Experiences Using Risk Graph & LOPA
Experiences Using Risk Graph & LOPA
Experiences Using Risk Graph & LOPA
Some Experiences using Risk Graph and LOPA in Conducting SIL Determination Study
Mefredi, CFSE
BP West Java. E-mail: mefredi@se1.bp.com
Abstract. Risk Graph and LOPA methods have been used to determine the required Safety Integrity Level. Both are most popular methods compared to other methods outlined in the SIS standard for process sector IEC 61511. Risk graph is a structured means to determine ILs using semi quantitative judgment based on series of parameters that are relevant to a risk. LOPA is one of process hazard analysis methods, which are also used to determine ILs. LOPA starts with the identification of initiating cause and protection layer of hazard mitigation. Both Risk Graph and LOPA are suitable tools to determine ILs based on complexity of process being assessed. In general, Risk Graph is particularly appropriate for screening application, while more detail study can be done using LOPA. This paper presents an overview of Risk Graph and LOPA. Results of applying those methods to existing offshore facilities, required documents and other aspects towards more effective workshop are also presented. It can be concluded that LOPA may give lower ILs compared to the Risk graph, but the shortcoming of LOPA is that it is more complex and time consuming. Keywords: Risk Graph, LOPA, Safety Integrity Level, Safety Instrumented System
requires the hazard and risk assessment to be carried out in order to identify the overall safety requirements; requires the allocation of safety requirements for safety instrumented system(s) to be carried out; works within the framework which is applicable to all instrumented methods to achieve functional safety; discusses the use of specified activities, such as safety management, that may be applicable to all methods for achieving functional safety. IEC 61511 also deals with guidance to determine Integrity Level (IL) in hazard and risk analysis processes. Within this standard, information is given to provide broad overview of the methods used in hazard and risk analysis process. There are many methods to determine the Integrity Level required, and they are addressed in IEC 61511 standard: Qualitative Safety Matrix Qualitative Risk Graph Semi Qualitative (Calibrated) Risk Graph Semi Quantitative using LOPA (Layer of Protection Analysis) In normal approach for risk-based standard document, i.e. IEC 61511, the guidance provided contains insufficient details for direct implementation. All methods to illustrate underlying principle have been subjected to simplification. The user will need to explore the real practice on how to implement the guidance to fit with each corporate or organization guideline. Many companies feel that the qualitative methods are not consistent with their risk criteria. In this regard, Calibrated Risk Graph and LOPA are able to provide alignment with the risk criteria of a company. In present paper, author would like to discuss about the workshop-based experiences using Calibrated Risk graph and LOPA method to determine ILs for either newly designed or existing-modified facilities. This paper aims to give reader a brief overview of Safety Integrity Level (SIL) determination workshop, available methods, required documents, and team involvement to achieve effective results.
1. Introduction
Safety Instrumented System has been used for many years to perform safety instrumented function in the process industries. If instrumentation is to be effectively used for safety-instrumented functions, it is essential that this instrumentation achieve certain minimum standard and performance levels. The international standard addressing the application of safety-instrumented system in the process industries is IEC 61511, which was finally published in 2003. IEC 61511 is process sector under the framework of IEC 61508 that covers all safety-related system. Within this standard, there are two fundamental concepts pertaining to their application, namely safety lifecycle and safety integrity level. IEC 61511 sets out an approach for safety life-cycle activities in order to achieve the performance standard. To achieve this objective, the IEC 61511:
Mefredi - 7
W3
CA X1
W2
W1
a a 1 2 3 4
--a a 1 2 3
----a a 1 2
X2 P A CB FA FB CC FA FB CD FA FB PB P A PB PA P B PA P B X6 X5 X4 X3
C = Consequence parameter F = Exposure time parameter P = Possibility of avoiding the hazard W = Hazard rate if SIS fails to act on demand
--- = No safety requirements a b = No special safety requirements = A single E/E/PES is not sufficient
Table 1. Safety Integrity Level DEMAND MODE OF OPERATION Target average probability of Target Risk Reduction failure on demand (PFD) Factor (RRF) 1 1 10-0 10-1 1 10 10-1 10-2 10 100 10-2 10-3 100 1,000 10-3 10-4 1,000 10,000 10-4 10-5 10,000 100,000
Mefredi - 8
ISSN: 1829-9466 2007 Journal of the Indonesian Oil and Gas Community. Published by Komunitas Migas Indonesia
One can determine Safety Integrity Level, Environmental Integrity Level and Commercial Integrity Level based on four discrete levels as specified in Table 1 for demand mode operation. Overall, integrity level of the highest IL requires safety, environmental or commercial category, and in general term, this level is called Safety Integrity Level (SIL).
