.) No. 16
8 Intergard 821 L 5
2
9 10mm XLPE/PVC Black Monitoring black Cable m 180
10 16mm2 XLPE/PVC Black Monitoring black Cable m 40
11 Surge Diverter (SG4) No. 2
Items Supplied by Others
Welded Cleats for Isolation Flanges locations by (EPC
12 No. 8
Contractor)
13 Cable Lugs and Tagging by (EPC Contractor) lot 1
14 Concrete foundations (EPC Contractor) lot 1
Page 12 of 12