Rules of Credit

Download as pdf or txt
Download as pdf or txt
You are on page 1of 14
At a glance
Powered by AI
The document discusses different methods for measuring and reporting construction progress, including earned manhours, weighting of overall project completion, and commodity curves.

Progress can be measured based on earned manhours at the work activity level, and overall project completion is reported on a monthly basis. Commodity curves also measure completion by concrete poured, steel erected, and other metrics.

Commodity curves measure completion of different construction elements by metrics like cubic yards of concrete poured, tons of steel erected, square feet of paving laid, and other quantities. These provide additional ways to measure physical progress.

..

l ..
Exhibit I, Part B
Attachment 1
Progress Measurement Requirements
General
Budgeted direct manhours and quantities with units of measure shall be in the progress
measurement system.
Schedule resource loading will be reconciled with the hours in the progress management
system to ensure proper loading.
Construction
Report Frequency - Progress will be issued on a weekly basis by the construction
contractor (CC).
Progress measurement
Progress will be based on earned manhours that will be earned at the detailed
work activity level.
Partial credit guidelines as proposed by the CC will be reviewed and approved
by the Company prior to t)le start of work. See Attachment 4 in this procedure
for minimum requirements.
- Progress curves will be provided for overall and discipline progress against the
baseline curves. Forecast and actual curves will be displayed as well.
Budget manhour details will be submitted by the CC at the beginning of
construction for Company review and approval.
Direct manhours - craft hours directly advancing the work.
Indirect manhours will be displayed using a series of work-off curves for each
category of indirect manhours. The schedule curve will be a direct reflection
of the CC staffmg plan. Actual and forecast manhour curves will be displayed
as well. Examples of indirect hours - superintendent, general foreman,
material control, document control, equipment operators, scaffolding,
holewatch, firewatch, etc.
Overall Progress
Report Frequency - Progress and perfonnance measurement results will be issued
on a monthly basis to the PMT.
The weighting of the overall project percent complete will be submitted to the
Company prior to the first invoice.
n(
~ . ,
Exhibit I, Part B
Attachment 2 Commodity Curves
Civil and Site - percent complete:
excavation / backfill in CY
concrete in CY cast
paving cast in SF
epoxy grout CY
cementitious grout CY
Structural Steel- percent complete:
steel erected in tons
EquipmentVessels & Exchangers - percent complete
Equipment-Rotating - percent complete
Equipment-Fired - percent complete
Fireproofing - percent complete:
structural in CY
skirts in SF
Piping - percent complete:
Spools - total, received, erected
Welds
- field erection, Small bore and large bore, each
- field fab, Small bore, each
footage erected
footage pre-hydro'd
footage hydro'd
footage post-hydro'd
Steam Tracing - percent complete
footage bare
footage pre-insulated
footage tested .
Insulation - percent complete
pipe insulation LF
equipment insulation SF
Electrical - percent complete
conduit LF
cable tray LF
wire LF
motor run-in each
MCC/Switchgear each
starters each
breaker panels each
transformers each
light fixtures each
low/med voltage terms each
high voltage terms each
Instrumentation - percent complete
devices bench calibration each
devices mounted each
devices mounted each
devices tubed each
devices tubing tested each
loops punch listed each
Buildings - percent complete
Partial Credit Guidelines
Construction
Sample Project, Location
Milestone Description Percent Complete
MISC. OR PKG. SYS
RECEIVE
SET
ALIGN FOR GROUT
SELL-OFF
CRANESIHOISTS
RECEIVE
PRE-ASSEMBLE
ERECT
FINAL ALIGNMENT
SELL-OFF
TOWER/COLUMNS
RECEIVE
SET/ALIGN FOR GROUT
INTERNALS
INSPECT/CLEAN
SELL-OFF
SHOP FAB VESSEL DRUMS (ASSUMES DELIVERY TO HOOK)
RECEIVE
SET
INSTALL INTERNALS (consider separate category)
INSPECT/CLEAN
CLOSE UP (sell-off)
HEAT EXCHANGERS
RECEIVE
SET EXCHANGER
FINAL ALIGNMENT FOR GROUT
SELL-OFF
AC EXCHANGERS
RECEIVE
PRE-ASSEMBLE
ERECT
REMOVE BELT FOR RUN IN
FINAL ALIGNMENT
SELL-OFF
HEATERS (ASSUMES SHOP PREFAB/MODULAR)
RECEIVE
SET/ASSEMBLE
BOLT OUT
WELD OUT
REFRACTORY
HYDRO TEST COILS
SELL-OFF
Exhibit I. Part B. Attachmerit 4
0
30
40
30
100
0
40
45
10
5
100
0
35
40
20
5
100
0
35
40
20
5
100
0
70
25
5
100
0
20
45
20
10
5
100
0
20
20
20
20
15
5
100
Page 1 of11
, .