consequence will not occur. Each protection layer counted must be independent of other protection layers, which means that there must be no failure that can deactivate two or more protection layers. If a protection layer is believed to be more reliable (a lower value for Probability of Failure on Demand PFD), a quantitative method should be used to confirm the PFD. For example, if the team desires to improve the unavailability of risk reduction logic in the Basic Process Control System (BPCS) by adding additional sensors or final elements, the impact event should be reviewed by a quantitative method such as Fault Tree. Some set rules for protection layer are: Specifically designed to prevent or mitigate consequences of a potentially hazardous event Dependable and can be counted on to do what it was intended to do Auditable and a system to audit and maintain Using the numerical values identified in the preceding steps, a simple calculation is performed to determine the PFDSIF. The numerator of the PFDSIF is the Mitigated Event Likelihood MEL (column-10), which is the companys risk tolerance for that scenario. The denominator of the PFDSIF is the product of the Initiation Likelihood and the Probability of Failure on Demand (PFD) of each Independent Protection Layer (IPL) identified. The formula for calculating the PFDSIF is presented below
PFDSIF =
If the PFDSIF is greater than or equal to one then existing protection layers in place are adequate. If the PFDSIF is less than one then SIF is required to provide necessary risk reduction to bring the process risk to a tolerable level. LOPA is used to determine the required Risk Reduction Factor (RRF) and Safety Integrity Level (SIL) for a Safety Instrumented System (SIS). To do this, the LOPA is calculated without giving any credit to the existing SIS. The RRF is calculated by taking the inverse of the PFDSIF
1 PFD SIF
Mefredi - 9
ISSN: 1829-9466 2007 Journal of the Indonesian Oil and Gas Community. Published by Komunitas Migas Indonesia
Another way is to identify SIFs by examining the engineering drawing such as P&IDs. Existing plant may have SIF depicted in P&IDs. Care should be taken when identifying the SIFs from P&ID. In some cases, expert judgment is required. Bear in mind that not all functions depicted in P&IDs are safety function. Some of the functions may only serve as an operational control function or alarm function. Identification of SIFs from engineering drawing P&IDs, Cause and Effect or SAFE chart may not cover the recommended SIFs as depicted in PHA/HAZOP report. In many cases, we also need to re-identify the hazardous event and initiating causes.
Pressure relief valve, operator intervention to high pressure alarm Pressure relief valve, operator intervention to high pressure alarm Low outlet flow pump shutdown (SIF)
SOV
Excerpt of PHA/HAZOP report also provides information of available existing SIF (i.e. low outlet pump shutdown). Both SIFs are qualified to go to further analysis with Risk graph or LOPA methods.
