Annex J Construction Plan and Cost Estimate
Annex J Construction Plan and Cost Estimate
Annex J Construction Plan and Cost Estimate
Construction Plan
and Cost Estimate
Annex J Construction Plan and Cost Estimate
Table of Contents
Page
J1 Conditions and Assumptions for Construction Plan and Schedule ............. J-1
J1.1 Workable Days .....................................................................................J-1
J1.2 Temporary Facilities ..............................................................................J-1
J1.3 Construction Materials ..........................................................................J-2
J1.4 Development Stage................................................................................J-2
J2 Construction Plan for Stage 1 Development ..................................................J-3
J2.1 Kaliwa Low Dam and Intake ................................................................J-3
J2.2 Kaliwa-Taytay 1st Waterway ................................................................J-4
J3 Construction Plan for Stage 2-1 Development ...............................................J-8
J3.1 Agos Dam..............................................................................................J-8
J3.2 Water Treatment Plant-Installation of Unit #2 ....................................J-10
J4 Construction Plan for Stage 2-2 Development .............................................J-11
J5 Construction Schedule ...................................................................................J-13
J6 Construction Cost Estimate ...........................................................................J-14
J6.1 Conditions and Assumptions ...............................................................J-14
J6.2 Method of Cost Estimate.....................................................................J-15
J6.3 Total Project Cost................................................................................J-16
J6.4 Annual Disbursement Schedule...........................................................J-16
List of Tables
Page
Table J1.1 Monthly Rainfall at Infanta between 1991 and 2000 ................................ JT-1
Table J1.2 Mean Monthly Rainy Days in the Project Area ......................................... JT-1
Table J1.3 Estimated Suspended Days by major Construction Work Item.................. JT-1
Table J1.4 Number of Workable Days for Respective Works ..................................... JT-2
Table J6.1 Project Cost Summary ................................................................................ JT-4
Table J6.2 Construction Cost Summary....................................................................... JT-5
Table J6.3 Bill of Quantities......................................................................................... JT-7
Table J6.4 Summary of Annual Disbursement Schedule............................................ JT-19
List of Figures
Page
Figure J1.1 Proposed Location Plan for Temporary Facilities ...................................... JF-1
Figure J5.1 Construction Schedule................................................................................ JF-2
Figure J5.2 Construction Program for Agos Dam and Agos Powerhouse .................... JF-3
Figure J5.3 Construction Program for Tunnels.............................................................. JF-4
J-i
Annex J Construction Plan and Cost Estimate
Based upon the above table and also taking into account the public holidays and
Sundays, monthly workable days for major construction works are estimated as
shown in Table J1.4.
The annual total and monthly mean workable days for the respective major work
items estimated above are summarized below:
J-1
Annex J Construction Plan and Cost Estimate
J-2
Annex J Construction Plan and Cost Estimate
J-3
Annex J Construction Plan and Cost Estimate
A schematic layout is shown below together with indication of the lengths and the
proposed plan of tunneling work:
J-4
Annex J Construction Plan and Cost Estimate
J-5
Annex J Construction Plan and Cost Estimate
The elevation of the area ranges from EL. 90-100 m in the relatively flat areas to
EL. 120 m on the hilltops. The area consists of a mixture of fruits plantation,
paddy field, uncultivated land and hilly areas with about 25 housings at scattered
locations. The plan envisages acquiring a total land of about 100 ha including
earth disposal area. The Stage 1 work will be constructed in the area of about 60 ha.
Earthworks to provide a 60 ha land require some 4 millions m3 of cut and fill.
Many kinds of heavy machinery such as 44 ton bulldozer with ripper, 10 m3 class
wheel loader, 3 m3 class backhoe (or larger), and 46 ton dump truck will be
employed to deal with about 4 million m3 earthworks within a limited construction
period. In order to dispose the surplus excavated materials, spoil bank is planned to
be secured at the nearby section.
Upon the completion of site formation works, structural works will then be carried
out at each location. The water treatment plant consists of many structures
including receiving well, mixing chamber, flocculation basin, sedimentation basin,
rapid sand filter, clear water basin, sludge thickening tank, and sludge drying bed.
The concrete will be produced at and transported from a central batching plant
installed at the site.
At the locations where the structural works will have been completed, the
mechanical and the electrical works will then be done accordingly.
(5) Pipelines
Embedded pipelines will be installed for the length of 5.1 km (main pipeline)
between the Morong WTP and Tunnel No.2 and 4.1 km (branch pipeline) between
Valve House No.2 and Antipolo Service Reservoir. The diameter is 3.4-3.3 m for
the main pipeline and 1.6 m for the branch pipeline, respectively.
The installation of pipes requires the excavation of a trench as deep as 6.6 m in the
sections of lowland area where soft silt-clay layers are dominant. The work will
require the use of steel sheetpile walling with strut supports. It is expected that
sheetpiling be needed for some 60 % of the total length of the pipelines to be
installed. The rest of the pipeline route will be installed after the open excavation
without sheetpiling.
Following the trench excavation, steel pipes of each 9m (or 6m) long segment will
then be installed in position by a 150-ton class capacity crawler crane. Each steel
pipe will be connected properly by the internal welding method.
Upon the completion of the pipe installation, backfill with adequate compaction
will be executed and sheetpile coffer-wall then removed. However, one side of
the sheetpile wall will be left in-situ without extraction, which would be used later
as a trench wall for the 2nd pipeline construction.
The similar construction method will be adopted for the 1.6m diameter pipeline.
It is estimated that the sheetpiling be needed for some 20 % section of the total
length of the pipeline.
J-6
Annex J Construction Plan and Cost Estimate
J-7
Annex J Construction Plan and Cost Estimate
J-8
Annex J Construction Plan and Cost Estimate
Upon the completion of 3 tunnels in a period of about 13 months, the upstream and
downstream cofferdams will then be constructed to divert the river flow into the
diversion tunnels.
In order to avoid seepage through dam body and to prevent piping phenomenon, the
upstream face of the both cofferdams is designed to be covered with impervious
materials. Slurry wall with 800mm thickness will be constructed at the upstream
toe of both upstream cofferdams to prevent water seepage under the cofferdams.
An access road to the proposed quarry site will be constructed upon the completion
of the cofferdam embankment.
(3) Main Dam
The proposed dam is a concrete face rockfill dam (CFRD) laid out as shown in
Figures F3.3 and F3.6 of Annex F.
Upon the completion of site clearance, excavation for the dam foundation will then
be executed from higher portion toward lower portion, while the earthworks at the
lowest portion need to await the diversion of river flow. Sufficient de-watering
system is to be established and maintained during the course of the excavation of
the lowest portion (at upstream toe of the dam), since the considerable amount of
underground water ingress is anticipated to take place through the upstream
riverbed. The excavation at this portion needs to be executed in the relatively dry
period, i.e. between February and September.
The excavation will be executed using bulldozer with ripper, backhoe, loader, and
dump truck. The rock excavation will be done in combination with blasting
method.
In parallel with the excavation operation at the damsite, the proposed quarry site
(approximately 1 km from damsite) is to be developed and be made available by
the time when embankment for dam body will be commenced.
The dam embankment volume is estimated to be about 13,000,000 m3 in total.
The materials for the embankment will be obtained from the proposed quarry site
and partly from the spillway excavation. It is anticipated that 50% of the
excavated rock from spillway be re-used and filled for dam embankment.
The embankment work will be carried out using heavy machines such as bulldozer
for spreading and vibrating roller for compaction. Some 400,000 m3 of rockfill
will have to be embanked per month in order to achieve the scheduled completion.
The face slab concrete will be placed with slip form. Concrete will be delivered to
the dam site by agitator trucks from a batching plant and further conveyed to the
placing location by concrete chute, crane with skip or concrete pump. The slip
form will move at a travelling speed of 1.5 m/hr and the concrete will continuously
be placed without making any horizontal joint once the work operation will be
started. The face slab concrete work will be carried out in 3 to 4 stages for the
whole surface of the dam.
J-9
Annex J Construction Plan and Cost Estimate
(4) Spillway
Spillway is located on the left side bank of the main dam.
Excavation work will be commenced from the higher portion to downward
direction along the chuteway by means of the bench cut method. The excavation
work for both earth and rock (about 9,000,000 m3 in total) will be carried out using
various heavy machines such as bulldozer, backhoe, crawler drill and dump truck in
combination with blasting operation (for rock portion). The selected rock
materials from the spillway excavation will be partly used for dam embankment as
stated above. Rock quantity expected to be usable for dam embankment is about
4,300,000 m3, while the rest will be hauled to the spoil bank.
Concrete work for the spillway construction, i.e. fore-bay structure, overflow weir,
chuteway and plunge pool walls, will be done by combination of various equipment
including fixed type tower crane, crawler/truck crane and concrete pump.
Electrical and mechanical works including radial gates (11m(h) x 14m(w) x 4 nos.)
and stoplogs will be carried out upon the completion of structural works.
Plunge pool will be excavated to the designated level after the left side diversion
tunnel will be closed and the downstream cofferdam will be relocated to further
downstream by about 300m. Closure of the left side diversion tunnel will have to
be done at the beginning of the dry season to allow the plunge pool construction to
be executed in the relatively dry period. During the course of excavation, proper
de-watering system is to be established and maintained since a considerable amount
of seepage water is anticipated.
(5) Hydropower Facilities
The hydropower plant and switchyard are constructed at the toe of the Agos Dam.
The works for power facilities consisting of intake structure, gate shaft, headrace
tunnel, penstock line and powerhouse will be carried out in parallel with the main
dam embankment and spillway construction.
Following the excavation works, concrete works for powerhouse substructure will
be carried out using the same equipment as used for the spillway construction.
Installation of overhead travelling crane in the powerhouse superstructure will be a
milestone event for the succeeding installation of generating equipment.
J3.2 Water Treatment Plant - Installation of Unit #2
In this Stage 2-1, an additional unit of water treatment plant is planned to be
installed in the adjacent area of Unit #1 that is to be installed under the Stage 1.
Since the site formation work is scheduled to be completed in the Stage 1, the work
involved at this stage will be limited to the structural and mechanical works for the
Unit #2.
J-10
Annex J Construction Plan and Cost Estimate
J-11
Annex J Construction Plan and Cost Estimate
been applied in the 1st stage construction, the distance between the pipes (edge to
edge) will be about 10 m.
(6) Tunnel No.2
The 2nd tunnel will be excavated in parallel with the 1st tunnel in the upstream part.
The distance between the 2 tunnels is 20 m. The tunnel in the downstream part is
aligned so as to take a shortest length to the proposed outlet site in the Taytay
Service Reservoir.
A faster progress of the tunneling is expected since the work will be able to be
arranged with advance knowledge of in-situ geology obtained through the
experience in the 1st tunnel.
(7) Service Reservoirs and Pump House
The construction work at this stage is virtually the expansion of facilities by
building structures similar to those built under the Stage 1. The work will use the
same method as adopted in the Stage 1 work.
J-12
Annex J Construction Plan and Cost Estimate
J5 Construction Schedule
Construction schedule of the proposed project was worked out in consideration of
required duration of each work activity, sequence of the works, progress rates,
seasonal constraints (weather and river flow conditions) and availability of
construction resources.
The proposed schedule is shown in a bar chart form in Figure J5.1. The detailed
programs for Agos Dam and tunnels are presented in Figure J5.2 and J5.3,
respectively.