(
..":"...
Partial Credit Guidelines
Construction
Sample Project, Location
Milestone Description
STACKS
RECEIVE
PRE-ASSEMBLE
ERECT STACK
SELL-OFF
PUMPS
RECEIVE
SET ON FOUNDATION
ALIGN: READY FOR GROUT
COUPLED
FINAL ALIGNMENT READY FOR STRESS
SELL-OFF
COOLING TOWER
RECEIVE
ERECTION
HYDRO TEST
SELL-OFF
COOLING WATER FANS
RECEIVE
INSTALL FANS
ROUGH ALIGN
CPL FOR RUN IN
FINAL ALIGNMENT
FANS & BLOWERS
RECEIVE
INSTALL
ROUGH ALIGN
CPL FOR RUN IN
FINAL ALIGNMENT
SELL-OFF
COMPRESSORS & AUX EQUIP
RECEIVE
SET READY FOR GROUT
ROUGH ALIGN
CPL FOR RUN IN
RUN IN
FINAL ALIGNMENT
SELL-OFF
FLD ERECT TANKS
FOUNDATION
BOTTOM
SHELL & INTERNAL
ROOF& INTERNAL
ACCESSORIES
Exhibit I. Part B. Attachment 4
Percent Complete
o
35
50
5
100
o
10
30
30
20
10
100
o
70
25
5
100
o
30
30
30
10
100
o
35
25
25
10
5
100
o
25
20
20
15
10
10
100
18
12
25
15
10
Page 2 of 11
, .
~ - ..
Sample Project, Location
Partial Credit Guidelines
Construction
Milestone Description Percent Complete
TESTING 5
PAINTING & CONTROLS 5
INSULATION 10
100
FLD ERECT TANKS
FOUNDATION 18
BOTTOM 12
SHELL & INTERNAL 30
ROOF & INTERNAL 20
ACCESSORIES 10
TESTING 5
PAINTING & CONTROLS 5
100
CONVEYORS
RECEIVE 0
PRE-ASSEMBLE 40
ERECT READY FOR GROUT 30
FINAL ALIGNMENTIBELT TRAIN 25
SELL-OFF 5
100
ELEVATORS
RECEIVE 0
ERECTELEV 80
CHECK OUTIFUNCTIONAL TEST 15
SELL-OFF 5
100
CRUSHERSIMILLS
RECEIVE 0
SET 30
ROUGH ALIGN 20
CPL FOR RUN IN 30
RUN IN 10
FINAL ALIGNMENT 5
SELL-OFF 5
100
EDUC, FILTERS, ETC.
RECEIVE 0
INSTALL 85
SELL-OFF 15
100
AGITATORS
RECEIVE 0
INSTALL 70
RUN IN 25
SELL-OFF 5
100
REACTORS
RECEIVE 0
SET <60
Exhibit I, Part B, Attachment 4 Page 3 of 11
.
