The Heavylift Engineer: ... Managing & Delivering Heavy Lift Projects
The Heavylift Engineer: ... Managing & Delivering Heavy Lift Projects
The Heavylift Engineer: ... Managing & Delivering Heavy Lift Projects
2
ISSUE 03
CONTENTS
EDITORIAL page 5
3
fig. 01 / Port crane
THE HEAVYLIFT ENGINEER
4
ISSUE 03
EDITORIAL
JOHN MACSWEEN, MANAGING DIRECTOR AT MALIN GROUP
Welcome to our latest edition of the Whether you are in shipbuilding, heavy
Heavylift Engineer, edition three. You fabrication, power generation or mining,
can find issues one and two online to the heavy lift engineer’s skill set is critical.
download (www.heavyliftengineer.com/ No other engineering discipline, if you
magazine). decide to dive deep enough, offers such
a range of technical challenges. We hope
It has been great to hear all of your that this edition reflects that variety,
responses and feedback to date and I look offering something of interest to you,
forward to your views on our latest edition. regardless of your background.
It has been a difficult 8 months, with Please do get in touch if you have a
companies forced to rethink their working topic you would like to see covered or
practices and colleagues adjusting to would like to guest feature for a future
either working from home, keeping release – and I hope you enjoy this new
occupied on furlough - or continuing work edition!
as an essential worker. Whilst difficult
and at times isolating, the Covid crisis We would love to hear from you! Please
has also offered a learning opportunity, send any questions to: heavyliftengineer@
from harnessing new technologies, to malingroup.com.
reviewing work life balance. We look at
this in more detail in our special, lockdown Please also sign up for exciting future
lessons article. This is teamed with a piece editions at: www.heavyliftengineer.com
enumerating the top 5 tips on the build
of fabrication jigs, including the need
to identify build methodology from the
beginning and things to consider when
planning the factory acceptance test (FAT).
There is also an article on one of the most
common, and crucial, elements of any
heavylift shipping project, the humble
stowage plan. Easy to do, and even easier
to do badly!
5
THE HEAVYLIFT ENGINEER
A lot of considerations must be taken into • provide specific advice on cargoes which
account when creating a stowage plan. are known to create difficulties and
• Does the cargo fit in the allocated hazards regarding their stowage and
space? securing
• What will be used to secure the cargo? • advising on actions that may be taken
• How will personnel stow and secure the when in heavy sea conditions
cargo? • advising on actions that may be taken to
• Is the deck strong enough to take the remedy the effects of cargo shifting
cargo?
• Does the cargo need segregated? The CSS Code provides the advice; however,
the overall responsibility of the vessel, crew
The safe stowage and securing of cargo and cargo always lies with the Master.
is dependent on the proper planning,
execution and supervision of the process. The Cargo Securing Manual is broken into
The cargo should be stowed and secured in five chapters:
such a way which does not put the ship or • Chapter 1 – General (Definitions and
personnel in any risk. Improper stowage and General Information)
securing can put the vessel, crew and other • Chapter 2 – Securing Devices and
cargo into a potentially hazardous situation. Arrangements
• Chapter 3 – Stowage and Securing
The International Maritime Organization of Non-Standardized and Semi-
(IMO) has developed guidelines which must Standardized Cargo
be followed when carrying cargo. This is the • Chapter 4 – Stowage and Securing of
Code of Safe Practice for Cargo Stowage and Containers and other Standardized Cargo
Securing (CSS Code). It is also a mandatory • Chapter 5 – Cargo Safe Access Plan
requirement for vessels to carry a Cargo
Securing Manual (CSM) specific to their cargo Using the guidelines laid out by the IMO, in
carrying capability. combination with the predominant industry
standards, we can look to answer the
The CSS Code provides an international aforementioned queries.
standard to promote the safe stowage and
securing of cargoes. It manages this by: Does the cargo fit in the allocated
• ensuring that ship owners and operators space?
utilise the ship for its intended purpose Vessel owners and charterers can supply
• providing advice to ensure vessels are vessel particulars, which will allow you
equipped with proper cargo securing to find the right vessel for the specific
means cargo. Many vessels have multiple holds
• providing advice on cargo stowage and for carrying cargo, which are normally
securing to minimize risks to the ship numbered starting at the bow and moving
and personnel aft.