J-13
Annex J Construction Plan and Cost Estimate
The prices of the main materials for the cost estimate are summarized as follows:
Material Unit Price (US$)
Diesel Oil litter 0.25
Cement ton 65
2
Plywood m 6.5
Reinforcement Steel ton 320
J-14
Annex J Construction Plan and Cost Estimate
J-15
Annex J Construction Plan and Cost Estimate
J-16
Table J1.1 Monthly Rainfall at Infanta between 1991 and 2000
(Unit: mm)
Year Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Total
1991 176 384 94 176 171 404 164 201 82 270 406 455 2,983
1992 234 122 104 134 164 104 495 266 172 535 637 233 3,199
1993 228 190 77 45 95 191 149 277 218 409 406 1,493 3,777
1994 468 148 187 116 162 416 63 105 274 423 165 412 2,940
1995 360 503 110 120 217 461 305 271 704 725 481 1,366 5,623
1996 395 181 174 809 123 357 222 64 102 420 899 367 4,112
1997 319 321 142 46 206 50 416 73 356 190 125 241 2,485
1998 114 41 - 40 109 232 208 204 126 784 476 1,536 3,869
1999 569 328 438 719 235 186 181 394 208 562 950 1,221 5,991
2000 362 372 292 180 243 347 231 100 403 766 789 1,021 5,105
Mean 323 259 180 238 172 275 243 195 265 508 533 834 4,026
JT-1
Table J1.4 Number of Workable Days for Respective Works (1/2)
JT-2
Table J1.4 Number of Workable Days for Respective Works (2/2)
JT-3
Table J6.1 Project Cost Summary
A. Total Construction Cost including Land Acquisition and Resettlement 917,170,364 482,667,119 1,399,837,483
JT-4
Table J6.2 Construction Cost Summary (1/2)
Stage 1 Kaliwa Low Dam + 1st Waterway F.C. L.C. TOTAL
1 Kaliwa Low Dam + 1st Waterway (excluding WTP #1)
(1) Land Acquisition & Resettlement excluding WTP #1
Land Acquisition 0.0 6,260,125.0 6,260,125.0
Resettlement and Compensation 0.0 14,710,400.0 14,710,400.0
Sub-total for (1) 0.0 20,970,525.0 20,970,525.0
(2) Kaliwa Low Dam (Temporary)
Preparatory Works 1,671,014.9 1,255,626.1 2,926,641.0
Kaliwa Low Dam 3,966,391.0 3,429,734.0 7,396,125.0
Intake Structure 3,208,733.0 2,533,817.0 5,742,550.0
Sub-total for (2) 8,846,138.9 7,219,177.1 16,065,316.0
(3) Waterway to Valve House no.1
Preparatory Works 13,838,326.7 4,745,572.6 18,583,899.3
Tunnel No.1 109,319,389.2 35,546,438.6 144,865,827.8
Sub-total for (3) 123,157,715.9 40,292,011.2 163,449,727.1
(4) Valve House No.1
Preparatory Works 270,849.3 128,873.4 399,722.7
Valve House Portion 1,887,347.0 779,273.0 2,666,620.0
Tailrace Portion 219,730.5 194,672.0 414,402.5
Sub-total for (4) 2,377,926.8 1,102,818.4 3,480,745.2
(5) Waterway from WTP to Reservoir
Preparatory Works 8,921,379.3 3,580,042.8 12,501,422.1
Pipeline No.1-1 (3.4m dia., 4.1km) 14,865,605.0 3,713,163.9 18,578,768.9
Pipeline No.1-2 (3.3m dia., 1.0km) 3,523,902.6 856,605.1 4,380,507.7
Valve House No.2 879,907.8 477,208.4 1,357,116.2
Pipeline No.2 (1.6m dia., 4.2km) 5,256,619.0 1,264,170.0 6,520,789.0
Surge Tank 17,194.8 23,167.2 40,362.0
Pumping Station #1 & #2 (80MLD) 10,521,727.9 3,107,370.1 13,629,098.0
Antipolo Service Reservoir #1 & #2 (30,000 m3) 1,654,962.5 1,433,382.6 3,088,345.1
Tunnel No.2 20,439,312.5 6,241,662.5 26,680,975.0
Taytay Service Reservoir #1 (180,000 m3) 9,910,595.2 7,866,960.1 17,777,555.3
Sub-total for (5) 75,991,206.7 28,563,732.4 104,554,939.2
JT-5
Table J6.2 Construction Cost Summary (2/2)
Stage 2-2 Kaliwa-Angono 2nd Waterway + WTP #3 & #4
1 2nd Waterway (excluding WTP #3)
(1) Land Acquisition & Resettlement excluding WTPs
Land Acquisition 0.0 5,977,163.0 5,977,163.0
Resettlement and Compensation 0.0 288,322.5 288,322.5
Sub-total for (1) 0.0 6,265,485.5 6,265,485.5
(2) Kaliwa Low Dam (Temporary)
Kaliwa Low Dam 239,652.0 159,768.0 399,420.0
Sub-total for (2) 239,652.0 159,768.0 399,420.0
(3) Waterway to Valve House No.1
Preparatory Works 10,745,154.2 3,672,136.2 14,417,290.3
Tunnel No.1 89,542,951.4 30,601,134.7 120,144,086.1
Sub-total for (3) 100,288,105.6 34,273,270.9 134,561,376.4
(4) Valve House No.1
Preparatory Works 132,775.2 14,752.8 147,528.0
Valve House Portion 1,069,200.0 118,800.0 1,188,000.0
Tailrace Portion 37,260.0 4,140.0 41,400.0
Sub-total for (4) 1,239,235.2 137,692.8 1,376,928.0
(5) Waterway from WTP to Reservoir
Preparatory Works 6,798,105.0 2,671,956.5 9,470,061.5
Pipeline No.1-1 (3.4m dia., 4.1km) 12,217,715.6 3,245,889.3 15,463,604.9
Pipeline No.1-2 (3.3m dia., 1.0km) 2,568,812.2 686,615.5 3,255,427.7
Pipeline No.2 (1.6m dia., 4.2km) 4,504,079.6 1,114,888.7 5,618,968.3
Surge Tank 17,194.8 23,167.2 40,362.0
Pumping Station (installation of additional pumps) 4,771,525.4 842,033.9 5,613,559.3
Antipolo Service Reservoir #3 (Expansion 30,000 m3 x 2 units) 2,968,351.3 2,699,345.9 5,667,697.2
Tunnel No.2 (Steel lined; 3.4m dia., 5.7km ) 20,439,312.5 6,241,662.5 26,680,975.0
Taytay Service Reservoir #3 (Expansion 180,000 m3) 9,163,883.7 7,412,701.3 16,576,585.0
Sub-total for (5) 63,448,980.2 24,938,260.7 88,387,240.9
Total for 1 165,215,973.0 65,774,477.9 230,990,450.9
JT-6
Table J6.3 Bill of Quantities (1/12)
JT-7
Table J6.3 Bill of Quantities (2/12)
Unit Price (US$) Amount (US$)
Item No Description Unit Quantity
F.C L.C. Total F.C L.C. Total
1 1 3 Tunnel excavation including all temp. m3 50,317 149.6 37.4 187.0 7,527,423.2 1,881,855.8 9,409,279.0
works (steel support, shotcrete, grouting,
power supply, etc.) other than conc.
1 1 3 Lining Concrete m3 17,221 50.0 75.0 125.0 861,050.0 1,291,575.0 2,152,625.0
1 1 3 Miscellaneous L.S. 5% 419,423.7 158,671.5 578,095.2
1 1 3 NATM 3
Open excavation at inlet & outlet portals m3 1,000 2.7 1.8 4.5 2,700.0 1,800.0 4,500.0
1 1 3 Tunnel excavation including all temp. m3 66,114 149.6 37.4 187.0 9,890,654.4 2,472,663.6 12,363,318.0
works (steel support, shotcrete, grouting,
power supply, etc.) other than conc.
1 1 3 Lining Concrete m3 22,627 50.0 75.0 125.0 1,131,350.0 1,697,025.0 2,828,375.0
Steel lining ton 100 1,062.5 187.5 1,250.0 106,250.0 18,750.0 125,000.0
1 1 3 Miscellaneous L.S. 5% 556,547.7 209,511.9 766,059.7
1 1 3 TBM 1
1 1 3 Open excavation at portal m3 0 2.7 1.8 4.5 0.0 0.0 0.0
1 1 3 Tunnel excavation including TBM and m3 163,205 237.6 59.4 297.0 38,777,508.0 9,694,377.0 48,471,885.0
all temp. works (steel support, shotcrete,
grouting, power supply, etc.) other than
conc. Lining
1 1 3 Lining Concrete m3 49,868 50.0 75.0 125.0 2,493,400.0 3,740,100.0 6,233,500.0
1 1 3 Miscellaneous L.S. 5% 2,063,545.4 671,723.9 2,735,269.3
1 1 3 TBM 2
1 1 3 Tunnel excavation including TBM and m3 68,025 237.6 59.4 297.0 16,162,740.0 4,040,685.0 20,203,425.0
all temp. works (steel support, shotcrete,
grouting, power supply, etc. other than
conc. lining)
1 1 3 Lining Concrete m3 20,785 50.0 75.0 125.0 1,039,250.0 1,558,875.0 2,598,125.0
1 1 3 Miscellaneous L.S. 5% 860,099.5 279,978.0 1,140,077.5
1 1 4 4 Valve House No.1
1 1 4 Preparatory Works
1 1 4 New Access m 100 180.0 120.0 300.0 18,000.0 12,000.0 30,000.0
1 1 4 Improvement m 0 90.0 60.0 150.0 0.0 0.0 0.0
1 1 4 Preparatory Works L.S. 252,849.3 116,873.4 369,722.7
1 1 4 Valve House Portion
1 1 4 Opencut excavation, common m3 23,600 2.7 1.8 4.5 63,720.0 42,480.0 106,200.0
1 1 4 Opencut excavation, rock m3 15,800 7.5 5.0 12.5 118,500.0 79,000.0 197,500.0
1 1 4 Backfill in random materials m3 16,900 4.5 3.0 7.5 76,050.0 50,700.0 126,750.0
