Report Update
Report Update
Report Update
PROJECT SUMMARY
CLIENT: DEPARTMENT OF TRADE, MARKETING, INDUSTRY, CULTURE AND TOURISM.
SCOPES OF WORKS:
6 NO. WATER TANK BASED & 24NO. 10,000 LITRES WATER TANKS
EXTERNAL WORKS – Cabro Paved Driveways, Walkways and Parking, Storm water
Management & Drainage System, Landscaping Works, Water Harvesting and Water Reticulation,
Driveway Street lighting,
MAIN CONTRACTOR: M/S CITILINK SOLUTIONS LTD P.O. BOX 316-01001 KALIMONI
CONTRACT DETAILS
Handing over date: 13th June, 2022
PROGRESS
Contract period: 6 Months (26 Weeks)
Period elapsed up to 9th January 2023: 27 Weeks 6days
% of contract period elapsed: 100%
% of work physically completed: 60%
Period beyond intended completion 8days
Time extension requested 45days
Time Extension Granted …………..
COST
Contract sum: Kshs. 172,885,038.20
Authorized additional: Kshs. NIL
Revised contract sum: Kshs. NIL
Amount certified to date: Kshs. 89,562,603.20
1st Certificate: Kshs. 59,929,096.00
2nd Certificate: Kshs. 29,633,507.20
Pending Certificates
3rd Certificate Ksh. 12,687,978.00
% of contract expended 51.80%
Activities in progress:
• Plaster to walls
• Roof cover installation
• Installation of roller shutter doors
PROJECT STATUS REPORT
PROPOSED CONSTRUCTION OF MAKUENI FRESH PRODUCE MARKET
AT EMALI TOWN
As at 9th January 2023
• Window cills
• Moulding edges and heads of walls and concrete surfaces
• Floor finish
• Painting
4 NO. RETAIL BLOCKS
Activities in progress:
• Wall finishes,
• Roof cover installation
• Installation of doors
Activities in planning:
• Floor finish
Dependencies:
Activities in planning:
• Plaster finish vs fitting of doors, completion of internal plumbing and electrical works
PROJECT STATUS REPORT
PROPOSED CONSTRUCTION OF MAKUENI FRESH PRODUCE MARKET
AT EMALI TOWN
As at 9th January 2023
Activities in planning:
Activities in planning:
• Plaster finish vs fitting of doors, completion of internal plumbing and electrical works
Activities in planning:
• Exhausting the active septic and filling and ramming it with hardcore to formation vs excavation
for strip foundation works
• Completion of demolition of ablution block
PROJECT STATUS REPORT
PROPOSED CONSTRUCTION OF MAKUENI FRESH PRODUCE MARKET
AT EMALI TOWN
As at 9th January 2023
Overall progress 5%
Activities in planning:
• Culvert works
• Drainage pipework installation
• Stripping roadways and parking areas
Dependencies:
Materials On Site