6
ISSUE 03
7
THE HEAVYLIFT ENGINEER
The rubber (or similar) protection should be Stowage and Securing Method
used to help protect the lashings. Web lashings The majority of cargoes will be lifted using
are also not recommended for use on exposed either a shore side crane or the vessel’s crane,
decks of a vessel, or on a barge where the from the quayside, either into the hold or onto
lashings cannot be checked. The webbing the deck of the vessel, straight into their final
material can deteriorate when exposed to salt position. However, some smaller cargoes may
water and UV rays from the sun. It is important then need manoeuvred once on the vessel.
to know the Minimum Breaking Load (MBL) of This may be done with the use of a forklift,
the lashing you are working with, and that they and in this instance, it would be important
are certified. to consider the forklifts manoeuvrability and
dimensions when creating a stowage plan.
Chain Lashings are heavy and can be quite
cumbersome when moving around the deck/ When uplift is calculated in the seagoing forces,
hold of a vessel. Care must be taken when additional vertical restraint is required on the
moving the chains around a piece of cargo to cargo. This may involve working at height,
prevent any damage from occurring, especially when using web or chain lashings for the
to painted surfaces. It is important, as with the vertical restraint, which in turn may require
web lashing, to know the MBL of the chain you the use of a cherry picker (or similar). Again, if
are working with, and that the chains have this is the case then the manoeuvrability and
been tested and certified. dimensions of the machinery on the vessel
should be considered when creating a stowage
Welded blockers/cleats are specified plan. In some cases, it may be necessary to
dependant on the findings from the seagoing install the vertical restraint on the cargo prior
forces. Blockers tend to be used when the only to lifting onboard the vessel. Another instance
considerations are transverse and longitudinal where a cherry picker may be required is when
forces; and cleats should be specified disconnecting the lifting equipment from the
whenever additional restraint is required cargo.
from uplift. When using blockers or cleats it
is important to know the vessel’s underdeck Deck Strength
framing in relation to the piece of cargo, Within the vessel particulars that you should
therefore an accurate drawing of the vessel receive from the owner or charterer, there
would be extremely useful. When welding the should be information on the deck strength
blockers or cleats to the deck it is important to of the vessel. This is normally presented in
do this in line with the underdeck framing, as the units’ tonne per metre squared (T/m2). If
this will be the strongest part of the deck (see loading cargo with a high point loading, deck
Figure 2). strength checks should be carried out to tie into
primary structure within the vessel. There are a
Welded bridge plates are used when few standards that we would recommend that
connecting a piece of cargo to a transportation you generally adhere to, these being, BS5950
frame, a good example of this would be when (British Standard – Structural use of steelwork
transporting offshore reels (see Figure 2). in building), AISC 360-10 (American institute of
Steel Construction – Specification for Structural
An important aspect to consider when choosing Steel Buildings), Lloyd’s Register (Rules and
welded seafastenings are the location of fuel regulations for the classification of ships) and
tanks or other flammable liquids or gases that Eurocode 3 (Design of steel structures).
may be stowed onboard the vessel. Since
heat produced during the welding process When loading cargoes with a high point
could pose a fire or explosion risk if exposed loading, it is important to land them to suitable
to flammable materials, the vessel’s owner or load spreading mats/dunnage, in order to
operator should always be consulted to ensure prevent any damage to the vessel’s deck.
it is safe to weld in the desired location. It is also important to consider the friction
coefficient of the load spreading devices, as
Twistlocks are used to secure containerised this will affect the results of seagoing forces
cargo. The twistlocks attach to the vessel’s deck being calculated.
in pre-set positions, where the four corners of
a container would land, and the container is
placed on top of them. Once the container is in
position, a lever is used on the twistlock to lock
the container in place.
8
ISSUE 03
9
THE HEAVYLIFT ENGINEER
FIG. 04
10
ISSUE 03
11
THE HEAVYLIFT ENGINEER
BUILDING
FABRICATION
JIGS - 5 TOP TIPS
12
ISSUE 03
Width Restrictions
< 2.9m Within Gauge
>2.9m <3.5m Notify police & local councils 2
clear days notice
>3.5m <5.0m 2nd Man required, notify police &
local councils 2 clear days’ notice
>4.3m <6.1m private escort required. See note
below.
>5.0m <6.1m VR1 required (www.highways.
gov.uk/esdal), notify police 2
clear days notice
>6.1m Special Order required ≤
27.4m O/all Length≤ 150 Te GVW
Length Restrictions
Max length 27.4m without special order.
2nd Man over 18.3m
If drawbar trailer above exclusive of tractor
Height Restrictions
16’ 1” (4.9m) clears motorway bridges at 16’ 6”
13
THE HEAVYLIFT ENGINEER
Hauliers will in most case use this option. you may have to redo the paint job , if areas are to be
reworked.
