Methode Statement of Pipe Welding Procedures
Methode Statement of Pipe Welding Procedures
Methode Statement of Pipe Welding Procedures
...
METHOD STATEMENT
METHOD STATEMENT i
Contents
PROJECT ............................................................................................................ i
Contents ...............................................................................................................ii
1 PURPOSE..................................................................................................... 1
2 SCOPE ......................................................................................................... 1
3 DEFINATION ................................................................................................ 1
4 RESPONSIBILITY......................................................................................... 1
5 EQUIPMENTS: ............................................................................................. 2
6 INSTALLATION............................................................................................. 3
METHOD STATEMENT ii
7.3.10 DEVELOPER APPLICATION ........................................................ 15
8 APPENDIX .................................................................................................. 17
2 SCOPE
Mechanical for Welding Pipe of the ... under ... shall be the scope of this
Field Inspection and Test Plan.
3 DEFINATION
TERMS DEFINATION
Project
Owner
Consultant (RE)
Main Construction
MOS Method of Statement
MSA Material Submission Approval
Table 1 Definition
4 RESPONSIBILITY
NO DESIGNATION QTY RESPONSIBILITY
Responsibility for Overall Commercial,
Project Manager
contractual & technical performances
1 1
associated with specific project. Reporting to
the Project Director.
M&E Engineer
2 3 Planning and supervising installation activities
QA/QC Engineer
Inspect, verify, and prepare work statement for
3 1
a quality installation works.
Safety Officers To provide toolbox and guidance to work and
4 1 to ensure that work is carries out in a safe
manner
METHOD STATEMENT 1
NO DESIGNATION QTY RESPONSIBILITY
Obtain permit to work, control the sequence
according to MOS, approved shops drawings,
and MSA, ensure mechanical aspect of the
work are according to the specification, ensure
safe practices are followed and ensure quality
of workmanships during execution.
5 Supervisor 3-5
Ensure material temporary storage and
Table 2 Responsibility
5 EQUIPMENTS:
METHOD STATEMENT 2
6 INSTALLATION
Below is the flow chart for the installation, tests and inspection of the piping system:
METHOD STATEMENT 3
6.1 CONSTRUCTION DRAWINGS
Before commencement of the work, reference drawings for construction (such as
isometric drawings, layout drawings) shall be verified for its latest status. Only latest
drawings with Issued for Construction or Issued for Use (IFC/IFU) status shall be
used at site. Any old or obsolete drawings shall be removed from site and shall be
returned to the engineering department/document controller.
METHOD STATEMENT 4
possible, smooth rough cuts, and clean to remove slag, metal particles, and
dirt.
Use pipe clamps or tack-weld joints with 1" long welds, 4 welds for
pipe sizes to 10", 8 welds for pipe sizes 12" to 20".
Butt-welding end (bevel angle) and root opening (root gap) shall be
prepared according to the approved WPS or as specified in the drawing.
METHOD STATEMENT 5
Pipe ends for socket weld connections shall be reamed to full inside
diameter to remove all burrs and obstructions.
In assembly of socket weld joints, before tack welding, the pipe shall
be inserted into the socket to the maximum depth (mark the maximum depth
all around the pipe with pencil or suitable means) and then withdrawn
approximately 1/16 in. (2.0 mm) away from contact between the end of the
pipe and the shoulder of the socket (refer to Figs. 127.4.4 B and C in Chapter
V of ASME Section B31.1 and the figures below). In sleeve-type joints
without internal shoulder, there shall be a distance of approximately 1/16 in.
(2.0 mm) between the butting ends of the pipe or tube.
METHOD STATEMENT 6
Piping components to be joined shall be confirmed for straightness and
squareness before and after fit up, and after welding.