Partial Credit Guidelines
Construction
Sample Project, Location
Milestone Description
INSTALL INTERNALS
INSPECT / CLEAN
CLOSE / SELL-OFF
BINIHOPPERISILO
RECEIVE
SET
INSTALL ACCESSORIES
SELL-OFF
GATESIDIVERTERS
RECEIVE
INSTALL
SELL-OFF
AIR DRYERS
RECEIVE
SET
ALIGN FOR GROUT
SELL-OFF
SCALES/CHLORINATORS
RECEIVE
INSTALL
ROUGH ALIGN
FINAL ALIGNMENT
SELL-OFF
COKE DRILL STEMS
RECEIVE
INSTALL
ROUGH ALIGN
FINAL ALIGNMENT FOR GROUT
SELL-OFF
HYDRAULIC EQUIPMENT
RECEIVE
INSTALL
FINAL ALIGNMENT
FILL SYS WITH HYDR FLUID
SELL-OFF
DUCTWORK
RECEIVE
PRE-ASSEMBLE
ERECT
WELD OUT
Exhibit I, Part B, Attachment 4
Percent Complete
>20
15
5
100
o
75
20
5
100
o
85
15
100
o
60
30
10
100
o
40
45
10
5
100
o
30
55
10
5
100
o
40
35
20
5
100
o
35
35
30
100
Page 4 of 11
l
Sample Project, Location
Partial Credit Guidelines
Construction
Milestone Description Percent Complete
GROUT
CHIP AND FORM 40
POUR GROUT 40
STRIP AND PATCH 20
100
FDN <2.3m3 (<3cy)
TIE REBAR 15
Set Rebar 10
Excavate 10
FORMIPOUR CONCRETE 45
STRIP FORMS! FINISH 10
BackfilVSell 10
100
FDN 2.3 -38.23 m3 (3-50 cy)
PREFAB REBAR 15
Excavate 10
SET REBAR 20
SET FORMS 20
POUR CONCRETE 20
STRIP FORMS! FINISH 10
BACKFILL 5
100
FDN> 38.23 m3 (>50cy)
PREFAB REBAR 10
Excavate 10
SET REBAR 30
SET FORMS 20
POUR CONCRETE 10
STRIP FORMS! FINISH 10
BACKFILL 10
100
SPECIAL SLABS @ GRADE
PREFAB REBAR 15
PREP GRADE IS
SET REBAR 25
SET FORMS 30
PLACE CONCRETE 10
STRIP FORMS / FINISH 5
100
ELEV. FDNS -PIERIW ALL 1.22m A/G
PREFAB REBAR 15
SET REBAR 30
SET FORMS 30
PLACE CONCRETE 15
STRIP FORMS ~ FINISH 10
100
ELEVATED STRUCTURES
PREFAB REBAR 20
SET REBAR 10
SET FORMS/SHORING 40
Exhibit I, Part B, Attachment 4 Page 5 of 11
.
