Cdot GDM
Cdot GDM
Cdot GDM
Design Manual
i
3.8.2 Rock Classification ................................................................................................. 23
ii
6.5.2 Monitoring Frequency and Baseline Measurements .......................................... 39
6.5.3 Action Levels ........................................................................................................... 40
6.5.4 Pre-Construction Surveys ...................................................................................... 40
6.5.5 Vibration Monitoring .............................................................................................. 40
6.5.6 Settlement Monitoring ........................................................................................... 40
6.5.7 Lateral Movement Monitoring .............................................................................. 40
6.5.8 Other Instruments .................................................................................................. 41
6.5.9 Data Reduction and Reporting ............................................................................. 41
LIST OF TABLES
2-1 Standards for CDOT Geotechnical Work ........................................................................... 3
2-2 Accepted Geotechnical Software For CDOT Projects ........................................................ 4
3-1 Common Sources Of Geotechnical And Geological Literature And Data ........................... 6
3-2 Minimum Requirements For Subsurface Explorations ................................................... 10
3-3 In-Situ Tests And Sampling Methods For Subsurface Explorations ................................. 15
5-1 Minimum Acceptable Factors Of Safety – Global Stability .............................................. 32
APPENDICES
iii
DEFINITIONS OF SELECTED TERMS
iv
CHAPTER 1. INTRODUCTION
1.1 PURPOSE
• Outline the roles and interaction of CDOT Soils & Geotechnical Services and
consultant engineers for CDOT projects.
• Identify standard procedures, practices, manuals, specifications, and
computer software for geotechnical work on CDOT projects, including
investigations, testing, design, and construction.
• Establish standards for presentation of geotechnical information,
including reports, boring logs, and laboratory test results.
• Define CDOT’s requirements and expectations for geotechnical work,
particularly where CDOT's expectations may differ from or are not clearly
addressed by the requirements of the referenced standards.
It is not the intent of this GDM to be all-inclusive. Where this GDM uses the terms
"include" or "including," the implied meaning is "including but not limited to." Address
all geotechnical issues that are pertinent to the project, regardless of whether or not
a given issue is specifically addressed by this GDM. Consult with CDOT Soils &
Geotechnical Services in developing an approach to geotechnical issues not
specifically addressed by this GDM or the referenced standards, and for clarification
as needed.
As discussed in the GDM, CDOT Soils & Geotechnical Services is available to review
submittals. CDOT Soils & Geotechnical Services will provide comments on submittals
at its discretion. Allow adequate time (a minimum of 10 business days) for CDOT
Soils & Geotechnical Services to provide comments on submittals.
1
accept project-specific exceptions to the requirements of this GDM at its discretion.
Where the Project GEO concludes that a specific exception is justified and
advantageous to the project, document justification for the proposed exception in the
geotechnical report.
CDOT Soils & Geotechnical Services maintains and updates this GDM to accommodate
advances in geotechnical engineering and American Association of State and Highway
Transportation Officials (AASHTO) practice, and welcomes comments and suggestions
to be considered for implementation in future editions.
At the outset of the project, the CDOT Region Project Manager should coordinate with
CDOT Soils & Geotechnical Services (SGS) to notify the SGS of project initiation and
maintain communications. The CDOT Soils & Geotechnical Services Manager will then
assign a CDOT SGSR, who will be available for consultation and coordination with the
Project GEO. As necessary, coordinate with the CDOT SGSR to discuss the field
investigation program, establish geotechnical design requirements, and to discuss
geotechnical design issues. The CDOT Region Project manager should submit draft
geotechnical reports via email to the CDOT SGSR. The GEO and CDOT Region Project
Manager should allow at least 10 business days for comment prior to finalizing
reports. The Project GEO bears the ultimate responsibility for all geotechnical work.
Conduct geotechnical work for CDOT Design-Build projects in accordance with the
standards listed by priority in the Project Request for Proposal (RFP).
2
CHAPTER 2. GEOTECHNICAL STANDARDS, REFERENCES, AND
SOFTWARE
2.1 GEOTECHNICAL STANDARDS AND ORDER OF PRECEDENCE
Conduct all geotechnical work in accordance with the standards listed in Table 2-1.
In the case of conflicting requirements, the requirements of the highest priority
standard take precedence.
TABLE 2-1
STANDARDS FOR CDOT GEOTECHNICAL WORK
In addition to the standards listed in Table 2-1, CDOT Soils & Geotechnical Services
commonly uses other resources referenced in this GDM, and may refer to these
references in reviewing geotechnical work, including geotechnical field
investigations, reports, and design submittals.
Accepted software for use in geotechnical analysis is listed in Table 2-2 on the
following page. Other industry-accepted software may be used on CDOT projects. As
necessary, use other software or hand calculations to confirm software results.
3
TABLE 2-2
ACCEPTED GEOTECHNICAL SOFTWARE FOR CDOT PROJECTS
4
2.4 FORMS
5
CHAPTER 3. GEOTECHNICAL INVESTIGATIONS
3.1 LITERATURE REVIEW
TABLE 3-1
COMMON SOURCES OF GEOTECHNICAL AND
GEOLOGICAL LITERATURE AND DATA
Following the literature review, the Project GEO should complete a site inspection.
Obtain as much information as possible prior to performing subsurface explorations,
including the following:
6
• Surface features that may affect design, construction, and performance
of proposed facility
• Distress of any existing structures
Where applicable, obtain information regarding the soil (nature and thickness of
strata) and bedrock (lithology and structure) by observing natural and man-made
exposures, including riverbanks, escarpments, quarries, and highway and railway
cuts.
Most projects are anticipated to be within CDOT’s right-of-way (ROW) and will require
a CDOT Utility/Special Use Permit to perform field investigations. Additional permits
may be required by local jurisdictions and other agencies. The Project GEO should
obtain all necessary permits required to complete field investigations.
3.3.2 Right-of-Entry
The Project GEO should obtain any required environmental clearances and permits
prior to initiating field investigations. Record and immediately report evidence of
contamination observed during the explorations to the CDOT Regional Project
Manager and the SGSM.
7
3.3.4 Traffic Control Requirements
Provide traffic control for field investigations in accordance with the FHWA (2009)
Manual on Uniform Traffic Control Devices (MUTCD) with Revisions 1 and 2 (May
2012). Obtain appropriate traffic control plans and traffic control services.
Review available utility plans prior to selecting subsurface exploration locations. All
utilities within the exploration boundaries shall be cleared per current State and
Local laws. Typical steps include marking areas of proposed subsurface explorations
with white paint (pavement or hard surfaces) or flagged stakes (soil or vegetated
surfaces). Perform utility locates through the Utility Notification Center of Colorado
(UNCC) at 811 or 1-800-922-1987 (also can be performed using the online service at
www.colorado811.org) at least two business days prior to the start of drilling or
digging. Contact any other entities, including Tier II utilities, (e.g., railroads,
irrigation companies, and private properties,) that may own or operate utilities in
the area, prior to the start of drilling or digging.
Retain a private utility locating company if private utilities (i.e. utilities not located
through the UNCC), such as service lines and power lines for privately owned
overhead lighting, are present.
The Code of Colorado Regulation (CCR) requires that a Notice of Intent (Notice) be
provided to the Colorado Division of Water Resources before drilling any test hole that
penetrates a confining layer or before installing a monitoring well (2 CCR 402-2). As
necessary, file a Notice at least three business days prior to drilling to the Colorado
Division of Water Resources by email at DWRpermitsonline@state.co.us. Forms and
8
other information are available online at https://dwr.colorado.gov/services/well-
permitting.
