Concrete Pavement at B05
Concrete Pavement at B05
Concrete Pavement at B05
: IRV/JMS/KA/CP
METHOD OF STATEMENT Rev. No. : 0
Issue Date : 21/9/2022
CONCRETE PAVEMENT Page : 1 OF 6
1.0 OBJECTIVE
To specify the requirements of concrete pavement activities complying with the contract
document, specification and scope of work and approved drawing/ documents.
2.0 SCOPE
This method statement applies to all the concrete pavement at Kualiti Alam.
3.0 REFERENCE
4.0 RESPONSIBILITY
NO. POSITIONS ROLES AND RESPONSIBILITIES
Responsibilities for overall commercial,
5.1 Project Manager/Assistant Project contractual and technical performances.
Manager Associated with specific projects.
Responsible to the Project Director.
Planning, coordinating and supervise
5.2 Site Engineer/ Site Supervisor
Site activities.
Safety Officer/Site Safety Supervisor / To control and ensure the safety, health
5.3
Environmental Officer and environmental is adhere at site.
1
IR VISION CONSTRUCTION AND SERVICES Doc. Ref. : IRV/JMS/KA/CP
METHOD OF STATEMENT Rev. No. : 0
Issue Date : 21/9/2022
CONCRETE PAVEMENT Page : 2 OF 6
5.0 MATERIALS
Approval shall be obtained for all the materials with reference to client’s preferred
vendor list, prior to commencement of activities. Material approval request will be
submitted to client upon material arrival to site. All materials must be stored properly as
per the manufacturer’s recommendations. The material shelf life will be monitored as
per Manufacturer’s data sheets.
NO EQUIPMENT/PLANT/TOOLS DESCRIPTION
1 Wheelbarrow To deliver small quantity of material
2 Rollers/compactors To compact soil / surface
3 Vibrators For removing air in concrete
8.1 General
8.1.1 Before concrete pavement work activities, contractor need to prepare request for
inspection (RFI) for dismantling and installation work and need to be approved from
Client. Client will inspect and check whether the situation at site in good order before
starting work such as the condition of the machine, the environment of site, and other
related issues.
8.1.2 All of the concrete pavement work activities must be supervised by site engineer and
assist by site supervisor to make sure all activities working according to the specification
and standard.
8.1.3 Site Engineer/Site Supervisor needs to identify all of the utilities before start work and
make sure construction of civil work activities not disturb the utilities and be careful with
the utilities during works.
2
IR VISION CONSTRUCTION AND SERVICES Doc. Ref. : IRV/JMS/KA/CP
METHOD OF STATEMENT Rev. No. : 0
Issue Date : 21/9/2022
CONCRETE PAVEMENT Page : 3 OF 6
Upon receipt of job instruction / drawing from client, initial site visit to be made along with the
client representative to confirm the site and demarcations. Proper hoarding and site sign boards
will be installed prior to the construction.
The pavement area shall be set out and elevations marked by contractor using steel pins and
paint markings. In case of any obstruction or existing services, it shall be intimated to the Kualiti
Alam and necessary modifications shall be carried out after getting approval from Client The
elevation shall be marked before proceed to any works.
i. Reinforcing steel
Engineer's approval will be obtained for reinforcement before using in permanent works. All
reinforcement will be stored on racks inside the stores. Different types & sizes will be kept
separately. All reinforcement will be kept to protect from damage, free from dirt, loose mill scale,
rust scale paint, oil, or other foreign substances. As per the specifications & drawing, the bar
bending schedules & bar lists, cutting schedules for each individual structure will be prepared by
the contractor and will obtained the approval from the engineer. Manual cutter or mechanical
cutter will be used for cutting of bars & bending machine will be used for bending of bars. All
reinforcement will be cleaned by a wire brush or any other means before placing. All
reinforcement placed should comply with the drawings. Lap length will be taken in to account
according to the project specification when binding reinforcement bars.
All formwork will be made by using plywood sheets, timber or by metal. Supports and scaffolding
will be G I pipes, Arco props, sawn timber or round timber. All surfaces of formwork will be
finished smooth and mortar tight. The dimensions & position of formwork will be carefully
checked after erection. Oil or grease will be used to avoid adhesion of mortar and to achieve a
smooth surface. Before placing concrete all dirt, wood chips, hardened concrete or mortar and all
other foreign matter will be removed from the forms. Before fixing of form work, detailed drawing
will be submitted to the engineer for approval. Well qualified foreman will be appointed for fixing
on formworks & reinforcement work.
