Request For Quotation: (FM-CSFP-CGSO-39 Revision No.03 04/01/2022)
Request For Quotation: (FM-CSFP-CGSO-39 Revision No.03 04/01/2022)
Request For Quotation: (FM-CSFP-CGSO-39 Revision No.03 04/01/2022)
Province of Pampanga
City of San Fernando
Office of the Bids and Awards Committee
REQUEST FOR QUOTATION
(FM-CSFP-CGSO-39; Revision No.03; 04/01/2022)
Project Title : Supply and Delivery of Training Equipment and Supplies to be used for the
Collapsed Structure Search and Rescue Training of the City Disaster Risk
Reduction and Management Division for 2024
Location of the Project : City Mayor's Office - City Disaster Risk Reduction and Management Division
Please quote your lowest price on the item/s listed below and submit your quotation duly signed by your
representative not later than Monday, July 22, 2024 10:00 AM at CGSO Building, City Civic Center, Alasas,
City of San Fernando, Pampanga.
Canvassed by: Approved by:
Item
Qty Unit Item Description Remarks Unit Price Total
No.
2 10 pair(s) Goggles
- Anti Mist
- Anti Fog
- Adjustable Strap
- Clear
- Standard: EN 166-1F; EN170-1F; EN166 B 3,4
- UV Protection
- Anti Static Lenses
4 12 pc(s) Whistle
Project Title : Supply and Delivery of Training Equipment and Supplies to be used for the
Collapsed Structure Search and Rescue Training of the City Disaster Risk
Reduction and Management Division for 2024
Location of the Project : City Mayor's Office - City Disaster Risk Reduction and Management Division
Item
Qty Unit Item Description Remarks Unit Price Total
No.
- puncture-resistant midsole that block sharp
objects
- shock-absorbing heel and foam footbed
Total Amount:
After having carefully read and accepted your General Conditions, I quote you on the item at prices noted above.
Date
TERMS OF REFERENCE
I. BACKGROUND
Earthquake occur along faults where tectonic plates meet. It is a weak to violent shaking of the ground
produced by the sudden movement of rock materials below the earth surface.
The city aims to adopt and implement public safety measures to protect or minimize the loss of life
and damage to properties caused by disastrous earthquake and build or strengthen resiliency. It’s
also aims to enhance the government in responding to the emergencies for the earthquake events.
Collapsed Structure Search and Rescue is a term applied to rescue and recovery operations at the
scene of a karge and complex structural collapse or multiple structural collapse. CSSR is an operation
to conduct safe and effective search and rescue operation in which a wide range of knowledge, skills
and ability are required with the use of advance techniques to locate, extricate and stabilize the victim
trapped inside the confine’s space/void of collapsed structure. The ultimate goal is to rescue the
trapped victim in the shortest span of time. In order to effectively facilitate the operations, this following
tool’s and equipment’s were needed to successfully execute the task.
The San Fernando Rescue Unit (SAFRU) were trained and responding to technical rescue operations
like Water Search and Rescue, Swift Water Rescue, Ropes Rescue/High Angle Rescue, Collapsed
Structure Search and Rescue Crashed Vehicle Extrication. This equipment was used in the rescue
operation.
Among the capability program for the responders is the CSSR Training that would equip them
advanced techniques and methods in the said search and rescue. The training would be very critical
especially that the City prepares for the impacts of possible ground-shaking, which is likewise reflected
in the LDRRMC’s formulation of contingency plan for earthquake.
The Budgetary Requirement for the Supply and Delivery of Training Materials to be used for the
Basic Ropemanship Training Course for the Accredited Community Disaster Volunteers (Batch 1
& 2) for 2024 in the City of San Fernando, Pampanga, is included in the PPMP in the amount of
Two hundred sixty-seven thousand pesos (P 267,000.00)
III. OBJECTIVES
During the procurement process and delivery/ implementation of the contract, the end-user and
the supplier/ contractor shall:
12 pc(s) Whistle
b. Procurement Process
1. For the End-user, ensure the completion of the documents in order to proceed with
the procurement process.
2. For the supplier/provider, ensure the completeness of the documents being required
by the Bids and Awards Committee (BAC) for the procurement process on- time-based
on the procurement schedule including this TOR duly signed by the end-user and
conformed by the supplier/contractor.
3. If the procurement process reaches the ensuing year, observe that the allowed
delivery is only up to what is stipulated in the contract.
4. Ensure to supply the requirements upon issuance of DOC.
5. Comply with the provisions of the Procurement Law regardless of the mode of
procurement, whether Competitive/Public Bidding or the use of Alternative Methods of
Procurement.
Date
Note: This TOR shall form part of the Contract and should be strictly followed by both parties
otherwise, the implementation of the project/ program might be affected as well as the performance
of the supplier/ contractor.