Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

MS-Remedial Action - 002-Blinding

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

Project Name: ALL SAINTS WWTW

Contract Number: SCMU5-21/22-0019


Project Number: MJCP-02/2022
Document Type: Method Statement

_______________________________________________________________________________________________
MS Number: MS-Remedial Construction MS Maturation Remedial Date: 2023/01/18
001 Tittle: Action
MS-Revision 00
1. Introduction:
The Purpose of this document is to discuss how site establishment will be done.
2. References:
a) Construction drawings f) Project Occupational health and safety specification
b) Site Instructions g) Occupational health and safety Act 1993
c) SABS 1200 G h) Construction regulations
d) Project specifications i) Project-SHE Plan
e) Approved Method statements
3. Man-Power plan, Tools and Equipment’s and PPE to be used.
3.1. Man- power plan 3.2. Tool and Equipment’s 3.3. PPE
Plant: Power tools: Hand Tools: -Overall (work suits)
- 1xConstruction Manager -None. -None -Shovels/spade - Boots
- 1xConstruction Supervisor -Straight edge - Rain suits
-Floats - Masks
-Dumpy Level -

Problem statement (s):

1. AS per SI 024 , The engineer has requested level to make a ruling on the finishing or appearance of the concrete casted on the surface as
blinding. Based on the visual inspection the engineer required that the Levels be picked to determine whether they are within the tolerance.
2. The tolerance is to be measured under SABS 1200 G ,6.2.3 (C) (4) , endorsed by the contract document page 219 ( see extracts attached below):

-
SABS 1200 G ,6.2.3 (C) (4)
-
3. The Spreadsheet is attached.
Proposed Repair method.

1. The Contractor has taken readings onsite , in the presence of the RE , and the reading are attached herein for further assessment by the Engineer.
2. As guided by the level checks ,all the Levels that are outside tolerance will be treated as follows.

 The levels that are below the -30mm requirement will be filled with screeds.
 The Levels that are above the +15mm requirement will be cut out to level.

3. Filling :

 The Surface where screeding is required will be cleaned to remove any loose material or debris. This will be done by sweeping the floors
with brooms and also sprayed with water to removed dust and hard soils.
 Screed will be mixed onsite as per these proportions :
 1 x 50kg , 42,5 N Cement Mixed with 3,5 Wheelbarrows of ( 1:3,5)
 Once the screeds are mixed, they will be place onto the cleaned surface and be levelled using a straight edge against the levels set out on
the surface.
 The treated area will be left to set( harden) and then a curing method will be applied. Water will be poured on the treated surface as a
measure to assist the are to cure.
4. Cutting :
 Any surface that is above the design level by + 15mm will be trimmed off by use of a chipping hammer or drill or Grinder.
 After the trimming is confirmed, the cleaning will be done and the are will be ready for the next stage of work.
5. After all the corrections are done the work will be verified by the Contractor and the Engineer. All records of inspections will be kept in the
quality file for reference.

You might also like