All work shall be done in compliance with CDOT Standard Specifications for Road and
Bridge Construction Section 107.06 (e), Project Safety & Health Requirements. Work
shall also comply with all federal (including Occupational Safety and Health
Administration [OSHA]), state, and local laws and ordinances. Conduct drilling using
appropriately trained and certified (as necessary) personnel equipped with
appropriate safety equipment.
Conduct all interactions with the public with respect and courtesy. Cooperate with
property owners, public safety officers, and CDOT personnel to minimize and
mitigate potential impacts and hazards of field investigations.
Protect the public from falling and tripping hazards posed by test holes. During
operation of heavy equipment, maintain an exclusion zone around the impacted area
to protect the public.
Refer specific questions from the public regarding CDOT projects to the CDOT
Public Relations Office.
9
Conduct subsurface explorations meeting the frequency and depth requirements
listed in Table 3-2. CPT probes may be used for some of the required test holes
where appropriate.
TABLE 3-2
MINIMUM REQUIREMENTS FOR SUBSURFACE EXPLORATIONS
Project conditions may require more and deeper test holes than specified by Table
3-2. As necessary, consult with the CDOT SGSM regarding requirements for the
subsurface investigation program. Wide embankments on compressible soils require
test holes with adequate depth and sampling to characterize any compressible
materials, regardless of embankment height. In all cases, perform sufficient
subsurface explorations to provide the information needed for the design and
construction of each project element. Base the extent and number of explorations on
the variability of subsurface conditions, design requirements, and engineering
judgment.
It is not the intent of this GDM to require test holes in excessive quantities or
depths. In particular, test holes for walls and embankments need not extend t o
excessive depths in competent, incompressible strata.
10
Additional information describing considerations and requirements for subsurface
explorations can be found in the following references:
• FHWA Report No. FHWA ED-88-053, FHWA Checklist and Guidelines for
Review of Geotechnical Reports and Preliminary Plans and Specifications
(FHWA, 2003), Table 2.
• CDOT Field Materials Manual, Chapter 200.
• AASHTO LRFD Bridge Design Specifications.
• Landslides: Investigations and Mitigations, Transportation Research Board
(TRB) Special Report 247 (TRB, 1996).
3.5 SUBSURFACE EXPLORATION METHODS
Subsurface explorations may include borings, test pits, trenches, and other methods
that obtain measurements or observations of soil and rock. Purposes of explorations
include the following:
3.5.1 Borings
• Solid stem auger drilling. This method is acceptable only where hole
collapse or sloughing does not occur.
• Hollow stem auger (HSA) drilling. Take care during drilling to mitigate heave
and loosening of saturated, cohesionless soils. Alternative methods, such as
mud rotary drilling, may be required to control heave.
• Mud or Air rotary drilling. Casing may be required in very loose or porous
soils.
• Sonic core drilling.
11
• Down-the-hole hammer methods.
• Rock coring. Obtain downhole digital images or oriented cores where
appropriate.
Drilling methods will vary depending on subsurface conditions. Use drill crews
trained and equipped to perform explorations in the anticipated geologic
conditions.
Record field observations on a Geological Boring Log – CDOT Form 1334 or equivalent.
The Project GEO may use test pits for shallow soil investigations, such as pavement
subgrade investigations, and may use exploratory trenches for fault investigations,
collapsible soils identification, etc. Test pits and trenches are typically limited in
depth to about 10 feet below the ground surface, depending on the trench stability,
groundwater, and equipment limitations (e.g. backhoe reach). All trenching shall be
in accordance with OSHA guidelines for worker safety.
Take photographs of the sides of the excavation and maintain a log of the test pit or
trench.
Abandon boreholes in accordance with Rule 16 of 2 CCR 402-2 and with any applicable
permit requirements. Where borings extend through existing pavements, sidewalks,
bridge decks, etc., properly patch the surface of the hole with asphalt, grout, or
concrete to maintain public safety. Pavement repairs should be completed in
accordance with the requirements of applicable local agencies and the CDOT Region.
Upon completion of test pits or trenches, backfill excavations with the excavated
material or other suitable material, such as grout or flow fill. All excavations should
be backfilled in accordance with the requirements of applicable local agencies and
the CDOT Region.
Where excavations are located in agricultural areas or other areas used to support
plant growth, cover the backfilled excavation with topsoil so that the impacted
area will support vegetation. Restore the area to conditions that are equal to or
better than the original condition.
12
3.5.4 Geophysical Surveys
Use geophysical surveys as appropriate for the Project. Refer to ASTM D6429 for
guidance in selecting geophysical methods. Guidance is also provided in FHWA Report
No. IF-04-021 (FHWA, 2004).
Geophysical methods are typically non-destructive and are performed from the
ground surface. Success depends on factors including surface features, site activity,
subsurface conditions, and groundwater. Perform geophysical methods under the
supervision of an experienced geophysicist. Conduct all geophysical methods in
accordance with applicable ASTM standards or in accordance with widely accepted
guidelines if standards do not exist. If geophysical surveys are conducted, the results
should be calibrated using data from a nearby boring in which physical samples are
obtained.
Present results in graphs, profiles, tables, or contour maps. Use U.S. Customary units.
Convert field measurements to data that is useful in engineering analyses.
Additional methods or processes for site exploration and characterization not included
in this manual are encouraged if there are estimated or measurable benefits towards
data quantity and reliability, foundation design and construction cost savings,
reductions in project delivery risk for CDOT, or other valuable criteria identified by
the consultant. Example methods include CPT, remote sensing methods, or downhole
optical surveys. The feasibility of using alternative approaches shall be discussed
with the CDOT SGSM prior to final cost estimation and submittal of the scope of work.
13
3.6 IN-SITU TESTING AND SAMPLING
In-situ testing and soil sampling (with subsequent laboratory testing) is performed to
determine the index and engineering properties of soil and rock. Perform soil
sampling and testing to obtain samples that are representative of subsurface
materials and conditions. Conduct sampling and testing in general accordance with
the NHI Reference Manual Subsurface Investigations – Geotechnical Site
Characterization (Mayne and others, 2002) and the NCHRP (2019) Manual on
Subsurface Investigations.
Potential sampling methods and in-situ tests include those listed in Table 3-3 on
the next page.
14
TABLE 3-3
IN-SITU TESTS AND SAMPLING METHODS FOR SUBSURFACE EXPLORATIONS
15
limitations of the method to be employed. Conduct in-situ testing in accordance with
the applicable CDOT, AASHTO, and ASTM standards.
Do not exclusively rely upon any type of testing that does not acquire a soil or rock
sample. Obtain representative samples for visual-manual classification and laboratory
testing. Supplement in-situ testing of strength with laboratory testing to confirm
correlated properties.
The following sections describe requirements for common methods of testing and
sampling for CDOT projects, but do not provide information on all testing and
sampling methods listed in Table 3-3. Conduct sampling and testing in accordance
with applicable CDOT, ASTM, and AASHTO Standards.
The SPT is a common sampling and testing method used for subsurface explorations
extending through soil and relatively low-strength rock. Perform the SPT in
accordance with ASTM D1586.
