List Submission Civil
List Submission Civil
List Submission Civil
Legend
Pending approval
Approved (A)
Approved with Comment (B)
Rejected
SUBMISSION TO CONSULTANT
NO DESCRIPTION
REV. NO. SUBMITTED RESPONDED STATUS LETTER/TRANSMITTAL REF. NO. REMARKS
ARCHI
1 100mm Thick Acc Block - Starken Product 0 14/6/2024 24/6/2024 A TRN/TLDSB/KPJBDO/MS/ARCHI/001
2 Clay Brickwall 0 14/6/2024 25/6/2024 A TRN/TLDSB/KPJBDO/MS/ARCHI/002
As stated in BQ “To supply and lay CEMSEAL FLEX (S2) waterproofing
system consist of cemseal 9 steps process at the rate of 1.80kg/m2 and
MATERIAL SUBMISSION OF WATER PROOFING PLANISEAL 388 reinforced with cemseal f100 onto clean honeycomb-free concrete
3 0 9/7/2024 11/7/2024 TRN/TLDSB/KPJBDO/MS/ARCHI/003
(BRAND MAPEI) surface (agent: cemseal industries sdn bhd) all strictly in accordance
with the manufacturer's instruction”. Please re-submit the proposed
brand for waterproofing
Please provide the presentation/ironmongery schedule and brand
IRONMONGERY MULTEC STAINLESS STEEL HINGES 503525 SS
4 0 3/7/2024 8/7/2024 TRN/TLDSB/KPJBDO/MS/ARCHI/004 brochure for our reference. Please re-submit with relevant certs such
(BRAND MULTEC)
as SIRIM and warranty cert.
Keying should be 16 pin instead of 6 pin. Please provide the
IRONMONGERY MULTEC EURO PROFILE CYLINDERS 6PPC70- presentation/ironmongery schedule, technical spec and brand
5 0 3/7/2024 8/7/2024 TRN/TLDSB/KPJBDO/MS/ARCHI/005
1380SS (BRAND MULTEC) brochure. re-submit with relevant certs such as SIRIM and warranty cer
for our reference
Please provide the presentation/ironmongery schedule and brand
6 IRONMONGERY MULTEC EURO MORTISE LOCKS (BRAND MULTEC 0 3/7/2024 8/7/2024 TRN/TLDSB/KPJBDO/MS/ARCHI/006 brochure for our reference. re-submit with relevant certs such as SIRIM
and warranty cert
Please provide the presentation/ironmongery schedule and brand
IRONMONGERY ACCESSORIES FOR DOUBLE LEAF DOORS (MULTEC
7 0 3/7/2024 8/7/2024 TRN/TLDSB/KPJBDO/MS/ARCHI/007 brochure for our reference. Please re-submit with relevant certs such
AUTOMATIC FLUSH BOLTS AS FBD19160SS (BRAND MULTEC)
as SIRIM and warranty cert
Please provide the presentation/ironmongery schedule and brand
IRONMONGERY ACCESSORIES FOR DOUBLE LEAF DOORS (MULTEC
8 0 3/7/2024 8/7/2024 TRN/TLDSB/KPJBDO/MS/ARCHI/008 brochure for our reference. Please re-submit with relevant certs such
EL663 DOOR COORDINATOR (BRAND MULTEC)
as SIRIM and warranty cert
Please provide the presentation/ironmongery schedule and brand
IRONMONGERY (MULTEC BRAND TS77 SERIES DOOR CLOSER)
9 0 3/7/2024 8/7/2024 TRN/TLDSB/KPJBDO/MS/ARCHI/009 brochure for our reference. Please re-submit with relevant certs such
(BRAND MULTEC)
as SIRIM and warranty cert
The proposed fire rated glass dimension differs from the construction
FIRED RATED DOOR (F1D-1400) SUPPLIER WOODLANDER WOOD
10 0 10/7/2024 12/7/2024 B TRN/TLDSB/KPJBDO/MS/ARCHI/010 drawing. Refer attached drawing for comment and reconfirm before
PRODUCTS SDN BHD
proceeding work. Please submit shop drawing too.
MATERIAL SUBMISSION OF FIRED RATED DOOR (F1DW-1400)
11 0 10/7/2024 12/7/2024 B TRN/TLDSB/KPJBDO/MS/ARCHI/011 Please submit shop drawing before proceeding work
SUPPLIER WOODLANDOOR WOOD PRODUCTS SDN BHD
SUMMARY OF MATERIAL SUBMISSION
Legend
Pending approval
Approved (A)
Approved with Comment (B)
Rejected
SUBMISSION TO CONSULTANT
NO DESCRIPTION
REV. NO. SUBMITTED RESPONDED STATUS LETTER/TRANSMITTAL REF. NO. REMARKS
The proposed fire rated glass dimension differs from the construction
FIRED RATED DOOR (F1DW-1800) SUPPLIER WOODLANDOOR
12 0 10/7/2024 12/7/2024 B TRN/TLDSB/KPJBDO/MS/ARCHI/012 drawing. Refer attached drawing for comment and reconfirm. Please
WOOD PRODUCTS SDN BHD
submit shop drawing too.
The proposed fire rated glass dimension differs from the construction
13 MATERIAL SUBMISSION OF FIRED RATED DOOR (F1S-1050) 0 10/7/2024 12/7/2024 B TRN/TLDSB/KPJBDO/MS/ARCHI/013 drawing. Refer attached drawing for comment and reconfirm. Please
submit shop drawing too.