Mefredi - 10
ISSN: 1829-9466 2007 Journal of the Indonesian Oil and Gas Community. Published by Komunitas Migas Indonesia
shall understand PHA/HAZOP and SIL determination methods, particularly understand the likelihood and potential consequences of event. Within the mature organization, the team members are usually familiar with PHA/HAZOP methods as they have prior experiences. It is found to be useful that the team members undergo the introduction training prior to attend the workshop. Having the awareness of SIS concepts, Risk Graph and LOPA methods, team members will gain the effective results. It will be perfect if the chairman/facilitator have the capability to explaining the methods just before the workshop started, say a half day of the first day within workshop schedule. This is proven useful since the team member will have refreshed memories. Workshop will flow smoothly, and may reduce time consumption, as all team members understand the methods and objective. In this regards, they may be able to contribute in a positive way. Based on reliable information received by author, some workshop was started without giving proper knowledge preparation for team members. In this event, after completing one week of SIL determination workshop, some team members still do not understand the basic concept of Safety Instrumented System and Safety Integrity Level. In authors viewpoint, this workshop cannot be categorized as an effective workshop.
LOPA assessment was also performed to the 80 SIFs. They were assigned as SIL 2 and above. The results left only 3 functions with SIL 2, and there was no SIL 3. The results of SIL determination based on LOPA assessment are summarized in Table 4. Table 3 ILs result using Risk Graph SIL Rating No of SIF NO IL 47 SIL 0 12 SIL 1 33 SIL 2 49 SIL 3 31 TOTAL 172 Table 4 ILs result using LOPA SIL Rating No of SIF NO IL 61 SIL 0 45 SIL 1 63 SIL 2 3 TOTAL 172 Comparing the results in Table 3 and Table 4, it can be seen some lowering of SIL required by one level or even two levels. It is important to note that this comparison can only be done if the Risk Graph has been calibrated with the same tolerable risk criteria used in LOPA. Analysis of totally 210 functions was completed within six-day workshop and the other 3-day was used to complete 80 SIFs, which had SIL 2 or SIL 3 rating. During 8-hour per day workshop, averagely 25 30 SIFs can be completed using Risk Graph method and averagely 20 25 SIFs using LOPA. The duration is expected to be longer if the assessment is conducted in spreadsheet tools. It is commonly known that the progress is a little bit slow in the beginning of assessment. However, as team member are familiar with the methods and scenarios, the progress will be faster. In addition to the above, LOPA can provide more detail results since it has information of required numerical PFD and associated SIL rating.
5. Conclusion
Based on some experiences using Risk Graph and LOPA, the conclusions can be drawn as follow: Risk graph and LOPA are suitable methods as SIL determination technique, and able to provide alignment with corporate risk criteria Risk Graph aims to be a screening method while LOPA aims to provide more detail assessment LOPA results will generally have lower SIL and time consuming than Risk Graph, but LOPA can provide more detail information
Mefredi - 11
ISSN: 1829-9466 2007 Journal of the Indonesian Oil and Gas Community. Published by Komunitas Migas Indonesia
Effective SIL determination workshop can be achieved by equipping team members with useful knowledge of the methods prior to the workshop.
6. References
[1] IEC 61511-3, Functional safety Safety instrumented systems for the process industry sector. Part 3: Guidance for the determination of the required safety integrity levels [2] GP 30-76, Guidance on Practice for Safety Instrumented Systems (SIS) Development of the Process Requirement Specification, BP Group Engineering Technical Practices, 2003 [3] Ed Marszal and Eric Scharpf. Safety Integrity Level Selection, Systematic Methods Including Layer of Protection Analysis, The Instrumentation, Systems and Automation Society ISA, 2002 [4] Layer of Protection Analysis, Simplified Process Risk Assessment, CCPS, 2001
7. Biography
Mefredi currently works for BP West Java as Fire & Gas Safety Instrumented System Engineer and Technical Authority. He obtained B.S. degree in Electrical Engineering from Institut Teknologi Bandung in 1997. He has over nine years of experience in oil and gas operating industry with area of interest of E&I Engineering, Risk Assessment, Process Safety Integrity Management, Operation and Maintenance, as well as SIS engineering, SIL Determination and Verification Study. He also holds a Certified Functional Safety Expert CFSE, a TV certification in area of functional safety.
Mefredi - 12