The number of blows to cause the last 12 inches of penetration (termed the standard
penetration resistance or N-value) should be determined by adding the number of
blows from the 2nd and 3rd 6-inch increment and recorded on the Geological Boring
Log. The number of blows for the first increment should be ignored. Examples of N-
value calculations are as follows:
• Blows per 6-inch increments = 25, 45, and 30: N-value = 45+30 = 75
• Blows per 6-inch to refusal = 25, 45, and 50/3”: N-value = 45/6”+50/3” = 95/9”
• Blows per 6-inch to refusal = 25 and 50/3”: N-value = 50/3”
• Blows until refusal (less than 6 inches driven) = 50/3”: N-value = 50/3”
Use of N-values in estimating soil properties for design may require correction of the
field measured N-values. These corrections are based on hammer efficiency, borehole
diameter, sampler dimensions, and sampling rod length. Details of the hammer (size,
weight, type), rod (size, length) and sampler information (size, liners) used during
testing shall be recorded on the Geological Boring Log.
16
Conduct SPT sampling using hammers that have been calibrated in accordance with
ASTM D 4633 within two years of the sampling date. Obtain hammer energy transfer
measurements from the driller and report the information on boring logs or in the
associated geotechnical report.
Examine and classify the sample collected in the split-spoon sampler in accordance
with ASTM D 2488. Record the sample descriptions on the boring log. After
identification and logging, transfer the sample to air-tight jars or bags labeled with
the project name/number, boring designation, sample date, and sample depth.
Requirements for sample identification are presented in Section 3.8.1.
Perform MC sampling and penetration testing in accordance with ASTM D3550. This
method is similar to the SPT. However, a slightly larger sampler is used, within which
brass liners are placed end-to-end to collect a soil sample. The sampler is also
typically driven 12 inches instead of 18 inches.
Determine the penetration resistance in blows per foot by adding the measured
penetration resistance for each six-inch increment (e.g. 25/6” + 55/6” = 75). Record
the penetration resistance, details of the hammer (size, weight, type), rod (size,
length) and sampler information (size, liners) used during testing on the boring log.
Conduct MC sampling using hammers that have been calibrated in accordance with
ASTM D 4633 within two years of the sampling date. Obtain hammer energy transfer
measurements from the driller and report the information on boring logs or in
associated geotechnical report.
Examine and classify the sample collected in the MC sampler in accordance with ASTM
D 2488. Record the sample description on the boring log. After identification and
logging, seal the individual brass liners with tight-fitting caps and label with the
project name/number, boring designation, sample date, and sample depth.
Requirements for sample identification are presented in Section 3.8.1.
Obtain thin-walled (Shelby) tube samples in cohesive soils where laboratory testing of
relatively undisturbed samples is required (e.g. consolidation testing, triaxial testing)
for design and analysis. Projects requiring the collection of thin-walled tube samples
include those with proposed embankments or retaining structures on cohesive soils
that could contribute to instability or post-construction settlement.
17
Collect thin-walled tube samples in accordance with ASTM D1587. In thick deposits of
cohesive soils, alternating SPT sampling with thin-walled tube sampling will provide
SPT N-values as well as sufficient sample volume for testing. Do not collect thin-
walled tube samples without also performing SPTs to determine the soil
density/consistency.
Only the ends of the tube sample may be observed in the field. The remainder of the
sample is observed when the sample is extruded in a laboratory prior to testing. Due
to potential interbeds of sand, sample disturbance, and other issues, some samples
may not be suitable for testing. Collect enough samples to perform the proposed
laboratory engineering tests considering that some samples may not be useful for
testing.
Other types of tube samples, including Osterberg samples, Pitcher barrel samples,
and piston samples, may be used. Follow applicable AASHTO or ASTM standards for
sampling. Do not attempt to use an MC sampler or any other type of driven sample to
obtain undisturbed samples.
Seal thin-walled tube samples with rubber stoppers, plastic caps, or paraffin wax, and
transport and store in an upright position with the sample oriented in the same
direction as the borehole. Make every effort to obtain, transport, and store samples in
a manner that ensures and maintains sample integrity and quality. Avoid exposing
samples to bumps, jolts, vibrations, or freezing temperatures during transport and
storage.
The Cone Penetration Test (CPT) consists of pushing an instrumented cone into the
ground at a controlled rate to obtain measurements of soil resistance. The cone can
be equipped with additional instrumentation to obtain measurements of pore water
pressure, shear and compression wave velocity, conductivity/resistivity, and other
parameters. Perform CPTs in accordance with ASTM D5778. The CPT method does not
obtain a soil sample and should be used as a supplement to methods in nearby borings
that acquire a sample.
Present the results of the CPT as plots including (at a minimum): the tip resistance,
sleeve resistance, friction ratio, and soil type interpretation versus depth. Use English
units. Include additional information such as pore pressures and seismic sounding
information where available. The CPT log should include the CPT designation, date
tested, ground elevation, estimated groundwater depth, and other pertinent data.
18
The log should also include the interpreted soil type versus depth as estimated using
published methods based on tip and friction resistance. Other test results associated
with the CPT (e.g. pore pressure dissipation tests) should also be presented as graphs
or tables.
Rock coring should extend at least 10 feet below the top of bedrock or to depths
indicated in Table 3-2, whichever is greater. Either double- or triple-tube core barrels
may be used. Single-tube core barrels are not permitted. Select the core barrel type
considering the nature of the rock and the required quality for the retrieved core.
Utilize N-, H-, or P-size core barrels.
After the core is retrieved from the borehole, examine, log, and photograph the core.
Transfer the core to cardboard or wood boxes, and use wood or foam spacers to
prevent core pieces from being dislodged in the box. Use spacers to identify zones of
core loss and to separate and identify core runs. Do not discard rock core. All
recovered core should be placed in the box. Requirements for sample identification
are presented in Section 3.8.2. Prepare core photographs clearly indicating the boring
designation, run number, run depths, recovery, and rock quality designation (RQD) in
accordance with ASTM D6032.
Table 3-3 includes numerous in-situ tests that have not been described in the previous
sections. Additional tests not listed in Table 3-3 may also be appropriate for the
project. Conduct all in-situ tests in accordance with applicable AASHTO or ASTM
standards, or in accordance with widely accepted guidelines if standards do not exist.
Present test results in graphs or tables, in U.S. Customary units. Convert field
measurements to data that is useful for use in engineering analysis.
19
3.7.1 Borings
For drilling methods that do not utilize drilling mud or added water, the groundwater
level can be estimated during drilling by noting evidence of water on the drill rods or
augers. Estimate the groundwater level both during drilling and after drilling is
complete.
In many cases, particularly in clay soils, the water level in a test hole will not
stabilize to the natural groundwater level until hours or days after drilling is
complete. Where necessary, install temporary pipe in test holes to allow subsequent
measurements of groundwater levels. Unless access restrictions are prohibitive (e.g.
in a live traffic lane), installation of a temporary standpipe, and a minimum of one
groundwater measurement at least 24 hours after completion of drilling, are required
in clay soils for any project where global stability or settlement calculations will be
performed.
If the primary drilling method does not permit reliable measurements of groundwater
levels, conduct supplementary test holes to determine the depth to groundwater or
install groundwater monitoring devices (see Section 3.7.2 and 3.7.3).
Confirm that the well is open to the bottom cap. If any water was used during drilling,
the well should be bailed dry. Well development is not required for typical
observation wells. Protect the top of the well from damage. In areas of traffic, a
flush-mounted steel monument may be required. In all cases, a locking cap should be
placed on well casing to prevent inflow of water or debris into the well.
