Ynk Installation Manual
Ynk Installation Manual
Ynk Installation Manual
:GES-001
YNK
Version:00
Installation Manual
Pages: 1 / 63
Modification Record
V Approved
Modification Description Revised By Date Date
Version By
00 First release
04
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 1 / 63
6. Car installation
8. Shaft wiring
1 ShaftInstallation Preparation
1.1.1 Layer door entrance installed to meet the safety requirements of the
protection device (guard), as shown in the following figure demands:
1.3 Scaffolding
First two lifelines the shaft fixed connection before entering the shaft.
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 5 / 63
In order to facilitate the shaft operation, according to the construction site of the case
and the relevant provisions of the local fixed reliable location lifeline.
The upper cam holder mounted on the shaft top level under about 1 meter the lower cam
being mounted in the pit, place approximately pit on the ground 1 meter. Up and down
like a model shape. The position of the template should not impede the intended position
of the long elevator apparatus. Installed at the top of the shaft the line transect board,
according to the arrangement drawing in line transect board put line adjustment of the
template, and the center of the next template logo and aligned with the plumb line, plumb
line fixed the next template.
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 6 / 63
Civil engineering layout elevator equipment under the contract, to determine the car
centerline, as far as possible so that A equals B.
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 7 / 63
A B
Warning
To ensure proper installation, construction tolerances should be guaranteed in a
certain range.
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 8 / 63
TH R ≤ 30 m 0~+25mm
60 m< R ≤ 90 m 0~+50mm
The installation layer gate device installed Door, layer gate device and Door
connection to be installed as shown.Mounting holes in the upper layer gate
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 9 / 63
device.Expansion boltM12 × 100 layer door unit temporary fixed mount.To be on the
threshold frame adjustment is completed and then tighten the bolts and nuts.
2.1.1 On the sill frame center identified and on the sill frame verticality adjustment
requirements: below left adjusted on the sill frame centeron the sill frame
vertical degrees below at right adjustment.
7±1
上坎架中心
层门地坎线
42.5±1
±1以内
导轨高 HH+70±2
轿厢出入中心
2.1.2 Landing door lifting adjustments: adjustments in place first door hanging
board,then install, adjust layer door panels.Layer door panels with a steel
ruler measuring the upper and lower ends and Door gap, in line with the icon
requirements and ensure the verticality of the door.
2.1.3 Installed hammer: the first hammer guide is mounted on the door panels,
upper door side connection, the lower part of the door and head
connection.Hammer and then loaded into the guide member, hang the rope
on the pulley, and the other end is fixed to the rope fixing plate is secured
with bolts off prevention member, it and the gap of the pulley is less
than2.5mm, and does not touch the pulley.
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 10 / 63
+2
3 -3 门全开
门套
±1以内
前后差
+2
4-1
门全闭
B=2-10
插入1枚以上的
调整垫片
门的间隙
0≤(A-B)≤0.5 倾斜度
±2以下
±2以内
上下差
地坎面
+1
5-2
A=2-10
Figure 18
Landing door apparatus rope tensioning the synchronizing rope adjustment in the
opener means, requirements in the door fully open state, and after adjustment with a
fastening nut.
接点的随动量
门挂板的倾斜度
2.5±1
(A-B)在±1以内
锁钩
挂板滚轮 接点(开启时)
2±1
E=0.1~0.3
A=4±1
门导轨 接点(关闭时)
B=4±1
拧紧力矩115~156kgf.cm 2±1 挂钩
上压滚轮
全闭状态时调整
Figure 19Figure 20
Note: the bottom of the rail bracket the code installation must level
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 13 / 63
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 14 / 63
Hoist female end of the rail down the male end up, followed by hanging into the
bottomless pit.And shaft space, rely on the shaft wall end of the rail, each rail shall be
placed vertically installed interface board, and the male end.
Rail lift, hoist mounting the rail rack from bottom to top.
IMPORTANT NOTE
Note: the rail and the rail joints must the rasp manually filing, forbidden to use grinder!
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 17 / 63
Traction machine damping pad installed on the load-bearing, and the use of the
template frame positioning traction machine, pay attention to the specifications and
location of the damping pad.
Installation damping pad platen
Platen
Installation guide wheel and adjust the position of the guide wheel pad welded beam
in the machine, as shown in the figure.
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 19 / 63
4 sets expansion bolts used for mounting the control cabinet pre-assembled at the
factory, according to the civil layout shown the location of installation of control
cabinet.
Note:
a) Motor, brake wiring, the governor wiring first into the metal tube, and
then into the trough.
b) When the power lines and control lines are in the same trunking
alignment of the power line cable tube in the trough, and fixed at both ends so
that the separation of power lines and control lines. Line pipe and duct ground.