6.4 WELDER
Qualifications of Welders: Welders performing work under this Contract shall be
certified and qualified in accordance with tests prescribed by Kementerian Tenaga
Kerja Republik Indonesia. All welders shall produce professional welder certificate
with appropriate classes by Kementerian Tenaga Kerja Republik Indonesia by
approved test procedures using methodology and procedures covered in the ASME
Boiler and Pressure Vessel Code, Section IX, "Qualification Standard for Welding
and Brazing Procedures, Welders, Brazers, and Welding and Brazing Operators".
Installation shall conform to ANSI 31.1 "Power Piping".
1. Submit for approval the names, identification, and welder's assigned
number, letter or symbol of welders assigned to this project.
2. The assigned identification symbol shall be used to identify the work of
each welder and shall be indelibly stamped immediately upon completion of
each weld.
3. Welders shall be tested and certified for all positions.
4. Submit identifying stencilled test coupons made by each operator.
5. Any or all welders may be required to retake welding certification tests
without additional expense.
6. When so requested, a welder shall not be permitted to work as a
welder on this project until he has been recertified in accordance with
Kementerian Tenaga Kerja Republik Indonesia.
7. Recertification of the welder shall be made after the welder has taken
and passed the required tests.
8. Where piping 1-1/2 inches and smaller is butt or socket welded, submit
3 samples of test welds for approval.
METHOD STATEMENT 7
3. Use pipe clamps or tack-weld joints with 1" long welds, 4 welds for pipe
sizes to 10", 8 welds for pipe sizes 12" to 20".
4. Build up welds with stringer-bead pass, followed by hot pass, followed by
cover or filler pass. Eliminate valleys at centre and at edges of each weld.
Weld by procedures which will ensure elimination of unsound or unfused
metal, cracks, oxidation, blow-holes, and non-metallic inclusions.
5. Do not weld out piping system imperfections by tack-welding procedures.
Refabricate to comply with requirements.
6. At Installer's option, install forged branch-connection fittings whenever
branch pipe is indicated, or install regular T-fitting. Tack welding may be
made directly to the groove of the weld joint or by using bridge (fit up lug).
The fit-up lug to be used shall be of the same composition as the base
metal to be welded.
Tack welds shall not remain on the finished welds and shall be removed by
grinding before the start of permanent welding.
Electrodes or filler metals to be used in tack welding shall be the same as
specified in the applicable WPS.
Preheating in tack welding shall also be applied when preheating is specified in
the applicable WPS.
In order to monitor and control the welding of each joint, a matrix indicating the
below information shall be written near the joint:
METHOD STATEMENT 8
No welding shall be done if there is impingement of rain, or high wind on the
weld area or when the weld area is wet. Protection from rain and wind shall be
provided in the event of rain or strong wind.
Piping shall be adequately supported prior to welding to avoid distortion
during welding.
Electrodes or filler metals to be used shall be as per applicable WPS.
Welding filler materials/electrodes shall be collectively stored and controlled
at site Welding Electrode Control Room protected from rain and moisture. A drying
(baking) and holding oven shall be provided at site Welding Electrode Control Room
for conditioning/re-conditioning of SMAW or low hydrogen covered electrodes.
All low hydrogen covered electrodes shall be dried (some electrode
manufacturer uses the term re-drying) in the drying oven at required time and
temperature according to the electrode manufacturer recommendation.
Low hydrogen covered electrodes, after drying shall be transferred to the holding
oven at required temperature recommended by the electrode manufacturer.
Each welder shall be issued portable oven or quiver and will use it during
receiving of electrodes from welding consumable controller, during work at site, and
during returning of unused electrodes.
Reinforcements for butt weld joints shall be according to the Table 127.4.2 of
ASME Section B31.1 (refer to the table below), while undercuts shall not exceed 1.0
mm.
METHOD STATEMENT 9
All socket weld joints require a minimum of two passes and shall have minimum
sizes as indicated in Figures 127.4.4 B and C in Chapter V of ASME Section B31.1.