1 1 4 Concrete for substructure m3 2,010 34.0 51.0 85.0 68,340.0 102,510.0 170,850.0
1 1 4 Concrete for superstructure m3 300 34.0 51.0 85.0 10,200.0 15,300.0 25,500.0
1 1 4 Reinforcement bar ton 770 248.0 372.0 620.0 190,960.0 286,440.0 477,400.0
1 1 4 Mechanical works L.S. 1,188,000.0 132,000.0 1,320,000.0
1 1 4 Miscellaneous L.S. 10% 171,577.0 70,843.0 242,420.0
1 1 4 Tailrace Portion
1 1 4 Opencut excavation, common m3 9,200 2.7 1.8 4.5 24,840.0 16,560.0 41,400.0
1 1 4 Opencut excavation, rock m3 3,900 7.5 5.0 12.5 29,250.0 19,500.0 48,750.0
1 1 4 Backfill in random materials m3 4,600 4.5 3.0 7.5 20,700.0 13,800.0 34,500.0
1 1 4 Structural concrete m3 1,380 34.0 51.0 85.0 46,920.0 70,380.0 117,300.0
1 1 4 Reinforcement bar ton 120 248.0 372.0 620.0 29,760.0 44,640.0 74,400.0
1 1 4 Hydroelectrical works L.S 39,600.0 4,400.0 44,000.0
1 1 4 Miscellaneous L.S. 15% 28,660.5 25,392.0 54,052.5
1 1 5 5 Waterway from WTP to Reservoir
1 1 5 Preparatory Works
1 1 5 New Access m 2,600 180.0 120.0 300.0 468,000.0 312,000.0 780,000.0
1 1 5 Improvement m 4,500 90.0 60.0 150.0 405,000.0 270,000.0 675,000.0
1 1 5 Preparatory Works L.S. 8,048,379.3 2,998,042.8 11,046,422.1
1 1 5 Pipeline No.1-1 (3.4m dia., 4.1km)
1 1 5 Open excavation, common m3 225,332 2.7 1.8 4.5 608,396.7 405,597.8 1,013,994.5
1 1 5 Open excavation, rock m3 25,037 7.5 5.0 12.5 187,776.8 125,184.5 312,961.3
1 1 5 Steel pipe installaiton and fitting m 4,100 1,893.0 334.1 2,227.0 7,761,095.0 1,369,605.0 9,130,700.0
1 1 5 Concrete for foundation of steel pipe m3 1,600 34.0 51.0 85.0 54,400.0 81,600.0 136,000.0
1 1 5 Reinforcement ton 80 248.0 372.0 620.0 19,840.0 29,760.0 49,600.0
1 1 5 Backfilling m3 211,908 4.5 3.0 7.5 953,586.0 635,724.0 1,589,310.0
1 1 5 Valves (air, isolating and drain) L.S. 297,500.0 52,500.0 350,000.0
1 1 5 Sheetpiling m 2,460 1,283.5 226.5 1,510.0 3,157,410.0 557,190.0 3,714,600.0
1 1 5 Miscellaneous L.S. 14% 1,825,600.6 456,002.6 2,281,603.2
1 1 5 Pipeline No.1-2 (3.3m dia., 1.0km)
1 1 5 Open excavation, common m3 54,202 2.7 1.8 4.5 146,344.3 97,562.9 243,907.2
1 1 5 Open excavation, rock m3 6,022 7.5 5.0 12.5 45,168.0 30,112.0 75,280.0
1 1 5 Steel pipe installaiton and fitting m 1,000 1,793.5 316.5 2,110.0 1,793,500.0 316,500.0 2,110,000.0
1 1 5 Concrete for foundation of steel pipe m3 100 34.0 51.0 85.0 3,400.0 5,100.0 8,500.0
1 1 5 Reinforcement ton 5 248.0 372.0 620.0 1,240.0 1,860.0 3,100.0
1 1 5 Backfilling m3 51,399 4.5 3.0 7.5 231,295.5 154,197.0 385,492.5
1 1 5 Valves (air, isolating and drain) L.S. 212,500.0 37,500.0 250,000.0
1 1 5 Sheetpiling m 600 1,283.5 226.5 1,510.0 770,100.0 135,900.0 906,000.0
1 1 5 Miscellaneous L.S. 10% 320,354.8 77,873.2 398,228.0
1 1 5 Valve House
JT-8
Table J6.3 Bill of Quantities (3/12)
Unit Price (US$) Amount (US$)
Item No Description Unit Quantity
F.C L.C. Total F.C L.C. Total
1 1 5 Open excavation for substructure m3 5,121 2.7 1.8 4.5 13,826.7 9,217.8 23,044.5
1 1 5 Backfilling m3 1,407 4.5 3.0 7.5 6,331.5 4,221.0 10,552.5
1 1 5 Concrete for substructure m3 3,321 34.0 51.0 85.0 112,914.0 169,371.0 282,285.0
1 1 5 Superstructure m3 60 34.0 51.0 85.0 2,040.0 3,060.0 5,100.0
1 1 5 Reinforcement ton 398 248.0 372.0 620.0 98,704.0 148,056.0 246,760.0
1 1 5 Valve L.S. 566,100.0 99,900.0 666,000.0
1 1 5 Miscellaneous L.S. 10% 79,991.6 43,382.6 123,374.2
1 1 5 Pipeline to Antipolo Pumping Station
1 1 5 Pipeline No.2 (1.6m dia., 4.2km)
1 1 5 Open excavation, common m3 70,509 2.7 1.8 4.5 190,374.3 126,916.2 317,290.5
1 1 5 Open excavation, rock m3 5,782 7.5 5.0 12.5 43,365.0 28,910.0 72,275.0
1 1 5 Steel pipe installaiton and fitting m 4,200 687.7 121.4 809.0 2,888,130.0 509,670.0 3,397,800.0
1 1 5 Concrete for foundation of steel pipe m3 600 34.0 51.0 85.0 20,400.0 30,600.0 51,000.0
1 1 5 Reinforcement ton 30 248.0 372.0 620.0 7,440.0 11,160.0 18,600.0
1 1 5 Backfilling m3 67,569 4.5 3.0 7.5 304,060.5 202,707.0 506,767.5
1 1 5 Valves (air, isolating and drain) L.S. 161,500.0 28,500.0 190,000.0
1 1 5 Sheetpiling m 840 1,283.5 226.5 1,510.0 1,078,140.0 190,260.0 1,268,400.0
1 1 5 Miscellaneous L.S. 12% 563,209.2 135,446.8 698,656.0
1 1 5 Surge Tank
1 1 5 Open excavation, common m3 500 2.7 1.8 4.5 1,350.0 900.0 2,250.0
1 1 5 Bckfilling m3 200 4.5 3.0 7.5 900.0 600.0 1,500.0
1 1 5 Concrete for structure m3 120 34.0 51.0 85.0 4,080.0 6,120.0 10,200.0
1 1 5 Reinforcement ton 24 248.0 372.0 620.0 5,952.0 8,928.0 14,880.0
1 1 5 Miscelaneous L.S. 40% 4,912.8 6,619.2 11,532.0
1 1 5 Pumping Station #1 & #2 (80MLD)
1 1 5 Open excavation, common m3 77,496 2.7 1.8 4.5 209,239.2 139,492.8 348,732.0
1 1 5 Bckfilling m3 31,079 4.5 3.0 7.5 139,855.5 93,237.0 233,092.5
1 1 5 Compacted gravel for foundation m3 328 5.4 3.6 9.0 1,771.2 1,180.8 2,952.0
1 1 5 Concrete for structure m3 4,979 34.0 51.0 85.0 169,286.0 253,929.0 423,215.0
1 1 5 Reinforcement ton 597 248.0 372.0 620.0 148,175.0 222,262.6 370,437.6
1 1 5 Pump house m2 900 340.0 510.0 850.0 306,000.0 459,000.0 765,000.0
1 1 5 Valve; 1,100mm pcs. 2 36,017.0 6,355.9 42,372.9 72,033.9 12,711.9 84,745.8
1 1 5 Valve; 1,600mm pcs. 1 64,830.5 11,440.7 76,271.2 64,830.5 11,440.7 76,271.2
1 1 5 flexible joint (1,600mm) pcs. 2 22,474.6 3,966.1 26,440.7 44,949.2 7,932.2 52,881.4
1 1 5 Booster pump pcs. 2 1,383,050.9 244,067.8 1,627,118.6 2,766,101.7 488,135.6 3,254,237.3
1 1 5 E & M Works other than booster pump L.S. 4,811,864.4 849,152.5 5,661,016.9
1 1 5 Guard House m2 100 340.0 510.0 850.0 34,000.0 51,000.0 85,000.0
1 1 5 Miscellaneous L.S. 20% 1,753,621.3 517,895.0 2,271,516.3
1 1 5 Antipolo Service Reservoir #1 & #2 (30,000 m3)
1 1 5 Open excavation, common m3 61,555 2.7 1.8 4.5 166,198.5 110,799.0 276,997.5
1 1 5 Bckfilling m3 27,238 4.5 3.0 7.5 122,571.0 81,714.0 204,285.0
1 1 5 Compacted gravel for foundation m3 1,083 5.4 3.6 9.0 5,848.2 3,898.8 9,747.0
1 1 5 Concrete for structure m3 9,026 34.0 51.0 85.0 306,884.0 460,326.0 767,210.0
1 1 5 Reinforcement ton 1,083 248.0 372.0 620.0 268,613.8 402,920.6 671,534.4
1 1 5 Valves L.S. 294,618.5 51,991.5 346,610.0
1 1 5 E & M Works other than valves L.S. 180,401.5 31,835.6 212,237.0
1 1 5 Guard House m2 100 340.0 510.0 850.0 34,000.0 51,000.0 85,000.0
1 1 5 Miscellaneous L.S. 20% 275,827.1 238,897.1 514,724.2
1 1 5 Tunnel No.2 (Steel lined; 3.3m dia., 5.3km )
1 1 5 NATM 4
1 1 5 Open excavation at portal m3 1,000 2.7 1.8 4.5 2,700.0 1,800.0 4,500.0
1 1 5 Tunnel excavation including all temp. m3 35,123 179.5 44.9 224.4 6,305,281.0 1,576,320.2 7,881,601.2
works (steel support, shotcrete, grouting,
power supply, etc.) other than conc.
1 1 5 Lining Concrete (Backfill Concrete) m3 11,933 50.0 75.0 125.0 596,650.0 894,975.0 1,491,625.0
1 1 5 Steel lining ton 2,662 1,062.5 187.5 1,250.0 2,828,375.0 499,125.0 3,327,500.0
1 1 5 Miscellaneous L.S. 5% 486,650.3 148,611.0 635,261.3
1 1 5 NATM 5
1 1 5 Open excavation at portal m3 1,000 2.7 1.8 4.5 2,700.0 1,800.0 4,500.0
1 1 5 Tunnel excavation including all temp. m3 35,123 179.5 44.9 224.4 6,305,281.0 1,576,320.2 7,881,601.2
works (steel support, shotcrete, grouting,
power supply, etc.) other than conc.
