PRESENT
FRANCIS. A. C : MEMBER
OP 31/2024-25
PETITIONER :-
1. Sri. Naufal. N,
Nedumkandathil House,
Kunnamangalam,
Calicut-673571.
RESPONDENTS :-
an application for shifting the service wire of his above cited consumer
to the petitioner for remitting the estimate amount. Petitioner claims that
there was a post, earlier at the location and the removal of the same by
the respondent resulted in the sagging of the service wire. The petitioner
requests for the reinstalling of the said pole and realignment of the
led to the sagging of the service wire and the officials of the KSEB, for
the sake of convenience tied the sagging service wire to the walls of the
existing MYG building in joint ownership of the petitioner and his brother.
2
As per the application of the petitioner, present Assistant Engineer
states that the estimate amount is Rs. 39,111/-. But the petitioner reveals
that he could not have much fund for expending this huge amount and he
argued that if the electric post which was removed by the KSEB officials
The petitioner also states that his mother is ailing from kidney
Version of Respondent :-
facilitate the ongoing construction work at his property. On the next day
of the service wire has been fixed based on the suggestion from the
demand notice was served to the petitioner for remitting the estimate
3
2024 itself that the feasibility of laying underground cable after installing
the meter at the nearby MyG future building could be checked. Since the
materialised. Hence a suitable realignment route has been fixed with the
that the service wire was tied at the nearby building and also on a GI
pipe. Since the petitioner didn’t turn upto remit the estimate amount, a
grounds.
by the Sub Engineer at the premises. No complaint has been made by the
the said location. The allegations made in the complaint are baseless. On
could be executed.
4
Having examined the petition in detail and statement of facts of
deliberations during the hearing, the Forum has come to the following
a site inspection.
letter dated 29-06-2024 was served to the petitioner. But the petitioner
work going on in the petitioner’s premises not due to the removal of any
support post at the location. Hence the petitioner has to remit the
estimate amount for the realignment of service wire as per Section 95(4)
5
During the hearing petitioner stated that, a certain portion of
will necessitate the shifting of service wire again. The Petitioner stated
that the property in which the construction work is going on also belongs
for the same without delay. The respondent will then prepare the estimate
for the same and take necessary steps to execute the work on remittance
Decision:-
Sd/- Sd/-
Francis. A. C Sajamma. J. Punnoor
Member Chairperson.
6
Endt.on CGRF-NR/OP 31/2023-24/197 Dt 30 /08 /2024 .
Forwarded to:
1) Naufal. N, If the petitioner is not satisfied with the
Nedumkandathil House, above order of this Forum, he is at
Kunnamangalam, liberty to prefer appeal before the
Calicut-673571. State Electricity Ombudsman,
D.H. Road, Offshore Road Junction
Gandhi Square, Eranakulam, Kerala-
682016.(Ph: 0484 2346488)
within 30 days from date of receipt of
this order.
Copy to:
1. The Secretary, KSEB Ltd, Vydyuthibhavanam,
Thiruvananthapuram.
Electrical Section,Kunnamangalam,
KSEB Ltd, Kozhikode District. Forwarded
Sd/-
Chairperson.
7
8