20
As necessary, discuss the timing and responsibility of permitting and well
abandonment with the CDOT SGSM. State regulations require that temporary
monitoring wells must be abandoned within 18 months of installation or permitted as
permanent monitoring wells with the Colorado Division of Water Resources.
Where used, multiple VWPs may be installed at various depths within a single
borehole. Install VWPs in accordance with the manufacturer’s recommendations. Coil
the VWP cables at the ground surface and place them inside a steel monument or
protective system.
Measure groundwater levels in monitoring wells using an electronic water level meter.
Measure groundwater levels with pressure loggers or VWPs according to
manufacturer’s instructions.
A consistent system of soil and rock classification is required for all CDOT projects.
Record all soil and rock classifications on the boring log.
21
3.8.1 Soil Classification
During drilling and sampling, classify soils in accordance with ASTM D2488 (visual-
manual classification). Record the basic soil profile elements in the field, including
changes in strata, relative properties of soil types in layered/bedded deposits, and
presence of cobbles or boulders. Make corrections and additions to the field
classification, where necessary, by conducting laboratory testing of the soil samples,
and prepare final boring logs using descriptions based on ASTM D2487 (Unified Soil
Classification System).
Record descriptions in the boring log for every soil sample collected. Provide
descriptions that are concise, precise, and comprehensive. Additional requirements
for soil classification on boring logs are below:
• Color: Record the basic color of a soil. Assign colors in accordance with Munsell
color charts. Note staining or mottling, as this information may indicate water
table fluctuations or contamination.
• Penetration Resistance: Use different indicators for different penetration
tests/samplers (e.g. SPT, Modified California). Indicate hammer and rod type
on boring logs. Add notations where the penetration resistance may have been
affected by large gravel, debris, or other disturbance (e.g. heaving or voids)
that could affect the validity of the recorded penetration resistance.
• Consistency of Cohesive Soils: Indicate the consistency (e.g. soft, stiff, etc.)
of cohesive soils based on SPT N-values in the soil description. Also utilize vane
shear, miniature vane shear (torvane), or pocket penetrometer testing to
evaluate the consistency of cohesive soil and report test results on the boring
log.
• Density of Granular Soils: Indicate the density (e.g. loose, medium dense,
etc.) of granular soils based on SPT N-values in the soil description.
• Structure: Describe discontinuities, inclusions and other features, including
joints or fissures, slickensides, bedding or laminations, veins, root holes, and
wood or other debris.
• Mineralogy: Note significant mineralogical information, such as cementation,
abundant mica, or unusual mineralogy such as pinhole structure, and other
information such as oxidation, ferrous minerals, calcium, organic debris, odor,
etc.
• Other Descriptors: Include other descriptors if important for the project or for
describing the sample, including particle size, range and percentages, particle
angularity, particle shape, maximum particle size, hardness of large particles,
plasticity of fines, dry strength, dilatancy, toughness, reaction to hydrochloric
22
acid, etc. If possible, describe the relict rock structure and identify the parent
rock for residual soils having characteristics of both rock and soil.
Where necessary for pavement design, refer to the requirements of the CDOT
Pavement Design Manual.
Classify rock core samples in accordance with the International Society of Rock
Mechanics (ISRM) publication Suggested Methods for the Quantitative Description of
Discontinuities in Rock Masses (ISRM, 1978).
23
CHAPTER 4. LABORATORY TESTING
Conduct the geotechnical laboratory testing program in accordance with the
requirements of the project and this GDM. Exercise engineering judgment in
developing the testing program. Use a testing laboratory accredited by AASHTO or
ASTM.
The Project GEO is ultimately responsible to CDOT for the laboratory testing for the
project, but may subcontract portions of the work to an accredited laboratory. Prior
to commencing any laboratory testing, review the laboratory's policies and
procedures. Adjust policies and procedures as necessary to meet project
requirements.
• Conduct shear strength tests, such as triaxial shear, direct shear, vane
shear, and/or unconfined compression, on samples from each definable soil
unit, depending on the soil type and the nature, purpose, and importance of
the project element. More information on projects for which these tests are
a requirement can be found below.
• Perform pH, resistivity, sulfate, chloride, and soluble salt tests to evaluate
potential for corrosion and deterioration of concrete and metal.
• Test to evaluate potential for collapse, swell, and other problematic
behavior. More information on projects for which these tests are a
requirement can be found below.
In selecting tests for specific project features, comply with the requirements and
guidelines of applicable AASHTO and CDOT design specifications and manuals.
Follow the applicable testing procedures outlined in the current AASHTO and ASTM
Standards specified in the CDOT Laboratory Manual of Test Procedures.
24
4.2.1 Index Testing
Index testing consists of tests that provide useful information about the soil without
directly measuring soil properties (e.g. strength tests). Index testing requirements for
CDOT projects are listed below:
• Measure the moisture content of all samples except granular soils below the
water table.
• Perform Atterberg limits tests on selected cohesive soil samples to provide
data for correlation and identification.
• Perform gradation testing to characterize cohesionless soils.
• Conduct unit weight determination tests on cohesive soils from MC and thin-
walled tube samples.
4.2.2 Consolidation and Swell/Collapse Testing
For any project where there is a potential for swell- or collapse-susceptible soil or
rock to impact infrastructure, one-dimensional swell/collapse testing is required.
Testing should be completed in accordance with ASTM D4546 or other widely accepted
test methods. Select loading conditions that are representative of field conditions or
select appropriate loading conditions for comparison to published correlations.
25
4.2.3 Shear Strength Testing
Conduct laboratory shear strength tests to supplement the results of field tests and
published correlations with index properties, as necessary for design of the project
elements.
For any project where undrained stability may control the design (e.g. embankments
or retaining structures constructed on cohesive soils), obtain relatively undisturbed
thin-walled tube samples and conduct unconsolidated-undrained (UU) and/or
consolidated-undrained (CU) triaxial shear strength testing. Complete an adequate
number of tests to characterize variability in soil properties at a given site.
Characterize drained shear strength parameters using CU triaxial tests with pore
water pressure measurement, consolidated-drained (CD) triaxial tests, direct shear
tests, or torsional ring shear tests. If direct shear tests are used, ensure that the test
strain rate is determined in accordance with ASTM D3080 and is slow enough to allow
dissipation of shear-induced pore water pressures. Relatively long test times will be
required for cohesive soils (potentially up to 24 hours).
Unconfined Compressive Strength (UCS) testing may be used for hard clay soils,
claystone, or Intermediate Geo-Materials. Soft to medium stiff clay soils are more
susceptible to disturbance from sampling; UCS testing shall not be used for these soil
types.
Perform compaction tests on soils that may be used as fill for a project or may be
compacted in place for a structure subgrade. Common compaction and related tests
include:
26
• Compaction Test – soil is compacted at multiple moisture contents for a given
compactive effort to generate a compaction curve. The results are used as a
comparison for evaluating the results of in-place compaction performed during
construction.
• R-Value Test - measures the response of a compacted sample to an applied
pressure. The test results are typically used for pavement design purposes. The
CDOT region Materials Engineers also may perform R-Value tests. These tests
should be coordinated with the Material Engineer.
4.3 QUALITY ASSURANCE AND QUALITY CONTROL
Retain and preserve samples in their original state until final acceptance of the
project following construction. Retain laboratory worksheets and records for
verification purposes for at least five years following construction of the project.