2. Identify build method from the outset If the black build is not possible for whatever reason,
a last precautionary measure is to hold a Factory
Fail to prepare, prepare to fail. Before commencing with Acceptance Test or “FAT” – this acts as the review stage
the fabrication phase, consideration must be given to before the structure is dis-assembled and dispatched to
the planning and build methodology. For more complex site. Although this is usually done after the structure is
details that require a large amount of local welding, you painted, it is a good opportunity to inspect and assess the
may wish to sub-assemble the units in their pre-weld structure before it is finally dispatched.
state (i.e after tack welding together). This ensures that
all the mating faces are accurately aligned prior to full Therefore, ensuring all is as it should be before arriving
welding. During welding the intense heat can often on site, usually the process would be as follows:
distort the steelwork and misalign the mating faces
resulting in additional efforts being required, not to
mention additional time and costs. It is better to catch
this distortion at this stage rather than fully weld and try
fit misaligned joints after welding, as by that point it’s far
too late.
4. Green
5. Black Builds & Factory Acceptance Testing (FAT) Written by Ross Marshall, Project Manager, Malin Group
14
ISSUE 03
BOOK RECOMMENDATIONS...
SKUNKWORKS BY BEN R. RICH & LEO JANOS
This book tells the true story behind Layered through all of this are leadership
Lockheed’s legendary Skunk Works from lessons and great stories behind the
the perspective of the second man to take development of iconic and ground breaking
the reins and who carried the flame of Kelly planes such as the U2 spy-plane, SR-71
Johnson through two further decades of Blackbird and the F-117 Stealth Bomber.
incredible success. There is not much marine
or even heavy lift in here, but the story of
how to deliver research and development
that results in actual products delivered
against aggressive technological and
competitive barriers has lessons that ring
true and we can learn a lot from today.
15
THE HEAVYLIFT ENGINEER
16
ISSUE 03
CRANES ON BARGES
The incident at Alphen aan den Rijn revealed Crane lifts on land require serious planning
a number of safety issues that occur when for a range of matters, including lift radius,
a crane is used on a barge. The collapse of ground conditions and load dimensions.
the two mobile construction cranes which However, when the lift calls for the crane
were standing on barges highlighted several to be on a floating platform, the risks and
serious shortcomings that should have been issues become even more complex. As well
addressed during the preparations for the as needing to determine the reduced lifting
lift, as well as recommendations to improve capacity of the crane due to the factors listed
risk management following the investigation. above, the stability of the whole system also
Although using cranes on barges is common needs to be considered. The vertical centre
practice, there are critical matters that need to of gravity is a significant factor in the stability
be considered before the lift commences. of the barge and knowing where this is at all
stages of a dynamic lift is paramount. In the
Mobile cranes are designed to be used on case of cranes on floating vessels, factors such
level ground. A mobile crane driver will be as the fact that on lifting a cargo clear the
meticulous about getting the crane level effect of the cog moves immediately to the
when setting the outriggers. This is because boom tip. Always ensure you have specialist
the slew ring bearings on land-based cranes assistance and that proper thought is given
are limited, typically, in out-of-level capacity to the various elements that come into play
by two degrees. Once you exceed this figure when a crane is subject to the dynamics of a
at maximum load, slew ring failure is a strong barge.
possibility. In addition, the fleet angle of crane
rope acting on the sheaves at the tip of the jib
is also limited. The sheaves are designed for
a vertical load, with only a slight out-of-plane
allowance. Written by Lindsay McDougall, Technical
Director, Malin Group
Although a typical flat top barge will have a
level surface, the equilibrium of the barge
will be affected by several factors such as the
load, ballasting and wind/wave conditions.
As soon as you introduce an off centre load
onto a barge - say by lifting a load using a
crane - the barge will want to tilt. This can be
countered by ballasting, but it is important to
note that this is rarely as quick as the crane
can take load. Any movement in the barge
will result in the crane limits discussed above
becoming close to being exceeded. In addition
to the above, any angle in the barge deck
can also result in a change in the lift radius
increasing load on the crane components
further.