Machine room trunking and cable laying Please see attached electrical laying
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 20 / 63
Note
Until after the alignment, 210Nm torque to tighten the bolts with a torque
wrench
Note
Spirit level and square to the side beam is perpendicular to the surface of the lower
beam
Note
Until after the alignment, 210Nm torque to tighten the
bolts with a torque wrench
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 25 / 63
Note:Please use horizontal ruler to adjust the level of the upper beam degrees
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 26 / 63
Note
Spring pre-compression length L from:
DL=630KG L=180
DL=800KG L=178
DL=1000KG L=175
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 32 / 63
6 Car installation
Beams mounting arm installation and car top Installation: When the beams mounting
arm installation below left straight beams in the car to install the crossbar mounting
arm, good oblique trolley is connected temporarily fastened until the door machine
adjusted to tighten the nut; would open the doorThe position of themachine in the
A-holemounting arm and beams installed.Below right when the car roof installation
installed in the car on top of the C-tube door, temporarily fastened to be adjusted and
then tighten the nut.Ensure consistent the Opener center and car access center.
50
斜拉杆
EE 轿厢地坎端线
100
轿厢地坎端线
3-A孔
M16×40 横梁安装臂
升高轿厢HH+510
07标准轿厢HH+405
06型: HH+405
A B
Opener installation: Figure by beams installed arm waist Hole andB to adjust door
opener from front to back, so that the waist hole through the door on side plate rail
and the car door
Hum the horizontal distance 58 ± 1mm, height direction and the sill guarantee HH
+87 ± 1mm, with reference to the connection level trolley assembly diagram (cabin
top installed withoutConnection).The above dimensions shall also comply with the
sides of the door opener.The height direction of the rail and the sill of the landing door
and the horizontal direction respectively HH +70, 43.5.
Sedan door installation: Figure with M8 bolt assemblies in small packets to door lifting
good Figure installed door slider, if the door is tilted in the door and hang
Board increase or decrease the gasket between vertical until you adjust the door.The
door inclination and seam gap to ensure that less than 2 mm.
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 40 / 63
层门导轨
轿门导轨 垫片
垫片
门滑块
轿门地坎 层门地坎
轿门地坎
轿门地坎
刀片连杆2和连杆3之间
确保有10mm间隙
层门地坎
滚轮
连杆2
连杆3
°
95
约
大
Blade adjustment: TKP131-06 opener door knife adjusted as shown in the Figure (A =
B = 10 ± 5) adjusted to maintain a state of self-locking blade and wheel in place
when the door opened; Shown off, the distance between two hanging panels of 50mm,
to open the door when the right spring locking cam locking device, movable blade
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 41 / 63
closed, size 72 to 46, then synchronized door knife and peg board synchronous
movement, open the door to start.The locking cam is moved upward or compression
of the locking means spring locking force can be increased.
到位打杆梢
门刀挡板
锁紧装置凸轮
锁紧装置弹簧
Closed stroke dimensions: closed place between two hanging plate distance of 50mm,
if it is not linked to fine-tune the plate hit the block extended length; Check the opening
stroke is reached (TKP131-06 to open the door itinerary JJ +32), if you reach
adjustment The hanging plate collision block extended length until it reaches the
requirements.
gf gf
张紧方向 张紧方向
电机皮带轮
型滑轮
门挂板的倾斜度
(A-B)在±1以内
挂板滚轮
门导轨
上压滚轮
The Safety Edge adjust: Safety Edge specific requirements according to diagram (the
diagram to the right part of TKP131-06 Safety Edge for example):
The safety contact plate is mounted on the car doors, and adjust the stopper, so that
the touch panel rotary projecting a maximum of 48 ± 2mm;
The length of the connecting rod A1 is selected according to the sizes and the
temporary fixing, and then the door is fully closed position to the touch panel is
pushed away from the door end16±2mm, and the clockwise direction touch panel,
encountered on the stopper A baffle position (left part when
counterclockwise),temporary fixed camwiththree M6 screws and
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 43 / 63
门板
轿门框 门中线
TKP131-06安全触板调整图
门板
轿门框 门中线
TKP131-07安全触板调整图
在安装现场开4mm孔打4X12的弹性圆柱销
臂
连接杆
触板 螺钉
挡块B
导轮
铝
型
材
挡块A
微动开关
挡板
Open the door to the fully open position, the door fully open position to confirm the
front end of the Safety Edge highlights13 ± 2mm, small connecting rod length
greater than 15mm should tune A1.And then set the touchpad, less than 15mm zoom
connecting rod length A1.
When maximum indentation of the touch panel for the door fully open position, the
stopper B adjusted to just touches the arm position, adjustment after drilling into fixed
Ф 4 holes with a spring pin.
Adjusted to the touch pad stroke adjustment bolt action micro switch should be 3 ~
6mm.
Note:
Fence since with standard parts
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 45 / 63
Balance block
Compensating chain bracket Pit intercom
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 46 / 63
7.1 Brought into the bottomless pit of the heavy framework, put on heavy
rail
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 49 / 63
8 Shaft wiring
20050mm
1. Optional: If you re-frame with safety gear, the installation of this tension device
2. Car or the re-tensioner weight underside from the ground height requirements
of 200 50mm.
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 54 / 63
9.4 Hall call box installation and on-line safety circuit wiring (safety circuit
Call the bottom of the cartridge with the distance from the ground must 1.2M, call cartridge
surface with the outer wall of the vertical ± 1MM
1.Install the
compensating chain
below the cabin bottom
The door light curtain transmitter and receiver, with screws along in the car
door or door pillar (next door)
No.:GES-001
YNK
Version:00
Installation Manual
Pages: 62 / 63