Consultants may retain laboratory records in accordance with applicable in-house
document retention policies.
27
CHAPTER 5. GEOTECHNICAL DESIGN
This Chapter provides an overview of accepted practices by CDOT for analysis and
design. It is not the intent of this Chapter to provide step-by-step procedures for
analysis and design. Use expertise and engineering judgment in carrying out the
analysis and design necessary to comply with all requirements. The CDOT SGSM is
available to review design assumptions and approaches.
Additional design requirements are presented in the CDOT Bridge Design Manual.
Comply with the CDOT Bridge Design Manual and the AASHTO LRFD Bridge Design
Specifications for all aspects of bridge design, unless otherwise specified by CDOT
Staff Bridge or the CDOT SGSM.
Bridge foundations for CDOT projects typically consist of driven piles, drilled shafts
(also referred to as caissons and piers), or spread footings. Spread footings are
generally not considered acceptable at stream crossings.
The foundation types applicable to a given project depend on anticipated loads and
scour depths (where applicable), along with consideration of settlement, downdrag,
bearing resistance, lateral resistance, seismic hazards, constructability, and other
applicable factors.
Driven piles generally consist of steel H-pile. Steel pipe piles may also be utilized.
Additional design requirements and considerations are presented in the CDOT Bridge
Design Manual.
28
For projects where drilled shafts may be proposed, rock coring is required in at least
1/3 of bridge borings (minimum of one boring). Rock coring in bedrock should be
performed in conjunction with SPT sampling between core runs or in adjacent
borings.
For sites with bedrock N-values typically greater than 100 blows per foot and where
rock coring produces suitable core recovery (i.e., samples can be recovered for
strength testing, and the rock mass can be characterized to an appropriate degree),
evaluate axial resistance using design methods based on the unconfined compressive
strength, as described in the AASHTO LRFD Bridge Design Specifications and FHWA
Report No. FHWA NHI-18-024 (Brown and others, 2018).
For sites with bedrock N-values typically less than 100 blows per foot, the “Soil-Like
Claystone” design procedure described in CDOT Research Report CDOT-DTD-R-2003-6
(Abu-Hejleh and others, 2003) may be used as appropriate to assess nominal axial
resistance. Use a resistance factor of 0.60 with the “Soil-Like Claystone” design
procedure.
Provide the appropriate parameters for p-y lateral analysis of deep foundations using
software such as LPILE or AllPile. Coordinate with CDOT Staff Bridge or the Structural
Engineer of Record to determine what software will be used for lateral analysis and
provide the appropriate soil/rock parameters.
Static load tests may be used to justify higher resistance factors for deep foundations
in accordance with the AASHTO LRFD Bridge Design Specifications. Account for the
following factors in determining whether to use static load testing:
• Cost of testing
• Potential savings resulting from increased resistance factors
• Number of foundations to which load tests will apply
• Group effects that may control available foundation resistance
• Schedule implications and timing of testing (design or construction phase)
• Adaptability of foundation design to account for test results
Evaluate site variability and determine the required number of load tests for each site
in accordance with the AASHTO LRFD Bridge Design Specifications.
29
5.2 FOUNDATIONS FOR SIGNS, LIGHTING, AND SIGNALS
Conduct subsurface explorations and testing for foundations of signs, lighting, and
signals, as specified in Section 3.4. Refer to the following documents to design
foundations for these structures:
Use earth slopes and embankments no steeper than 2H:1V (Horizontal: Vertical)
without approval from the CDOT SGSM.
Evaluate all new embankment fills, retaining walls and modifications of existing fills
for settlement, stability, and other applicable geotechnical considerations. For global
stability of embankment slopes and retaining walls, meet the requirements of this
GDM.
5.3.1 Settlement
For cohesive soils, determine settlement properties (including both elastic and
consolidation parameters) using laboratory test results and published correlations
with index properties. Consider the potential for unsaturated cohesive soils to
transition to a saturated condition and exhibit time-dependent settlement behavior
due to compression induced by increased loading from embankments or other
structures.
5.3.2 Utilities
Evaluate settlement impacts on new and existing utilities, and consider the impacts of
abandoned utility lines on settlements.
30
Design settlement mitigation as necessary to allow for effective operation through the
design life of utilities.
For cohesive soils, determine shear strength parameters used in global stability
analyses based on laboratory shear strength testing and published correlations with
index properties. Evaluate stability considering undrained and drained shear strengths
for cohesive soils. Consider the potential for residual or fully softened conditions to
apply, and select appropriate shear strength parameters based on laboratory testing
and published correlations.
For granular soils, select shear strength parameters based on ring shear testing, direct
shear testing, or published correlations with index properties or in-situ test results
(e.g. N-values).
Do not utilize an artificial cohesion intercept to eliminate shallow slip surfaces for the
analysis; instead, adjust the search method to produce appropriate slip surfaces for
design and analysis.
For analysis of slope failures or landslides, use residual shear strengths and an
effective cohesion of zero for the failure surface.
Table 5-1 lists the minimum acceptable factors of safety for global stability of
embankments and retaining walls on CDOT projects.
31
TABLE 5-1
MINIMUM ACCEPTABLE FACTORS OF SAFETY – GLOBAL STABILITY
The factors of safety in Table 5-1 were developed based on the AAHTO LRFD Bridge
Design Specifications and recommendations contained in the Federal Lands Highway
Division (FLHD) Project Development and Design Manual (FLHD, 2018).
Exceptions to the factors of safety specified in Table 5-1 may be appropriate in some
instances. For example, it may be cost-prohibitive or infeasible to mitigate an existing
landslide to a factor of safety of 1.3. Provide justification for use of factors of safety
lower than those specified in Table 5-1. During construction, if a wall or slope will be
monitored, then a lower factor of safety may be acceptable. Monitoring in this case
should consist of adhering to a written monitoring plan, and may include methods
such as instrumentation, survey monitoring, or recurrent visual observation.
Evaluate and recommend appropriate means of meeting the factors of safety listed in
Table 5-1. Acceptable means of improving factors of safety include modifying
embankment slopes, dimensions, and materials, reinforcing embankment and
foundation soils, drainage improvements, and ground improvement. For short-term
construction-phase stability deficiencies, evaluate the potential benefits of staged fill
placement, using instrumentation to monitor stability and embankment/structure
performance.
32
5.3.4 Permanent Cut Slopes
For permanent cut slopes, meet the minimum factors of safety listed in Table 5-1.
Design of permanent cut slopes should consider runoff of surface water, surficial
erosion, and future slope maintenance (e.g., mowing of vegetated slopes).
Select and design retaining walls in accordance with the CDOT Bridge Design Manual
and the AASHTO LRFD Bridge Design Specifications.
For MSE walls, it is recommended that the wall embedment meet the requirements
specified in Table 2-2 of FHWA Report No. FHWA-NHI-10-024 (Berg and others, 2009).
The embedment depth should be selected based on wall stability, frost depth, and
subsurface conditions.
Fill and geotechnical materials should be in accordance with the CDOT Standard
Specifications for Road and Bridge Construction.
Swelling and collapse-prone soil/rock has the potential to adversely affect structures.
The Project GEO should adequately investigate and characterize swell-susceptible and
collapse-prone soil/rock. As necessary, the Project GEO should provide
recommendations to mitigate these hazards. Potential mitigation options include
over-excavation beneath shallow footings and retaining structures, chemical
stabilization, and the use of deep foundations.