1 1 5 Lining Concrete (Backfill Concrete) m3 11,933 50.0 75.0 125.0 596,650.0 894,975.0 1,491,625.0
1 1 5 Steel lining ton 2,662 1,062.5 187.5 1,250.0 2,828,375.0 499,125.0 3,327,500.0
1 1 5 Miscellaneous L.S. 5% 486,650.3 148,611.0 635,261.3
1 1 5 Taytay Service Reservoir #1 (180,000 m3)
1 1 5 Open excavation, common m3 881,871 2.7 1.8 4.5 2,381,051.7 1,587,367.8 3,968,419.5
1 1 5 Bckfilling m3 26,915 4.5 3.0 7.5 121,117.5 80,745.0 201,862.5
1 1 5 Compacted gravel for foundation m3 6,906 5.4 3.6 9.0 37,292.4 24,861.6 62,154.0
1 1 5 Concrete for structure m3 45,131 34.0 51.0 85.0 1,534,454.0 2,301,681.0 3,836,135.0
1 1 5 Reinforcement ton 5,416 248.0 372.0 620.0 1,343,098.6 2,014,647.8 3,357,746.4
1 1 5 Valves L.S. 1,391,478.1 245,555.0 1,637,033.0
1 1 5 E & M Works other than valves L.S. 1,416,337.2 249,941.9 1,666,279.0
1 1 5 Guard House m2 100 340.0 510.0 850.0 34,000.0 51,000.0 85,000.0
1 1 5 Miscellaneous L.S. 20% 1,651,765.9 1,311,160.0 2,962,925.9
JT-9
Table J6.3 Bill of Quantities (4/12)
Unit Price (US$) Amount (US$)
Item No Description Unit Quantity
F.C L.C. Total F.C L.C. Total
1 2 WATER TREATMENT PLANT #1
1 2 1 1 Land Acquisition & Resettlement for WTP #1 and #2
1 2 1 Land Acquisition L.S. 0.0 2,435,096.0 2,435,096.0
1 2 1 Resettlement L.S. 0.0 121,420.4 121,420.4
1 2 2 2 Waterway Facility
1 2 2 Preparatory Works
1 2 2 New Access m 0 180.0 120.0 300.0 0.0 0.0 0.0
1 2 2 Improvement m 2,000 90.0 60.0 150.0 180,000.0 120,000.0 300,000.0
1 2 2 Preparatory Works L.S. 7,244,322.4 3,628,179.1 10,872,501.5
1 2 2 Water Treatment Plant #1 (910 MLD)
1 2 2 Site Formation for #1 & #2
1 2 2 Open excavation,common m3 3,374,640 2.5 1.7 4.2 8,504,092.8 5,669,395.2 14,173,488.0
1 2 2 Open excavation, rock m3 843,660 6.3 4.2 10.5 5,315,058.0 3,543,372.0 8,858,430.0
1 2 2 Embanakment m3 109,200 4.2 2.8 7.0 458,640.0 305,760.0 764,400.0
Power Transmission/Substation Equipment
Transmission Lines L.S. 4,808,115.0 534,235.0 5,342,350.0
Substation Equipment L.S. 2,509,991.1 278,887.9 2,788,879.0
1 2 2 Receiving Well
1 2 2 Open excavation, common m3 9,281 2.7 1.8 4.5 25,058.7 16,705.8 41,764.5
1 2 2 Bckfilling m3 1,030 4.5 3.0 7.5 4,635.0 3,090.0 7,725.0
1 2 2 Compacted gravel for foundation m3 204 5.4 3.6 9.0 1,101.6 734.4 1,836.0
1 2 2 Concrete for structure m3 2,056 34.0 51.0 85.0 69,904.0 104,856.0 174,760.0
1 2 2 Reinforcement ton 247 248.0 372.0 620.0 61,186.6 91,779.8 152,966.4
1 2 2 E & M Works L.S. 1,041,609.6 183,813.5 1,225,423.0
1 2 2 Miscellaneous L.S. 10% 120,349.5 40,098.0 160,447.5
1 2 2 Flocculation & Sedimentation Basin
1 2 2 Open excavation, common m3 247,488 2.7 1.8 4.5 668,217.6 445,478.4 1,113,696.0
1 2 2 Bckfilling m3 17,495 4.5 3.0 7.5 78,727.5 52,485.0 131,212.5
1 2 2 Compacted gravel for foundation m3 6,098 5.4 3.6 9.0 32,929.2 21,952.8 54,882.0
1 2 2 Concrete for structure m3 30,763 34.0 51.0 85.0 1,045,942.0 1,568,913.0 2,614,855.0
1 2 2 Reinforcement ton 3,076 248.0 372.0 620.0 762,922.4 1,144,383.6 1,907,306.0
1 2 2 E & M Works L.S. 4,863,151.8 858,203.3 5,721,355.0
1 2 2 Miscellaneous L.S. 20% 1,490,378.1 818,283.2 2,308,661.3
1 2 2 Filter
1 2 2 Open excavation, common m3 74,858 2.7 1.8 4.5 202,116.6 134,744.4 336,861.0
1 2 2 Bckfilling m3 6,189 4.5 3.0 7.5 27,850.5 18,567.0 46,417.5
1 2 2 Compacted gravel for foundation m3 1,912 5.4 3.6 9.0 10,324.8 6,883.2 17,208.0
1 2 2 Concrete for structure m3 20,265 34.0 51.0 85.0 689,010.0 1,033,515.0 1,722,525.0
1 2 2 Reinforcement ton 2,432 248.0 372.0 620.0 603,086.4 904,629.6 1,507,716.0
1 2 2 E & M Works L.S. 4,807,542.2 848,389.8 5,655,932.0
1 2 2 Micellaneous L.S. 20% 1,267,986.1 589,345.8 1,857,331.9
1 2 2 Clear Water Reservoir
1 2 2 Open excavation, common m3 91,023 2.7 1.8 4.5 245,762.1 163,841.4 409,603.5
1 2 2 Bckfilling m3 5,378 4.5 3.0 7.5 24,201.0 16,134.0 40,335.0
1 2 2 Compacted gravel for foundation m3 3,252 5.4 3.6 9.0 17,560.8 11,707.2 29,268.0
1 2 2 Concrete for structure m3 18,292 34.0 51.0 85.0 621,928.0 932,892.0 1,554,820.0
1 2 2 Reinforcement ton 2,195 248.0 372.0 620.0 544,369.9 816,554.9 1,360,924.8
1 2 2 E & M Works L.S. 1,169,830.4 206,440.7 1,376,271.0
1 2 2 Micellaneous L.S. 10% 262,365.2 214,757.0 477,122.2
1 2 2 Back Wash Water Storage
1 2 2 Open excavation, common m3 22,211 2.7 1.8 4.5 59,969.7 39,979.8 99,949.5
1 2 2 Bckfilling m3 762 4.5 3.0 7.5 3,429.0 2,286.0 5,715.0
1 2 2 Compacted gravel for foundation m3 474 5.4 3.6 9.0 2,559.6 1,706.4 4,266.0
1 2 2 Concrete for structure m3 3,805 34.0 51.0 85.0 129,370.0 194,055.0 323,425.0
1 2 2 Reinforcement ton 457 248.0 372.0 620.0 113,236.8 169,855.2 283,092.0
1 2 2 E & M Works L.S. 74,338.5 13,118.6 87,457.0
1 2 2 Miscellaneous L.S. 20% 76,580.7 84,200.2 160,780.9
1 2 2 Thickening Tank
1 2 2 Open excavation, common m3 20,906 2.7 1.8 4.5 56,446.2 37,630.8 94,077.0
1 2 2 Bckfilling m3 1,831 4.5 3.0 7.5 8,239.5 5,493.0 13,732.5
1 2 2 Compacted gravel for foundation m3 634 5.4 3.6 9.0 3,423.6 2,282.4 5,706.0
1 2 2 Concrete for structure m3 2,647 34.0 51.0 85.0 89,998.0 134,997.0 224,995.0
1 2 2 Reinforcement ton 265 248.0 372.0 620.0 65,720.0 98,580.0 164,300.0
1 2 2 E & M Works L.S. 540,830.4 95,440.7 636,271.0
1 2 2 Miscellaneous L.S. 20% 152,931.5 74,884.8 227,816.3
1 2 2 Sludge Drying Bed
1 2 2 Open excavation, common m3 72,117 2.7 1.8 4.5 194,715.9 129,810.6 324,526.5
1 2 2 Bckfilling m3 4,178 4.5 3.0 7.5 18,801.0 12,534.0 31,335.0
1 2 2 Compacted gravel for foundation m3 3,606 5.4 3.6 9.0 19,472.4 12,981.6 32,454.0
1 2 2 Concrete for structure m3 8,232 34.0 51.0 85.0 279,888.0 419,832.0 699,720.0
1 2 2 Reinforcement ton 247 248.0 372.0 620.0 61,256.0 91,884.0 153,140.0
1 2 2 E & M Works L.S. 14,406.7 2,542.4 16,949.0
1 2 2 Micellaneous L.S. 20% 117,708.0 133,916.9 251,624.9
1 2 2 Others
1 2 2 Office m2 2,000 680.0 1,020.0 1,700.0 1,360,000.0 2,040,000.0 3,400,000.0
1 2 2 Chemicals Handling House m2 2,700 340.0 510.0 850.0 918,000.0 1,377,000.0 2,295,000.0
JT-10
Table J6.3 Bill of Quantities (5/12)
Unit Price (US$) Amount (US$)
Item No Description Unit Quantity
F.C L.C. Total F.C L.C. Total
1 2 2 Chlorination House m2 1,500 340.0 510.0 850.0 510,000.0 765,000.0 1,275,000.0
1 2 2 Generator House m2 600 762.7 84.8 847.5 457,626.0 50,850.0 508,476.0
1 2 2 Guard House m2 150 340.0 510.0 850.0 51,000.0 76,500.0 127,500.0
1 2 2 Connecting pipes and E & M L.S. 8,957,287.8 995,254.2 9,952,542.0
1 2 2 Micellaneous L.S. 30% 3,676,174.1 1,591,381.3 5,267,555.4
JT-11
Table J6.3 Bill of Quantities (6/12)
Unit Price (US$) Amount (US$)
Item No Description Unit Quantity
F.C L.C. Total F.C L.C. Total
2 1 2 Mass concrete for spillway m3 81,500 32.0 48.0 80.0 2,608,000.0 3,912,000.0 6,520,000.0
2 1 2 Spillway gate L.S. 3,196,000.0 564,000.0 3,760,000.0
2 1 2 Stoplog L.S. 93,500.0 16,500.0 110,000.0
2 1 2 Miscellaneous L.S. 10% 5,699,827.6 4,133,324.4 9,833,152.0
2 1 3 3 Agos Hydropower Facility
Preparatory Works
Preparatory Works L.S. 5,830,445.2 1,175,442.2 7,005,887.3
2 1 3 Intake Structure
2 1 3 Open excavation for intake, common m3 5,500 2.7 1.8 4.5 14,850.0 9,900.0 24,750.0
2 1 3 Open excavation for intakey, rock m3 5,500 7.5 5.0 12.5 41,250.0 27,500.0 68,750.0
2 1 3 Backfilling m3 400 4.5 3.0 7.5 1,800.0 1,200.0 3,000.0
2 1 3 Structural concrete for intake structure m3 270 34.0 51.0 85.0 9,180.0 13,770.0 22,950.0
2 1 3 Reinforcement ton 27 248.0 372.0 620.0 6,696.0 10,044.0 16,740.0
2 1 3 Mass concrete for intake m3 40 32.0 48.0 80.0 1,280.0 1,920.0 3,200.0
2 1 3 Trash rack 6m(h) x 3.7m(w)x2nos L.S. 40,800.0 7,200.0 48,000.0
2 1 3 Intake gate 5.0m(h) x 5.0m(w)x1no L.S. 204,000.0 36,000.0 240,000.0
2 1 3 Stoplog 0.3m(h) x 5.0m(w)x10nos L.S. 187,000.0 33,000.0 220,000.0
2 1 3 Gate hoistx2nos L.S. 238,000.0 42,000.0 280,000.0
2 1 3 Miscellaneous L.S. 10% 74,485.6 18,253.4 92,739.0
2 1 3 Headrace Tunnel
2 1 3 Tunnel excavation including all temp. m3 3,700 149.6 37.4 187.0 553,520.0 138,380.0 691,900.0
works (steel support, shotcrete, grouting,
power supply, etc.) other than conc.
2 1 3 Steel support ton 20 1,190.0 210.0 1,400.0 23,800.0 4,200.0 28,000.0
2 1 3 Lining Concrete m3 1,360 50.0 75.0 125.0 68,000.0 102,000.0 170,000.0
2 1 3 Backfill grout m3 13 80.0 120.0 200.0 1,040.0 1,560.0 2,600.0
2 1 3 Reinforcement ton 110 248.0 372.0 620.0 27,280.0 40,920.0 68,200.0
2 1 3 Miscellaneous L.S. 10% 67,364.0 28,706.0 96,070.0
2 1 3 Penstock Line
2 1 3 Tunnel excavation including all temp. m3 17,700 149.6 37.4 187.0 2,647,920.0 661,980.0 3,309,900.0
works (steel support, shotcrete, grouting,
power supply, etc.) other than conc.