17
THE HEAVYLIFT ENGINEER
LOCKDOWN LESSONS
These unusual times have had a lot written at the start - from initial interpretation on
about them on key issues such as struggles what is acceptable while on furlough to
with mental health, business cutbacks, failing to immediately update claims when
regulations and government assistance folk come off furlough in a rush to service
and what it means to try and work when work that comes in.
at home with the entire family. I thought I
would share our experiences and mistakes For example, we had put some senior
in case it provides any assistance to others. staff on furlough and told them to do no
work but maintain a watching brief on
The last point is perhaps the most their critical projects and flag up to those
common. I had a quote passed to me by still working if anything needs done… this
a colleague that noted this is not a period is not permitted. In another example, we
of working from home, but one of trying had a director on furlough under similar
to do work while forced to stay at home. conditions and then failed to take him off
This is not semantics but an important when he had to go on site for a rush job,
difference. I have had a half clothed six compounding the error. Similarly, we had a
year old come into Teams meetings and draughtsman re skill and do some training
ask that I tell everyone on the call how old to be able to work in Inventor… which
he is. I have had our last chicken (fox got is permitted… but one of the models he
the rest a few weeks ago) photo bomb created of a hatch found its way into a bid
a meeting. This is not business as normal as an example graphic… which is not.
and the message to our staff is to do
your best, but don’t worry if you have not My advice? Get guidance and do a root and
logged your allotted hours (and be careful branch review now and learn the lessons
if you are logging a lot more as work and so you can declare and correct errors
home life blur together). as we did. We were lucky when a staff
member pointed out these out to us which
The effect this lockdown has had on staff made us quickly stop and re-assess. We
forced to stay at home, in our experience, found errors in a minority of over 60 claims
is also wide and varied. Some thrive, some made, but nevertheless whether errors in
don’t. I have heard from most that there interpretation or procedure, mistakes they
are good days and bad days. Celebrate the certainly were. If we had not done the
good days and give yourself and your staff review, these would have compounded
time to recover from the bad ones. It has, and we possibly would have sailed on to a
however, lessened our apprehension for disaster.
working from home and it has forced us all
to employ the technology we had at our We also operate in a range of sectors. One
fingertips but were not utilising fully. When of these, transport and shipping, is deemed
back, first task for us will be a review with critical and so here we can continue to
everyone to see what positive lessons can work. But to do so, we have to put in
come from this experience. place procedures to ensure the setup and
working of a safe, temporary, marine site.
The furlough provisions from the
government were a welcome relief and a
huge help however, we made some errors
18
ISSUE 03
We also have a small fabrication facility be. Legislative compliance, staff well being,
based in Scotland, working on a range of and even just the day to day good running of
projects from defence to renewables. We had your business processes and updating when
implemented procedures and processes that required, which under normal circumstances is
allowed continuation of safe work. There was par for the course, all need a part of your time
some confusion in our sector though, whether as well.
or not this was permitted in Scotland and we
stood the team down for a week while we But don’t lose sight of the positives – time
investigated. Fortunately a clarifying question for training, increased use of technology and
in the Scottish Assembly made the position especially in our own case, a reminder of
clear and allowed us to restart projects the tenacity and team spirit of colleagues,
deemed critical,with all the right procedures even in the toughest times. And most of all,
in place. if at home, welcome the opportunity to turn
commuting time into family time.
Wider government support for the fall out
from this will need to be far reaching as
everyone adjusts to a new way of doing
things. The economic effects of this situation Written by John A. MacSween, Managing
in certain industries will reverberate for Director, Malin Group
years. The overarching message to owners
and managers though is that the risks to
your business are greater than just getting
revenue through the door, hard as that may
19
THE HEAVYLIFT ENGINEER
20
ISSUE 03
DECK STRENGTH
When selecting a suitable vessel to In addition to the above, the loads due
transport project cargo, you often receive to the motion of the ship are often-
a very basic specification for the ship overlooked, i.e. the combination of static
itself, informing you of the ship’s main weight, heave acceleration and either roll
particulars and hold size. A key factor or pitch accelerations and motions. The
that is considered at this stage is the hold ships motions will increase these local
dimension; i.e. whether the project cargo deck loads further.
will fit. Sometimes the global deck load
capacity is considered, but this only tends If not properly engineered, there is risk
to be with respect to the Cargo's overall that the ship’s deck structure becomes
footprint area and weight vs the ship’s damaged due to extreme loads, which
deck capacity in tonnes per square metre. could lead to the cargo being damaged or
lost. However, the issue can be mitigated
Consider a hypothetical cargo weighing through structural analysis of the vessel’s
200 Te with a foot print of 10m x 8m (or deck structure in way of the supports
80m2). This would show a static deck load and implementing load-spreading where
of 2.5Te/m2, acceptable for most cargo required.
vessels, regardless of whether the cargo
is stowed on the tank-top, tween deck or In any case, you should always look to
hatch covers. engage a highly-skilled engineer – such
as a structural engineer or naval architect
However, issues can arise once the vessel - who can perform such checks on the
has been booked and further details of the vessels deck structure where there are
cargo are then later released. Suddenly it concerns over the deck strength.
is noted that the cargo has bearing pads or
support feet (4 off at 0.3m X 0.3m each)
and it is not permitted to support the cargo
anywhere else. Now we realise that the Written by Lindsay McDougall, Technical
static weight of 200Te is supported on a Director, Malin Group
total contact area of 0.36m2; the total area
of the supporting feet.