33
Specifications. These can be obtained by using the current USGS tools found online at
https://www.usgs.gov/natural-hazards/earthquake-hazards/design-ground-motions.
Do not use PDF or paper maps, or ZIP code lookup tools, to determine ground motion
parameters for CDOT projects.
Geotechnical reports should satisfy the requirements of the report checklist provided
in Appendix B. Final reports should be signed and sealed by a Professional Engineer
registered in the State of Colorado.
Submit draft geotechnical reports to the CDOT SGSM prior to finalizing the report.
Allow a minimum of 10 days for CDOT to review the report. Submit the final report to
the CDOT SGSM in electronic PDF format.
Prepare signed and sealed engineering geology sheets for inclusion in the plans for
each structure. Include pertinent boring logs and laboratory test results. Use the
drawing format provided in CDOT Drawing Worksheet B-GEO-1.
34
CHAPTER 6. CONSTRUCTION-PHASE SERVICES
Geotechnical conditions encountered during construction may affect the design
recommendations developed by the Project GEO. Therefore, it is important for the
Project GEO to remain involved during the construction phase of the Project.
The CDOT SGSM may request that the Project GEO provide the following services
during construction of the project:
Maintain a log of all field visits and record all observations and recommendations on a
daily field report. If requested, submit daily field reports to the CDOT SGSM on a
regularly basis. The daily field report should include logs, data sheets, photographs,
notes, and other information collected by the field representative.
Where requested, observe pile driving in accordance with the Deep Foundations
Institute (DFI) Inspector's Manual for Driven Pile Foundations (1997). Note any
observed or reported anomalies on the pile driving log.
If diesel hammers are used to drive piles, use an ESaximeter to record the hammer
blows and stroke in addition to maintaining a handwritten log. The ESaximeter data
(blow count, rate, stroke) can be used by the Project GEO to evaluate pile driving
conditions and confirm design assumptions.
Conduct or provide oversight of static load tests where required. Use the procedures
specified in the AASHTO LRFD Bridge Design Specifications. Submit load test results,
analyses, and conclusions to the CDOT SGSM.
Section 502 of the CDOT Standard Specifications for Road and Bridge Construction
specifies procedures for driven pile installation and PDA testing with signal matching
on CDOT projects.
The CDOT Project Engineer will arrange for PDA testing with signal matching analyses
to be conducted by either CDOT Soils & Geotechnical Services or a qualified PDA
testing firm. The PDA testing firm is responsible for quality management of its work.
The CDOT Project Engineer will coordinate with the CDOT SGSM and the Project GEO
to resolve deficiencies in driving resistance determined from PDA testing.
On Design-Build Projects, unless otherwise specified by the Project RFP, the Design-
Builder is responsible for PDA testing and signal matching analyses.
Establish production pile driving criteria based on a pile for which the required driving
resistance has been verified by PDA testing and signal matching analysis. The pile
driving criteria should specify the minimum blow count and either the hammer energy
or the hammer stroke corresponding to the minimum blow count.
36
If any unusual or otherwise unanticipated pile-driving condition are encountered
(including not achieving the minimum tip elevation), notify the Project GEO.
Acceptance of piles based on projected setup is not allowed. Where additional setup
is anticipated and is necessary to meet the required driving resistance, conduct PDA
testing and signal matching analysis after the setup has occurred.
Document drilled shaft construction using CDOT Form 1333. Include a log of concrete
placement volume by depth and time.
Conduct or provide oversight of static load tests where required. Use the procedures
specified in the AASHTO LRFD Bridge Design Specifications. Submit load test results,
analyses, and conclusions to the CDOT SGSM or CDOT Project Engineer.
37
• Monitor the degree to which these protective or remedial measures are limiting
damage and to provide early warning when alternative means of protection are
necessary.
• Provide data for settling legal disputes either between the Contractor and
CDOT or with owners of adjacent facilities.
• Monitor the performance of temporary construction structures.
• Confirm design assumptions and provide data that could improve future
designs.
As appropriate, recommend preconstruction surveys and the monitoring of vibrations
and settlements at structures, utilities, properties, and facilities potentially impacted
by vibrations or settlement caused by construction activities. Instrumentation
programs may include monitoring of:
The types, numbers, and locations of the instruments depend on the Contractor’s
proposed construction methods, sequence, and durations, as well as on the proximity,
characteristics, and conditions of adjacent facilities. As appropriate, develop an
instrumentation plan to monitor parameters including settlements, slope/wall
stability and movements, movements and vibrations of nearby structures,
groundwater levels and flows, pore pressures (as applicable), and other geotechnical
parameters during construction. Develop and implement plans to mitigate these
impacts, both within and outside the planned Right-of-Way. Where long-term
settlement of embankments or facilities may occur, provide long-term settlement
instrumentation arrays in secure locations.
38
The instrumentation plan may include the following:
Monitoring frequency would vary widely for each of the instrument systems and for
each category of construction. Obtain initial measurements in advance of construction
so baseline data can be developed.
39
6.5.3 Action Levels
• Survey Monitoring Points: Monitoring points (e.g. targets, nails, etc.) can be
placed on shoring, utilities, structures, or in the ground to monitor lateral
movement over time (also used for vertical movement monitoring). The points
40
are measured using optical survey equipment at regular intervals during
excavation.
• Inclinometers: Inclinometers are instruments that monitor lateral
displacements. Inclinometers may be used to monitor slope stability and
performance. Near sensitive facilities, inclinometers may also be used to
monitor ground deformation caused by construction of embankments.
6.5.8 Other Instruments
• Crack Monitors: gages that measure cracks and joint openings in structures or
rock. It is recommended that these gages be installed on existing cracks and
sensitive joints of adjacent existing structures during the preconstruction
survey or other time prior to construction. The gages can then be used during
or after construction to monitor potential change.
• Monitoring Wells/VWPs (see Section 3.7): existing or new wells/VWPs can be
used to observe groundwater level change during construction dewatering.
• Liquid Level Gages: a system used to measure deformation along a linear
feature such as a utility, tunnel, or other long structure.
6.5.9 Data Reduction and Reporting
All data should be collected, reduced, and presented in useful, legible, and well
labeled plots in U.S. Customary units. The plots should include construction
information on construction activities associated with the monitoring program. Plots
might also include geotechnical data, including soil layers and groundwater levels, or
other features which may impact the interpretation of the data.
41
REFERENCES
AASHTO, 2011, Guide Specifications for LRFD Seismic Bridge Design, 2nd Edition.
AASHTO, 2015, LRFD Specifications for Structural Supports for Highway Signs,
Luminaires, and Traffic Signals, 1st Edition.
Abu-Hejleh, N., O’Neill, M., Hanneman, D., and Atwooll, W.J., 2003, Improvement of
the Geotechnical Axial Design Methodology for Colorado’s Drilled Shafts Socketed
in Weak Rocks, CDOT Research Branch, Report No. CDOT-DTD-R-2003-6.
Berg, R.R., Christopher, B.R., and Samtani, N.C., 2009, Design of Mechanically
Stabilized Earth Walls and Reinforced Slopes, Geotechnical Engineering Circular
No. 11, Report No. FHWA NHI-10-024.
Brown, D.A., Turner, J.P., and Castelli, R.J., and Loehr, E.J., 2018, Drilled Shafts:
Construction Procedures and Design Methods, NHI Course No. 132014,
Geotechnical Engineering Circular No. 10, Report No. FHWA NHI-18-024.