2 1 3 Steel support ton 40 1,190.0 210.0 1,400.0 47,600.0 8,400.0 56,000.0
2 1 3 Lining Concrete m3 10,590 50.0 75.0 125.0 529,500.0 794,250.0 1,323,750.0
2 1 3 Steel lining ton 1,220 1,062.5 187.5 1,250.0 1,296,250.0 228,750.0 1,525,000.0
2 1 3 Backfill grout m3 70 80.0 120.0 200.0 5,600.0 8,400.0 14,000.0
2 1 3 Reinforcement ton 850 248.0 372.0 620.0 210,800.0 316,200.0 527,000.0
2 1 3 Miscellaneous L.S. 10% 473,767.0 201,798.0 675,565.0
2 1 3 Powerhouse
2 1 3 Open excavation for substructure, commo m3 36,200 2.7 1.8 4.5 97,740.0 65,160.0 162,900.0
2 1 3 Open excavation for substructure, rock m3 33,600 7.5 5.0 12.5 252,000.0 168,000.0 420,000.0
2 1 3 Backfilling m3 4,400 4.5 3.0 7.5 19,800.0 13,200.0 33,000.0
2 1 3 Concrete for substructure m3 13,800 34.0 51.0 85.0 469,200.0 703,800.0 1,173,000.0
2 1 3 Concrete for superstructure m3 1,590 34.0 51.0 85.0 54,060.0 81,090.0 135,150.0
2 1 3 Reinforcement ton 1,020 248.0 372.0 620.0 252,960.0 379,440.0 632,400.0
2 1 3 Miscellaneous L.S. 10% 114,576.0 141,069.0 255,645.0
2 1 3 Tailrace
2 1 3 Excavation of river deposit m3 2,500 2.7 1.8 4.5 6,750.0 4,500.0 11,250.0
2 1 3 Excavation, common m3 19,000 2.7 1.8 4.5 51,300.0 34,200.0 85,500.0
2 1 3 Open excavation, rock m3 10,300 7.5 5.0 12.5 77,250.0 51,500.0 128,750.0
2 1 3 Concrete slab m3 750 34.0 51.0 85.0 25,500.0 38,250.0 63,750.0
2 1 3 Concrete for wall m3 8,100 34.0 51.0 85.0 275,400.0 413,100.0 688,500.0
2 1 3 Reinforcing bar ton 270 248.0 372.0 620.0 66,960.0 100,440.0 167,400.0
2 1 3 Miscellaneous L.S. 10% 50,316.0 64,199.0 114,515.0
2 1 3 Switchyard
2 1 3 Open excavation, common m3 1,500 2.7 1.8 4.5 4,050.0 2,700.0 6,750.0
2 1 3 Rock embankment m3 52,100 4.2 2.8 7.0 218,820.0 145,880.0 364,700.0
2 1 3 Gravel bedding m3 22,300 5.4 3.6 9.0 120,420.0 80,280.0 200,700.0
2 1 3 Concrete for switchyard equipment m3 15 34.0 51.0 85.0 510.0 765.0 1,275.0
2 1 3 Reinforcement ton 1 248.0 372.0 620.0 297.6 446.4 744.0
2 1 3 Miscellaneous L.S. 10% 34,409.8 23,007.1 57,416.9
2 1 3 Hydromechanical and Hydroelectric Works for Upper Headrace tunnel
2 1 3 Hydromechanical works
2 1 3 Diversion outlet works
2 1 3 Penstock L.S. 1,071,000.0 189,000.0 1,260,000.0
2 1 3 Tailrace gate (Roller gate) with gantry L.S. 280,500.0 49,500.0 330,000.0
crane
2 1 3 Valve L.S. 204,000.0 36,000.0 240,000.0
2 1 3 Overhead Crane (120t) L.S. 467,500.0 82,500.0 550,000.0
2 1 3 Miscellaneous L.S. 10% 202,300.0 35,700.0 238,000.0
2 1 3 Hydroelectrical Work
2 1 3 Generating equipment (Generator, main L.S. 22,770,000.0 2,530,000.0 25,300,000.0
transformer, etc.)
2 1 3 Transmission line L.S. 8,590,497.3 954,499.7 9,544,997.0
2 1 3 Substation & switchyard L.S. 2,637,358.2 293,039.8 2,930,398.0
2 1 3 Miscellaneous L.S. 10% 3,399,785.6 377,754.0 3,777,539.5
JT-12
Table J6.3 Bill of Quantities (7/12)
Unit Price (US$) Amount (US$)
Item No Description Unit Quantity
F.C L.C. Total F.C L.C. Total
2
2
2 2 WATER TREATMENT PLANT #2 + SERVICE RESERVOIRS #2
2 2 Preparatory Works
2 2 Preparatory Works L.S. 5,118,188.3 2,797,851.8 7,916,040.1
2 2 Water Treatment Plant #2 (Expansion 910 MLD)
2 2 Receiving Well
2 2 Open excavation, common m3 9,281 2.7 1.8 4.5 25,058.7 16,705.8 41,764.5
2 2 Bckfilling m3 1,030 4.5 3.0 7.5 4,635.0 3,090.0 7,725.0
2 2 Compacted gravel for foundation m3 204 5.4 3.6 9.0 1,101.6 734.4 1,836.0
2 2 Concrete for structure m3 2,056 34.0 51.0 85.0 69,904.0 104,856.0 174,760.0
2 2 Reinforcement ton 247 248.0 372.0 620.0 61,256.0 91,884.0 153,140.0
2 2 E & M Works L.S. 527,647.7 93,114.3 620,762.0
2 2 Miscellaneous L.S. 10% 68,960.3 31,038.5 99,998.8
2 2 Flocculation & Sedimentation Basin
2 2 Open excavation, common m3 247,488 2.7 1.8 4.5 668,217.6 445,478.4 1,113,696.0
2 2 Bckfilling m3 17,495 4.5 3.0 7.5 78,727.5 52,485.0 131,212.5
2 2 Compacted gravel for foundation m3 6,098 5.4 3.6 9.0 32,929.2 21,952.8 54,882.0
2 2 Concrete for structure m3 30,763 34.0 51.0 85.0 1,045,942.0 1,568,913.0 2,614,855.0
2 2 Reinforcement ton 3,076 248.0 372.0 620.0 762,848.0 1,144,272.0 1,907,120.0
2 2 E & M Works L.S. 4,863,151.8 858,203.3 5,721,355.0
2 2 Miscellaneous L.S. 20% 1,490,363.2 818,260.9 2,308,624.1
2 2 Filter
2 2 Open excavation, common m3 74,858 2.7 1.8 4.5 202,116.6 134,744.4 336,861.0
2 2 Bckfilling m3 6,189 4.5 3.0 7.5 27,850.5 18,567.0 46,417.5
2 2 Compacted gravel for foundation m3 1,912 5.4 3.6 9.0 10,324.8 6,883.2 17,208.0
2 2 Concrete for structure m3 20,265 34.0 51.0 85.0 689,010.0 1,033,515.0 1,722,525.0
2 2 Reinforcement ton 2,432 248.0 372.0 620.0 603,136.0 904,704.0 1,507,840.0
2 2 E & M Works L.S. 4,807,542.2 848,389.8 5,655,932.0
2 2 Micellaneous L.S. 20% 1,267,996.0 589,360.7 1,857,356.7
2 2 Clear Water Reservoir
2 2 Open excavation, common m3 91,023 2.7 1.8 4.5 245,762.1 163,841.4 409,603.5
2 2 Bckfilling m3 5,378 4.5 3.0 7.5 24,201.0 16,134.0 40,335.0
2 2 Compacted gravel for foundation m3 3,252 5.4 3.6 9.0 17,560.8 11,707.2 29,268.0
2 2 Concrete for structure m3 18,292 34.0 51.0 85.0 621,928.0 932,892.0 1,554,820.0
2 2 Reinforcement ton 2,195 248.0 372.0 620.0 544,360.0 816,540.0 1,360,900.0
2 2 E & M Works L.S. 1,005,592.5 177,457.5 1,183,050.0
2 2 Micellaneous L.S. 10% 245,940.4 211,857.2 457,797.7
2 2 Back Wash Water Storage
2 2 Open excavation, common m3 22,211 2.7 1.8 4.5 59,969.7 39,979.8 99,949.5
2 2 Bckfilling m3 762 4.5 3.0 7.5 3,429.0 2,286.0 5,715.0
2 2 Compacted gravel for foundation m3 474 5.4 3.6 9.0 2,559.6 1,706.4 4,266.0
2 2 Concrete for structure m3 3,805 34.0 51.0 85.0 129,370.0 194,055.0 323,425.0
2 2 Reinforcement ton 457 248.0 372.0 620.0 113,336.0 170,004.0 283,340.0
2 2 E & M Works L.S. 74,338.5 13,118.6 87,457.0
2 2 Miscellaneous L.S. 20% 76,600.6 84,230.0 160,830.5
2 2 Thickening Tank
2 2 Open excavation, common m3 20,906 2.7 1.8 4.5 56,446.2 37,630.8 94,077.0
2 2 Bckfilling m3 1,831 4.5 3.0 7.5 8,239.5 5,493.0 13,732.5
2 2 Compacted gravel for foundation m3 634 5.4 3.6 9.0 3,423.6 2,282.4 5,706.0
2 2 Concrete for structure m3 2,647 34.0 51.0 85.0 89,998.0 134,997.0 224,995.0
2 2 Reinforcement ton 265 248.0 372.0 620.0 65,720.0 98,580.0 164,300.0
2 2 E & M Works L.S. 540,830.4 95,440.7 636,271.0
2 2 Miscellaneous L.S. 20% 152,931.5 74,884.8 227,816.3
2 2 Sludge Drying Bed
2 2 Open excavation, common m3 72,117 2.7 1.8 4.5 194,715.9 129,810.6 324,526.5
2 2 Bckfilling m3 4,178 4.5 3.0 7.5 18,801.0 12,534.0 31,335.0
2 2 Compacted gravel for foundation m3 3,606 5.4 3.6 9.0 19,472.4 12,981.6 32,454.0
2 2 Concrete for structure m3 8,232 34.0 51.0 85.0 279,888.0 419,832.0 699,720.0
2 2 Reinforcement ton 247 248.0 372.0 620.0 61,256.0 91,884.0 153,140.0
2 2 E & M Works L.S. 14,406.7 2,542.4 16,949.0
2 2 Micellaneous L.S. 20% 117,708.0 133,916.9 251,624.9
2 2 Others
2 2 Chemicals Handling House m2 2,700 340.0 510.0 850.0 918,000.0 1,377,000.0 2,295,000.0
2 2 Chlorination House m2 1,500 340.0 510.0 850.0 510,000.0 765,000.0 1,275,000.0
2 2 Generator House m2 600 720.3 127.1 847.5 432,204.0 76,272.0 508,476.0
2 2 Connection pipes and E & M L.S. 8,957,287.8 995,254.2 9,952,542.0
2 2 Micellaneous L.S. 30% 3,245,247.5 964,057.9 4,209,305.4
2 2 Taytay Service Reservoir #2 (180,000 m3)
2 2 Open excavation, common m3 291,071 2.7 1.8 4.5 785,891.7 523,927.8 1,309,819.5
2 2 Bckfilling m3 23,415 4.5 3.0 7.5 105,367.5 70,245.0 175,612.5
2 2 Compacted gravel for foundation m3 6,906 5.4 3.6 9.0 37,292.4 24,861.6 62,154.0
2 2 Concrete for structure m3 45,131 34.0 51.0 85.0 1,534,454.0 2,301,681.0 3,836,135.0
2 2 Reinforcement ton 5,416 248.0 372.0 620.0 1,343,168.0 2,014,752.0 3,357,920.0
2 2 Valves L.S. 520,084.4 91,779.6 611,864.0
2 2 E & M Works other than valves L.S. 1,083,180.5 191,149.5 1,274,330.0
JT-13
Table J6.3 Bill of Quantities (8/12)
Unit Price (US$) Amount (US$)
Item No Description Unit Quantity
F.C L.C. Total F.C L.C. Total
2 2 Miscellaneous L.S. 20% 1,081,887.7 1,043,679.3 2,125,567.0
0.0
3 1 STAGE 2-2 KALIWA-ANGONO 2nd WATERWAY + WTP #3 & #4
3 1 2ND WATERWAY (excluding WTP #3)
3 1 1 1 Land Acquisition & Resettlement excluding WTPs
3 1 1 Land Acquisition L.S. 0.0 5,977,163.0 5,977,163.0
3 1 1 Resettlement L.S. 0.0 288,322.5 288,322.5
3 1 2 2 Kaliwa Low Dam (Temporary)
3 1 2 Partial removal of dam body m3 66,570 3.6 2.4 6.0 239,652.0 159,768.0 399,420.0
3 1 2 Miscellaneous L.S. 0.0 0.0 0.0
3 1 3 3 Waterway to Valve House No.1
3 1 3 Preparatory Works
3 1 3 Preparatory Works L.S. 10,745,154.2 3,672,136.2 14,417,290.3
3 1 3 Tunnel No.1
3 1 3 Adit 1
3 1 3 Modification L.S. 40,000.0 10,000.0 50,000.0
3 1 3 Adit 2
3 1 3 Modification L.S. 40,000.0 10,000.0 50,000.0
3 1 3 Adit 3
3 1 3 Modification L.S. 40,000.0 10,000.0 50,000.0
3 1 3 NATM 1
3 1 3 Open excavation at portal m3 2.7 1.8 4.5 0.0 0.0 0.0
3 1 3 Tunnel excavation including all temp. m3 43,150 149.6 37.4 187.0 6,455,240.0 1,613,810.0 8,069,050.0
works (steel support, shotcrete, grouting,
power supply, etc.) other than conc.