14 MATERIAL SUBMISSION OF PAINTING (BRAND JOTUN) 0 11/7/2024 12/7/2024 A TRN/TLDSB/KPJBDO/MS/ARCHI/014
SUMMARY OF WORK METHOD STATEMENT
Legend
Pending approval
Approved (A)
Approved with Comment (B)
Rejected
SUBMISSION TO CONSULTANT
NO DESCRIPTION
REV. NO. SUBMITTED RESPONDED STATUS LETTER/TRANSMITTAL REF. NO. REMARKS
ARCHI
Not comply to the JKR Specifications in general. Refer
1 Brickworks 0 24/6/2024 3/7/2024 TRN/TLDSB/KPJBDO/MST/ARCHI/001 to JKR Standard Specifications for Building Works 2020
Section E: Wall System
Refer to JKR Standard Specifications for Building Works
2 Plaster works 0 24/6/2024 3/7/2024 TRN/TLDSB/KPJBDO/MST/ARCHI/002 2020 Section K: Plastering, Paving Tiling and Carpet
(Plaster Work
3 Screeding Please submit the material approval before proceeding
0 24/6/2024 3/7/2024 B TRN/TLDSB/KPJBDO/MST/ARCHI/003
the work
4 Tiling works Refer to JKR Standard Specifications for Building Works
0 24/6/2024 3/7/2024 TRN/TLDSB/KPJBDO/MST/ARCHI/004 2020 Section K: Plastering, Paving Tiling and Carpet
(Tiling Work)
5 Waterproofing Please submit the material approval before proceeding
0 24/6/2024 3/7/2024 B TRN/TLDSB/KPJBDO/MST/ARCHI/005
the work
6 Doorframes Please submit the material approval and sample
0 24/6/2024 3/7/2024 B TRN/TLDSB/KPJBDO/MST/ARCHI/006
before proceeding the work
7 Ceiling Works Refer to JKR Standard Specifications for Building Works
0 24/6/2024 3/7/2024 TRN/TLDSB/KPJBDO/MST/ARCHI/007
2020 Section I: Ceilin
8 Painting Works Refer to JKR Standard Specifications for Building Works
0 24/6/2024 3/7/2024 TRN/TLDSB/KPJBDO/MST/ARCHI/008
2020 Section O: Painting
SUMMARY OF REQUEST FOR INFORMATION
Legend
Pending approval
Approved (A)
Approved with Comment (B)
Rejected
SUBMISSION TO CONSULTANT
NO DESCRIPTION
REV. NO. SUBMITTED RESPONDED STATUS LETTER/TRANSMITTAL REF. NO. REMARKS
ARCHI
Referring to the Key Plan Level 8 & 9 architecture drawing no. HTS / KPJ
BDO / CD / ARC / KP 102 Rev02 Please find attached drawings Key Plan 08 REV 03
received on 22 June 2024 attached. Please confirm that the said (HTS / KPJ BDO / CD / ARC / KP 101) and Key Plan
1 0 23/6/2024 26/6/2024 B RFI/TLDSB/KPJBDO/ARCHI/001
drawing can be used for construction 09 REV 03 (HTS / KPJ BDO / CD / ARC / KP 102) for
purposes and please provide details for the dimensions, alignments etc your reference and necessary actions.
for the affected areas.
Referring to the Key Plan Level 8 & 9 architecture drawing no. HTS / KPJ
BDO / CD / ARC / KP 102 Rev02 and M&E sanitary plumbing system
drawing KAC_0788_Plumbing_P01, we notice that the position of floor Please refer to our revised drawing keyplan level
2 0 25/6/2024 4/7/2024 B RFI/TLDSB/KPJBDO/ARCHI/002
trap & EWC at the toilet area does not match. Please confirm which 08 and level 09 REV04 for the floor trap location.
drawing need to follow and provide details dimension position to us
start coring work.
Legend
Pending approval
Approved (A)
Approved with Comment (B)
Rejected
SUBMISSION TO CONSULTANT
NO DESCRIPTION
REV. NO. SUBMITTED RESPONDED STATUS LETTER/TRANSMITTAL REF. NO. REMARKS
Request information regarding the solution for the leaking issues
9 0 12/7/2024 RFI/TLDSB/KPJBDO/ARCHI/009
on Level 8 and 9
10 Request information regarding the paint type and colour codes 0 14/7/2024 RFI/TLDSB/KPJBDO/ARCHI/010
SUMMARY OF REQUEST FOR INSPECTION
Legend
Pending approval
Approved (A)
Approved with Comment (B)
Rejected
SUBMISSION TO CONSULTANT
NO DESCRIPTION REV. NO. SUBMITTED RESPONDED STATUS LETTER/TRANSMITTAL REF. NO. REMARKS
ARCHI
1. FEW WALL POSITION ARE TO BE ADJUSTED AS
DISCUSSED
Inspection Of Setting-Out Brickworks
1 0 13/6/2024 13/6/2024 B RFWI/TLDSB/KPJBDO/ARCHI/001 2. FEW WINDOWS ARE TO BE ADDED
Level 8
PARTITIONS DUE TO WALL POSITION
3. AHU ROOM WALL TO BE 270MM
Inspection Of Setting-Out Brickworks 1. ARCHITECT WILL ISSUE REVISED DRAWING BY
2 0 20/6/2024 20/6/2024 B RFWI/TLDSB/KPJBDO/ARCHI/002
Level 9 21/6/24 AS PER DISCUSSION