CS 2-03 (Version 3)
CS 2-03 (Version 3)
CS 2-03 (Version 3)
CS 2-03
COMMISSIONING SWITCHING
SCHEDULES
Copies or prints of the electronic master will only be valid on the day of copying or printing
Central Networks plc Protection, Control, Automation & Signalling
Commissioning Specification
CS 2-03
Commissioning Switching Schedules
Document Author
Graham Brewster
Central Networks plc
Copies or prints of the electronic master will only be valid on the day of copying or printing
Central Networks plc Protection, Control, Automation & Signalling
Commissioning Specification
CS 2-03
Commissioning Switching Schedules
REVISION LOG
Copies or prints of the electronic master will only be valid on the day of copying or printing
Central Networks plc Protection, Control, Automation & Signalling
Commissioning Specification
CS 2-03
Commissioning Switching Schedules
CONTENTS
1. INTRODUCTION 6
2. DEFINITIONS 6
3. ASSOCIATED DOCUMENTATION 6
4 GENERAL REQUIREMENTS 6
4.1 General 6
4.15 Format 12
Copies or prints of the electronic master will only be valid on the day of copying or printing
Central Networks plc Protection, Control, Automation & Signalling
Commissioning Specification
CS 2-03
Commissioning Switching Schedules
Copies or prints of the electronic master will only be valid on the day of copying or printing
Central Networks plc Protection, Control, Automation & Signalling
Commissioning Specification
CS 2-03
Commissioning Switching Schedules
1. INTRODUCTION
2. DEFINITIONS
Definitions of some of the terms used within this document can be found in
Commissioning General CG-02: Commissioning Terminology.
3. ASSOCIATED DOCUMENTATION
4. GENERAL REQUIREMENTS
4.1 GENERAL
Copies or prints of the electronic master will only be valid on the day of copying or printing
Central Networks plc Protection, Control, Automation & Signalling
Commissioning Specification
CS 2-03
Commissioning Switching Schedules
The title page of the commissioning switching schedule shall include the following
information:
− Title (Commissioning Switching Schedule)
− The name of the construction project
− The substation where the new or modified equipment is located
− The circuit on which the new or modified equipment resides
− The date on which energisation and on-load testing is to take place
− The version number of the schedule
− The person responsible for preparing the schedule (Protection Commissioning
Engineer) and the date of preparation
− The person responsible for endorsing the schedule (Protection Commissioning
Supervisor) and the date of endorsement
− The persons responsible for accepting the schedule (Central Networks Contract
Manager / Project Manager & Control Engineer) and the date of acceptance
The commissioning switching schedule shall be separated out into eleven sections as
follows:
− Introduction
− Unproven equipment
− Key stages
− Circulation list
− Personnel executing switching schedule
− Communications
− Pre-energisation checks
− Agreement to proceed
− Initial starting conditions
− Switching, energisation inspections and on-load testing
− Final switching
Copies or prints of the electronic master will only be valid on the day of copying or printing
Central Networks plc Protection, Control, Automation & Signalling
Commissioning Specification
CS 2-03
Commissioning Switching Schedules
The key stages section shall summarise the significant activities to be undertaken. It
shall typically include:
− Identification of the proven primary and protection equipment to be used to
energise the unproven equipment & whether temporary relay settings are
required
− Energisation inspections of unproven equipment
− Naming of the location where phasing out of the primary circuits is to take
place
− The arrangements for the application of load current
− On-load testing of unproven equipment
The circulation list section shall identify all individuals involved with, or affected by the
energisation inspection and on-load testing process, including:
− Control Engineer
− Protection Commissioning Engineer
− Protection Commissioning Supervisor
− Central Networks Contract Manager / Project Manager
Copies or prints of the electronic master will only be valid on the day of copying or printing
Central Networks plc Protection, Control, Automation & Signalling
Commissioning Specification
CS 2-03
Commissioning Switching Schedules
All personnel on the circulation list shall receive draft copies of, and be encouraged to
make comments on, the commissioning switching schedule.
All personnel on the circulation list shall receive a copy of the final version prior to the
implementation of the commissioning switching schedule.
The personnel executing the switching schedule section shall identify all individuals to be
involved with the execution of the commissioning switching schedule. It shall typically
include:
− Control Engineer
− Protection Commissioning Engineer
− Protection Commissioning Supervisor
− Central Networks Contract Manager / Project Manager
− Other personnel assigned to operational switching duties
The communications section shall list the contact telephone numbers for those
personnel responsible for implementing the commissioning switching schedule
(identified in section 4.8).
It shall include:
− Control room telephone numbers (plus the planned work approval number for
the telephone operated menu system)
− Relevant substation telephone numbers
− Appropriate mobile phone numbers
Copies or prints of the electronic master will only be valid on the day of copying or printing
Central Networks plc Protection, Control, Automation & Signalling
Commissioning Specification
CS 2-03
Commissioning Switching Schedules
The pre-energisation checks section shall identify the pre-energisation checks that
must be completed before the commissioning switching schedule can commence.
The ‘agreement to proceed’ section shall identify those parties who have responsibility
for the safety of personnel, the integrity of the distribution / transmission / customer
network and ownership of the equipment to be energised. All parties are required to
signal their agreement to proceed with the execution of the Commissioning Switching
Schedule.
Guidance Note
Copies or prints of the electronic master will only be valid on the day of copying or printing
Central Networks plc Protection, Control, Automation & Signalling
Commissioning Specification
CS 2-03
Commissioning Switching Schedules
− Control Engineer
− Central Networks Contract Manager / Project Manager
− External Service Provider / Principal Contractor’s Project Manager
The initial starting conditions section shall identify the status of plant and equipment that
must be achieved before the commissioning switching schedule can commence.
The plant and equipment whose status is to be identified shall include all those which
are affected by the commissioning switching schedule and not just those elements
which form part of the construction works.
The switching, energisation inspections & on-load testing section shall list the activities
to be carried out, on a step-by-step basis in order to:
Copies or prints of the electronic master will only be valid on the day of copying or printing
Central Networks plc Protection, Control, Automation & Signalling
Commissioning Specification
CS 2-03
Commissioning Switching Schedules
The final switching section shall list the activities to be carried out, on a step-by-step
basis in order to place the distribution network in its normal running arrangement.
4.15 FORMAT
Copies of all switching schedules shall be provided in duplicate in the following formats:
− One electronic copy
− One paper copy
The electronic copy shall be supplied in Microsoft Word (*.doc) format using the
Central Networks template where possible.
Copies or prints of the electronic master will only be valid on the day of copying or printing
Central Networks plc Protection, Control, Automation & Signalling
Commissioning Specification
CS 2-03
Commissioning Switching Schedules
The electronic copy shall be included within the electronic version of the
Commissioning File.
The paper copy shall be supplied in A4 size format on white paper of a quality not
less than 80g/m2.
The paper copy shall be included within the paper copy version of the Commissioning
File.
Central Networks plc has prepared a suite of Commissioning Guidance Notes which
provide practical guidance with respect to Commissioning Specifications.
Copies or prints of the electronic master will only be valid on the day of copying or printing