3 1 3 Lining Concrete m3 14,768 50.0 75.0 125.0 738,400.0 1,107,600.0 1,846,000.0
3 1 3 Miscellaneous L.S. 5% 359,682.0 136,070.5 495,752.5
3 1 3 NATM 2
3 1 3 Open excavation at portal m3 0 2.7 1.8 4.5 0.0 0.0 0.0
3 1 3 Tunnel excavation including all temp. m3 50,317 149.6 37.4 187.0 7,527,423.2 1,881,855.8 9,409,279.0
works (steel support, shotcrete, grouting,
power supply, etc.) other than conc.
3 1 3 Lining Concrete m3 17,221 50.0 75.0 125.0 861,050.0 1,291,575.0 2,152,625.0
3 1 3 Miscellaneous L.S. 5% 419,423.7 158,671.5 578,095.2
3 1 3 NATM 3
3 1 3 Open excavation at portal m3 1,000 2.7 1.8 4.5 2,700.0 1,800.0 4,500.0
3 1 3 Tunnel excavation including all temp. m3 66,114 149.6 37.4 187.0 9,890,654.4 2,472,663.6 12,363,318.0
works (steel support, shotcrete, grouting,
power supply, etc.) other than conc.
3 1 3 Lining Concrete m3 22,627 50.0 75.0 125.0 1,131,350.0 1,697,025.0 2,828,375.0
3 1 3 Steel lining ton 80 1,062.5 187.5 1,250.0 85,000.0 15,000.0 100,000.0
3 1 3 Miscellaneous L.S. 5% 555,485.2 209,324.4 764,809.7
3 1 3 TBM 1
3 1 3 Open excavation at portal m3 0 2.7 1.8 4.5 0.0 0.0 0.0
3 1 3 Tunnel excavation including TBM and m3 163,205 237.6 59.4 297.0 38,777,508.0 9,694,377.0 48,471,885.0
all temp. works (steel support, shotcrete,
grouting, power supply, etc. other than
conc. lining)
3 1 3 Lining Concrete m3 49,868 50.0 75.0 125.0 2,493,400.0 3,740,100.0 6,233,500.0
3 1 3 Miscellaneous L.S. 5% 2,063,545.4 671,723.9 2,735,269.3
3 1 3 TBM 2
3 1 3 Open excavation at portal m3 0 2.7 1.8 4.5 0.0 0.0 0.0
3 1 3 Tunnel excavation including TBM and m3 68,025 237.6 59.4 297.0 16,162,740.0 4,040,685.0 20,203,425.0
all temp. works (steel support, shotcrete,
grouting, power supply, etc.) other than
conc. Lining
3 1 3 Lining Concrete m3 20,785 50.0 75.0 125.0 1,039,250.0 1,558,875.0 2,598,125.0
3 1 3 Miscellaneous L.S. 5% 860,099.5 279,978.0 1,140,077.5
3 1 4 4 Valve House No.1
3 1 4 Preparatory Works
3 1 4 Preparatory Works L.S. 132,775.2 14,752.8 147,528.0
3 1 4 Valve House Portion
3 1 4 Mechanical works L.S. 972,000.0 108,000.0 1,080,000.0
3 1 4 Miscellaneous L.S. 10% 97,200.0 10,800.0 108,000.0
3 1 4 Tailrace Portion
3 1 4 Hydroelectrical works L.S 32,400.0 3,600.0 36,000.0
3 1 4 Miscellaneous L.S. 15% 4,860.0 540.0 5,400.0
3 1 5 5 Waterway from WTP to Reservoir
3 1 5 Preparatory Works
3 1 5 Preparatory Works L.S. 6,798,105.0 2,671,956.5 9,470,061.5
3 1 5 Pipeline No.1-1 (3.4m dia., 4.1km)
3 1 5 Open excavation, common m3 225,332 2.7 1.8 4.5 608,396.7 405,597.8 1,013,994.5
3 1 5 Open excavation, rock m3 25,037 7.5 5.0 12.5 187,776.8 125,184.5 312,961.3
3 1 5 Steel pipe installaiton and fitting m 3,900 1,893.0 334.1 2,227.0 7,382,505.0 1,302,795.0 8,685,300.0
3 1 5 Concrete for foundation of steel pipe m3 1,600 34.0 51.0 85.0 54,400.0 81,600.0 136,000.0
3 1 5 Reinforcement ton 80 248.0 372.0 620.0 19,840.0 29,760.0 49,600.0
JT-14
Table J6.3 Bill of Quantities (9/12)
Unit Price (US$) Amount (US$)
Item No Description Unit Quantity
F.C L.C. Total F.C L.C. Total
3 1 5 Backfilling m3 211,908 4.5 3.0 7.5 953,586.0 635,724.0 1,589,310.0
3 1 5 Valves (air, isolating and drain) L.S. 297,500.0 52,500.0 350,000.0
3 1 5 Sheetpiling m 2,340 518.5 91.5 610.0 1,213,290.0 214,110.0 1,427,400.0
3 1 5 Miscellaneous L.S. 14% 1,500,421.2 398,618.0 1,899,039.2
3 1 5 Pipeline No.1-2 (3.3m dia., 1.0km)
3 1 5 Open excavation, common m3 54,202 2.7 1.8 4.5 146,344.3 97,562.9 243,907.2
3 1 5 Open excavation, rock m3 6,022 7.5 5.0 12.5 45,168.0 30,112.0 75,280.0
3 1 5 Steel pipe installaiton and fitting m 800 1,793.5 316.5 2,110.0 1,434,800.0 253,200.0 1,688,000.0
3 1 5 Concrete for foundation of steel pipe m3 100 34.0 51.0 85.0 3,400.0 5,100.0 8,500.0
3 1 5 Reinforcement ton 1 248.0 372.0 620.0 248.0 372.0 620.0
3 1 5 Backfilling m3 51,399 4.5 3.0 7.5 231,295.5 154,197.0 385,492.5
3 1 5 Valves (air, isolating and drain) L.S. 212,500.0 37,500.0 250,000.0
3 1 5 Sheetpiling m 480 544.9 96.2 641.0 261,528.0 46,152.0 307,680.0
3 1 5 Miscellaneous L.S. 10% 233,528.4 62,419.6 295,948.0
3 1 5 Pipeline to Antipolo Pumping Station
3 1 5 Pipeline No.2 (1.6m dia., 4.2km)
3 1 5 Open excavation, common m3 70,509 2.7 1.8 4.5 190,374.3 126,916.2 317,290.5
3 1 5 Open excavation, rock m3 5,782 7.5 5.0 12.5 43,365.0 28,910.0 72,275.0
3 1 5 Steel pipe installaiton and fitting m 4,200 687.7 121.4 809.0 2,888,130.0 509,670.0 3,397,800.0
3 1 5 Concrete for foundation of steel pipe m3 600 34.0 51.0 85.0 20,400.0 30,600.0 51,000.0
3 1 5 Reinforcement ton 1 248.0 372.0 620.0 248.0 372.0 620.0
3 1 5 Backfilling m3 67,569 4.5 3.0 7.5 304,060.5 202,707.0 506,767.5
3 1 5 Valves (air, isolating and drain) L.S. 212,500.0 37,500.0 250,000.0
3 1 5 Sheetpiling m 840 518.5 91.5 610.0 435,540.0 76,860.0 512,400.0
3 1 5 Miscellaneous L.S. 10% 409,461.8 101,353.5 510,815.3
3 1 5 Surge Tank
3 1 5 Open excavation, common m3 500 2.7 1.8 4.5 1,350.0 900.0 2,250.0
3 1 5 Bckfilling m3 200 4.5 3.0 7.5 900.0 600.0 1,500.0
3 1 5 Concrete for structure m3 120 34.0 51.0 85.0 4,080.0 6,120.0 10,200.0
3 1 5 Reinforcement ton 24 248.0 372.0 620.0 5,952.0 8,928.0 14,880.0
3 1 5 Miscelaneous L.S. 40% 4,912.8 6,619.2 11,532.0
3 1 5 Pumping Station (installation of additional pumps)
3 1 5 Booster pump pcs. 3 1,383,050.9 244,067.8 1,627,118.6 4,149,152.6 732,203.4 4,881,356.0
3 1 5 Miscellaneous L.S. 15% 622,372.9 109,830.5 732,203.4
3 1 5 Pipeline to Antipolo Service Reservoir
3 1 5 Antipolo Service Reservoir #3 (Expansion 30,000 m3 x 2 units)
3 1 5 Open excavation, common m3 155,710 2.7 1.8 4.5 420,417.0 280,278.0 700,695.0
3 1 5 Bckfilling m3 35,276 4.5 3.0 7.5 158,742.0 105,828.0 264,570.0
3 1 5 Compacted gravel for foundation m3 2,166 5.4 3.6 9.0 11,696.4 7,797.6 19,494.0
3 1 5 Concrete for structure m3 18,052 34.0 51.0 85.0 613,768.0 920,652.0 1,534,420.0
3 1 5 Reinforcement ton 2,166 248.0 372.0 620.0 537,168.0 805,752.0 1,342,920.0
3 1 5 Valves L.S. 484,787.3 85,550.7 570,338.0
3 1 5 E & M Works other than valves L.S. 247,047.4 43,596.6 290,644.0
3 1 5 Miscellaneous L.S. 20% 494,725.2 449,891.0 944,616.2
3 1 5 Tunnel No.2 (Steel lined; 3.3m dia., 5.3km )
3 1 5 NATM 4
3 1 5 Open excavation at portal m3 1,000 2.7 1.8 4.5 2,700.0 1,800.0 4,500.0
3 1 5 Tunnel excavation including all temp. m3 35,123 179.5 44.9 224.4 6,305,281.0 1,576,320.2 7,881,601.2
works (steel support, shotcrete, grouting,
power supply, etc.) other than conc.
3 1 5 Lining Concrete (Backfill Concrete) m3 11,933 50.0 75.0 125.0 596,650.0 894,975.0 1,491,625.0
3 1 5 Steel lining ton 2,662 1,062.5 187.5 1,250.0 2,828,375.0 499,125.0 3,327,500.0
3 1 5 Miscellaneous L.S. 5% 486,650.3 148,611.0 635,261.3
3 1 5 NATM 5
3 1 5 Open excavation at portal m3 1,000 2.7 1.8 4.5 2,700.0 1,800.0 4,500.0
3 1 5 Tunnel excavation including all temp. m3 35,123 179.5 44.9 224.4 6,305,281.0 1,576,320.2 7,881,601.2
works (steel support, shotcrete, grouting,
power supply, etc.) other than conc.