21
THE HEAVYLIFT ENGINEER
22
ISSUE 03
23
THE HEAVYLIFT ENGINEER
fig. 9 / inTank BWTS in situ – single unit serving all four pontoons
If IC is such a good solution, why are there inTank has received orders for; Capes from
no ICBWTS on the market? For years the CMB Bocimar and Alpha Bulkers, Heavy
Cold Harbour inert gas based ICBWTS has Lifts from NYK, MR’s from Enterprises
been available but without USCG Type and VLCC’s from Pantheon Tankers and a
Approval. More recently another ICBWTS leading ME VLCC owner operator, with half
has come to market; Using DNV-GL as the a dozen systems now installed.
Independent Laboratory inTank was USCG/
IMO Type Approved last year. inTank is a Significantly for semi-submersible vessels,
BWTS product of Envirocleanse LLC based in Diamond Offshore installed inTank aboard
Houston Texas. their recommissioned semi-submersible rig
the Ocean Onyx. This sale was specifically
As an independent Consultant in 2016, I because inTank allows a semi-submersible
read the first Press Release for the inTank to complete its normal operations with
BWTS. I’d not heard of Envirocleanse, minimal disruption due to ballast water
but I’d heard of Berkshire Hathaway, treatment.
the owner of their parent company so
I reached out to Matt Hughes, VP at
Envirocleanse. I was soon sure this ICBWTS
would make it to market, now it has. Written by Giles Candy, Envirocleanse LLC
25
THE HEAVYLIFT ENGINEER
26
ISSUE 03
HOOK HEIGHTS
Most people involved in heavy lift and • Crane specification; when using mobile
cargo loading operation are familiar with cranes for lifting cargo we need to
the term ‘Hook Height’ describing the take care to consider the available
vertical distance from the ground up to the hook height for the total lift weight
highest point the crane hook can go. at the various radii of the lift. As the
mobile crane booms out (increasing
When it comes to loading project cargo radius) the available hook height
or any crane lift really, getting this wrong decreases as a function of the boom
could be the difference between being length and radius of interest. Thus we
able to complete the lift or not. So, what need to consider the hook height at
are the factors that could adversely affect the following radii; initial lift, hatch
the ‘Hook Height’ (HH) of a lift? coaming or vertical obstruction and set
down.
• Height of cargo lift points, the higher
these are the less height there is left It should be noted that although you can
for the lift. get a crane capable of lifting a particular
• Lift rigging; the height of the rigging weight at the required radius it may not
between the hook and cargo lifting have the available hook height when the
points, this height is added to the 4 points above are considered and a large
height of the lift points and the total crane may be required.
subtracted from the hook height.
The rigging arrangement will further When discussing your lifting requirements
reduce the available hook height. with your designated ‘Appointed Person,’
• Height of hatch coaming above quay make sure they are given all the relevant
side during lift, or any other vertical information with respect to lifting radii,
obstruction we need to lift over. On obstructions, height of lift points and lift
tidal berths the height of the hatch rigging requirements. Early engagement
coaming will vary with the state with a suitable lifting specialist will help to
of tide, i.e. at high water the hatch ensure you have the right crane with the
coaming will be at the highest point available hook height to perform the lift.
above the quay and so this height
is also subtracted from the available
hook height.
Written by Lindsay McDougall, Technical
Director, Malin Group
27
COMING UP IN AUTUMN 2020
HEAVYLIFT MAGAZINE EDITION 4:
FEATURING ARTICLES ON MOORING ANALYSIS, DESIGN OF SHIP
BUILD AND TRANSPORTATION CRADLES FOR FLOAT OFF LAUNCHES
& KEY HEAVY LIFT TIP - “SINGLE POINT OF CONTACT”
A PUBLICATION
SOUTH ROTUNDA
100 GOVAN ROAD
PACIFIC QUAY
GLASGOW
G51 1AY
WWW.MALINGROUP.COM