CDOT, 2019, Standard Specifications for Road and Bridge Construction, available at
https://www.codot.gov/business/designsupport/cdot-construction-
specifications/2019-construction-specifications/2019-specs-book
CDOT, 2012, Dynamic Sign Monotube Structures, Standard Plan No S-614-60, available
at: https://www.codot.gov/safety/traffic-safety/assets/s-standard-plans/2019/s-
614-60
CDOT, 2020, Laboratory Manual of Test Procedures, with 2021 Revisions, available at:
https://www.codot.gov/business/designsupport/materials-and-
geotechnical/manuals/2020-lab-manual-test-procedures-with-2021-corrections
DFI, 1997, Inspector’s Manual for Driven Pile Foundations, 2nd Edition.
42
DFI, 2004, Drilled Shaft Inspector’s Manual, 2nd Edition.
FHWA, 2003, Checklist and Guidelines for Review of Geotechnical Reports and
Preliminary Plans and Specifications, Report No. FHWA ED-88-053.
FHWA, 2009, Manual on Uniform Traffic Control Devices, with Revisions 1 and 2, May
2012.
International Society for Rock Mechanics, 1978, Suggested Methods for the
Quantitative Description of Discontinuities in Rock Masses, ed. Brown, E.T.
Mayne, P.W., Christopher, B.R., and DeJong, J., 2002, Subsurface Investigations,
Report No. FHWA-NHI-01-031.
Stark, Timothy, 2021, Drained Residual and Fully Softened Secant Friction Angles &
Shear Stresses, Excel Spreadsheet.
Wightman, W.E., Jalinoos, F., Sirles, P., and Hanna, K., 2004, Application of
Geophysical Methods to Highway Related Problems, Report No. FHWA-IF-04-021.
43
Appendix A:
Example Field Forms
(For information only. See
https://www.codot.gov/library/forms for official forms.)
Drilling Checklist
Job Number: Date:
Job Name: Subcontractors:
Location:
Field Representative:
Contacts (#s): Client/Owner:
Project Confidential?
Project Management
Purpose & description of work to be performed/completed:
Drilling Method
Hollow Stem Auger TUBEX/ODEX
Solid Stem Auger Mud Rotary
Rock Coring Air Rotary
Other Other
Field Checklist
Hole Completion
Type Monitoring wells, see instructions above.
Cuttings Backfill tailings borings with cuttings.
Bentonite
Sand
Jet Set
Asphalt Cold Patch
Other
Utility Locate
Utility Locate? (UNCC, 1-800-922-1987 for Colorado, or 811 locally from any state)
• Ticket Number(s):
• Other:
Special Instructions
Before leaving the office did you: Before leaving the site did you:
Read/copy the proposal? Complete logs?
Have a briefing with the project manager? Measure and map exploration locations?
Research local geology? Record Water Levels?
Research site conditions? Restore disturbed areas? Asphalt? Concrete?
Arrange for site access? Lock gates?
Other? Other?
Equipment/Materials Checklist
Personal Safety Gear Camera Clinometer Brass Tubes Hand Level Daily Reports
Rock hammer Compass Rangefinder Tube Caps Sunscreen Contact Lists
Screwdriver Measuring tape Markers/Pens Plastic Bags Truck Mileage Log Specs
Soil knife Flagging & stakes Compass Hand Level Engineering Plans
Rubber gloves Bucket & brush Sample Jars Survey Gear Maps (topo, geo)
Warm weather gear First Aid Kit Core Boxes Water File
Cold weather gear Spray Paint Duct Tape Rain Gear Permits
Water Level Indicator Clipboard Sampler Liners GPS Logs/Forms
Drill Interval Intact Rock Strength RQD Joint Spacing Joint Condition Groundwater Total
(feet) Description Rating RQD Rating Spacing Rating Description Rating Description Rating RMR Remarks
From To (0-20) (percent) (0-20) (feet) (0-20) (0-30) (0-15) (0-100)
FIELD LOG OF TEST PIT
LOGGED BY: ______ SUBCONTRACTOR: ______________________
Depth, Ft.
Samples
Sketch of ___________ Pit Side Surface Elevation: Approx. ____ Ft.
% Water
Content
Ground
Water
SOIL DESCRIPTION Horizontal Distance in Feet
0 2 4 6 8 10 12
0
10
NOTE
FIG.
12
WELL / VWP CONSTRUCTION LOG JOB NO.
TREMIE
SLOTTED
FILTER
DEPTH DEPTH
SOLID
POUR
SEAL
WELL / SAND BENT. CHIPS
VWP
(include OD/ID, slot (include seal or
VWP NO. width, pipe material, filter type, size,
FROM TO schedule, etc.) BENT. GROUT BENT. CEMENT FROM TO gINT code, etc.)
SOIL
Screen
Length
ft.
Sump
Length
ft.
NOT TO SCALE
Use Reverse Side if Desired
CASING JOINTS: Threaded End Cap Type: SER.# / PRESSURE RATING: VWP #1 / psi
Glued How Secured: VWP #2 / psi
DEPTH TO WATER AFTER INSTALLATION: ft. VWP # and Zero Zero Date and Time Readout
Reading Type Reading Temp of Reading Box S/N
#1 Saturated
SAND: bags
CEMENT: bags #2 Unsaturated
BENTONITE POWDER: bags #2 Saturated
BENT. CHIPS/PELLETS: bags
ADDITIONAL
SLOTTED PVC: ft. COMMENTS:
BLANK PVC: ft.
PILE DRIVING RECORD JOB NO.
SITE DATE
ELEV. OF TIP
REMARKS*
FT. BLOWS FT. BLOWS FT. BLOWS FT. BLOWS FT. BLOWS FT. BLOWS FT. BLOWS FT. BLOWS
0 15 30 45 60 75 90 105
1 16 31 46 61 76 91 106
2 17 32 47 62 77 92 107
3 18 33 48 63 78 93 108
4 19 34 49 64 79 94 109
5 20 35 50 65 80 95 110
6 21 36 51 66 81 96 111
7 22 37 52 67 82 97 112
8 23 38 53 68 83 98 113
9 24 39 54 69 84 99 114
10 25 40 55 70 85 100 115
11 26 41 56 71 86 101 116
12 27 42 57 72 87 102 117
13 28 43 58 73 88 103 118
14 29 44 59 74 89 104 119
15 30 45 60 75 90 105 120
Other comments (drilling equipment changes, contractor communication, out of roundness, change in cage elevation, weather,
changes to design):
The following checklists are provided to assist a reviewer with geotechnical reports concerning
CDOT projects. The checklists are only intended as guides, are not all-inclusive, and not a
replacement for a lack of geotechnical experience or knowledge. The checklists are modified
from the Federal Highway Administration (FHWA) Publication No. FHWA ED-88-053,
Checklist and Guidelines for Review of Geotechnical Reports and Preliminary Plans and
Specifications.
F. Landslides and Slope Stability – Including Checklist A, the report should include
general exploration techniques, monitoring results, and remedial options and their
associated estimated costs.
Modified from the FHWA Publication No. FHWA ED-88-053, Checklist and Guidelines for Review of Geotechnical Reports and
Preliminary Plans and Specifications.
Rev. 06/2021 Page B-1
A. GENERAL REPORT INFORMATION YES NO N/A
□.......... □ ......... □
Is there a general project scope and purpose? .......................................................