3 1 5 Lining Concrete (Backfill Concrete) m3 11,933 50.0 75.0 125.0 596,650.0 894,975.0 1,491,625.0
3 1 5 Steel lining ton 2,662 1,062.5 187.5 1,250.0 2,828,375.0 499,125.0 3,327,500.0
3 1 5 Miscellaneous L.S. 5% 486,650.3 148,611.0 635,261.3
3 1 5 Taytay Service Reservoir #3 (Expansion 180,000 m3)
3 1 5 Open excavation, common m3 1,104,271 2.5 1.7 4.2 2,782,762.9 1,855,175.3 4,637,938.2
3 1 5 Bckfilling m3 35,215 4.5 3.0 7.5 158,467.5 105,645.0 264,112.5
3 1 5 Compacted gravel for foundation m3 6,906 5.4 3.6 9.0 37,292.4 24,861.6 62,154.0
3 1 5 Concrete for structure m3 45,131 34.0 51.0 85.0 1,534,454.0 2,301,681.0 3,836,135.0
3 1 5 Reinforcement ton 5,416 248.0 372.0 620.0 1,343,168.0 2,014,752.0 3,357,920.0
3 1 5 Valves L.S. 1,391,478.1 245,555.0 1,637,033.0
3 1 5 E & M Works other than valves L.S. 1,083,180.5 191,149.5 1,274,330.0
3 1 5 Miscellaneous L.S. 10% 833,080.3 673,881.9 1,506,962.3
3
3 2 WATER TREATMENT PLANT #3
3 2 1 1 Land Acquisition & Resettlement for WTP #3 & #4
3 2 1 Land Acquisition L.S. 0.0 2,406,250.0 2,406,250.0
3 2 1 Resettlement L.S. 0.0 1,524,814.4 1,524,814.4
3 2 2 2 Waterway Facility
JT-15
Table J6.3 Bill of Quantities (10/12)
Unit Price (US$) Amount (US$)
Item No Description Unit Quantity
F.C L.C. Total F.C L.C. Total
3 2 2 Preparatory Works
3 2 2 Preparatory Works L.S. 7,145,818.6 3,933,844.1 11,079,662.8
3 2 2 Water Treatment Plant #3 (Expamsion 910 MLD)
3 2 2 Site Formation for #3 & #4
3 2 2 Open excavation,common m3 5,457,920 2.5 1.7 4.2 13,753,958.4 9,169,305.6 22,923,264.0
3 2 2 Open excavation, rock m3 1,364,480 6.3 4.2 10.5 8,596,224.0 5,730,816.0 14,327,040.0
3 2 2 Embanakment m3 384,800 4.2 2.8 7.0 1,616,160.0 1,077,440.0 2,693,600.0
Power Transmission/Substation Equipment
Transmission Lines L.S. 0.0
Substation Equipment L.S. 251,069.4 27,896.6 278,966.0
3 2 2 Receiving Well
3 2 2 Open excavation, common m3 9,281 2.7 1.8 4.5 25,058.7 16,705.8 41,764.5
3 2 2 Bckfilling m3 1,030 4.5 3.0 7.5 4,635.0 3,090.0 7,725.0
3 2 2 Compacted gravel for foundation m3 204 5.4 3.6 9.0 1,101.6 734.4 1,836.0
3 2 2 Concrete for structure m3 2,056 34.0 51.0 85.0 69,904.0 104,856.0 174,760.0
3 2 2 Reinforcement ton 247 248.0 372.0 620.0 61,256.0 91,884.0 153,140.0
3 2 2 E & M Works L.S. 1,041,609.6 183,813.5 1,225,423.0
3 2 2 Miscellaneous L.S. 10% 120,356.5 40,108.4 160,464.9
3 2 2 Flocculation & Sedimentation Basin
3 2 2 Open excavation, common m3 247,488 2.7 1.8 4.5 668,217.6 445,478.4 1,113,696.0
3 2 2 Bckfilling m3 17,495 4.5 3.0 7.5 78,727.5 52,485.0 131,212.5
3 2 2 Compacted gravel for foundation m3 6,098 5.4 3.6 9.0 32,929.2 21,952.8 54,882.0
3 2 2 Concrete for structure m3 30,763 34.0 51.0 85.0 1,045,942.0 1,568,913.0 2,614,855.0
3 2 2 Reinforcement ton 3,076 248.0 372.0 620.0 762,848.0 1,144,272.0 1,907,120.0
3 2 2 E & M Works L.S. 4,863,151.8 858,203.3 5,721,355.0
3 2 2 Miscellaneous L.S. 20% 1,490,363.2 818,260.9 2,308,624.1
3 2 2 Filter
3 2 2 Open excavation, common m3 74,858 2.7 1.8 4.5 202,116.6 134,744.4 336,861.0
3 2 2 Bckfilling m3 6,189 4.5 3.0 7.5 27,850.5 18,567.0 46,417.5
3 2 2 Compacted gravel for foundation m3 1,912 5.4 3.6 9.0 10,324.8 6,883.2 17,208.0
3 2 2 Concrete for structure m3 20,265 34.0 51.0 85.0 689,010.0 1,033,515.0 1,722,525.0
3 2 2 Reinforcement ton 2,432 248.0 372.0 620.0 603,136.0 904,704.0 1,507,840.0
3 2 2 E & M Works L.S. 4,326,355.5 763,474.5 5,089,830.0
3 2 2 Micellaneous L.S. 20% 1,171,758.7 572,377.6 1,744,136.3
3 2 2 Clear Water Reservoir
3 2 2 Open excavation, common m3 91,023 2.7 1.8 4.5 245,762.1 163,841.4 409,603.5
3 2 2 Bckfilling m3 5,378 4.5 3.0 7.5 24,201.0 16,134.0 40,335.0
3 2 2 Compacted gravel for foundation m3 3,252 5.4 3.6 9.0 17,560.8 11,707.2 29,268.0
3 2 2 Concrete for structure m3 18,292 34.0 51.0 85.0 621,928.0 932,892.0 1,554,820.0
3 2 2 Reinforcement ton 2,195 248.0 372.0 620.0 544,360.0 816,540.0 1,360,900.0
3 2 2 E & M Works L.S. 1,246,185.9 219,915.2 1,466,101.0
3 2 2 Micellaneous L.S. 10% 269,999.8 216,103.0 486,102.8
3 2 2 Back Wash Water Storage
3 2 2 Open excavation, common m3 22,211 2.7 1.8 4.5 59,969.7 39,979.8 99,949.5
3 2 2 Bckfilling m3 762 4.5 3.0 7.5 3,429.0 2,286.0 5,715.0
3 2 2 Compacted gravel for foundation m3 474 5.4 3.6 9.0 2,559.6 1,706.4 4,266.0
3 2 2 Concrete for structure m3 3,805 34.0 51.0 85.0 129,370.0 194,055.0 323,425.0
3 2 2 Reinforcement ton 457 248.0 372.0 620.0 113,336.0 170,004.0 283,340.0
3 2 2 E & M Works L.S. 74,338.5 13,118.6 87,457.0
3 2 2 Miscellaneous L.S. 20% 76,600.6 84,230.0 160,830.5
3 2 2 Thickening Tank
3 2 2 Open excavation, common m3 20,906 2.7 1.8 4.5 56,446.2 37,630.8 94,077.0
3 2 2 Bckfilling m3 1,831 4.5 3.0 7.5 8,239.5 5,493.0 13,732.5
3 2 2 Compacted gravel for foundation m3 634 5.4 3.6 9.0 3,423.6 2,282.4 5,706.0
3 2 2 Concrete for structure m3 2,647 34.0 51.0 85.0 89,998.0 134,997.0 224,995.0
3 2 2 Reinforcement ton 265 248.0 372.0 620.0 65,720.0 98,580.0 164,300.0
3 2 2 E & M Works L.S. 540,830.4 95,440.7 636,271.0
3 2 2 Miscellaneous L.S. 20% 152,931.5 74,884.8 227,816.3
3 2 2 Sludge Drying Bed
3 2 2 Open excavation, common m3 72,117 2.7 1.8 4.5 194,715.9 129,810.6 324,526.5
3 2 2 Bckfilling m3 4,178 4.5 3.0 7.5 18,801.0 12,534.0 31,335.0
3 2 2 Compacted gravel for foundation m3 3,606 5.4 3.6 9.0 19,472.4 12,981.6 32,454.0
3 2 2 Concrete for structure m3 8,232 34.0 51.0 85.0 279,888.0 419,832.0 699,720.0
3 2 2 Reinforcement ton 247 248.0 372.0 620.0 61,256.0 91,884.0 153,140.0
3 2 2 E & M Works L.S. 14,403.3 2,541.8 16,945.0
3 2 2 Micellaneous L.S. 20% 117,707.3 133,916.8 251,624.1
3 2 2 Others
3 2 2 Chemicals Handling House m2 2,700 340.0 510.0 850.0 918,000.0 1,377,000.0 2,295,000.0
3 2 2 Chlorination House m2 1,500 340.0 510.0 850.0 510,000.0 765,000.0 1,275,000.0
3 2 2 Generator House m2 600 720.3 127.1 847.5 432,204.0 76,272.0 508,476.0
3 2 2 Connecting pipes and E & M L.S. 8,957,287.8 995,254.2 9,952,542.0
3 2 2 Micellaneous L.S. 20% 2,163,498.4 642,705.2 2,806,203.6
3
3 3 WATER TREATMENT PLANT #4 + SERVICE RESERVOIRS #4
3 3 Waterway Facility
3 3 Preparatory Works
JT-16
Table J6.3 Bill of Quantities (11/12)
Unit Price (US$) Amount (US$)
Item No Description Unit Quantity
F.C L.C. Total F.C L.C. Total
3 3 Preparatory Works L.S. 7,309,282.9 3,659,924.3 10,969,207.2
3 3 Water Treatment Plant #4 (Expansion 910 MLD)
3 3 Receiving Well
3 3 Open excavation, common m3 9,281 2.7 1.8 4.5 25,058.7 16,705.8 41,764.5
3 3 Bckfilling m3 1,030 4.5 3.0 7.5 4,635.0 3,090.0 7,725.0
3 3 Compacted gravel for foundation m3 204 5.4 3.6 9.0 1,101.6 734.4 1,836.0
3 3 Concrete for structure m3 2,056 34.0 51.0 85.0 69,904.0 104,856.0 174,760.0
3 3 Reinforcement ton 247 248.0 372.0 620.0 61,256.0 91,884.0 153,140.0
3 3 E & M Works L.S. 486,228.1 85,805.0 572,033.0
3 3 Miscellaneous L.S. 10% 64,818.3 30,307.5 95,125.9
3 3 Flocculation & Sedimentation Basin
3 3 Open excavation, common m3 247,488 2.7 1.8 4.5 668,217.6 445,478.4 1,113,696.0
3 3 Bckfilling m3 17,495 4.5 3.0 7.5 78,727.5 52,485.0 131,212.5
3 3 Compacted gravel for foundation m3 6,098 5.4 3.6 9.0 32,929.2 21,952.8 54,882.0
3 3 Concrete for structure m3 30,763 34.0 51.0 85.0 1,045,942.0 1,568,913.0 2,614,855.0
3 3 Reinforcement ton 3,076 248.0 372.0 620.0 762,848.0 1,144,272.0 1,907,120.0
3 3 E & M Works L.S. 4,863,151.8 858,203.3 5,721,355.0
3 3 Miscellaneous L.S. 20% 1,490,363.2 818,260.9 2,308,624.1
3 3 Filter
3 3 Open excavation, common m3 74,858 2.7 1.8 4.5 202,116.6 134,744.4 336,861.0
3 3 Bckfilling m3 6,189 4.5 3.0 7.5 27,850.5 18,567.0 46,417.5
3 3 Compacted gravel for foundation m3 1,912 5.4 3.6 9.0 10,324.8 6,883.2 17,208.0
3 3 Concrete for structure m3 20,265 34.0 51.0 85.0 689,010.0 1,033,515.0 1,722,525.0
3 3 Reinforcement ton 2,432 248.0 372.0 620.0 603,136.0 904,704.0 1,507,840.0
3 3 E & M Works L.S. 4,807,542.2 848,389.8 5,655,932.0
3 3 Micellaneous L.S. 20% 1,267,996.0 589,360.7 1,857,356.7
3 3 Clear Water Reservoir
3 3 Open excavation, common m3 91,023 2.7 1.8 4.5 245,762.1 163,841.4 409,603.5
3 3 Bckfilling m3 5,378 4.5 3.0 7.5 24,201.0 16,134.0 40,335.0
3 3 Compacted gravel for foundation m3 3,252 5.4 3.6 9.0 17,560.8 11,707.2 29,268.0
3 3 Concrete for structure m3 18,292 34.0 51.0 85.0 621,928.0 932,892.0 1,554,820.0