Partial Credit Guidelines
Construction
Sample Project, Location
Milestone Description
PLACE CONCRETE
STRIP FORMS / FINISH
ERECT PRECAST CONCRETE
MOVE FROM LA YDOWN
ERECT
POUR JOINT
ELEVATED SLABS W/Q-DECKING
o DECKING
FORMING
FABREBAR
SET REBAR
POUR CONCRETE
STRIP FORMS / FINISH
ELEVATED SLABS WI SHORING
PREFAB REBAR
SET REBAR
SET FORMS
SHORING
POUR CONCRETE
STRIP FORMS / FINISH
PlPE SUPPORTS POURED IN-PLACE
TIE REBAR
F AB A. BOLTIEMBEDS
FORMIPOUR CONCRETE
STRIP FORMS / FINISH
RETAIN1NG WALLS
PREFAB REBAR
SET FORMS
SET REBAR
POUR CONCRETE
STRIP FORMS / FINISH
GROUT
CHIP & FORM
POUR GROUT
STRIP& PATCH
DRILLED FOOTINGS
DRll..L, SET REBAR, POUR CONCRETE
PITS & BASINS
PREFAB REBAR
EXCAVATE
SET REBAR
Exhibit I, Part B, Attachment 4
Percent Complete
10
20
100
25
50
25
100
30
15
10
15
20
10
100
20
10
20
20
10
20
100
15
10
65
10
100
15
40
25
10
10
100
40
40
20
100
100
15
15
15
Page 6 of11
(
\...- -
Partial Credit Guidelines
Construction
Sample Project, Location
Milestone Description
SET FORMS
POUR CONCRETE
STRlP FORMS / FINISH
BACKFILL
CIVIL STRUCTURES
PREFAB REBAR
EXCAVATE-
SET REBAR
SET FORMS
POUR CONCRETE
STRlP FORMS / FINISH
BACKFILL
ABOVE GROUND SPOOL FABRICATION
CUT AND TACK
WELD OUT
RECENE ON SITE
PIPE SPOOL ERECTION (L B )
ERECTION
CONNECT
TRIM OUTSUPPORTS

TESTING
POST-HYDRO
FIELD RUN PIPE
FAB
ERECT
SUPPORT
PRE-HYDRO
TESTING
POST-HYDRO
STEAM TRACE MANIFOLDS
FAB MANIFOLDS
INSTALL
LUBE OIL TUBE
TRAY / SUPPORT
INSTALL TUBE
TEST (AIR)
PROCESS SIDE PIPING AND HOOK-UP
TUBERACEWAYSUPPORT -
PROCESS TUBING HOOK-UPS
Exhibit I, Part B, Attachment 4
Percent Complete
25
10
10
10
100
15
15
15
25
10
10
10
100
40
40
20
100
40
25
15
10
5
10
100
20
35
20
10
5
10
100
80
20
100
50
40
10
100
60
40
100
Page 7 of 11
~ - ..... __ .
Partial Credit Guidelines
Construction
Sample Project, Location
Milestone Description Percent Complete
PIPE TESTING
STEAM TRACE TUBING
TIE-INS
LOCATE
EXECUTE TIE-IN/COMPLETE
MISCSTEELFAB
CUT & TACK
WELD OUT
RECEIVE ON SITE
ERECT MAJOR FRAME
SHAKEOUT
PRE-ASSEMBLE
ERECTION
BOLT-UP
ALIGNIHARD BOLT
FINISH / SELL
LADDERS, CAGES & EQUIP PLTFRMS
SHAKEOUT
PRE-ASSEMBLE
ERECTION
BOLT-UP
ALIGN I HARD BOLT
FINISH / SELL
PIPERACKS
PRE-ASSEMBLE
ERECTION
BOLT-UP
ALIGN / HARD BOLT
FINISH I SELL
MISCSTEEL
PRE-ASSEMBLE
ERECTION
INSTRUMENT DEVICES
RECV ICAL/SPEC CHECK
INSTALL DEVICES
ELECTRlCALL Y COMPLETE
SELL-OFF
ANALYTICAL INSTRUMENTS
RECV ICAL/SPEC CHECK
INSTALL DEVICES
Exhibit I, Part B, Attachment 4
15
85
100
50
30
20
100
10
20
25
20
20
5
100
10
20
25
20
20
5
100
20
30
35
10
5
100
55
45
100
10
60
20
10
100
10
60
Page 8 of 11
(
' .
/1 '
Partial Credit Guidelines
Construction
Sample Project, Location
Milestone Description
ELECTRICALLY COMPLETE
VERIFY CONNECTIONS
IN-LINE DEVICES
STORAGE/SPEC CHECK/CAL.