METHOD STATEMENT 10
B. Joint number
C. Piping and components orientation according to the drawing
D. Cleanliness of the pipe internal and external
E. Cleanliness of weld edge preparation
F. Groove angle, root gap and internal
G. Straightness and squareness of piping assembly
H. Electrode or filler metal used in tack welding
I. Inspection matrix written near the joint
Items to be checked and verified during Weld Visual Inspection are but not
limited to the following:
A. Material specification
B. Joint number
C. Applied WPS
D. Applied preheat temperature (if required)
E. Electrode or filler metal used in welding
F. Inspection matrix written near the joint
G. Name of welder
H. Cleanliness of the joint
I. Surface of welds shall be sufficiently free from coarse ripples, grooves,
overlaps, abrupt ridges, and valleys and shall meet the criteria listed in
ASME B31.1 Paragraphs 127.4.2 to 127.4.8., and Paragraph 136.4.2
METHOD STATEMENT 11
7.3 Liquid Penetrant Examination Procedure
7.3.1 Scope
This procedure details the techniques to be applied for Visible (Colour
Contrast) Solvent Removable Liquid Penetrant Examination (PT), to find the defects
open to surface on all types of non-porous metals and non-metals including welds,
pipes, tubes, forgings, fittings and other wrought products when such examination is
required by the construction Code and/or material specification.
The extent of examination shall be as specified in the drawing and test plan.
d) ASME Sec. IX
METHOD STATEMENT 12
e) ASME B31.1 & ASME B31.3
f) ASME Sec. 1
The surface to be examined and all adjacent area within at least 1 inch
(25mm) shall be dry and free of all dirt grease, lint, and scale, welding flux, weld
spatter, paint, oil and other extraneous matter.
7.3.5 CLEANING
The surface to be examined shall be cleaned using solvent cleaners before liquid
penetrant examination.
Minimum drying time after cleaning shall be 1 minute. Drying shall be by natural
evaporation.
METHOD STATEMENT 13
7.3.6 TEMPERATURE OF THE TEST SURFACE
The temperature of the test surface shall be between 40oF (5oC) and 125oF
(52oC) throughout the examination period. Local heating or cooling is permitted to
maintain the required surface temperature.
7.3.11 EXAMINATION
Developing time for final interpretation begins immediately after the
application of developer, as soon as wet developer coating is dry. Final interpretation
shall be made not less than 10 minutes nor more than 30 minutes after the coating is
dry. See Table 1.
A linear indication is one having a length greater than 3 times the width. A
rounded indication is one of circular or elliptical shape with the length equal to or less
than three times the width.
METHOD STATEMENT 15
7.3.13 ACCEPTANCE STANDARDS
These acceptance standards shall apply unless other more restrictive
standards are specified by contract and specified in drawing and / or test plan. All
surfaces to be examined shall be free of following.
After a defect is thought to have been removed and prior to making weld
repairs, the area shall be examined by suitable methods to confirm the defect has
been removed or reduced to an acceptable size of imperfection.
After repairs have been made, the repaired area shall be blended into the
surrounding surface so as to avoid sharp notches, crevices, or corners and re-
examined by the liquid penetrant method and by all other methods of examination
that were originally required for the affected area, except that, when the depth of
repair is less than the radiographic sensitivity required, re radiography may be
omitted.
METHOD STATEMENT 16
7.3.15 POST EXAMINATION CLEANING
The area after examination will be cleaned using dry/wet cloth or water
washed. Other special cleaning if required shall be specified on Inspection & Test
Plan.
8 APPENDIX
1. APPENDIX 1 Welding Procedure Specification (WPS)
2. APPENDIX 2 Permit to Work (PTW)
3. APPENDIX 3 Job Safety Analysis (JSA)
METHOD STATEMENT 17
APPENDIX 1 Welding Procedure Specification (WPS)
METHOD STATEMENT 18
METHOD STATEMENT 19
METHOD STATEMENT
APPENDIX 2 Permit to Work (PTW)
METHOD STATEMENT 2
APPENDIX 3 Job Safety Analysis (JSA)
METHOD STATEMENT 2