3 3 Reinforcement ton 2,195 248.0 372.0 620.0 544,360.0 816,540.0 1,360,900.0
3 3 E & M Works L.S. 1,169,830.4 206,440.7 1,376,271.0
3 3 Micellaneous L.S. 10% 262,364.2 214,755.5 477,119.8
3 3 Back Wash Water Storage
3 3 Open excavation, common m3 22,211 2.7 1.8 4.5 59,969.7 39,979.8 99,949.5
3 3 Bckfilling m3 762 4.5 3.0 7.5 3,429.0 2,286.0 5,715.0
3 3 Compacted gravel for foundation m3 474 5.4 3.6 9.0 2,559.6 1,706.4 4,266.0
3 3 Concrete for structure m3 3,805 34.0 51.0 85.0 129,370.0 194,055.0 323,425.0
3 3 Reinforcement ton 457 248.0 372.0 620.0 113,336.0 170,004.0 283,340.0
3 3 E & M Works L.S. 74,338.5 13,118.6 87,457.0
3 3 Miscellaneous L.S. 20% 76,600.6 84,230.0 160,830.5
3 3 Thickening Tank
3 3 Open excavation, common m3 20,906 2.7 1.8 4.5 56,446.2 37,630.8 94,077.0
3 3 Bckfilling m3 1,831 4.5 3.0 7.5 8,239.5 5,493.0 13,732.5
3 3 Compacted gravel for foundation m3 634 5.4 3.6 9.0 3,423.6 2,282.4 5,706.0
3 3 Concrete for structure m3 2,647 34.0 51.0 85.0 89,998.0 134,997.0 224,995.0
3 3 Reinforcement ton 265 248.0 372.0 620.0 65,720.0 98,580.0 164,300.0
3 3 E & M Works L.S. 540,830.4 95,440.7 636,271.0
3 3 Miscellaneous L.S. 20% 152,931.5 74,884.8 227,816.3
3 3 Sludge Drying Bed
3 3 Open excavation, common m3 72,117 2.7 1.8 4.5 194,715.9 129,810.6 324,526.5
3 3 Bckfilling m3 4,178 4.5 3.0 7.5 18,801.0 12,534.0 31,335.0
3 3 Compacted gravel for foundation m3 3,606 5.4 3.6 9.0 19,472.4 12,981.6 32,454.0
3 3 Concrete for structure m3 8,232 34.0 51.0 85.0 279,888.0 419,832.0 699,720.0
3 3 Reinforcement ton 247 248.0 372.0 620.0 61,256.0 91,884.0 153,140.0
3 3 E & M Works L.S. 14,406.7 2,542.4 16,949.0
3 3 Micellaneous L.S. 20% 117,708.0 133,916.9 251,624.9
3 3 Others
3 3 Chemicals Handling House m2 2,700 340.0 510.0 850.0 918,000.0 1,377,000.0 2,295,000.0
3 3 Chlorination House m2 1,500 340.0 510.0 850.0 510,000.0 765,000.0 1,275,000.0
3 3 Generator House m2 600 722.5 127.5 850.0 433,500.0 76,500.0 510,000.0
3 3 Guard House m2 150 340.0 510.0 850.0 51,000.0 76,500.0 127,500.0
3 3 Connection pipes and E & M works L.S. 8,957,287.8 995,254.2 9,952,542.0
3 3 Micellaneous L.S. 20% 2,173,957.6 658,050.8 2,832,008.4
3 3 Pumping Station (Expansion 340 MLD)
3 3 Open excavation, common m3 11,896 2.7 1.8 4.5 32,119.2 21,412.8 53,532.0
3 3 Bckfilling m3 2,279 4.5 3.0 7.5 10,255.5 6,837.0 17,092.5
3 3 Compacted gravel for foundation m3 328 5.4 3.6 9.0 1,771.2 1,180.8 2,952.0
3 3 Concrete for structure m3 4,979 34.0 51.0 85.0 169,286.0 253,929.0 423,215.0
3 3 Reinforcement ton 597 248.0 372.0 620.0 148,175.0 222,262.6 370,437.6
3 3 Pump house m2 900 340.0 510.0 850.0 306,000.0 459,000.0 765,000.0
3 3 Valve; 1,100mm pcs. 2 36,017.0 6,355.9 42,372.9 72,033.9 12,711.9 84,745.8
3 3 Valve; 1,600mm pcs. 1 64,830.5 11,440.7 76,271.2 64,830.5 11,440.7 76,271.2
3 3 flexible joint (1,600mm) pcs. 2 22,474.6 3,966.1 26,440.7 44,949.2 7,932.2 52,881.4
3 3 Booster pump pcs. 5 1,383,050.9 244,067.8 1,627,118.6 6,915,254.3 1,220,339.0 8,135,593.3
JT-17
Table J6.3 Bill of Quantities (12/12)
Unit Price (US$) Amount (US$)
Item No Description Unit Quantity
F.C L.C. Total F.C L.C. Total
3 3 E & M Works other than booster pump L.S. 4,811,864.4 849,152.5 5,661,016.9
3 3 Miscellaneous L.S. 20% 2,515,307.8 613,239.7 3,128,547.5
3 3 Antipolo Service Reservoir #4 (Expansion 30,000 m3 x 3 units)
3 3 Open excavation, common m3 136,665 2.7 1.8 4.5 368,995.5 245,997.0 614,992.5
3 3 Bckfilling m3 9,714 4.5 3.0 7.5 43,713.0 29,142.0 72,855.0
3 3 Compacted gravel for foundation m3 3,249 5.4 3.6 9.0 17,544.6 11,696.4 29,241.0
3 3 Concrete for structure m3 27,078 34.0 51.0 85.0 920,652.0 1,380,978.0 2,301,630.0
3 3 Reinforcement ton 3,249 248.0 372.0 620.0 805,752.0 1,208,628.0 2,014,380.0
3 3 Valves L.S. 710,974.0 125,466.0 836,440.0
3 3 E & M Works other than valves L.S. 583,258.1 102,927.9 686,186.0
3 3 Miscellaneous L.S. 20% 690,177.8 620,967.1 1,311,144.9
3 3 Taytay Service Reservoir #4 (Expansion 180,000 m3)
3 3 Open excavation, common m3 291,071 2.7 1.8 4.5 785,891.7 523,927.8 1,309,819.5
3 3 Bckfilling m3 23,415 4.5 3.0 7.5 105,367.5 70,245.0 175,612.5
3 3 Compacted gravel for foundation m3 6,906 5.4 3.6 9.0 37,292.4 24,861.6 62,154.0
3 3 Concrete for structure m3 45,131 34.0 51.0 85.0 1,534,454.0 2,301,681.0 3,836,135.0
3 3 Reinforcement ton 5,416 248.0 372.0 620.0 1,343,168.0 2,014,752.0 3,357,920.0
3 3 Valves L.S. 520,084.4 91,779.6 611,864.0
3 3 E & M Works other than valves L.S. 1,008,264.9 177,929.1 1,186,194.0
3 3 Miscellaneous L.S. 20% 1,066,904.6 1,041,035.2 2,107,939.8
JT-18
Table J6.4 Summary of Annual Disbursement Schedule
(Unit: 106 US$)
Year Stage 1 Stage 2-1 Stage 2-2 Total
2005 5 5
2006 7 1 9
2007 9 1 10
2008 9 3 12
2009 77 3 79
2010 141 3 144
2011 165 64 229
2012 169 174 343
2013 107 152 258
2014 141 2 142
2015 251 58 310
2016 190 143 332
2017 179 179
2018 173 173
2019 98 98
2020 0 0
2021 109 109
2022 111 111
Total 690 982 871 2,543
Note: Excluding price contingency and tax
JT-19
Description 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Stage 1
Land Acquisition and Compensation
Kaliwa Low Dam
Access and preparatory works
Kaliwa Low Dam
Intake structure
Waterway to WTP
Access and preparatory works
Tunnel no.1
Waterway from WTP to Reservoirs
Access and preparatory works
Pipeline No.1-1
Pipeline No.1-2
Valve House
Pipeline No.2
Pumping Station
Antipolo Service Reservoir #1
Tunnel No.2
Taytay Service Reservoir #1
Water Treatment Plant #1
Land Acquisition and Compensation
Access and preparatory works
Site Formation
Structural Works and E & M
Stage 2-1
Land Acquisition and Compensation
Agos Dam
Access and preparatory works
Agos Dam
Diversion Works
Main Dam
Spillway
Agos Hydropower Facility
Intake Structure
Headrace Tunnel
Surge Tank
Tailrace
Penstock Line
Power House
Switchyard
Hydro-mechanical works
Hydro-electrical Works
JF-2
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
Description Quantity Unit Rate Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75
Diversion Tunnel
Right side Gate Closure (Right side diversion tunnel)
Upstream Portal 3.0 Water diversion
NATM 800 m 80 10.0 Plug Concrete
Downstream Portal 3.0
NATM 800 m 80 10.0
Left side Gate Closure (Left side diversion tunnel)
Upstream Portal 3.0 Water diversion
NATM 800 m 80 10.0 Plug Concrete
Connecting Tunnel
Downstream Portal 3.0
NATM 450 m 80 5.6
Upstream Cofferdam
Excavation 1,200 m3 100,000 0.0
To be completed within the dry season
Embankment 900,000 m3 100,000 9.0
Main Dam Excavated material to Cofferdams Excavated material to Main Dam embankment
JF- 3
Plunge Pool
Earthworks
Structural Works
Power House
Earthworks
Structural Works
E & M Works
Power Generation
Commencement of
Rock Quarry Power Generation
Site Clearance & Preparatory works
Quarry Plant
Rock Excavatio 4,300,000 m3 350,000 12.3 Plant set up
Rock excavation for concrete (aggregate)
Concrete Batching Plant
Site Clearance & Preparatory works
Plant set up
Batching Plant
Figure J5.2 Constrcution Program for Agos Dam and Agos Powerhouse
Length Unit Rate Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60
1st Waterway
Tunnel No.1
Access to Portal 500 m
Portal 1 no
Adit 1 400 m 130 3.1
TBM 1 11,780 m 400 29.5
Conc. Lining 11,780 m 1,000 11.8 Concrete Lining
Tunnel No.2
Portal 1 no
NATM 4 2,650 m 80 33.1 Steel Lining
Steel lining 2,650 m 300 8.8
Backfill Concrete 2,650 m 300 8.8 Concrete Lining
Portal
JF-4
2nd Waterway
Tunnel No.1
Portal 1 no Adit modification
Adit 1
TBM 1 11,780 m 400 29.5 Concrete Lining
Conc. Lining 11,780 m 1,000 11.8
Portal Adit modification
Adit 2 1 no
TBM 2 4,910 m 400 12.3 Concrete Lining
Conc. Lining 4,910 m 1,000 4.9
NATM 1 2,950 m 130 22.7 Concrete Lining
Conc. Lining 2,950 m3 1,000 3.0
Portal Adit modification
Adit 3 950 m 130 7.3
NATM 2 3,440 m 130 26.5 Concrete Lining
Conc. Lining 3,440 m 1,000 3.4
NATM 3 4,520 m 130 34.8
Conc. Lining 4,520 m3 1,000 4.5 Concrete Lining
Tunnel No.2
Portal
NATM 4 2,650 m 80 33.1 Steel Lining
Steel lining 2,650 m 300 8.8
Backfill Concrete 2,650 m 300 8.8 Concrete Lining
Portal 1 no
NATM 5 2,650 m 80 33.1 Steel Lining
Steel lining 2,650 m 300 8.8
Backfill Concrete 2,650 m 300 8.8 Concrete Lining