.INSTALL
ELECTRICALLY COMPLETE
VERIFY CONNECTIONS
INSTRUMENTS AND CONTROLS
Percent Complete
20
10
100
10
60
20
10
100
THIS ACCOUNT NOT USED-ALL ITEMS ACCOUNTED FOR IN OTHER ACCOUNTS
CONTROL PANELS
SET 20
WIRING 40
CHECK-OUT 20
FINAL SELL-OFF 20
100
PNEUM IPROC CNTRL TUBING
TRAY / SUPPORTS 50
INSTALL TUBING 30
CLEANITEST 10
SELL-OFF 10
100
STANDS, MOUNTS, AND SUPPORTS
FAB 60
INSTALL 40
100
WINTERIZATION
STEAM TRACE 75
INSTALL HEAT PACK 25
100
SPEC CHECK AND PRE-CAL.
THIS ACCOUNT NOT USED-ALL ITEMS ACCOUNTED FOR IN OTHER ACCOUNTS
LOOP COMPONENTS INSTALLED
LOOP READY TO SELL
SELL-OFF
PAINT EQUIPMENT
BLAST & PRIME COAT
INTERMCOAT
FINAL COAT
PAINT PIPE
BLAST & PRIME COAT
INTERMCOAT
FINAL COAT
Exhibit I, Part B, Attachment 4
40
60
100
35
30
35
100
60
20
20
100
Page 9 of 11
("
'-:,."
Sample Project, Location
Partial Credit Guidelines
Construction
Milestone Description Percent Complete
PAINT STEEL
BLAST & PRIME COAT 50
INTERMCOAT 25
FINAL COAT 25
100
MCC I SWITCHGEAR
SETINPLACE 25
ALIGNMENT 25
TERMINATE AND TEST 40
ENERGIZE 10
100
UPS SYSTEMS
SET IN PLACE 25
ALIGNMENT 25
TEST 25
ENERGIZE 25
100
CABLE TRA Y/J-BOXES
INSTALL 85
TRAY COVER 15
100
POWER BREAKERS AND EQUIPMENT
SETILEVEL 25
TERMINATE 50
CHECKOUT 25
100
EQUIPMENT INSULATION
INSULATE 40
METAL 50
SELL 10
100
PIPE INSULATION (SINGLE LAYER)
INSULATE 40
METAL 50
SELL 10
100
CONCRETE PAVING
PREFAB REBAR 15
PREP ARE GRADE 15
SET REBAR 15
SET FORMS 15
POUR CONCRETE & FINISH 30
STRlP FORMS / FINISH / BACKFILL 10
100
CONCRETE DITCH LINING
PREFAB REBAR 15
PREPARE GRADE 15
SET REBAR 15
SET FORMS 15
Exhibit I, Part B, Attachment 4 Page 10 of11
. .
c ...
Partial Credit Guidelines
Construction
Sample Project, Location
Milestone Description
POUR CONCRETE & FINISH
STRIP FORMS / FINISH
LIGHT POLE FDNS.
TIE REBAR
FAB A. BOLTIEMBEDS
FORM / POUR CONCRETE
STRIP FORMS / FINISH
GUARD POSTIRAILING
PREFAB POST
INSTALL POST
VALVE BOXES, MANHOLES, CB
PREFAB ENTIRE VL V BOX
EXCAVATE PLACE SEAL SLAB
SET AND ALIGN
BACKFILL
UNDERGROUND PIPE "CIS"
EXCAVATION
BED INSTALLED
FAB PIPE
PIPE INSTALLED
TEST
BACKFILL
UNDERGROUND PIPE "RCP"
EXCAVATION
BED INSTALLED
FABPIPE
PIPE INSTALLED
TEST
BACKFILL
EQUIP FIREPROOFING
PREPARATION
PLACE FIREPROOFING & CLEAN
CAULK
Exhibit I, Part B, Attachment 4
Percent Complete
30
10
100
15
10
65
10
100
50
50
100
60
20
10
10
100
10
10
30
35
5
10
100
20
10
20
35
5
10
100
45
50
5
100
Page 11 of11