PROJECT STATUS REPORT

PROPOSED CONSTRUCTION OF MAKUENI FRESH PRODUCE MARKET


AT EMALI TOWN
As at 9th January 2023

Overall Progress Registered 67%

PROJECT SUMMARY
CLIENT: DEPARTMENT OF TRADE, MARKETING, INDUSTRY, CULTURE AND TOURISM.

FUNDED BY: GOVERNMENT OF MAKUENI

PROJECT CONTRACT NO: 948610-2021-2022

SCOPES OF WORKS:

 3 NO WHOLESALE BLOCKS comprising of 30no. individual wholesale stalls

 4 NO RETAILS BLOCKS comprising of 96no. individual retail stalls

 4 NO. MARKET SHEDS

 ADMINISTRATION AND REVENUE office

 KITCHEN & RESTAURANT

 HOME NURSING/ BREASTFEEDING CENTER

 ABLUTION BLOCK, SEPTIC TANK & SOAK PIT

 6 NO. WATER TANK BASED & 24NO. 10,000 LITRES WATER TANKS

 WASTE DISPOSAL BIN & HAND WASHING POINTS

 EXTERNAL WORKS – Cabro Paved Driveways, Walkways and Parking, Storm water
Management & Drainage System, Landscaping Works, Water Harvesting and Water Reticulation,
Driveway Street lighting,

 SPECIALIST WORKS- Cold Rooms, Mobile Weigh Bridge.

SUPERVISION: DEPARTMENT OF INFRASTRUCUTRE, TRANSPORT, PUBLIC WORKS &


ENERGY

MAIN CONTRACTOR: M/S CITILINK SOLUTIONS LTD P.O. BOX 316-01001 KALIMONI

ELECTRICAL SUB-CONTRACTOR: DOMESTIC

MECHANICAL SUB-CONTRACTOR: DOMESTIC


PROJECT STATUS REPORT
PROPOSED CONSTRUCTION OF MAKUENI FRESH PRODUCE MARKET
AT EMALI TOWN
As at 9th January 2023

Overall Progress Registered 67%

CONTRACT DETAILS
Handing over date: 13th June, 2022

Commencement date: 27th June, 2022

Contract period: 6 months (26 Weeks)

Intended completion date: 27th December,2022

First revised completion date: 1st January, 2023

PROGRESS
Contract period: 6 Months (26 Weeks)
Period elapsed up to 9th January 2023: 27 Weeks 6days
% of contract period elapsed: 100%
% of work physically completed: 60%
Period beyond intended completion 8days
Time extension requested 45days
Time Extension Granted …………..

COST
Contract sum: Kshs. 172,885,038.20
Authorized additional: Kshs. NIL
Revised contract sum: Kshs. NIL
Amount certified to date: Kshs. 89,562,603.20
 1st Certificate: Kshs. 59,929,096.00
 2nd Certificate: Kshs. 29,633,507.20
Pending Certificates
 3rd Certificate Ksh. 12,687,978.00
% of contract expended 51.80%

KEY MILESTONES & DELIVERABLES

3NO. WHOLESALE BLOCKS

Overall progress 70%

Activities in progress:

• Plaster to walls
• Roof cover installation
• Installation of roller shutter doors
PROJECT STATUS REPORT
PROPOSED CONSTRUCTION OF MAKUENI FRESH PRODUCE MARKET
AT EMALI TOWN
As at 9th January 2023

Overall Progress Registered 67%


Activities in planning:

• Window cills
• Moulding edges and heads of walls and concrete surfaces
• Floor finish
• Painting
4 NO. RETAIL BLOCKS

Overall progress 75%

Activities in progress:

• Wall finishes,
• Roof cover installation

• Installation of doors

Activities in planning:

• Floor finish
Dependencies:

• Installation of doors vs plaster finish around door openings

ADMINSTRATION & REVENUE OFFICE

Overall progress 85%

Activities in planning:

• Installation of internal doors


• Completion of internal plaster
• Internal plumbing and electrical installations
• Glazing
• Floor finish
Dependencies:

• Plaster finish vs fitting of doors, completion of internal plumbing and electrical works
PROJECT STATUS REPORT
PROPOSED CONSTRUCTION OF MAKUENI FRESH PRODUCE MARKET
AT EMALI TOWN
As at 9th January 2023

Overall Progress Registered 67%


4NO. MARKET SHEDS

Overall progress 69%

Activities in planning:

• Roof cover installation


• Demolition of internal walling as per instructions
• Floor finish
• Installation of steel gutters and rain water goods
HOME NURSING CENTRE

Overall progress 68%

Activities in planning:

• Roof truss fabrication and fixing


• Roof cover installation
• Installation of internal doors
• Completion of internal and external wall finishes
• Internal plumbing and electrical installations
• Glazing
• Floor finish
Dependencies:

• Plaster finish vs fitting of doors, completion of internal plumbing and electrical works

NEW ABLUTION BLOCK, SEPTIC TANK, SOAK PIT, KITCHEN &RESTAURANT

Overall progress 15%

Activities in planning:

• Completion of substructure works


Dependencies:

• Exhausting the active septic and filling and ramming it with hardcore to formation vs excavation
for strip foundation works
• Completion of demolition of ablution block
PROJECT STATUS REPORT
PROPOSED CONSTRUCTION OF MAKUENI FRESH PRODUCE MARKET
AT EMALI TOWN
As at 9th January 2023

Overall Progress Registered 67%


EXTERNAL WORKS

Overall progress 5%

Activities in planning:

• Culvert works
• Drainage pipework installation
• Stripping roadways and parking areas
Dependencies:

• Setting out and survey works


• Favorable weather
• Minimal external activities
• Mobilization of adequate equipment
Detailed phased activities as per the revised work program

Materials On Site

Roofing sheets for all the blocks

Adequate river sand for plaster-120tons

Adequate cement 420bags