Is there a project location description included or a vicinity map? ......................... □.......... □ ......... □
Is there a detailed description of the field investigation and procedures? ................ □.......... □ ......... □
Is there a detailed description of:
Soil characteristics (density, color, depth/elevation, etc.)? ........................ □.......... □ ......... □
Bedrock characteristics (hardness, jointing, depth/elevation, etc.)? ............ □.......... □ ......... □
Is a legend provided that is easy to use and informative? .......................... □.......... □ ......... □
Are exploration locations plotted (boring, penetrometer, seismic, etc.)?..... □.......... □ ......... □
Are exploration logs (boring, penetrometer, etc.) presented? ................................. □.......... □ ......... □
Are geologic units presented visually and described in detail? .................. □.......... □ ......... □
Are sample types, labels, and depths reported? ........................................ □.......... □ ......... □
Is exploration method reported (wireline, auger, penetrometer, etc.)? ........ □.......... □ ......... □
Are testing data presented (blow counts, recovery, RQD, etc.)? ................ □.......... □ ......... □
Are estimated minimum tip elevations provided along with reasoning? ................. □.......... □ ......... □
For friction bearing piles, is a bearing capacity vs. depth chart/table provided? ...... □.......... □ ......... □
For boulder/cobble units, has driving been analyzed to verify tip
elevation and determine if there will be any pile damage? .................................... □.......... □ ......... □
Is minimum penetration into bedrock provided for end bearing piles? ................... □.......... □ ......... □
Is PDA required per CDOT Standard Special Provision 502? ............................... □.......... □ ......... □
Are resistance factors provided per AASHTO LRFD Bridge Design
□ .......... □ .......... □
Specifications? .........................................................................................................
Is predrilling recommended and does evidence support it? ................................... □.......... □ ......... □
Are materials testing results for corrosion provided (sulfate, resistivity, pH,
□.......... □ ......... □
chlorides)? ........................................................................................................
Have pile driving effects been considered (damage to homes and noise in
urban areas, environmental impacts)?.................................................................. □.......... □ ......... □
Modified from the FHWA Publication No. FHWA ED-88-053, Checklist and Guidelines for Review of Geotechnical Reports and
Preliminary Plans and Specifications.
Rev. 06/2021 Page B-3
Has the site been analyzed for AASHTO Specifications for LRFD
Seismic Bridge Design? ..................................................................................... □.......... □ ......... □
Is the site classified (letter) along with a seismic zone (number)? .............. □.......... □ ......... □
Modified from the FHWA Publication No. FHWA ED-88-053, Checklist and Guidelines for Review of Geotechnical Reports and
Preliminary Plans and Specifications.
Rev. 06/2021 Page B-4
C. FOUNDATIONS – DRILLED SHAFT (CAISSON) YES NO N/A
Is bedrock elevation provided? ........................................................................... □.......... □ ......... □
Based on materials and drilling, is casing or slurry required to maintain hole
stability? ........................................................................................................... □.......... □ ......... □
Based on groundwater data, could dewatering or tremie concrete placement
be required per CDOT Standard Specification 503? ............................................. □.......... □ ......... □
Are capacities (end bearing and side shear) provided? ......................................... □.......... □ ......... □
Are estimated minimum tip elevations provided along with reasoning? ................. □.......... □ ......... □
For friction bearing shafts, is a capacity vs. depth chart/table provided? ................ □.......... □ ......... □
Is minimum penetration into bedrock provided for end bearing shafts?.................. □.......... □ ......... □
Has lateral load analysis been performed or are analysis parameters provided? ...... □.......... □ ......... □
Modified from the FHWA Publication No. FHWA ED-88-053, Checklist and Guidelines for Review of Geotechnical Reports and
Preliminary Plans and Specifications.
Rev. 06/2021 Page B-5
D. FOUNDATIONS – SPREAD FOOTINGS YES NO N/A
Is bearing capacity vs. depth/elevation vs. footing size provided? ......................... □.......... □ ......... □
If not, is there a recommended depth/elevation, footing size, and
□.......... □ ......... □
bearing capacity? ...................................................................................
Are materials testing results for corrosion provided (sulfate, resistivity, pH,
□.......... □ ......... □
chlorides)? ........................................................................................................
Based on groundwater data, is construction dewatering required and discussed? .... □.......... □ ......... □
Is a minimum depth of embedment recommended for frost protection? ................. □.......... □ ......... □
Has settlement been evaluated using parameters based on lab testing, and
□ .......... □ .......... □
estimated values and time reported? ..........................................................................
Are settlement values reasonable?........................................................... □.......... □ ......... □
Has global stability been evaluated using shear strengths based on lab testing? ...... □.......... □ ......... □
Have excavation parameters (shoring, sloping, sheeting, etc.) been discussed? ...... □.......... □ ......... □
Has the site been analyzed for AASHTO Specifications for LRFD Seismic
□ .......... □ .......... □
Bridge Design)? .........................................................................................................
Is the site classified (letter) along with a seismic zone (number)? .............. □.......... □ ......... □
Modified from the FHWA Publication No. FHWA ED-88-053, Checklist and Guidelines for Review of Geotechnical Reports and
Preliminary Plans and Specifications.
Rev. 06/2021 Page B-6
E. RETAINING STRUCTURES YES NO N/A
Is recommended wall type appropriate based on site conditions? .......................... □.......... □ ......... □
Has settlement been evaluated using parameters based on lab testing, and
□ .......... □ .......... □
estimated values and time reported? ..........................................................................
Are settlement values reasonable, i.e., within limits of wall design? .......... □.......... □ ......... □
Has groundwater been considered (drainage, fluctuations, stability, etc.)?
Are materials testing results for corrosion provided (sulfate, resistivity, pH,
□.......... □ ......... □
chlorides)? ........................................................................................................
Is a bearing capacity vs. depth elevation vs. footing size provided? ....................... □.......... □ ......... □
Soil parameters provided (unit weight, friction angle, cohesion, etc.)? ................... □.......... □ ......... □
For soil nail and tieback walls, are estimated bond strengths reasonable?............... □.......... □ ......... □
Modified from the FHWA Publication No. FHWA ED-88-053, Checklist and Guidelines for Review of Geotechnical Reports and
Preliminary Plans and Specifications.
Rev. 06/2021 Page B-7
F. LANDSLIDE AND SLOPE STABILITY YES NO N/A
Is a scaled cross-section provided showing slide characteristics (soil profile,
water table, soil unit weights, inclinometers, failure plane, etc.)? .......................... □.......... □ ......... □
Were sufficient monitoring points (inclinometers, piezometers, etc.), installed
to properly characterize the slide? ....................................................................... □.......... □ ......... □
Is history of the slide area summarized including movement, maintenance
work and costs, and any corrective measures taken?............................................. □.......... □ ......... □
Has modeling been performed to evaluate triggering mechanisms and
possible remedial measures?............................................................................... □.......... □ ......... □
Are detailed slide features (ground surface cracks, headscarp, toe bulge,
etc.) shown on the site plan? ............................................................................... □.......... □ ......... □
For an active slide, was soil strength along the slide failure plane back-
calculated using a F.S. = 1.0 at the time of failure? .............................................. □.......... □ ......... □
For an existing slide, are residual shear strengths used? ............................ □.......... □ ......... □
Modified from the FHWA Publication No. FHWA ED-88-053, Checklist and Guidelines for Review of Geotechnical Reports and
Preliminary Plans and Specifications.
Rev. 06/2021 Page B-8