3
IR VISION CONSTRUCTION AND SERVICES Doc. Ref. : IRV/JMS/KA/CP
METHOD OF STATEMENT Rev. No. : 0
Issue Date : 21/9/2022
CONCRETE PAVEMENT Page : 4 OF 6
The method for placing of concrete will be worked out to prevent segregation of the material &
engineer’s approval before concreting begins. Before placing concrete all formwork therein will
be cleaned of all extraneous material and dust and made free of any standing water. In
continuing concrete, fresh concrete will be placed before the already placed concrete is less than
20 minutes.
Concrete of specified grade will be placed & compacted in horizontal layers normally not
exceeding 300m in depth. Concrete will not be dropped from height greater than 1.5m to prevent
segregation. Concrete will be free of all rock pockets, honey combs & voids. Complete records
showing the detail of placing concrete in each part of the work will be maintained and will be
available for inspection at the site.
Mechanical vibrators will be used for compaction. For this stand by units will available in the site
during the period of compacting. All operators handling vibrators will be trained in their operation
properly.
v. Curing
Continuous curing will be carried out in a moist atmosphere for a minimum period of 10 days and
for a further period required by engineer. Concrete area will be kept covered with hessian clothes
or polyethylene sheets which will be kept moist throughout the curing period.
The surface of the hardened concrete will be cleaned and made free from laitance and will also
have an exposed aggregate finish. The fresh concrete will be placed and compacted so that is
bonds properly to the prepared surface of the previously laid concrete. Laitance on the surface
will be completely removed from the concrete in order to achieve a good bond with fresh
concrete. Between one and two hours after placing concrete, water will be sprayed gently and
laitance will be removed with two brushes, one with soft and other with hard bristles. After
finishing this operation, just the tips of the aggregate should be showing. If the laitance has
hardened, a wire brush will be used to remove it. Clean water will be rinsed to get rid of the dust.
Water stops in construction joints will be installed & approval for this will be take form the
engineer.
Frequent slump test will be carried out in accordance with BS 1881 on samples of concrete taken
immediately before placing to determine the consistency of concrete. All the test reports will be
maintained in the site office & will be available for the inspection whenever required.
4
IR VISION CONSTRUCTION AND SERVICES Doc. Ref. : IRV/JMS/KA/CP
METHOD OF STATEMENT Rev. No. : 0
Issue Date : 21/9/2022
CONCRETE PAVEMENT Page : 5 OF 6
All necessary arrangements for the sampling & testing of fresh & harden concrete in accordance
with the BS 1881 will be taken. Crushing test will be carried out on conerete cubes formed in
150mm molds. One set of cubes (2 cubes crushed in 7 days & other in 28days) will be done to
maintain the quality of work. Particular care will be taken to ensure that the test cubes are stored
under uniform conditions in the site & during any transit between site & laboratory.
in approved colour/textures as per the manufacturer’s specifications. The number of coats shall
be shown on the drawings or as directed by the engineer.
Plastic emulsion paint, vinyl emulsion paint or matt enamel paint of the approved make and
shade shall be applied to surfaces as shown on drawings as per manufacturer’s instructions. The
number of coats shall be as indicated on drawings or as directed by the engineer. Inspection
request to be submitted for checking and approval of the engineer.
Hazard identification, risk assessment and determining control shall be carried out for the
drainage work. Prior to any works commencement, cautions and awareness signs shall be
established at location of work. The hazards in a particular activity and the control measures
implemented shall be brief to the workers during ESH induction and tool box talk.
9.2.1 All workers employed in the project site compulsory have CIDB green card.
9.2.2 All new workers and staff to attend the ESH training / induction before commencing work
site and attendance shall be recorded in an induction list.
9.2.3 All site personnel shall wear proper personnel protective equipment (PPE). Workers who
fail to comply with this requirement will be removed from site.
9.2.4 All workers to attend the weekly toolbox meetings conducted by SSS/ SHO held at site
and attendance shall be recorded.
9.2.5 In summation, in order to achieve safe, free risk and healthy working environment,
including loss prevention, every practicable step must be taken by each and every one
engaged in this project site.
The permit required for this activity will be acquired when necessary.
5
IR VISION CONSTRUCTION AND SERVICES Doc. Ref. : IRV/JMS/KA/RG
METHOD OF STATEMENT Rev. No. : 0
Issue Date : 09/02/2022
CLEARANCE EXISTING LANDSCAPE WORK Page : 6 OF 6
10.1 Housekeeping
- Housekeeping is an essential part of safety for the daily routine. Housekeeping would
include the following items:
11.2.1 Maintain the access/egress to all working area
11.2.2 Store and stack all construction materials in safe and orderly manner
11.2.3 No littering around the site and provide sufficient waste bin.